HomeMy WebLinkAboutChange Orde 7 FINAL/ENG/-$11,000/Calumet Civil/16-ENG-37-116TH DocuSign Envelope ID:399A3E29-3B85-4ACO-BOOD-9EF0F465E732
C i ty of Carmel Project 16-E N G-3 7 APPeROVEDkhn„aaePm,ren+e,zos.
Roundabout Improvements : 116' Street
and Medical Drive at Range Line Road
CHANGE ORDER #7
Change Order#7 is a balancing change order for the final contract cost for Contract I6-ENG-37.
Contract Price prior to this Change Order $5,329,312.55
Contract Price will be changed by this Change Order ($11,000.00)
New Contract Price including this Change Order $5,318,312.55
Amount Adjusted Contract Cumulative%Change
Price from Original Contract
Original Contract $5,439,000.00 N/A N/A
CO1 $0.00 $5,439,000.00 0.0%
CO2 $174.00 $5,439,174.00 0.003%
CO3 $29,196.00 $5,468,370.00 0.5%
C04 $46,020.59 $5,514,390.59 1.4%
C05 $40,867.29 $5,555,257.88 2.1%
C06 ($225,945.33) $5,329,312.55 (2.0%)
C07 ($11,000.00) $5,318,312.55 (2.22%)
DocuSign Envelope ID:399A3E29-3B85-4ACO-BOOD-9EF0F465E732
CITY OF CARMEL
TO: Jeremy Kashman CONTRACT CHANGE ORDER NO.: 7
City Engineer DATE: February 19,2024
City of Carmel Indiana PROJECT NAME: 116th and Range Line RAB
One Civic Square CITY REQ. NO.:
Carmel, IN 46032 CITY PO NO.: 16-ENG-37
CITY PO DATE:
I. You are directed to make the following changes in this Contract:
Change Order#7 will balance the final contract price for Carmel Project No. 16-ENG-37. The
adjustment is to deduct$6,000 for pay item#0156 and deduct$5,000 for Liquidated Damages. Total
deduction equals$11,000. Final contract amount is$5,318,312.55 and matches the final pay estimate
(#19).
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+)OR(-)DAYS
II. The following referenced Documents further describe the changes outlined in Paragraph I,
and are to be considered a part of this Change Order: R.F.P.: N/A W.D.C.NO.: N/A
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $ 5,329,312.55
Contract Price will be decreased by this Change Order $ (11,000.00)
New Contract Price including this Change Order $ 5,318,312.55
Contract Time prior to this Change Order Days 10/16/2022 Substantial Completion Date
Contract Time prior to this Change Order 12/8/2022 Final Completion Date
Net change resulting from this Change Order 0 Calendar Days
Current Contract Time including this Change Order Substantial Completion Date
Current Contract Time including this Change Order Final Completion Date
This Change Order is for full and final settlement of all direct,indirect,impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are The Above Changes Are Accepted Approved
Recommended
American Structurepoint,Inc. Calumet Civil Contractors,Inc. NOT PRESENT
ENGINEER CONTRACTOR Sue Finkam,Mayor
9025 River Road,Suite 200 4898 Fieldstone Drive (aw.(A.,pbt.U,
Address Address Laura Campbell, Member
Indianapolis,IN 46240 Whitestown,IN 46075 F Q S
City/State/Zip City/State/Zip Alan Potasnik,Member
Jer K hman,PE,City Engineer
By: Daozd-leac.loia- By:Sib
ATTEST:
Phone:317-281-9563 Phone: 317-362-1763 cJacti‘Mau,co euinn,City Clerk
3/6/2024
Date:02-19-2024 Date: 02/19/2024 Date: