HomeMy WebLinkAbout06080182 Sewer
"
CLAY TOWNSHIP REGIONAL WASTE DISTRICT
SANITARY SEWER PERMIT
r ] Conditional Permit r x ] Final Permit
INDIVIDUAL LOTS/EXISTING BUILDINGS
Project Title:
Primary
Location:
Townhomes at Guilford bldg 14
Pulte
Owner/Builder:
Lot# 1401
Street address: 773 Ivy Lane
Zip: 46032
City: Carmel
." ---':"':':;-'- -
~--._---....::... ~-- --- .-,
County: Hamilton ~ _ . ~_.. . ~ 0--1
Interceptor Charges Paid:
PRI:
EDU Fee:1650.00
Application fee: 100.00
PLEASE NOTE: .' Installation of building sewer shall be per the specifications of the Clay Township
Regional Waste District (see reverse) and any conditions noted below. All installations shall be inspected by District
personnel during "open trench" phase and before backfilling with stone to six inches above the pipe. NO footing or
foundation drains, or other sources of ground or stormwater, shall be permitted to enter the District's sanitary sewer
system. The District will assume no Iiabilitv for drains which are below the arade level of the nearest I
downstream manhole nor for laterals which are extended beneath drivewavs or sidewalks. The permit holder
(property owner, developer or builder) will be responsible for damages to the District's sewer system. This includes
damages to manholes, castings, manhole lids and the like; caused by construction activity on the building site y.,hich
is the subject of this permit. :
Inspections by the District are MANDATORY and shall be arranged by contacting the District's office at 844-9200
24 hours in advance. All new construction will be placed on biliing six months after connection has been made or
when water is connected, whichever comes first.
g The District reserves the right to inspect all sump pump connections to ensure no illegal
connections have been made.
~I have received a copy of Ordinance No. 9-13-99 and agree to follow all District standards. Building
has a [ ] crawl space r x] slab or [ ] basement that [ ]will be finished with grinder pump installed to
comply with elevation requirements r ]rough-in plumbing with arinder pump installed during construction,
r ] rough-in plumbing only and arinder pump will not be installed during construction, [ ] no plumbing in
the basement. (Please check appropriate box.)
~anholes shall remain accessible at aJI times. If a manhole is buried, it shall be the
builder/homeowner responsibility to correct per District standards.
_Conditional Permit Terms:
r ] NO CONNECTION to the sewer until further notification.
[ ] Certificate oflnsurance must be on file with CTRWD listed as certificate holder.
[ ] 48 hours notice before work starts on manhole core drilling or cuts of active lines
and District inspector must inspect all work before covered.
[ ] All District fees will be paid in full.
[ ] Approval pending Districts review of plans.
[ ] Copies of approved permits from appropriate county or city agencies for work in
the right-of-way road cuts or are required.
[ ] No occupancy until further notification
[ ]
All Conditions have been met and final permit issued
2006.
By signing below, I a,t!?
work done under.this p
/
hat I am familiar with the District's specifications and agree to accept responsibility for all
it.
575-2350
Phone
Candy J. Feltner
Director of Administration & Custo
sv
ervice
Permit issued this 30.h day of August, 2006.
Permit is valid for ONE- YEAR from the date issued.
"
)
Please note chanaes on lateral specification as of Januarv 2006.
Permit valid only with CTRWD seal in red Ink.
Permit-rev.05-0S.06cf