2. Docket No. PZ-2022-00224 OA: BJ's Wholesale Club-146th & Keystone PUD Amend
The applicant seeks to amend the PUD to add accessory uses and update various other development standards
requirements to construct a BJ’s Wholesale Club building. The site is located at 14480 Lowes Way. It is currently
zoned PUD: Z-344 - 146th & Keystone Ave. PUD. Filed by Marc LaVoie, PE, of BJ’s Wholesale Club, Inc.
*Updates to the Report are written in blue
Project Overview:
The Petitioner proposes to amend the current 146 & Keystone Ave. PUD to allow for a new user, BJ’s Wholesale, to
occupy the remainder of the site. Lowe’s occupies the north portion of the property, and the south portion has two
restaurants and a vacant parcel at the southernmost portion. US 31 and Keystone Parkway have had many improvements
around this site, providing greater access to and from 146th Street. Danbury Estates residential subdivision is located
across Lowe’s Way to the east, zoned R-4/Residential. To the southeast across Lowe’s Way and separated by Cool Creek
is the Laura Vista Subdivision, zoned R-1/Residential. Please see the Petitioner’s Information packet for more details.
PUD (Planned Unit Development) Standards this project MEETS:
• Permitted Use: Retail
• Minimum tract size: 5 acres required, 8.5 proposed
• Min. Building Height: 14’ required, 39’4” proposed
• Minimum Gross Floor Area: 15,000 sq. ft. required;
101,826 sq. ft. proposed
• Maximum FAR is 0.7: 0.27 proposed (101,826 sq.
ft./8.5 acres)
• Architectural Design Requirements:
o Minimum of 3 building materials required, brick,
stone, precast concrete panel, and EIFS proposed
o 8 eternal corners minimum required, 12 provided
• Lighting Plan: No changes proposed to Section 9
• Loading berths: No changes proposed to Section 11.2
• Rooftop Mechanical equipment screening: No changes
proposed to Section 11.4
• Cart Corrals: No changes to Section 11.5
• Maximum Parcel Coverage allowed: 30% for retail
permitted, 22% proposed
•
• Landscaping:
o Greenbelt: New 0.15-acre area shown along
Keystone Parkway to preserve existing landscaping
and vegetation – minimum of 30’, 30’ was also
required in existing PUD. Please note that much of
the previous greenbelt has been acquired by INDOT
for ROW for road improvements. 0.37 acres is now
proposed as a new no-mow area at the south end of
the site. This will help clean run-off and pollutants
before getting to the creek.
o Parallel roadways: previously required 10’ planting
area adjacent to Keystone, proposal now is to have
the 10’ area adjacent to Lowe’s way, about 16’
proposed currently
o Section 7.2.C. – Building base plantings – concept
plan/site plan has been modified to meet PUD
requirements
o Parking lot landscaping – 6% required, 7.2%
proposed
Existing PUD Standards NOT MET, therefore NEW PUD standards proposed or items unknown:
• Minimum Building Setback: New proposed distance is 60’ from ROW, 90’ previously required, 65’ proposed with
concept plan
• Architectural Design Requirements: Golden Section – PUD has been altered to state the main entrance design must
meet the Golden Section, and an exhibit has been provided to illustrate this.
• Parking requirements: UDO would require 1/200 sq. ft. of floor area = 509 spaces, 407 spaces proposed, PUD
proposed change to allow the 407 shown on the concept plan.
• Outside Storage of Refuse or Merchandise: Changed to only allow propane tanks as overnight outside storage and
allows daily merchandise to be displayed adjacent to the front entrance. However, daily merchandise may not remain
overnight. Meaning if something is brought out, it must be placed back inside the building overnight.
• Signs: PUD has been updated to more closely resemble what the UDO would require, as well as still provide ample
identification similarly to what was previously allowed by the original PUD language. Staff is supportive of the
proposed changes.
4
• New PUD sections:
o Bike Parking to follow UDO requirements
o Overnight parking – not allowed except for trucks actively unloading at the loading docks
o Offsite Roadway Improvements: adding dedicated right lane out of the round-a-bout, right turn only at
south end of site, adjustments to 146th St. & Lowe’s Way intersection to improve traffic flow
Concept Site Plan:
The proposed concept site plan has the BJ’s building at the east side of the site, oriented west with the main entrance
visible from US 31 and Keystone Parkway. The main vehicular entrance into the site from Lowe’s Way will remain as is
constructed today, with a few proposed enhancements to accommodate additional vehicles. For example, BJ’s would
construct a right turn lane at the round-a-bout going southbound on Lowe’s Way to aid in dispersing traffic. They also
propose to add a right-out (only) cut at the south end of the site (to Lowe’s Way), for large trucks to have a secondary way
out of the site.
