From: Brewer, Scott I
Sent: Thursday, April 27, 2006 6:31 PM
To: Lillard, Sarah N
Subject: RE: Allen Building @ Weston Pointe
Yes, he will pick them up tomorrow and drop off page 2
Scott Brewer, City Forester
Environmental Planner, DOCS
City of Carmel,
One Civic Square
Carmel, IN 46032
PH: 317-571-2478
FAX: 317-571-2426
From: Lillard, Sarah N
Sent: Wednesday, April 19, 2006 3:44 PM
To: Brewer, Scott I
Subject: Allen Building @ Weston Pointe
Scott,
Were you able to determine if you have stamped the Allen Office building @ Weston Point site plans?
Please let me know.
Thank you,
Sarah
4/28/2006
Page 1 of 1
Lillard, Sarah N
From: Hoyt, Gary A
Sent: Thursday, April 27, 2006 1 :56 PM
To: Lillard, Sarah N
Sarah,
I met today with Gordon Allen who has a project off Weston Dr. in western Clay
Township. The only thing I requested was a Knox box, which Mr. Allen agreed
to.
Thank you
Gary
CFD
4/27/2006
Lillard, Sarah N
Cc:
Subject:
Duncan, Gary R
Tuesday, April 04, 2006 9:47 AM I
Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer: Scott
I; Dolan, Veronica A; Akers, William P; 'grh@co.hamilton.in.us'; 'john-south@iaswcd.org';
'Candy Feltner'; 'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Matt L
'wallen@prudentialallen.com'
RE: Pre-Submittal for the Allen Building @ Weston Pointe
From:
Sent:
To:
Sarah,
I believe that this is outside of the Engineering's current jurisdiction.
Thanks so much,
Gary
-----Original Message--m
From: Lillard, Sarah N
Sent: Tuesday, April 04, 2006 09:42
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I; Dolan, Veronica
A; Akers, William P; 'grh@co.hamilton.in.us'; 'john-south@iaswcd.org'; 'Candy Feltner';
'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R
Cc: 'wallen@prudentialallen.com'
Subject: RE: Pre-Submittal for the Allen Building @ Weston Pointe
Mr. Allen,
The following requests for copies of certain parts of the approved plan come from members of our
Planning and Zoning office. One copy of each stamped plan is required for submittal for the building
permit.
Please submit four (4) copies of the approved site plan to Scott Brewer, DOCS, One Civic Square, Carmel, IN, 46032.
You will be notified when your copies are ready for pickup.
Scott Brewer
City Forester/Environmental Planner
One Civic Square
Carmel. IN 46032
(317) 571-2478
FAX (317) 571-2426
Please submit three (3) copies of the architectural elevation drawings for the structure to Matt Griffin, DOCS, One Civic
Square, Carmel, IN, 46032. You will be notified when your copies are ready for pickup.
Matt Griffin
Planning Administrator
One Civic Square
Carmel. IN 46032
(317) 571-2417
FAX (317) 571-2426
Thank you,
Sarah
I
Pre-Submittal for the Allen Building @ Weston Pointe
Page I of2
Lillard, Sarah N
Sent:
To:
From: Candy Feltner [Candy.Feltner@ctrwd.org]
Wednesday, April 05, 2006 11 :45 AM
Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I;
Dolan, Veronica A; Akers, William P; grh@co.hamilton.in.us; john-south@iaswcd.org;
mbm@co.hamilton.in.us; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R
Cc: wallen@prudentialallen.com; Jennifer Bruner
Subject: RE: Pre-Submittal for the Allen Building @ Weston Pointe
Plans and a District application need to be submitted to the District Engineer for review.
Candy J. Feltner
Director of Administration
and Customer Service
Clay Twp RWD
317 -844-9200
317 -844-9203 fax
From: Lillard, Sarah N [mailto:SLillard@carmel.in.gov]
Sent: Tuesday, April 04, 2006 8:36 AM
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I; Dolan,
Veronica A; Akers, William P; grh@co.hamilton.in.us; john-south@iaswcd.org; Candy Feltner;
mbm@co.hamilton.in.us; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R
Cc: wallen@prudentialallen.com
Subject: Pre-Submittal for the Allen Building @ Weston Pointe
The Dept. of Community Services, Building & Code Services division, has
received a request to schedule a pre-submittal meeting for the purpose of
obtaining a building permit. PLEASE ""REPLY TO ALL"" WITHIN 48 HOURS.lf
YOU HAVE OUTSTANDING ISSUES. After that time, we may proceed with the
meeting and submittal.
Project:
The Allen Office Building @ Weston Pointe Retail Center
(4 tenant office building)
Meeting Date:
PENDING
Time:
PENDING
Related Planning & Zoning docket numbers:
05090008 ADLS
Representative:
Gordon Allen
04/05/2006
Lillard. Sarah N
From:
Sent
To:
Greg Hayes [grh@co.hamilton.in.us]
Tuesday, April 04, 2006 10:14 AM
Conn, Angelina V; Foley, Amanda J; Hill, Dick B; Duncan, Gary R; Hoy1, Gary A; Blanchard,
Jim E; Griffin, Matt L; Brewer, Scott I; Lillard, Sarah N; Dolan, Veronica A; Akers, William P;
Michael McBride; Candy.Feltner@ctrwd.org; john-south@iaswcd.org
wallen@prudentialallen.com
Re: Pre-Submittal for the Allen Building @ Weston Pointe
Cc:
Subject
Sarah
The Hamilton County Surveyor's Office has no outstanding issues. If you have any questions, please let
me know.
Greg Hoyes
HCSO Plan Reviewer
>>> "Lillard, Sarah N" <SLillard@carmeLin.gov> 9:35 AM Tuesday, April 04, 2006, 2006 >>>
The Dept. of Community Services, Building & Code Services division, has received a request to
schedule a pre'submittal meeting for the purpose of obtaining a building permit. PLEASE "REPLY TO
ALL" WITHIN 48 HOURS, IF YOU HAVE OUTSTANDING ISSUES. After that time, we may proceed
with the meeting and submittal.
Project:
The Allen Office Building @ Weston Pointe Retail Center
( 4 tenant office building)
Meeting Date: PENDING
Time: PENDING
Related Planning & Zoning docket numbers:
05090008 ADLS
Representative:
Gordon Allen
Prudential Allen
wallen@prudentialallen.com
cell: (317) 502,3621
office: (317) 870'7625
Again, if there are concerns that might affect the issuance of this permit, please REPLY TO ALL on this
e'mail.
1
Lillard, Sarah N
Cc:
Subject:
Lillard, Sarah N
Tuesday, April 04, 2006 9:42 AM
Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott
I; Dolan, Veronica A; Akers, William P; 'grh@co.hamilton.in.us'; 'john-south@iaswcd.org';
'Candy Feltner'; 'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R
'wallen@prudentialallen.com'
RE: Pre-Submittal for the Allen Building @ Weston Pointe
From:
Sent:
To:
Mr. Allen,
The following requests for copies of certain parts of the approved plan come from members of our
Planning and Zoning office. One copy of each stamped plan is required for submittal for the building
permit.
Please submit four (4) copies of the approved site plan to Scott Brewer, DOCS, One Civic Square, Carmel, IN, 46032.
You will be notified when your copies are ready for pickup.
Scott Brewer
City Forester/Environmental Planner
One Civic Square
Carmel. IN 46032
(317) 571-2478
FAX (317) 571-2426
Please submit three (3) copies of the architectural elevation drawings for the structure to Matt Griffin, DOCS, One Civic
Square, Carmel, IN, 46032. You will be notified when your copies are ready for pickup.
