Blanchard, Jim E
From: Hollibaugh, Mike P
Sent: Tuesday, August 22, 2006 8:12 PM
To: Charlie Frankenberger
Subject: RE: Fidelity on Meridian
I
thanks Charlie for the note. interesting about mccomas. if DOCS or the City is the primary cause of the I
construction hold up, let me first apologize for any inconvenience or dismay cause by the delay...then, since the
situation is not fully of your own cause or control, I would say that continuous constuction has commenced and I
that your zoning approvals are not in jeopardy. Finally, I will ask for the permit to be issued tomorrow, and follow-
up with Gary to get whatever outstanding comments to you. I figure we can work through the engineering issues
concurrent with construction.
From: Charlie Frankenberger [mailto:chalie@NF-LAW.COM]
Sent: Tue 8/22/2006 5:05 PM
To: Hollibaugh, Mike P
Subject: Fidelity on Meridian--docket nos. 05040003 DP/ADLS, 05040004 ZW, 0504005 ZW, and Variances
05050037 thru 42
Hi Mike,
I have a couple of questions, but first I need to relay to you the following context.
Approvals were obtained on 6/25/05 and, because construction had not commenced, John Robinson
requested and you granted a 6 month extension. Since then, the existing Sunrise building was demolished, but
the construction contractor, Zeller Construction and Development (Bruce Zeller), has been delayed in obtaining a
building permit. John Robinson relays to me that the delay is caused by the disappearance of their I
architect/owner's representative. Apparently, after the DP/ADLS, zoning waivers, and developmental variances
were obtained, the architect/owner's rep left for a job in Chicago and "dropped the ball". This was not '
discovered until Bruce Zeller became involved and attempted 10 obtain a building permit, only to learn that there
were many outstanding technical/construction matters. Bruce has succeeded in clearing most of these issues,
but has been waiting for communication from the engineering department.
My questions are twofold. First, I wanted to confirm with you that the demolition of the building, and the
subsequent attempts to obtain a building permit, constitute the commencement of continuous construction,
obviating the need for another ex1ension; if not, we may need to ask the BZA for a variance extending the time.
Please let me know. Once the building permit is obtained, they will immediately continue with the physical
process of development and building. They are very anxious to get going, and somewhat distraught over the
situation.
Second, I wanted to know whether you thought there was anything we might diplomatically do to get feedback
from the engineering department. I could call and inquire, but I know that they are very busy, making prompt t
replies somewhat difficult. Perhaps we could be placed on the T AC agenda for 9/20, but they really do not want
to wait that long. I am just brain stormlng--they are very anxious to get this redevelopment completed. '
Any thoughts you may have would be helpful. Thanks.
8/28/2006
Page 1 of1
Lillard, Sarah N
From: Brewer, Scott I
Sent: Wednesday, August 23, 2006 2:40 PM
To: 'Charlie Frankenberger'
Cc: Hollibaugh, Mike P; Griffin, Matt L; Lillard, Sarah N
Subject: Fidelity
Charlie:
I talked to Bruce Zeller the builder for Fidelity this afternoon. He is going to bring in 4 copies of the landscape
plan for me to sign tomorrow morning and a check for the missing trees, and I will get everything to Sarah Lillard:
tomorrow. '
I also believe that Mr. Zellers issues with Engineering were resolved today as well.
I think that will take care of things.
Scott Brewer, City Forester
Environmental Planner, DOCS
City of Carmel,
One Civic Square
Carmel, IN 46032
PH: 317-571-2478
FAX: 317-571-2426
8/23/2006
Brewer, Scott I
From:
Sent:
To:
Cc:
Subject:
Brewer, Scott I
Wednesday, July 12, 2006 4:36 PM
'ZELLER'
Griffin, Matt L; Holmes, Christine B; Lillard, Sarah N
FW: 05-110 Fidelity Center
Attachments:
image001.jpg; 05-11 0.C8.0.LP.dwg; Recommended Trees doc
.
