HomeMy WebLinkAbout3D Company, Inc/ENG/CO #1/20-ENG-02 DocuSign Envelope ID: E3DF1AE4-D2F6-4C0E-B51B-5B387E45F6DF
City of Carmel Project 20- ENG-02
Intersection Improvements : 106th Street
and College Avenue Roundabout a'APPROVED
By zza pm,Feb,s,zou
CHANGE ORDER #1
Pay items are being created and deducted for switching to concrete pavement for the raised crosswalks,
adding a larger manhole, encountered rock excavation, modifications to planned structures due to
differing site conditions, delays due to utilities, irrigation conduits, bulk series handholes, additional pipe
and structure removal, and payment for lowering storm sewer to avoid utilities.The number of calendar
days for closure of the intersection is being increased by 18 days. Adjustment to the Substantial and
Final completion dates for the project will be reviewed and adjusted after additional claims are
reviewed.
Contract Price prior to this Change Order $3,660,000.00
Contract Price will be changed by this Change Order $99,360.21
New Contract Price including this Change Order $3,759,360.21
Amount Adjusted Contract Cumulative%Change
Price from Original Contract
Original Contract $3,660,000.00 N/A N/A
CO1 $99,360.21 $3,759.360.21 2.71%
DocuSign Envelope ID: E3DF1AE4-D2F6-4COE-B51B-5B387E45F6DF
CITY OF CARMEL
TO: Jeremy Kashman CONTRACT CHANGE ORDER NO.: 1
City Engineer DATE: February 13, 2023
City of Carmel Indiana PROJECT NAME: 106th and College Ave RAB
One Civic Square CITY REQ. NO.:
Carmel, IN 46032 CITY PO NO.: 20-ENG-02
CITY PO DATE:
I. You are directed to make the following changes in this Contract:
This Change Order includes Change Order Requests 1,3,5,6,9,10,11,15,16,17,18,19,20,21,22,23,and
24, which are included as attachments. These change orders include various differing site conditions,
delays due to adjustments necessary due to utilities, and additions to the contract. Note this change
order adds 18 days to the maxium days for the closure of the intersection,which was closed on
9/6/2022. Overall substantial completion date and final completion date will be adjusted upon change
order day review.
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+)OR(-)DAYS
II. The following referenced Documents further describe the changes outlined in Paragraph I,
and are to be considered a part of this Change Order: R.F.P.: N/A W.P.C.NO.: N/A
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $ 3,660,000.00
Contract Price will be increased by this Change Order $ 99,360.21
New Contract Price including this Change Order $ 3,759,360.21
Contract Time prior to this Change Order 60 Days Closure 12/2/2022 Substantial Completion Date
Contract Time prior to this Change Order 1/3/2023 Final Completion Date
Net increased/decreased resulting from this Change Order 18 Days
Current Contract Time including this Change 78 Days Closure 12/2/2022 Substantial Completion Date
Current Contract Time including this Change Order 1/3/2023 Final Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are The Above Changes Are Accepted Approved
Recommended �DoDDSigned by:
American Structurepoint,Inc. 3D Company,Inc. /
ENGINEER CONTRACTOR a Arai n
Jamess Brainard, Mayor
9025 River Road,Suite 200 7240 North State Road 3 C^ at A,,, ,
'r
Address Address I Xnn Burke,Member
Indianapolis,IN 46240 Muncie,IN 47303 Zvi(Wu', _
City/State/Zip City/State/Zip 1231rWatson,Member
Jerem ash an,PE,City Engineer
Joseph A Dubyal ��• ;� ~~ Seth Blalock
y: y:
317-501-8111 765-730-1831 ATTEST DocuSi9netlby:
Phone: Phone: �S� J'
Sue Wolfgang,Clerk
Date: 02/14/2023 Date: 2/14/23 Date: 3/1/2023
DocuSign Envelope ID: E3DF1AE4-D2F6-4C0E-B51B-5B387E45F6DF
o sraucru POINT American Structurepoint, Inc.
■ Change Order Details
20-ENG-02- 106th and College RAB
Description Intersection improvements at 106th Street and College Avenue will consist of replacing a signalized intersection with a roundabout The
reconstruction of the intersection will include new full-depth pavement,curb and gutter,enclosed storm water network,lighting,and shared-use
paths with new curb ramps and raised crosswalks
Prime Contractor 3D Company,Inc
Muncie
Change Order 1
Status Pending
Date Created 12.'15.2022
Type Changed Conditions
Summary Change Order I
Change Order Description This Change Order includes the Change Order Request 1,3,5,6,9, 10,11, 15, 16,17,18,19,20,21,22,23,and 24
These requests were submitted and reviewed,including at a meeting on 1-31-23 to discuss
Total Days added to the closure from these change orders totals 18 days Total Cost added to the contract is$99,360 21 See attached summary
table and CORs for more information
Awarded Project Amount S3,660,000 00
Authorized Project Amount S3,660,000 00
Change Order Amount S99,360 21
Revised Project Amount S3,759,360 21
Change Order Details: 02/14/2023
20-ENG-02-106th and College RAB Page 1 of 5
DocuSign Envelope ID: E3DF1AE4-D2F6-4C0E-B51B-5B387E45F6DF
Increases/Decreases
Line Number Item ID unit Unit Price Current Change Revised
Quantity Amount Quantity Amount Quantity Amount
Section: 1-Description
0035 00003 SYS $197 830 430-000 385,066-90 -430 000 -385,066 90 0 000 $0.00
RAISED PEDESTRIAN CROSSING
Reason:COR#I -Switch to concrete
0087 720-95422 EACH $8.287.000 3.000 $24,861.00 -1.000 -$8.287.00 2.000 $16,574.00
MANHOLE.,14
Reason:COR#9-Lamer M U needed
2 items Totals $109,927.90 -S93,353.90 $16,574.00
New Items
m1€f `+iliii!.I;- I11i.diititi) lEiiirys 1.0.11isbii lt'r - - Igai((alHil✓p 1^3({fdryfi116
Section: 1-Description
0151 502-08202 SYS 187 000 $269 500 $50,396 50
PCCP, 10 5 IN
Reason:COR#1-Stamped Concrete-Change to Concrete from Brick Pavers
Change Order Details: 02/14/2023
20-ENG-02-106th and College RAB Page 2 of 5
DocuSign Envelope ID: E3DF1AE4-D2F6-4COE-B51B-5B387E45F6DF
Line Number Item II? Unit Quantity Unit Price Extension
aft,'
11152 502-08202 SYS 243.000 81188a0 $28.868.40
PCCP, 10.5IN
Reason:COR##1-PCCP Plain Raised Concrete
0153 203-02010 CYS 187000 $125.000 $23,375.00
EXCAVATION,ROCK
Reason:COR#3,6,16-Change Condition
0154 105-06807 LS 1.000 $754.560 $754.56
ADDITIONAL
Reason:COR#5-Modification oi`STR 173
0155 720-92884 EACH 1000 $12,195.040 $12,195.04
MANHOLE,K4,MODIFIED
Reason:COR#9-STR 125A
0156 105-06807 LS 1000 $1,126 790 $1,126.79
ADDITIONAL
Reason:COR#10-Adjustments at STR 175
0157 105-06807 LS 1.000 $2,404 410 $2,404 41
ADDITIONAL
Reason:COR41 I -Gas service line adjustment
Change Order Details: 02/14/2023
20-ENG-02-106th and College RAB Page 3 of 5
DocuSign Envelope ID: E3DF1AE4-D2F6-4C0E-B51B-5B387E45F6DF
line Number Item ID unit Quantity Unit Price Extension
I1158 Iu5-06S07 L.S I U00 $5.669 27( $S,669 27
ADDITIONAL
Reason:COR#15-Adjustments at SIR 171 and SIR 172 due to AT&T
0159 105-06807 LS 1.000 $4,836.I80 $4,83618
ADDITIONAL
Reason:COR#17-Lowering of utility line
0160 105-06807 LS 1.000 S1.577.660 S1.577.66
ADDITIONAL
Reason:COR#l8-Underdrain adjustments at SIR 154
0161 805-95568 LFT 280 000 $64 150 S17,962.00
CONDUIT,PVC,4"
Reason:COR#19-Addition of irrigation conduits
0162 105-06807 LS 1.000 85,558180 $5,558.18
ADDITIONAL
Reason:COR#20-Fiber Optic Protection
0163 807-78590 EACH 2.000 $3,966 370 $7,932 74
HANDHOLE
Reason:COR#21 -Bulk Series Handholes
Change Order Details: 02/1412023
20-ENG-02-106th and College RAB Page 4 of 5
DocuSign Envelope ID: E3DF1AE4-D2F6-4C0E-B51B-5B387E45F6DF
line Number Item ID Unit Quantity Unit Price Extension
I1164 ICiS-I6307 LS in.() 52.52t).440 $2.520.44
ADDITIONAL
Reason:COR#22-Concrete Road Widening
0165 105-06807 LS 1,000 87,720.150 $7,720.15
ADDITIONAL
Reason:COR1l23-Remove Additional Pipe and Structures
0166 105-06807 LS 1_000 519,816,790 819.816.79
ADDITIONAL
Reason:COR#24-Lowering of STR 154, 155. 156. 157, 159, 160. 161 to avoid AT&T Conflict
16 items Total:$192,714.1 1
Time Limit Changes
'I,ype Original Deadline Current Deadline Pending Extension Pending Deadline
Calendar Days 60 0 Days 60 0 Days 18 0 Days 78 0 Days
60-day Maximum Intersection Closure
Reason: Extra Work,Changed Condition
I time limit
Change Order Details: 02/14/2023
20-ENG-02-106th and College RAB Page 5 of 5
DocuSign Envelope ID: E3DF1AE4-D2F6-4C0E-B51B-5B387E45F6DF
CHANGE ORDER 1 SUMMARY 20-ENG-02 106th and College RAB
Change Order Request Approved
Approved Cost
Number Date Description Days
1 1/11/2023 Raised Crosswalks $ (5,802.00) 3
3 1/11/2023 Remove Non-Removable Flowfill $ 11,687.50 1
5 1/11/2023 STR 173 Modification $ 754.56 0.25
6 1/11/2023 Remove Non-Removable Flowfill $ 7,187.50 1
9 1/12/2023 STR 125A-Size Change $ 3,908.04 0
10 1/12/2023 STR 175-Redesign $ 1,126.79 0.25
11 1/12/2023 Gas Main Conflict $ 2,404.41 0.5
15 1/12/2023 STR 171 and STR 172 $ 5,669.27 0.5
16 1/12/2023 Non-Removable Flowfill $ 4,500.00 1
17 1/12/2023 Relocate communication utility $ 4,836.18 0
18 1/12/2023 Rework underdrain pipe $ 1,577.66 0.25
19 1/12/2023 Irrigation Conduits $ 17,962.00 1
20 1/12/2023 Fiber Optic Protection $ 5,558.18 1
21 1/12/2023 Bulk Series Handhole $ 7,932.74 0
22 1/12/2023 MOT Concrete Widening $ 2,520.44 0
23 1/12/2023 Remove existing Inlets and Pipe $ 7,720.15 0.5
24 1/17/2023 Lower storm pipe for AT&T $ 19,816.79 7
Totals $ 99,360.21 18