HomeMy WebLinkAboutHartman Field Improvements Full SetE. 126TH STREET HAZEL DELL PARKWAYGRAY ROADE. MAIN STREET
PROJECT SITE
PROJECT SITE
FANNING HOWEY
ASSOCIATES INC.
OWNER ARCHITECT/LANDSCAPE ARCHITECT
THE SKILLMAN CORPORATION
CONSTRUCTION MANAGER
TLF
CIVIL ENGINEER
CARMEL CLAY
SCHOOLS
COVER SHEET
TAC SUBMITTAL
TAC SUBMITTAL
CARMEL HIGH SCHOOL
HARTMAN FIELD IMPROVEMENTS
5201 E. MAIN ST.
CARMEL, INDIANA 46033
LAKEPORTERLAPORTEST. JOSEPHELKHARTLAGRANGESTEUBENDEKALBNOBLEKOSCIUSKOMARSHALL STARKEJASPER
NEWTONPULASKIFULTONWHITLEYALLENADAMS
WELLSHUNTINGTONWABASH MIAMICASSWHITEBENTONCARROL TIPPECANOEWARRENHOWARDGRANTBLACKFORDJAYRANDOLPHDELAWAREMADISON TIPTONCLINTONBOONEHAMILTONHANCOCK HENRYWAYNE
UNIO
NFAYETTERUSHMONTGOMERY FOUNTAINPARKEVERMILLIONVIGOCLAYPUTNAM MORGANHENDRICKS
MARION JOHNSONSHELBYFRANKLINDECATURBARTHOLOMEWBROWNMONROEOWEN
GREENESULLIVANDEARBORNRIPLEYJENNINGS LAWRENCEMARTINORANGE WASHINGTONSCOTTJEFFERSON SWITZ
E
R
L
AND
OHIOCLARK
FLOYDHARRISON CRAWFORDPERRYDUBOISDAVIESS KNOXPIKE GIBSON SPENCERWARRICKPOSEYJACKSONVANDER-BURGHSTATE OF INDIANA
SITE LOCATION
VICINITY MAP LOCATION MAP
CIVIL SHEET INDEX
CS COVER SHEET
GD0.01 GENERAL NOTES AND LEGEND
SV-1 TOPOGRAPHIC SURVEY
SV-2 TOPOGRAPHIC SURVEY
SV-3 TOPOGRAPHIC SURVEY
GD1.01 SITE DEMOLITION PLAN - NORTH
GD1.02 SITE DEMOLITION PLAN - SOUTH
GD1.03 SITE DEMOLITION PLAN - VARSITY BASEBALL FIELD
GD1.04 SITE DEMO. PLAN - JV BASEBALL COMP. PHOTO DETAILS
GD1.05 SITE DEMO. PLAN - V BASEBALL COMP. PHOTO DETAILS
GD1.06 SITE UTILITY DEMOLITION PLAN - NORTH
GD1.07 SITE UTILITY DEMOLITION PLAN - SOUTHWEST
GD1.08 SITE UTILITY DEMOLITION PLAN - SOUTHEAST
G1.0 OVERALL SITE LAYOUT PLAN
G1.01 SITE LAYOUT PLAN - NORTH PARKING LOT
G1.02 SITE LAYOUT PLAN - BASEBALL COMPLEXES
G1.03 VARSITY BASEBALL TURF FIELD LAYOUT PLAN
G1.04 VARSITY BASEBALL FIELD TURF GRAPHIC PLAN
G2.0 OVERALL GRADING PLAN
G2.01 GRADING PLAN - NORTH
G2.02 GRADING PLAN - SOUTHWEST
G2.03 GRADING PLAN - SOUTHEAST
G2.04 EROSION CONTROL PLAN - NORTH
G2.05 EROSION CONTROL PLAN - SOUTHWEST
G2.06 EROSION CONTROL PLAN - SOUTHEAST
G2.07 STORMWATER POLLUTION PREVENTION PLAN
G2.08 EROSION CONTROL DETAILS
G4.0 SITE DETAILS
G4.01 SITE DETAILS - VARSITY SYNTHETIC TURF FIELD
G4.02 SITE DETAILS - VARSITY SYNTHETIC TURF FIELD
SU1.0 OVERALL SITE UTILITY PLAN
SU1.01 SITE UTILITY PLAN - NORTH
SU1.02 SITE UTILITY PLAN - SOUTHWEST
SU1.03 SITE UTILITY PLAN - SOUTHEAST
SU3.01 SITE UTILITY DETAILS
SU3.02 SITE UTILITY DETAILS
SU3.03 SITE UTILITY DETAILS
SU3.04 SITE UTILITY DETAILS
L1.0 SITE LANDSCAPE PLAN
L1.01 SITE LANDSCAPE DETAILS
E2.02 PHOTOMETRIC SITE PLAN
REV.