~
~j~
9
imageOO1.jpg (13
KB)
05-110.C8.0.LP.dw Recommended
9 (1 MB) Trees.doc (52 KB)
Dear
Kathy:
,
afternoon and told him I would forward my emails with Chris McComas
arrangements that were made for Fidelity on Meridian for the I
I
I
The plan is missing 11 shade trees and 6 ornamental trees. Chris McComas valued the ~hade
trees at $381.25 and the ornamental trees at $227. That total would be $5558.75. The
check can be made out to the Carmel Urban Forestry Fund.
I
The substitution for the globe maple should be from the attached recommended Street Tree
List, or sugar maple (Acer saccharum) is ok as well. If you want to have your landsc~per
look at the list to recommend a species to you, or he can call me. If you want to make
the substitution commitment in a letter form, just address it to me. '
I spoke to Bruce this
to him concerning the
landscape plans.
Please call or email if there are any questions, please submit four copies of the
landscape plan with all of the same required information as the previous plan to me.
Scott Brewer, City Forester
Environmental Planner, DOCS
City of Carmel,
One Civic Square
Carmel, IN 46032
PH: 317-571-2478
FAX: 317-571-2426
-----Original Message-----
From: Chris McComas [mailto:cmccomas@advocati.us]
Sent: Wednesday, June 08, 2005 8:58 AM
To: Brewer, Scott 1
Subject: FW: 05-110 Fidelity Center
Scott,
Does this help?
Thanks
Chris McComas
-----Original Message--~--
From: "Oarci pellom" <dpellom@Civil-Oesigns.com>
Sent: 6/7/05 5:30:52 PM
To: "Chris McComas" <cmccomas@advocati.us>
Subject: RE: 05-110 Fidelity Center
Chris,
Attached is an AutoCAO drawing with the latest changes in the landscape plan.
1.
I changed the trees on the north to the Magnolia trees.
2. Lake County Nursery in Perry Ohio began carrying this tree is Fall of 1999 and J.
Frank Schmidt & Son Co. in Boring, Oregon also carries them.
Some information found off the internet about these trees.
Deciduous tree, 15 ft (4.5 m) high, with 18 it (5.5 m) spread, very denseiy
branched, compact, formal globe ("lollipop") habit. Often grafted on a standard. Leaves
sharply and acutely dentate, red-brown in spring, developing to medium green, and yellow
in fall.
-Zone 4 Introduced in 1873 by Van Houtte.
I will ernail the information about these trees to Scott Brewer.
3.
We are short 11 shade trees and 6 ornamental trees
11
Shade Trees 2-1/2" cal. $381.25 each = $4193.75
6
Ornamental Trees 2" cal. $227.50 each = $1365.00
Total
$5558.75
If you need anything else, please let me know.
Thanks
Darci pellom
Civil Designs
2415 Director's Row, Suite E
Indianapolis, IN 46241
phone: (317)244-1968
fax: (317)244-1969
email: dpellom@civil-designs.com
2
-----Original Message-----
From: Chris McComas [mailto:cmccomas@advocati.us]
Sent: Friday, June 03, 2005 9:51 AM
To: Darci Pellom
Cc: Charlie Frankenberger; jrobinson@mresonline.com
Subject: RE: 05-110 Fidelity Center
Darci,
I met with the Urban Forester on Wednesday and he will approve our plan based on the
following:
1. He would like the tress at the end of the walk to the adjacent building to the
north changed to a Ginko or Magnolia.
2. He would like to get some information for his file on Globe maples
3. For the trees we can not plant to meet the requirements he would like us to make a
donation to the Urban street tree fund in the amount of the value of the trees. He wbuld
like us to corne up with a number based on the following: 1. cost of the tree 2. east to
plant and 3 cost for the one year warranty. Can you give me an idea of this cost?
Thanks
Christopher S. McComas, NCARS, CS1, CCS
Advocati, lIe
Bringing focus to inspiration.