A fueling station and an indoor tire sales and service area are proposed as part of this PUD Amendment. Currently, Auto
Service or Filling Stations are not allowed as primary uses in the PUD. The PUD also references Accessory Uses allowed
in the B2 District would be allowed here. However, neither of these uses are allowed as accessory uses in the B2 District.
So, the proposed PUD amendment would allow for these uses: auto service (meaning tire sales and service inside the
building) and auto filling stations, to be accessory uses to the primary use of the retail building. Staff has worked with the
Petitioner regarding the placement of the filling station, as we had concerns regarding the proximity of a filling station to
Cool Creek, which runs directly south of the property. The Petitioner is proposing additional safety measures against fuel
leaking and spilling, which are comparable to the precautions taken by the gas station at 146th and River Road. The
Engineering Department has reviewed these proposals in detail and offered suggestions regarding additional measures.
The Petitioner has stated they are continuing to work through these items with the Engineering Department.
The fueling station and associated underground tanks are now proposed to run north/south at the SW corner of the
property. The pumps and all aspects of the gas component are located more than 500’ away from the residential
neighborhoods to the east, which complies with the recent City Code amendment restricting gas stations to be within 500’
of residential areas.
Architectural Design:
Staff has been working with the Petitioner on the design of the building to enhance the exterior design to be unique, have
four-sided architecture, and be context sensitive. We worked to create symmetry throughout the facades and designate
feature areas to break down the scale of the structure. The building will be constructed of pre-cast concrete panels, with
brick inlay, a stone base, and a textured upper area (so it is not plain concrete walls) to give additional character (below
the cornice line). A theme across most BJ’s buildings is a diamond shape as an accent. We encouraged them to use this
design element around the building as an additional feature, and it has been incorporated into bump out/tower elements
around the building. Faux windows have also been added to each façade at the upper levels, which help to give additional
character and break up the scale of the building.
The main entrance on the west elevation has been updated to include more brick and awnings over the two sets of entry
doors. This addresses the concerns of proper proportion and design aesthetic of this main entry feature. The rear of the
upper parapet walls have also been altered to appear like fronts, rather than blank walls. The awnings around the building
have also been modified to all be the same color, as requested.
Signage:
Signage shown on the Concept Plan elevations is now directly tied to the PUD language. Main identification signs are
provided on the West, North, and East around the main entrance to the building. Supplemental signs are provided on the
West and South in reference to other services provided at the building. Signage square footages relate to the architectural
spandrel panel areas where they are proposed. This keeps signage in line with what the UDO would require. Staff is in
support of the proposed signage changes to the PUD.
January 17, 2023 Public Hearing recap:
Petitioner went over project details, outlining the work that had been done with Staff prior to coming to the Plan
5
Commission. They advertised for and held a neighborhood meeting for any neighbors interested in the project. No one
came to that meeting. The Petitioner is proposing additional road improvements in the general area, to aid in traffic flow
and existing traffic concerns. Plan Commission members talked about the placement of the gas station, asked for a recap
of what changes had made already to the concept plan, requested views of the building/site from Keystone Parkway
headed north, and if there were concerns about traffic coming into the site from the south. The Plan Commission voted to
allow the Commercial Committee to have final voting authority to send to City Council.
DOCS Remaining Comments/Concerns:
Staff has two remaining comments that can continue to be worked on/addressed as the project proceeds to City Council
level, and if approved, at the DP/ADLS level. The first is the additional gas station underground storage tanks protective
measures. We recommend that the Petitioner continue to work with the Engineering Department to provide the highest
level of protection possible for a proposed fuel station adjacent to Cool Creek. The second is the layout of the vehicular
entrance into the site, and its proximity to the main pedestrian entrance into the building. It is offset, which requires an
immediate right turn/curve to head down the main drive aisle in front of the building. Because this is a concept plan, the
final location for the entrance can still be adjusted. We recommend the Petitioner continue to work through this entry
alignment, for the safest possible arrangement.
Recommendation:
The Department of Community Services recommends the Commercial Committee votes to send this item to the City
Council with a Favorable Recommendation.