NO. DESCRIPTION DATE
PROJECT INFORMATION
3901 W 86TH ST., SUITE 200
INDIANAPOLIS, IN 46268
CONTACT: BRITTANY N. HEIDENREICH, PE
PHONE: (317) 334-1500
EMAIL: bheidenreich@tlf-engineers.com
3834 S. EMERSON AVE., BLDG A
INDIANAPOLIS, IN 46203
CONTACT: ELI MILLER, MBA
PHONE: (317) 788-5149
EMAIL: emiller@skillman.com
520 E. MAIN ST.
CARMEL, INDIANA 46032
CONTACT: RON FARRAND JR., RA
PHONE: (317) 815-3962
EMAIL: rfarrand@ccs.k12.in.us
350 EAST NEW YORK STREET, SUITE 300
INDIANAPOLIS, INDIANA 46204
CONTACT: WILLIAM E. PAYNE, AIA, LEED AP
PHONE: (317) 848-0966, 10307
EMAIL: wpayne@fhai.com
TAC SUBMITTAL 02/17/2021A
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 02/17/2021
DRAWN BY: HHW
08/19/21
GENERAL
1. ALL CONSTRUCTION METHODS AND MATERIALS MUST CONFORM TO CURRENT
STANDARDS AND SPECIFICATIONS OF THE FEDERAL, STATE, COUNTY, CITY OR
LOCAL REQUIREMENTS, WHICHEVER HAS JURISDICTION.
2. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO OBTAIN ALL FEDERAL,
STATE, COUNTY, CITY, AND LOCAL PERMITS FOR ANY AND ALL WORK REQUIRED
UNLESS OTHERWISE NOTED. THIS SHALL INCLUDE ALL SUBMITTALS AS
REQUIRED INCLUDING STORMWATER RUNOFF CONTROL (RULE 5). THE
CONTRACTOR IS RESPONSIBLE FOR PAYING FOR ALL REQUIRED PERMITS BY
ANY OR ALL AGENCIES MENTIONED ABOVE UNLESS OTHERWISE NOTED BY THE
CONTRACT OR SPECIFICATIONS.
3. CONTRACTOR SHALL VERIFY DATE OF PLANS WITH ENGINEER PRIOR TO
CONSTRUCTION TO ENSURE USE OF CURRENT PLANS.
4. ALL QUANTITIES PROVIDED ARE ESTIMATES AND SHALL BE CONFIRMED BY THE
BIDDING CONTRACTORS.
5. PROTECT AND MAINTAIN BENCHMARKS AND SURVEY CONTROL POINTS FROM
DISTURBANCE DURING CONSTRUCTION.
SITE LAYOUT
1. THE CONTRACTOR SHALL VERIFY ALL DIMENSIONS IN THE FIELD PRIOR TO
STARTING CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL
FIELD DIMENSIONS. IF ANY DISCREPANCIES ARE FOUND IN THESE PLANS FROM
THE ACTUAL FIELD CONDITIONS, THE CONTRACTOR SHALL NOTIFY THE ENGINEER
IMMEDIATELY.
2. DIMENSIONS SHOWN ARE TO FACE OF CURB AND TO FACE OF BUILDING UNLESS
NOTED OTHERWISE.
3. RADII NOT DIMENSIONED ARE TO BE 5'.
4. ALL PROPOSED SPOT ELEVATIONS ARE THE FINAL PAVEMENT AND FINAL GRADE
ELEVATIONS.
5. REFER TO APPROPRIATE SITE DETAILS TO DETERMINE SUBGRADE ELEVATIONS
BELOW FINISH GRADE ELEVATIONS INDICATED.
6. TAPER CURB HEIGHT TO 1" IN FINAL 2' OF ALL CURB ENDINGS OR AS NOTED ON
PLANS.
7. EXACT LOCATION OF SIGNS TO BE COORDINATED WITH OWNER AND APPROVED
PRIOR TO INSTALLATION.
8. SITE BOUNDARY, TOPOGRAPHY, UTILITY, STRUCTURES AND ROAD INFORMATION
TAKEN FROM A SURVEY PREPARED BY CEC.
GRADING AND EARTHWORK
1. THE CONTRACTOR SHALL CONTACT ALL UTILITY COMPANIES TO LOCATE MAINS,
CONDUITS, SERVICE LINES, ETC. IN THE AFFECTED CONSTRUCTION AREA.
EXISTING UTILITY STRUCTURES ARE SHOWN IN ACCORDANCE WITH AVAILABLE
INFORMATION. THE LOCATION AND PROTECTION OF UTILITY STRUCTURES, THEIR
SUPPORT AND MAINTENANCE DURING CONSTRUCTION (IN COOPERATION WITH
THE APPLICABLE UTILITY COMPANY) IS THE RESPONSIBILITY OF THE
CONTRACTOR.
2. ALL CONSTRUCTION METHODS AND MATERIALS MUST CONFORM TO CURRENT
STANDARDS AND SPECIFICATIONS OF THE FEDERAL, STATE, COUNTY, CITY OR
LOCAL REQUIREMENTS, WHICHEVER HAS JURISDICTION.
3. PROTECT STRUCTURES, UTILITIES, SIDEWALKS, PAVEMENTS, AND OTHER
FACILITIES FROM DAMAGE CAUSED BY SETTLEMENT, LATERAL MOVEMENT,
UNDERMINING, WASHOUT, AND OTHER HAZARDS CREATED BY EARTH MOVING
OPERATIONS.
4. IT IS THE CONTRACTOR'S RESPONSIBILITY TO ACQUAINT HIMSELF WITH SUBSOIL
CONDITIONS PRIOR TO BIDDING.
5. CONTRACTOR SHALL VERIFY WITH OWNER EXACT LOCATION AND DEPTH OF ALL
PRIVATE/OWNER INSTALLED UTILITIES PRIOR TO CONSTRUCTION.
6. DETERMINE LOCATION OF UNDERGROUND UTILITIES AND PERFORM WORK IN A
MANNER WHICH WILL AVOID POSSIBLE DAMAGE. HAND EXCAVATE AS REQUIRED.
7. THE EXCAVATING CONTRACTOR MUST TAKE PARTICULAR CARE WHEN
EXCAVATING IN AND AROUND EXISTING UTILITY LINES AND EQUIPMENT. VERIFY
COVER REQUIREMENTS BY UTILITY CONTRACTOR AND/OR UTILITY COMPANIES SO
AS NOT TO CAUSE DAMAGE.
8. THE CONTRACTOR SHALL NOTIFY ALL UTILITY COMPANIES 72 HOURS BEFORE
CONSTRUCTION IS TO START, TO VERIFY IF ANY UTILITIES ARE PRESENT ON SITE.
ALL VERIFICATIONS (LOCATIONS, SIZE AND DEPTH) SHALL BE MADE BY THE
APPROPRIATE UTILITY COMPANIES. WHEN EXCAVATING AROUND OR OVER
EXISTING UTILITIES, THE CONTRACTOR MUST NOTIFY THE UTILITY COMPANY SO A
REPRESENTATIVE OF THAT UTILITY COMPANY CAN BE PRESENT TO INSTRUCT AND
OBSERVE DURING CONSTRUCTION.
9. EXCAVATE TO SUBGRADE ELEVATIONS REGARDLESS OF THE CHARACTER OF
SURFACE AND SUBSURFACE CONDITIONS ENCOUNTERED. UNCLASSIFIED
EXCAVATED MATERIALS MAY INCLUDE ROCK, SOIL MATERIALS, AND
OBSTRUCTIONS.
10. PREVENT SURFACE WATER AND GROUND WATER FROM ENTERING EXCAVATIONS,
FROM PONDING ON PREPARED SUBGRADES, AND FROM FLOODING THE PROJECT
SITE AND SURROUNDING AREA. REROUTE SURFACE WATER RUNOFF AWAY FROM
EXCAVATED AREAS. DO NOT ALLOW WATER TO ACCUMULATE IN EXCAVATIONS.
DO NOT USE EXCAVATED TRENCHES AS TEMPORARY DRAINAGE DITCHES.
11. STOCKPILE BULK MATERIALS AWAY FROM EDGE OF EXCAVATIONS WITHOUT
INTERMIXING WITH SUBSOIL. GRADE AND SHAPE STOCKPILES TO DRAIN SURFACE
WATER. COVER TO PREVENT WINDBLOWN DUST AND EROSION BY WATER. DO
NOT STORE WITHIN DRIP LINE OF TREES THAT WILL REMAIN.
