HomeMy WebLinkAboutROW Engineers Estimate 4-8-20Pulte Homes
Project: Bear Creek Addition
HWC Project No. 2015-165
Date: 04/08/20
ITEM NAME: UNIT QUANTITY UNIT COST AMOUNT
LITTE EAGLE CREEK AVE.1.5" HMA SURFACE, 9.5mm TON 62 85.00$ 5,306.90$
ROW IMPROVEMENTS 2.5" HMA INTERMEDIATE, 19.0mm TON 104 75.00$ 7,804.27$
3.5" HMA BASE, 25.0mm TON 146 65.00$ 9,469.18$
2.5" HMA INTERMEDIATE, OG 19.0mm TON 104 75.00$ 7,804.27$
3" HMA BASE, 25.0mm TON 125 65.00$ 8,116.44$
INDOT STABILIZED SUBGRADE, TYPE 1B OR 1C SYD 1004 4.00$ 4,016.00$
1.5" RESURFACE EXISTING PAVEMENT TON 97 85.00$ 8,254.49$
8" DEEP, 3' STONE SHOULDER, #53 STONE TON 59 23.00$ 1,354.96$
2' ROLL CURB & GUTTER LF 128 8.50$ 1,088.00$
ADA RAMPS EA 2 1,500.00$ 3,000.00$
LITTLE EAGLE CREEK AVE PATH - 1.5" HMA SURFACE, 9.5mm TON 69 150.00$ 10,298.75$
/141ST ST PATH PATH - 2.5" HMA INTERMEDIATE, 19.0mm TON 114 110.00$ 12,587.36$
PATH - 6" COMPACTED AGGREGATE #53 TON 275 30.00$ 8,239.00$
PATH - PREPARED SUBGRADE SYD 999 4.00$ 3,994.67$
91,334.29$
This Engineer's Estimate is an opinion of probable construction cost made on the basis of Engineer's experience and
represent Engineer's judgement as a qualified professional generally familiar with the industry. However, since Engineer has
no control over the cost of materials, equipement, labor or market conditions, Engineer cannot guarantee that actual
construction cost will not vary from this Engineer's Estimate.
Brandon T. Burke, P.E.
HWC Engineering
RIGHT-OF-WAY - ENGINEERS ESTIMATE
ROW IMPROVEMENTS SUBTOTAL: