Miser, Craig
From:
Sent:
To:
Miser, Craig
Friday, September 01,20069:00 AM
'Michael Smith'
Subject: RE: Weng addition plan review
Mike..
The request for information was based on the following:
1. On several occasions enclosed sunrooms have been tied into existing roof structures. In these instances
roofing shingles have been nailed into the aluminum panels. I n this case there is a concern about the withdrawal
of roofing nails applied to the roofing panels. If the enclosure in question does not have roofing shingles applied
to it, in any fashion, then this requirement may be waived. The drawings submitted do not detail the specific
method of attachment for the enclosure to the existing structure. If we do not have specific information to the
project we will require information that mayor may not be applicable to the project.
2. Section E3801.2 (Convenience Receptacle Distribution) in the Indiana Residential Code, 2005 Edition,
requires that convenience receptacles shall be provided, per code, in this space.
3. If an addition is provided with heating and/or cooling, all smoke detectors throughout the structure shall meet
the requirements of the Indiana Residential Code, 2005 Edition. Please indicate on the floor plan of the
resubmittal whether or not heating and/or cooling will be provided to the space.
4. Engineered drawings 3 and 4 show details of attaching the structure to a masonry wall or wood framing The
plans submitted for the project indicate that the existing structure is wood frame with a masonry veneer. A
masonry veneer may not be used to support loading. Please submit proper detail for application to a masonry
veneer wall system.
Thank You..
-----Original Message-----
From: Michael Smith [mailto:smith5756@sbcglobal.net]
Sent: Thursday, August 31, 20069:56 AM
To: Miser, Craig
Subject: Re: Weng addition plan review
Craig,
1) This patio room is not getting shingles on the roof.
2) There is no electrical going in this room.
3) There is no heating and cooling in this room
4) Engineered drawings page 3 and 4 shows details for attaching our unitsto walls and
floor.
"Miser, Craig" <cmiser@carmel.in.gov> wrote:
Please provide the following information for plan review.
9/1/2006
.."(:.
Page 2 of2
I
NOTES FOR:
DATE
OPERATOR
06080188 SLDG 1 - PR
TIME NOTE TEXT
2006-08-31 09:20:12 1. Provide documentation regarding
cmiser
Craig Miser
Inspector/Plan Examiner
One Civic Square
Carmel, IN 46032
317-571-2289
cmiser@carmel.in.gov
9/1/2006
uplifting of screws and nails in roof
panels.Uplift requirements must meet 90
mph sustaioned wind loads. Also
provide requirements from shingle
manufacturer.
2. Provide floor plan indicating
location of required electrical
recepticles.
3. Indicate whether structure is to be
provided with heating and or cooling.
4. Provide detail for attaching panel
units to masonry veneer structure.
(Masonr
y veneer shall not be used to support ro
of loading).
Page I of 1
Miser, Craig
From: Michael Smith [smith5756@sbcglobal.net]
Sent: Thursday, August 31,20069:56 AM
To: Miser, Craig
Subject: Re: Weng addition plan review
Craig,
1) This patio room is not getting shingles on the roof.
2) There is no electrical going in this room.
3) There is no heating and cooling in this room
4) Engineered drawings page 3 and 4 shows details for attaching our unitsto walls and floor.
"Miser, Craig" <cmiser@!carmel.in.gov> wrote:
Please provide the following information for plan review.
NOTES FOR: 06080188 BLDG 1 - PR
DATE TIME NOTE TEXT
OPERF.TOR
2006-08-31 09:20:12 1. Provide documentation regarding
uplifting of screws and nails in roof
panels.Uplift requirements must meet 90
mph sustaioned wind loads. Also
provide requirements from shingle
manufacturer.
2. Provide floor plan indicating
location of required electrical
recepticles.
3. Indicate whether structure is to be
provided with heating and or cooling.
4. Provide detail for attaching panel
units to masonry veneer structure.
(Masonr
y veneer shall not be used to support ro
of loading).
Cffilser
Craig Miser
Inspector/Plan Examiner
One Civic Square
Carmel, IN 46032
317-571-2289
cmiser@carmel.in.gov
8/31/2006
ENCOMPASS NOTEPAD - 08/31/06
NOTES FOR: 06080188 BLDG 1 - PR
DATE TIME NOTE TEXT
---------- -------- ----------------------------------------
2006-08-31 09:20:12
1. Provide documentation regarding
uplifting of screws and nails in roof
panels. Uplift requirements must meet 90
mph sustaioned wind loads. Also
provide requirements from shingle
manufacturer.
2. Provide floor plan indicating
location of required electrical
recepticles.
3. Indicate whether structure is to be
provided with heating and or cooling.
4. Provide detail for attaching panel
units to masonry veneer structure.
(Masonr
y veneer shall not be used to support ro
of loading).
TOTAL LINES OF NOTES: 16