Loading...
HomeMy WebLinkAboutHoward Asphalt, LLC/STREET/$77,625/CO #3/23-STR-01 DocuSign Envelope ID:0E78FDE3-E214-4C63-913E-41C321B83C9F City of Carmel Project 23-S TR-01 Paving -APPROVED Program ` Se geyGrechukhln at 11:23 am,May 04,2023 Change Order #3 — Plunge Mill Line Item Change Order# 3 is an additional plunge mill line item. Contract Price prior to this Change Order $ 3,685,093.16 Contract Price will be increased/decreased by this Change Order $ 77,625.00 New Contract Price including this Change Order $ 3,762,718.16 Adjusted Contract Cumulative Amount Price Change from Original Contract Original Contract $ 3,641,478.16 N/A Additional MOT for $ 15,070.00 $ 3,656,548.16 0.41 % CC&T Additional Concrete $ 28,545.00 $ 3,685,093.16 1.20 % Drive Line Items Additional Plunge Mill $ 77,625.00 $ 3,762,718.16 3.33 % Line Item DocuSign Envelope ID:0E78FDE3-E214-4C63-913E-41 C321 B83C9F CITY OF CARMEL TO: CONTRACT CHANGE ORDER NO.: 3 DATE: 04/26/23 PROJECT NAME: 23-STR-01 Paving Program CITY REQ. NO.: N/A CITY PO NO.: 108575 CITY PO DATE: 03/02/2023 L You are directed to make the following changes in this Contract: Change Order#3 is an additional plunge mill line item SCHEDULED ADJUSTMENT ITEM AMOUNT (+) OR (-)DAYS Additional Plunge Mill Line Item $ 77,625.00 +2 II. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: R.F.P.: N/A W.D.C. No.: N/A Other: See attached proposals The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order $_3,685,093.16 Contract Price will be increased/decreased by this Change Order $ 77,625.00 New Contract Price including this Change Order $_3,762,718.16 Contract Time Prior to this Change Order N/A Days N/A Completion Date Net increased/decreased resulting from this Change Order +2 Days Current Contract Time including this Change Order 126 Days 8/09/23 Completion Date This Change Order is for full and final settlement of all direct,indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. Version 2016-08-31 DocuSign Envelope ID:0E78FDE3-E214-4C63-913E-41 C321 B83C9F City of Carmel Howard Asphalt LLC DomSigned by: �.. 9/2b6bS21UUb431,.. STREET CONTRACTOR James Brainard, Mayor 1 Civic Square 2916 Kentucky Ave CDomSigned by: aww 1d, btS/l.UWbbt4l.4.. Address Address Mary Ann Burke, Member Carmel, IN 46023 Indianapolis, IN 46221 Docusignetlby: Eavi Mow tll;UL13b ICLb ... City/State/Zip City/State/Zip Lon Wa4tso4UUn, Member Matt Higginbotham, Commissioner, Street Department By: M 7V�i eFei Matt Higgi .tham Phone: 317-733-2001 Phone: 317-849-9666 L6" i'L T°y: Date: 04/26/2023 Date: ` wg vcro `eoa o e, ya4 w_. Sue Wolfgang, Clerk Date: 5717/2023 Version 2016-08-31 DocuSign Envelope ID:0E78FDE3-E214-4C63-913E-41C321B83C9F I.IOIdhIARD 2916 Kentucky Avenue Indianapolis, Indiana 46221 COMPANIESwww.HowardCompanies.com REQUEST FOR CHANGEdiE S A Project: 23-STR-01 Paving Program Address: Carmel, Indiana RFC# 3 Date: 4/25/2023 Owner/Contractor: City of Carmel -Street Department Project# 23-1161 Submitted To: Matt Higginbotham PO# 108575 Title: Street Commissioner The following change(s) in scope and price are formally requested: ITEM DESCRIPTION AMOUNT 1 Addition of 1,500 sys of 6" Plunge Mill on Main Street(City of Carmel request) Request to add Line Item #29 -6" Plunge Mill/Fill - 25mm Base 1,500 sys @ $51.75/sys $ 77,625.00 Total Requested Reason for RFC: Owner/Contractor Requested Change: $ 77,625.00 Additional Day(s) Required: 2 Attachments? 0 Yes Submitted By: Approved By: Mike Parrish NAME SIGNATURE DATE Sr. Project Manager TITLE PRINTED TITLE All terms and conditions of the original contract apply to and govern this Request for Change. *In lieu of issuing a formal change order to Howard Companies as a response to this request,you may have an authorized representative of your company sign,date,and return this request. 1