HomeMy WebLinkAboutS400 - STRUCTURAL SECOND FLOORãLATERAL BRACING & SHEAR WALL
SHEATHING SPECIFICATIONS
THIS MODEL HAS BEEN DESIGNED TO RESIST LATERAL
FORCES RESULTING FROM:
115 MPH WIND IN 2020 InRC MAP
(115 MPH WIND SPEED IN ASCE 7-16
WIND MAP, PER IRC R301.2.1.1)
EXP. B, RISK CAT. 2 & SEISMIC CAT. A/B.
THE DESIGN WAS COMPLETED PER 2018 IBC
(SECTION 1609) & ASCE 7-16, AS PERMITTED BY
R301.1.3 OF THE 2020 InRC, OR THE SIMPLIFIED
PRESCRIPTIVE PROCEDURE IN ACCORDANCE
WITH THE 2020 InRC IF THE PARAMETERS OF
SECTION R602.12 COMPLY. ACCORDINGLY, THIS
MODEL, AS DOCUMENTED AND DETAILED
HEREWITHIN, IS ADEQUATE TO RESIST THE CODE
REQUIRED LATERAL FORCES.
SEE CONNECTION SPECIFICATIONS CHART FOR
STANDARD SHEAR TRANSFER DETAILING. IF
ADDITIONAL CAPACITY IS REQUIRED BY DESIGN, IT
WILL BE SPECIFICALLY NOTED ON PLAN.
ALL STRUCTURAL PANELS ARE TO BE DIRECTLY
APPLIED TO STUD FRAMING.
NOTES
PRE-MANUFACTURED PANELIZED WALLS:
ALL SHEATHED (OSB OR PLYWOOD) PANELIZED
WALLS SHALL BE FASTENED TOGETHER AT END STUDS
WITH 0.131x3” NAILS AT 4” O.C (VERTICALLY)
THROUGH ONE SIDE. WHEN SIDE NAILING OF
PANELIZED WALLS IS NOT POSSIBLE, FASTEN PANELS
TOGETHER WITH 0.162x3.5” TOENAILS AT 4” O.C.
(VERTICALLY). ALL NON-SHEATHED PANELIZED
WALLS SHALL BE FASTENED TOGETHER WITH 0.131x3”
NAILS AT 16” O.C. (VERTICALLY) THROUGH ONE SIDE.
3" O.C. EDGE NAILING
7/16" OSB OR 15/32" PLYWOOD:
FASTEN SHEATHING w/ 2-3/8"x0.113 NAILS @ 6"
O.C. AT EDGES & @ 12" O.C. IN THE PANEL FIELD.
(TYP, U.N.O.)
ALL SHEATHING PANELS SHALL BE ORIENTED
VERTICALLY (LONG DIRECTION PARALLEL TO STUDS)
AND INSTALLED FULL HEIGHT OF SHEAR WALL - OR -
2x HORIZONTAL BLOCKING SHALL BE PROVIDED TO
SUPPORT ALL UNSUPPORTED PANEL EDGES & EDGE
FASTENING.
EXT. WALL SHEATHING SPECIFICATION
ALL EXT. WALLS SHALL BE CONTINUOUSLY SHEATHED
AND ARE CONSIDERED SHEAR WALLS.
ALT. STAPLE CONNECTION SPEC: 1-3/4" 16 GA
STAPLES (7/16" CROWN) @ 3" O.C. AT EDGES & @ 6"
O.C IN FIELD.
AT DESIGNATED AREAS - FASTEN PANEL EDGES OF
WOOD STRUCTURAL WALL SHEATHING TO FRAMING
w/ 2-3/8"x0.113" NAILS @ 3" o.c. AND 12" o.c. IN THE
PANEL FIELD. NO STAPLE ALTERNATIVE AVAILABLE AT
THIS SPEC. ALL SHEATHING PANELS SHALL BE
ORIENTED VERTICALLY (LONG DIRECTION PARALLEL
TO STUD) AND INSTALLED FULL HEIGHT OF SHEAR
WALL - OR - 2x HORIZONTAL BLOCKING SHALL BE
PROVIDED TO SUPPORT UNSUPPORTED PANEL EDGES
AND 3" O.C. EDGE FASTENING.
DESIGN ASSUMES 16" O.C MAX. STUD SPACING,
U.N.O.
INDICATES HOLDOWN
INDICATES EXTENT OF INT. OSB
SHEARWALL AND/OR 3" O.C. EDGE
NAILING
INDICATES POST ABOVE (P.A.) PROVIDE
SOLID BLOCKING UNDER POST OR JAMB
ABOVE.
CONNECTION SPECIFICATIONS (TYP. U.N.O.)
JOIST TO SOLE PLATE (3)10d TOENAILS
SOLE PLATE TO JOIST/BLK'G. 10d NAILS @ 6" o.c.
STUD TO SOLE PLATE (3)10d TOENAILS
BLK'G. BTWN. JOISTS TO TOP PL. (3)10d TOENAILS
RIM TO TOP PLATE 10d TOENAILS @ 6" o.c.
RAFTER/TRUSS TO TOP PLATE (3)10d TOENAILS + (1) SIMPSON
H2.5A
TOP OR SOLE PLATE TO STUD (3)10d NAILS
DOUBLE STUD 10d NAILS @ 24" o.c.
DOUBLE TOP PLATE 10d NAILS @ 24" o.c.
DOUBLE TOP PLATE LAP SPLICE (10)10d NAILS IN LAPPED AREA
TOP PLATE LAP @ CORNERS & (2)10d NAILS
INTERSECTING WALLS
WALL TO FOUNDATION WALL SHTG. LAP w/ SILL PL. &
FASTENED PER SHEAR WALL
FASTENING SPEC.
NOTE: 10d NAIL = 3" x 0.131" GUN NAIL
GAB. END TRUSS TO DBL. TOP PL. 10d TOENAILS @ 8" o.c.
R.T. w/ HEEL HT. 9 14" TO 12" 2x10 BLK EVERY 3RD BAY
FASTENED TO DBL. TOP PLATE w/
10d TOENAILS @ 6" O.C.
R.T. w/ HEEL HT. UP TO 24" LAP WALL SHTG. w/ DBL. TOP PL.
& INSTALL ON TRUSS VERT. -
FASTEN w/ 8d NAILS @ 6" O.C.
R.T. w/ HEEL HT. 24" TO 48" LAP WALL SHTG. w/ DBL. TOP PL.
& INSTALL ON TRUSS VERT. -
FASTEN w/ 8d NAILS @ 6" O.C.
PROVIDE 2x BLK @ EA. BAY AT
TOP OF HEEL
R.T. w/ HEEL HT. 12" TO 16" 2x12 BLK EVERY 3RD BAY
FASTENED TO DBL. TOP PLATE w/
10d TOENAILS @ 6" O.C.
LUCERNE
UNIT B
ZURICH
UNIT A
03/03/23