HomeMy WebLinkAboutResolution BPW 01-11-24-10/BOND RELEASE/St. Mary & St. Mark Coptic Church/Erosion Control, ROW
To: Board of Public Works Date: January 2, 2024
and Safety
City of Carmel, Indiana Resolution No: BPW-01-11-24-10
From: CITY ENGINEER
Principal: St. Mary & St. Mark Coptic Orthodox Church, INC.
Surety: The Ohio Casualty Insurance Co.
Board Members:
I have conducted final inspection at St. Mary & St. Mark Coptic Orthodox Church for the
following improvements:
ITEM SURETY NUMBER AMOUNT
Erosion Control 69C005305 $85,865.10
Right of Way 69C005306 $13,559.00
The above improvements have been inspected and are acceptable to the City of Carmel. I
recommend acceptance of said improvement, subject to the following conditions:
3-year maintenance guarantees to replace the surety listed above must be submitted to
replace the performance guarantee. The required maintenance guarantee amounts are as
follows:
ITEM AMOUNT
Erosion Control $8,586.51
APPROVED:
_____________________________
Jeremy Kashman, City Engineer
Be it resolved by the board of Public Works and Safety, City of Carmel, Indiana on this
11th day of January 2024, that the performance guarantee for St. Mary & St. Mark Coptic
Orthodox Church listed above is accepted and released by the City of Carmel, Indiana
subject to any conditions listed above.
Signed:_____________________________(Presiding Officer)
_____________________________ (Member)
_____________________________ (Member)
Board of Public Works and Safety
DocuSign Envelope ID: 26D15E17-5C6F-4682-9F06-12E228FB6A23