5140 North Park Ave.
Indianapolis, IN 46205
(317) 430-3504
FAX (800) 865-6310
cmccomas@advocati.us
www.advocati.us
--~--Original Message~~---
From: Darci Pellom [mailto:dpellom@Civil~Designs.comJ
Sent: Thursday, May 19, 2005 1:00 PM
To: Chris McComas
Subject: RE: 05-110 Fidelity Center
Chris,
I left Scott and message this morning.
3
We can do two renderings for you. We won't be able to showing damaged or diseased tree in
the rendering so I suggest we can some photos showing the existing landscaping and either
print them in a book or do a computer slideshow.
It probably will be mid next week before we can get those to you.
a problem and I will see what I can do.
Let me know if that is
Thanks
Darci pellom
Civil Designs
2415 Director's Row, Suite E
Indianapolis, IN 46241
phone: (317)244-1968
fax: (317)244-1969
email: dpellom@civil-designs.com
-----Original Message-----
From: Chris McComas [mailto:cmccomas@advocati.us]
Sent: Tuesday, May 17, 2005 7:55 PM
To: Darci Pellom
Cc: jrobinson@mresonline.com; Charlie Frankenberger; Aaron Hurt
Subject: RE: 05-110 Fidelity Center
Darci,
Can you please see if you can get a hold of the Carmel Urban Forester and see if he has
completed his review. We were before the plan commission tonight and the fact that we can
not provide all the trees required has become an issue that we need to bring to closure.
Can you also do a quick color rendering of the existing landscaping vs. the proposed.
Time is of the essence. Let me know if you have any questions and thanks for your help.
Christopher S. McComas, NCARB, CSI, CCS
Advocati, llc
Bringing focus to inspiration.
5140 North Park Ave.
Indianapolis, IN 46205
(317) 430-3504
FAX (800) 865-6310
cmccornas@advocati.us
4
www.advocati.us
-----Original Message-----
From: Darci Pellom [mailto:dpellom@Civil-Designs.com]
Sent: Wednesday, March 30, 2005 8:06 AM
To: cmccomas@advocati.us
Subject: 05-110 Fidelity Center
Chris,
Attached is a 11 x 17 POF and an AutoCAD file for the landscape plan for this project..
Let me know if you need anything else.
Thank you
Darci Pellom
Graduate Landscape Architect
Civil Designs
2415 Director's Row, Suite E
Indianapolis, IN 46241
phone: (317)244-1968
fax: (317)244-1969
email: dpellom@civil-designs.com
5
Page 1 of 1
Lillard, Sarah N
From: Brewer, Scott I
Sent: Tuesday, July 11,20064:21 PM
To: 'ZELLER'
Cc: Griffin, Matt L; Lillard, Sarah N
Subject: RE: Fidelity on Meridian - Landscape Plans
Dear Kathy:
I need to do some research in our records, because negotiations about this plan where suddenly halted last year
without any indication why. The plan is short trees, and certain numbers are required, or alternatives committed
to, and the final conditions were not completed at the time. I was not at the approval meeting, so I need to check
on what is required. If the Plan Commission, did not have all the information, or imposed certain conditions, ,
need to check on what they did.
Scott Brewer, City Forester
Environmental Planner, DOCS
City of Carmel,
One Civic Square
Carmel, IN 46032
PH: 317-571-2478
FAX: 317-571-2426
From: ZELLER [mailto:forzellers@sbcglobal.net]
Sent: Monday, July 10, 2006 3:28 PM
To: Brewer, Scott I
Subject: Fidelity on Meridian - Landscape Plans
I dropped off drawings to your office today in regards to Fidelity on Meridain - 4 sets of the landscape
plans. Please let me know if you need anythng else.
Thanks,
Kathy Zeller
Zeller Construction & Development, LLC.
(317) 843-9394
FAX (317) 843-9381
F orZellers@sbcglobal.net
7/13/2006
Page 1 of2
Lillard, Sarah N
From: Hoyt, Gary A
Sent: Monday, July 10, 2006 12:08 PM
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Blanchard, Jim E; Brewer, Scott I; Dolan, Veronica
A; Akers, William P; 'grh@co.hamilton.in.us'; 'rct@co.hamiiton.in.us'; 'Ryan.hartman@ctrwd.org';
'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R; Redden, Nick
Cc: 'Forzellers@sbcglobal.net'
Subject: RE: Pre-Submittal for Fidelity on Meridian Bldg.
The fire department requested a Knox box and FOC caps for this project. Knox:
products may be purchased online at www.knoxbox.com
Gary Hoyt
CFO
From: Lillard, Sarah N
Sent: Monday, July 10, 2006 12:09 PM
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I; Dolan,
Veronica A; Akers, William P; 'grh@co.hamilton.in.us'; 'rct@co.hamilton.in.us'; 'Ryan.hartman@ctrwd.org';
'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R; Redden, Nick
Cc: 'Forzellers@sbcglobal.net'
Subject: Pre-Submittal for Fidelity on Meridian Bldg.
The Dept. of Community Service, Building & Code Enforcement division, has
received a request to schedule a pre-submittal meeting for the purpose of
obtaining a building permit. PLEASE "REPLY TO A~L" WITHIN 48 HOURS, IF
YOU HAVE OUTSTANDING ISSUES. After that time, we may proceed with the
meeting and submittal.
Project:
FIDELITY ON MERIDIAN Bldg.
11450 Meridian St. N. (?)
Meeting Date:
PENDING
Time:
PENDING
Related Planning & Zoning docket numbers:
05040003 DP/ADLS; 05050037 DSV Other (lot coverage); 05050038 DSV
Other (signage); 05050039 DSV Other (sign age); 05050040 DSV Other
(usage); 05050041 DSV Other (landscape); 05050042 DSV Other (site
access/parking);
7/11/2006
I
Page 1 of2
Lillard, Sarah N
From: Ryan Hartman [Ryan.Hartman@CTRWD.ORG]
Sent: Monday, July 10, 2006 2:33 PM
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I;
Dolan, Veronica A; Akers, William P; grh@co.hamilton.in.us; rct@co.hamilton.in.us;
mbm@co.hamilton.in.us; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R; Redden, Nick
Cc: Forzellers@sbcglobal.net
Subject: RE: Pre-Submittal for Fidelity on Meridian Bldg.
Sarah,
We are still waiting for invoice #2100, sent out on 1/19/2006, to be paid. Once paid, we can schedule a
preconstruct ion meeting.
Thank you.
Ryan
From: Lillard, Sarah N [mailto:SLillard@carmel.in.gov]
Sent: Monday, July 10, 2006 12:09 PM
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I; Dolan,
Veronica A; Akers, William P; grh@co.hamilton.in.us; rct@co.hamilton.in,us; Ryan Hartman;
mbm@co.hamilton.in.us; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R; Redden, Nick
Cc: Forzellers@sbcglobal.net
Subject: Pre-Submittal for Fidelity on Meridian Bldg.
The Dept. of Community Service, Building & Code Enforcement division, has
received a request to schedule a pre-submittal meeting for the purpose of
obtaining a building permit. PLEASE uRI;~"'-YTO _l'J-t" WITHIN 48 HOURS. IF
YOU HAVE OUTSTANDING ISSUES. After that time, we may proceed with the
meeting and submittal.
Project:
FIDELITY ON MERIDIAN Bldg.
11450 Meridian St. N. (1)
Meeting Date:
PENDING
Time:
PENDING
Related Planning & Zoning docket numbers:
05040003 DP/ADLSj 05050037 DSV Other (lot coverage); 05050038 DSV
Other (signage)j 05050039 DSV Other (signage)j 05050040 DSV Other
(usage); 05050041 DSV Other (landscape); 05050042 DSV Other (site
access/parking);
7/11/2006
Page 1 0[2
Lillard, Sarah N
From: Duncan, Gary R
Monday, July 10, 20061 :21 PM
Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I;
Dolan, Veronica A; Akers, William P; 'grh@co.hamllton.in.us'; 'rct@co.hamilton.in.us';
'Ryan.hartman@ctrwd.org'; 'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Matt L; Redden,
Nick
Cc: 'Forzellers@sbcglobal.nel'
Subject: RE: Pre-Submittal for Fidelity on Meridian Bldg.
Sent:
To:
If this is the project that was called the Fidelity Center, Engineering issued a letter on June 10 stating that they
had received no response to the comments issued at the April TAC meeting.
Thanks so much,
Gary
-----Original Message-----
From: Lillard, Sarah N
Sent: Monday, July 10, 2006 12:09
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I; Dolan,
Veronica A; Akers, William P; 'grh@co.hamilton.in.us'; 'rct@co.hamilton.in,us'; 'Ryan.hartman@ctrwd.org';
'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R; Redden, Nick
Cc: 'Forzellers@sbcglobal.net'
Subject: Pre-Submittal for Fidelity on Meridian Bldg.
The Dept. of Community Service, Building & Code Enforcement division, has
received a request to schedule a pre-submittal meeting for the purpose of
obtaining a building permit. PLEASE "REPLY TO ALL" WITHIN 48 HOURS. IF
YOU HAVE OUTSTANDING ISSUES. After that time, we may proceed with the
meeting and submittal.
Project:
FIDELITY ON MERIDIAN Bldg.
11450 Meridian St. N. (?)
Meeting Date:
PENDING
Time:
PENDING
Related Planning & Zoning docket numbers:
05040003 DP/ADLSj 05050037 DSV Other (lot coverage); 05050038 DSV
Other (signage); 05050039 DSV Other (signage)j 05050040 DSV Other
(usage); 05050041 DSV Other (landscape); 05050042 DSV Other (site
access/parking)j
7/11/2006
Page I of2
Lillard, Sarah N
From:
Sent:
To:
Duncan, Gary R
Tuesday, July 11, 2006 9:59 AM
'ZELLER'
Cc: Lillard, Sarah N
Subject: RE: Pre-Submittal for Fidelity on Meridian Bldg.
April TAC meeting referenced in this email. Any info on this would be helpful. Thanks' Bruce
"Duncan, Gary R" <gduncan@Carmel.in.gov> wrote:
If this is the project that was called the Fidelity Center, Engineering issued a letter on June 10 stating that
they had received no response to the comments issued at the April TAC meeting.
Bruce,
I apologize, but we are struggling to find any documentation of this project having been reviewed. I am
trying to establish where this project is located and when it was reviewed so we can check status of any
comments having been addressed. Did the project change names? Do you have drainage approval and
approved construction drawings from Engineering? Have any and all Board of Public Works and Safety
approvals been obtained and any outstanding fees paid and performance guarantees been posted?
Thanks so much,
Gary
-----Original Message-----
From: ZELLER [mailto:forzellers@sbcglobal.net]
Sent: Tuesday, July 11, 2006 10:53
To: Duncan, Gary R
Subject: Pre-Submittal for Fidelity on Meridian Bldg.
Thanks so much,
Gary
-----Original Message-----
From: Lillard, Sarah N
Sent: Monday, July 10, 2006 12:09
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I;
Dolan, Veronica A; Akers, William P; 'grh@co.hamilton.in.us'; 'rct@co.hamilton.in.us';
'Ryan.hartman@ctrwd.org'; 'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R;
Redden, Nick
Cc: 'Forzellers@sbcglobal.net'
Subject: Pre-Submittal for Fidelity on Meridian Bldg.
The Dept. of Community Service, Building & Code Enforcement division, has
received a request to schedule a pre-submittal meeting for the purpose of
obtaining a building permit. PLEASE "REPLY TO ALL" WITHIN 48
HOURS, IF YOU HAVE OUTSTANDING ISSUES. After that time, we may
7/11/2006
r
Page 1 of2
Lillard, Sarah N
From: Griffin, Matt L
Thursday, July 13, 2006 8:28 AM
Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scotti;
Dolan, Veronica A; Akers, William P; 'grh@co.hamilton.in.us'; 'rct@co.hamilton.in.us';
'Ryan.hartman@ctrwd.org'; 'mbm@co.hamilton.in.us'; Foley, Amanda J; Duncan, Gary R; Redden,
Nick
Cc; 'Forzellers@sbcglobal.net'
Subject: RE: Pre-Submittal for Fidelity on Meridian Bldg.
Sent:
To:
DOCS will need to approve elevations (we require 3 sets to be submitted).
Matthew L. Griffin, AICP
Planning Administrator
Department of Community Services
City of Carmel
One Civic Square
Carmel, IN 46032
phone: 317.571.2417
fax: 317.571.2426
email: mariffinavcarmel.in.gQ.Y.
From: Lillard, Sarah N
Sent: Monday, July 10, 2006 12:09 PM
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I; Dolan,
Veronica A; Akers, William P; 'grh@co.hamilton.in.us'; 'rct@co,hamilton.in.us'; 'Ryan.hartman@ctrwd.org';
'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Matt L; Duncan, Gary R; Redden, Nick
Cc: 'Forzellers@sbcglobal.net'
Subject: Pre-Submittal for Fidelity on Meridian Bldg.
The Dept. of Community Service, Building & Code Enforcement division, has
received a request to schedule a pre-submittal meeting for the purpose of
obtaining a building permit. PLEASE "REPLY TO ALL" WITHIN 48 HOURS, IF
YOU HAVE OUTSTANDING ISSUES. After that time, we may proceed with the
meeting and submittal.
Project:
FIDELITY ON MERIDIAN Bldg.
11450 Meridian St. N. (?)
Meeting Date:
PENDING
Time:
PENDING
Related Planning & Zoning docket numbers:
05040003 DP/ADLSj 05050037 DSV Other (lot coverage); 05050038 DSV
Other (signage); 05050039 DSV Other (signage)j 05050040 DSV Other
7/13/2006
I
Page 1 of2
Lillard, Sarah N
From: Lillard, Sarah N
Sent: Monday, July 10, 2006 11 :09 AM
To: Lillard, Sarah N; Conn, Angelina V; Hill, Dick B; Hoyt, Gary A; Blanchard, Jim E; Brewer, Scott I;
Dolan, Veronica A; Akers, William P; 'grh@co.hamilton.in.us'; 'rct@co.hamilton.in.us';
'Ryan.hartman@ctrwd.org'; 'mbm@co.hamilton.in.us'; Foley, Amanda J; Griffin, Malt L; Duncan,
Gary R; Redden, Nick
Cc: 'Forzellers@sbcglobal.net'
Subject: Pre-Submiltal for Fidelity on Meridian Bldg.
The Dept. of Community Service, Building & Code Enforcement division, has
received a request to schedule a pre-submittal meeting for the purpose of
obtaining a building permit. PLEASE "REPLY TO ALL" WITHIN 48 HOURS, IF
YOU HAVE OUTSTANDING ISSUES. After that time, we may proceed with the
meeting and submittal.
Project:
FIDELITY ON MERIDIAN Bldg.
11450 Meridian St. N. (?)
Meeting Date:
PENDING
Time:
PENDING
Related Planning & Zoning docket numbers:
05040003 DP/ADLSj 05050037 DSV Other (lot coverage); 05050038 DSV
Other (sign age); 05050039 DSV Other (signage)j 05050040 DSV Other
(usage)j 05050041 DSV Other (landscape); 05050042 DSV Other (site
access/parking);
Representative(s):
Bruce Zellers
Zeller Construction
forzellers@sbcg lobal. net
Ph. (317) 557-3218
Again, if there are concerns that might affect the issuance of this permit,
please REPLY TO ALL on this e-mail.