Project: Bear Creek Addition
HWC Project No. 2015-165
Date: 04/08/20
ITEM NAME: UNIT QUANTITY UNIT COST AMOUNT
EROSION CONTROL MEASURES PERIMETER SILT FENCE LF 4220 1.00$ 4,220.00$
TREE PROTECTION FENCE LF 920 2.00$ 1,840.00$
WETLANDS PROTECTION FENCE LF 1365 2.00$ 2,730.00$
COMPOST/MULCH FILTER TUBE LF 920 2.00$ 1,840.00$
CURB INLET PROTECTION EA 24 130.00$ 3,120.00$
BEEHIVE INLET PROTECTION EA 22 50.00$ 1,100.00$
TEMPORARY SEED AND MULCH SY 34790 0.25$ 8,697.50$
PERMANENT SEED AND MULCH SY 56162 0.50$ 28,081.00$
PERMANENT SEED AND BLANKET SY 13895 1.20$ 16,674.00$
WATER QUALITY MECHANICAL UNIT - AS-10 EA 1 65,000.00$ 65,000.00$
WATER QUALITY MECHANICAL UNIT - AS-4 EA 1 20,000.00$ 20,000.00$
DIVERSION STRUCTURES EA 2 4,500.00$ 9,000.00$
NATIVE/WETLAND LITTORAL POND PLANTINGS EA 7145 6.00$ 42,867.00$
POND AERATORS EA 3 7,500.00$ 22,500.00$
SNOUT HOOD EA 4 700.00$ 2,800.00$
SNOUT SUMPED MANHOLE EA 4 3,200.00$ 12,800.00$
TEMPORARY CONSTRUCTION ENTRANCE SY 333 12.00$ 3,996.00$
CONCRETE WASHOUT EA 1 650.00$ 650.00$
247,915.50$
This Engineer's Estimate is an opinion of probable construction cost made on the basis of Engineer's experience and
represent Engineer's judgement as a qualified professional generally familiar with the industry. However, since Engineer has
no control over the cost of materials, equipement, labor or market conditions, Engineer cannot guarantee that actual
construction cost will not vary from this Engineer's Estimate.
Brandon T. Burke, P.E.
HWC Engineering
EROSION CONTROL - ENGINEERS ESTIMATE
EROSION CONTROL MEASURES SUBTOTAL: