HomeMy WebLinkAboutCC&T Construction/STREET/$14,713.80/CO #1 - 22-STR-10 - Concrete Panels DocuSign Envelope ID: E35D61 E6-7B79-45EC-933E-FA86BEAE9A57
City of Carmel Project
22-STR-10 Concrete Panels
Change Order#1 —
Quantity Change- Concrete Street Panel- Sq Yds APPROVESBy Bergey Grechukhon al„o,am Dec o=
022
Quantity Change- Aggregate Base-Tons
Quantity Change- High Early 2% per Cu Yd
Change Order#1
Contract Price prior to this Change Order $ 143,600.00
Contract Price will be increased/decreased by this Change Order $ 14,713.80
New Contract Price including this Change Order $ 158,313.80
Adjusted Contract Cumulative
Amount Price Change from Original
Contract
Original Contract $ 143,600.00 $ 143,600.00 N/A
List of Items to Change $ 14,713.80 $ 158,313.80 10.25%
on this Project
DocuSign Envelope ID: E35D61E6-7B79-45EC-933E-FA86BEAE9A57
CITY OF CARMEL
TO: CONTRACT CHANGE ORDER NO.: 1
DATE: 12/15/2022
PROJECT NAME: 22-STR-10 Concrete Panels
CITY REQ. NO.: N/A
CITY PO NO.: 106985
CITY PO DATE: 11/16/2022
I. You are directed to make the following changes in this Contract:
Change Order#1 listed below.
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+) OR(-) DAYS
Concrete Street Panel- Sq Yds 1,220.400 0
Aggregate Base- Tons 447.130 0
High Early 2%per Cu Yd 209.000 0
The following referenced Documents further describe the changes outlined in Paragraph I, and are to
be considered a part of this Change Order: R.F.P.: N/A W.D.C. No.: N/A_Other: See
attached proposals
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $_143,600.00
Contract Price will be increased/decreased by this Change Order $ 14,713.80
New Contract Price including this Change Order $_158,313.80
Contract Time Prior to this Change Order N/A Days N/A Completion Date
Net increased/decreased resulting from this Change Order 0 Days
Current Contract Time including this Change Order 28 Days 12/31/22 Completion Date
Version 2016-08-31
DocuSign Envelope ID: E35D61E6-7B79-45EC-933E-FA86BEAE9A57
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
City of Carmel CC&T Construction Not Present
STREET CONTRACTOR James Brainard, Mayor
-DocuSigned by:
1 Civic Square 5051 Prospect St t
Address Address Pia Do d*urke, Member
Carmel, IN 46023 Indianapolis, IN 46203 (Avi 00afsoa.
City/State/Zip City/State/Zip Ldri-Watsono,DMember
By: �sy:
QMatt Higginbotham � DocuSigned by:
3 v.
Phone: 317-733-2001 Phone: 311— 510-(03 �
byJc.A2 "c�`"U/Abb44U5...
Sue Wolfgang Clerk
Date: 12/15/22 Date: /ai 5/2 z Date: 1/19/2023