Matt Griffin
Planning Administrator
One Civic Square
Carmel. IN 46032
(317) 571-2417
FAX (317) 571-2426
Thank you,
Sarah
mnOriginal Message-----
From: Lillard, Sarah N
Sent: Tuesday, April 04, 2006 9:36 AM
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I; Dolan, Veronica A; Akers, Wiiliam P;
'grh@co.hamilton.in.us'; 'john-south@iaswcd.org'; 'Candy Feltner'; 'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Matt L;
Duncan, Gary R
Cc: 'wallen@prudentialallen.com'
Subject: Pre-Submittal for the Allen Building @ Weston Pointe
The Dept. of Community Services, Building & Code Services division, has received'a
request to schedule a pre-submittal meeting for the purpose of obtaining a building
permit. PLEASE "REPLY TO ALL" WITHIN 48 HOURS. IF YOU HAVE
OUTSTANDING ISSUES. After that time, we may proceed with the meeting and submittal.
1
Lillard, Sarah N
Cc:
Subject:
Griffin, Matt L
Tuesday, April 04, 2006 9:39 AM ,
Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewei, Scott
,
I; Dolan, Veronica A; Akers, William P; 'grh@co.hamilton.in.us'; 'john-south@iaswcd.org';
'Candy Feltner'; 'mbm@co.hamilton.in.us'; Foley, Amanda J; Duncan, Gary R
'wallen@prudentialallen.com'
RE: Pre-Submittal for the Allen Building @ Weston Pointe
From:
Sent:
To:
We will require 3 sets of elevations.
Matthew L. Griffin, AICP
Planning Administrator
Department of Community Services
City of Carmel
One Civic Square
Carmel, IN 46032
phone: 317.571.2417
fax: 317.663.3208
email: mariffin(a)carmel.ln.aov <mailto:mariffin@carmel.in.Qov>
From: Lillard, Sarah N
Sent: Tuesday, April 04, 2006 9:36 AM
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I; Dolan, Veronica A;
Akers, William P; 'grh@co.hamilton.in.us'; 'john-south@iaswcd.org'; 'Candy Feltner'; 'mbm@co.hamilton.in.us'; Foley,
Amanda J; Griffin, Matt L; Duncan, Gary R
Cc: 'wallen@prudentialallen.com'
Subject: Pre-Submittal for the Allen Building @ Weston Pointe
The Dept. of Community Services, Building & Code Services division, has received a
request to schedule a pre-submittal meeting for the purpose of obtaining a building
permit. PLEASE "REPLY TO ALL" WITHIN 48 HOURS. IF YOU HAVE OUTSTANDING
ISSUES. After that time, we may proceed with the meeting and submittal.
Project:
The Allen Office Building @ Weston Pointe Retail Center
(4 tenant office building)
Meeting Date:
PENDING
Time:
PENDING
Related Planning & Zoning docket numbers:
05090008 ADLS
Representative:
Gordon Allen
Prudential Allen
1
Lillard. Sarah N
From:
Sent:
To:
Lillard, Sarah N
Tuesday, April 04, 2006 9:36 AM I
Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott
I; Dolan, Veronica A; Akers, William P; 'grh@co,hamilton.in,us'; 'john-south@iaswcd,org';
'Candy Feltner'; 'mbm@co,hamilton.in,us'; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R
'wallen@prudentialallen,com'
Pre-Submittal for the Allen Building @ Weston Pointe
Cc:
Subject:
,
,
The Dept. of Community Services, Building & Code Services division, has received al
request to schedule a pre-submittal meeting for the purpose of obtaining a building I
permit. PLEASE "REPLY TO ALL" WITHIN 48 HOURS. IF YOU HAVE OUTSTANDING
ISSUES. After that time, we may proceed with the meeting and submittal.
Project:
The Allen Office Building @ Weston Pointe Retail Center
(4 tenant office building)
Meeting Date:
PENDING
Time:
PENDING
Related Planning & Zoning docket numbers:
05090008 ADLS
Representative:
Gordon Allen
Prudential Allen
wallen@prudentialallen.com
cell: (317) 502-3621
office: (317) 870-7625
Again, if there are concerns that might affect the issuance of this permit, please