HomeMy WebLinkAbout3D Company, Inc/ENG/CO #2/106th and College Ave RAB DocuSign Envelope ID:A05EB794-4E8D-4CBB-BD32-DEE1134F9112
(
APPROVED
By Jon Oberlander at 9:45 am,Apr 13,2023
City of Carmel Project 20-ENG-02
Intersection Improvements : 106th Street
and College Avenue Roundabout
CHANGE ORDER #2
Pay item is being created for the demolition of the existing structure on the northwest corner of the
new roundabout. The cost includes all demolition and removal of existing structure, utility disconnects,
asbestos reports, backfill, dump fees, labor and equipment. There is no time extension for this work.
Pay item 0037 is not used on project so quantity being adjusted.
Contract Price prior to this Change Order $3,759,360.21
Contract Price will be changed by this Change Order $21,026.40
New Contract Price including this Change Order $3,780,396.6 I
Amount Adjusted Contract Cumulative%Change
Price from Original Contract
Original Contract $3,660,000.00 N/A N/A
CO1 $99,360.21 $3,759.360.21 2.71%
CO2 $21,026.40 $3,780,396.61 3.29%
DocuSign Envelope ID:A05EB794-4E8D-4CBB-BD32-DEE1134F9112
CITY OF CARMEL
TO: Jeremy Kashman CONTRACT CHANGE ORDER NO.: 2
City Engineer DATE: April 12, 2023
City of Carmel Indiana PROJECT NAME: 106th and College Ave RAB
One Civic Square CITY REQ. NO.:
Carmel, IN 46032 CITY PO NO.: 20-ENG-02
CITY PO DATE:
I. You are directed to make the following changes in this Contract:
Pay item is being created for the demolition of the existing structure on the northwest corner fo the
new roundabout at 106th Street and College Avenue. The cost includes all demolition and removal of
existing structure, utility disconnects,asbestos report, backfill, dump fees, labor and equipment. There
is no time extension for this work. Pay item 0037 being deleted from contract since not used.
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+)OR(-)DAYS
II. The following referenced Documents further describe the changes outlined in Paragraph I,
and are to be considered a part of this Change Order: R.F.P.: N/A W.D.C.NO.: N/A
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $ 3,759,360.21
Contract Price will be increased by this Change Order $ 21,026.40
New Contract Price including this Change Order $ 3,780,386.61
Contract Time prior to this Change Order Days Closure 12/2/2022 Substantial Completion Date
Contract Time prior to this Change Order 1/3/2023 Final Completion Date
Net increased/decreased resulting from this Change Order 0 Days
Current Contract Time including this Change Order Days Closure 12/2/2022 Substantial Completion Date
Current Contract Time including this Change Order 1/3/2023 Final Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are The Above Changes Are Accepted Approved
Recommended DocuSigned by:
American Structurepoint,Inc. 3D Company,Inc. C wi
ENGINEER CONTRACTOR yilbbr ibugasi..
James Brainard,Mayor
9025 River Road,Suite 200 7240 North State Road 3
eA,l nV
Address Address t''
"h4 �ttin Burke, Member
by
Indianapolis,IN 46240 Muncie,IN 47303 IU„hnu,.
City/State/Zip City/State/Zip `LtS911"PV°ftson, Member
Deanna D. ' .7-:'rzno—
Je y K shman,pE,City Engineer
By: T ar.Ard�y iz By: Case
"—DocuSigned by:
ATTEST:
Phone: 317-281-9563 Phone:7 Sic (AMC
65-288-3326 ro
s iasaaac;o...
Sue Wolfgang,a u°l�erc
4/19/2023
Date: 04-12-2023 Date: 4/12/2023 Date:
DocuSign Envelope ID:A05EB794-4E8D-4CBB-BD32-DEE1134F9112
in
°■ 5TRUCTUREP01N7
American Structurepoint, Inc,
■ Change Order Details
20-ENG-02 - 106th and College RAB
Description intersection improvements at 106th Street and College Avenue will consist of replacing a signalized intersection with a roundabout. The
reconstruction of the intersection will include new full-depth pavement,curb and gutter, enclosed storm water network,lighting,and shared-use
paths with new curb ramps and raised crosswalks.
Prime Contractor 31)Company,Inc
Muncie
Change Order 2
Status Pending
Date Created 04/12/2023
Type Owner Requested Change
Summary Change Order 42
Change Order Description Pay item is being created for the demolition of the existing structure on the northwest corner of the new roundabout. The cost includes all
demolition and removal of existing structure, utility disconnects, asbestos reports, hacklll, dump fees, labor and equipment. There is no time
extension for this work.
Awarded Project Amount S3,660,000.UU
Authorized Project Amount S3,759,360.2I
Change Order Amount S21,026.40
Revised Project Amount S3,7811,386.61
Change Order Details: 04/12/2023
20-ENG-02-106th and College RAB Page 1 of 2
DocuSign Envelope ID:A05EB794-4E8D-4CBB-BD32-DEE1134F9112
Increases/Decreases
Line Number Item ID Unit Unit Price Current Change Revised
Quantity Amount Quantity Amount Quantity Amount
Section: 1 -Description
0037 503-05240 LFT $11.000 176.000 81,936.00 -176.000 -$1,936.00 0.000 .5U Illl
D-1 CONTRACTION JOINT
Reason: Not used on contract.
1 item Totals $1,936.00 -$1,936.00 S0.00
New Items
Line Number Item ID Unit Quantity Unit Price Extension
Section: 1 -Description
0167 202-05668 LS 1.000 $22,962.400 S22,962.40
DEMOLITION
Reason: Existing structure on NW Quadrant of RAB
l item Total: S22,962.40
Change Order Details: 04/12/2023
20-ENG-02- 106th and College RAB Page 2 of 2
DocuSign Envelope ID:A05EB794-4E8D-4CBB-BD32-DEE1134F9112
From: Maghala, Dave
To: "Seth Blalock;Ogg,Chris
Cc: Don Case; Deanna Case;ChrisRhodesMuncie@omail.com
Subject: RE: Existing Building Demo
Date: Tuesday,April 11, 2023 3:37:00 PM
Attachments: im.ge001.pnq
image002.onq
image003.pnq
image004.onq
im•ge005.onq
image006.pnq
image007.pnq
Seth,
The City of Carmel is approving the cost for the building demo submitted by Deanna Case on March
2, 2023 in the amount of$22,962.40. There will be no additional days added to the contract for the
closure period for this work. 3D is reminded to protect all newly constructed road items (path, curb,
etc.) as repairs to any items will not be reimbursed by the City of Carmel. A new pay item for this
building demo will be created on CO/12 to be drafted in the coming weeks—my target would be
before the end of April.
Thanks,
David
David Machala RI r
Resident Project Representative
■ STRUCTUREPUINT
. CELL •
WEB
0 0 0 0 Best Places to Work in Indiana
0 •r JAW Best Employers in Ohio
From: Seth Blalock<sblalock@3dcompanyinc.com>
Sent: Friday, April 7, 2023 8:11 PM
To: Machala, Dave<DMachala@structurepoint.com>; Ogg, Chris <cogg@carmel.in.gov>
Cc: Don Case<Don@3dcompanyinc.com>; Deanna Case <dcase@3dcompanyinc.com>;
ChrisRhodesMuncie@gmail.com
Subject: Existing Building Demo
EXTERNAL EMAIL: Do not click any links or open any attachments unless you trust the
sender and know the content is safe!