HomeMy WebLinkAboutFredericks, Inc./ICS/$9,590/CO #5 - Carmel Data Center - Sidewalk DocuSign Envelope ID: DA831258-B752-4D2A-A665-0FAD844E92A8
CITY OF CARMEL APPROVED
By Sergey Grechukhin at 10:05 am,Jan 23,2023
TO: CONTRACT CHANGE ORDER NO.: 5
Frederick's, Inc. DATE: 1/20/2023
5448 West State Road 132 PROJECT NAME: Carmel Data Center
Pendleton, IN 46064 CITY REQ. NO.:
CITY PO NO.:105712
CITY PO DATE:
I. You are directed to make the following changes in this Contract:
(Brief Description)
ADD - Grade, form, furnish, place and finish approx. 75 feet of new 4" concrete sidewalk
on 4" #53 stone - $9,590.00
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+) OR( DAYS
II. The following referenced Documents further describe the changes outlined in Paragraph I, and
arc to be considered a part of this Change Order: R.P.P.: W.D.C. No.:
Other;
The changes result in the following adjustment of-Contract Price and Contract Time:
Contract Price prior to this Change Order $ 634,626.00
Contract Price will be increased/decreased by this Change Order $ 9,590.00
New Contract Price including this Change Order $ 644,216.00
Contract Time Prior to this Change Order Days NC Completion Date
Net increased decreased resulting from this Change Order NC Days
Current Contract Time including this Change Order Days NC Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
AR-1
DocuSign Envelope ID: DA831258-B752-4D2A-A665-0FAD844E92A8
The Above Changes Are The Above Changes Are Approved:
Recommended Requested/Accepted:
Studio M Architecture Frederick's, Inc. Not Present
ARCHITECT CONTRACTOR James Brainard, Mayor
2 West Main Street 5448 West State Road 132 ,—DocuSigned by:
Address Address M �SArtnY: ajrke, Member
Sri alot{satn,
B Al en, mbe-
Carmel, IN 46032 Pendleton, IN 46064
City/State/Zip City/State/Zip Audie Tarpley, DCG
Construction Project Manager
(324 zg A.
nines Crider, Director of
Administration
13y: BY:
C u-<4.X =? - ATTEST fES1
' TT T).—DocuSigned by:
Phone:....1211 .4 ite • o48 /(, Phone: 176.S J 77 : -7S- f Su., co.
Sue WoR ,171.3tYk
Date: I" 20 • 1".°1---Z Date: l-2-c'-2-?2.3 Date: 2/1/2023
AR-2
DocuSign Envelope ID: DA831258-B752-4D2A-A665-0FAD844E92A8
i � 1
r
) CONTRACTORConstruction Proposal
11/25/2022
Dillon Construction Group
Attn: RJ Beckerich
6828 Hillsdale Court
Indianapolis, IN 46250
reckerich@dillongcg.com
RE: Carmel IT Data Center—Additional Sidewalk
Mr. Beckerich,
Fredericks Contractors is pleased to offer this proposal for the labor, material, equipment, &insurance to complete the Scope
of Work as noted below:
• Grade, form,furnish, place &finish approximately 75 feet of new 4"concrete sidewalk on 4"#53 stone
Total Added Cost for Complete Scope of Work: $9,590.00
Exclusions/Notes
• Based on sketches dated 11/16/22
• Excludes Indiana sales &use tax
• Includes P&P bond costs
• Material testing by others, if required
I appreciate the opportunity to quote this work. If there is any additional information I can provide or any other service
Fredericks can offer you at this time, please let me know.
Sincerely,
Andrew Brinks
765.425.3107 (cell)
andrew.brinks@fredericksinc.com