12. CONTRACTOR SHALL INSTALL ALL SLEEVES/CONDUITS AS REQUIRED BY THE
UTILITY COMPANIES. COORDINATE FINAL LOCATIONS WITH THE UTILITY
COMPANIES.
13. THE CONTRACTOR SHALL PROVIDE AT LEAST 18"' OF COVER OVER ALL STORM
SEWERS, UNLESS OTHERWISE INDICATED BY PLANS.
14. PROVIDE COMPACTED "B" BORROW BACKFILL OVER ALL UTILITIES IN PAVED
AREAS.
15. PROVIDE A SMOOTH TRANSITION BETWEEN ADJACENT EXISTING GRADES AND
NEW GRADES.
16. MAINTAIN GRADE STAKES SET BY OTHERS UNTIL REMOVAL IS MUTUALLY AGREED
UPON BY PARTIES CONCERNED.
17. ALL EXISTING MANHOLE AND CATCH BASIN CASTINGS, WATER OR GAS VALVE
BOXES SHALL BE ADJUSTED TO NEW FINISH GRADE ELEVATION.
18. PROVIDE POSITIVE DRAINAGE WITHOUT PONDING, IN ALL AREAS. AFTER
INSTALLATION, CONTRACTOR TO TEST FOR, AND CORRECT, IF ANY, "BIRD BATH"
CONDITIONS.
19. MAXIMUM LAWN SLOPE SHALL BE 3:1.
20. DURING FINISH GRADING, ELIMINATE RILLS AND GULLIES. REMOVE ALL STONES,
RUBBLE, STICKS, WIRE, PLANT MASS AND DEBRIS OVER 1 INCH IN ANY DIMENSION,
AS WELL AS OBVIOUS QUANTITIES OF SMALL STONE.
21. REPAIR AND REESTABLISH GRADES TO SPECIFIED TOLERANCES WHERE
COMPLETED OR PARTIALLY COMPLETED SURFACES BECOME ERODED, RUTTED,
SETTLED, OR WHERE COMPACTION IS LOST DUE TO SUBSEQUENT
CONSTRUCTION OPERATIONS OR WEATHER CONDITIONS.
22. ADD ADDITIONAL TOPSOIL AND GRADE AS NECESSARY IN AREAS OF SETTLEMENT
AND EROSION, AND AS REQUIRED TO MEET FINISH GRADE.
DEMOLITION
1. DEMOLITION PERMIT WILL BE PROCURED BY THE SUBCONTRACTOR AND COST
SHALL BE INCLUDED AS PART OF THEIR WORK.
2. DURING DEMOLITION PROCESS, EROSION CONTROL MEASURES SHALL BE
ESTABLISHED. THESE SHALL INCLUDE TREATMENT OF DUST AND POTENTIAL
STORMWATER DISCHARGE. REFER TO EROSION CONTROL DRAWINGS.
3. REMOVAL OF THE EXISTING IMPROVEMENTS ARE AS NOTED ON THE PLANS OR
AS REQUIRED BY THE PROJECT. THE MATERIALS REMOVED FROM THE SITE
SHALL BE DISPOSED OF IN A PROPER AND LEGAL MANNER PER FEDERAL,
STATE, AND OR LOCAL LAWS AND ORDINANCES.
4. EXISTING ITEMS TO REMAIN SHALL BE PROTECTED FROM DAMAGE BY THE
CONTRACTOR. ANY DAMAGE DURING CONSTRUCTION SHALL BE RESTORED,
RECONSTRUCTED OR REPLACED BY THE CONTRACTOR AT HIS EXPENSE. ALL
DAMAGES SHALL BE RESTORED OR REPLACED TO AT LEAST THEIR ORIGINAL
CONDITION OR AS REQUIRED OR DICTATED BY FEDERAL, STATE, COUNTY, CITY
OR LOCAL REGULATIONS.
5. IT IS THE CONTRACTOR'S RESPONSIBILITY TO NOTIFY ALL THE UTILITY
COMPANIES AND DEPARTMENTS 72 HOURS BEFORE DEMOLITION IS TO START
TO VERIFY ANY UTILITIES THAT MAY BE PRESENT ON SITE. ALL VERIFICATIONS,
LOCATIONS, SIZE AND DEPTHS SHALL BE MADE BY THE APPROPRIATE UTILITY
COMPANIES OR DEPARTMENTS. WHEN EXCAVATING AROUND OR OVER
EXISTING UTILITIES, THE CONTRACTOR MUST NOTIFY THE UTILITY COMPANY SO
A REPRESENTATIVE OF THE UTILITY MAY BE PRESENT DURING THE
EXCAVATION TO INSTRUCT AND OBSERVE DURING THE EXCAVATION.
6. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY WITH EACH
UTILITY COMPANY AND OR AGENT WHO IS RESPONSIBLE TO REMOVE OR
RELOCATE EACH EXISTING UTILITY. IT IS THE RESPONSIBILITY OF THE
CONTRACTOR TO BEAR THE COST FOR THE REMOVAL, TERMINATION OR
RELOCATION OF UTILITIES IF THE RESPONSIBILITY IS NOT COVERED BY THE
UTILITY COMPANY.
7. LOCATE, IDENTIFY, DISCONNECT, AND SEAL OR CAP UTILITIES INDICATED TO BE
REMOVED OR ABANDONED IN PLACE.
8. REMOVAL OF EXISTING CONCRETE OR OTHER PAVED AREAS INDICATED ON
THE PLANS SHALL INCLUDE ALL AGGREGATE BASE MATERIALS. AREAS TO BE
REMOVED SHALL BE SAW CUT CLEAN, NEAT AND TRUE TO LINE. REMOVE ALL
NON-ORGANIC MATTER THAT WOULD INTERFERE WITH THE GROWTH OF TURF
OR PLANT MATERIAL.
9. ALL CONTRACTORS MUST TAKE PARTICULAR CARE WHEN EXCAVATING IN AND
AROUND EXISTING UTILITY LINES AND EQUIPMENT. ACTUAL FIELD LOCATIONS
OF ALL EXISTING UTILITIES ARE THE CONTRACTORS RESPONSIBILITY AND
MUST BE LOCATED EITHER BY THE REPRESENTATIVE OF THE UTILITY COMPANY
OR BY A PRIVATE UNDERGROUND UTILITY LOCATING COMPANY PRIOR TO THE
START OF DEMOLITION ACTIVITIES.
10. SAW CUT THE EDGES OF PAVED AREAS CLEAN, NEAT AND TRUE TO LINE SO NO
UNWANTED CHIPPING OR BREAKING OF EXISTING PAVEMENT TO REMAIN WILL
OCCUR.
11. UNLESS EXISTING FULL-DEPTH JOINTS COINCIDE WITH LINE OF DEMOLITION,
NEATLY SAW-CUT ALONG LINE OF EXISTING PAVEMENT TO REMAIN BEFORE
REMOVING ADJACENT EXISTING PAVEMENT. SAW-CUT FACES VERTICALLY.
12. DO NOT ALLOW MATERIALS AND DEBRIS GENERATED BY DEMOLITION TO
ACCUMULATE ON THE JOB SITE FOR MORE THAN 48 HOURS. REMOVE AND
DISPOSE OF IN A LEGAL MANNER.
13. GRIND DOWN STUMPS AND REMOVE ROOTS, OBSTRUCTIONS, AND DEBRIS TO A
DEPTH OF 18 INCHES BELOW EXPOSED SUBGRADE.
14. FILL DEPRESSIONS CAUSED BY CLEARING AND GRUBBING OPERATIONS WITH
SATISFACTORY SOIL MATERIAL UNLESS FURTHER EXCAVATION OR
EARTHWORK IS INDICATED.
15. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO INSPECT EACH DAY AND
REMOVE ALL MUD, DIRT, GRAVEL AND LOOSE MATERIALS TRACKED, DUMPED,
SPILLED OR WIND BLOWN FROM THIS SITE ONTO OTHER SITES, RIGHT OF
WAYS, PUBLIC OR PRIVATE STREETS OR ROADS, DRIVEWAYS, YARDS OR
SIDEWALKS. THE CONTRACTOR MUST CLEAN OR PICK UP DAILY IF NECESSARY.
THE CONTRACTOR SHALL REDUCE THE AIRBORNE DUST DURING THE ENTIRE
DEMOLITION SCHEDULE. WATER MAY BE USED AS A REDUCER.
16. THE CONTRACTOR SHALL DOCUMENT THE FINAL DISPOSITION OF ALL
MATERIALS REMOVED FROM THE SITE.
17. DEMOLITION ITEMS INCLUDE BUT ARE NOT LIMITED TO DEMOLITION ITEMS
INDICATED ON THESE DRAWINGS. IT IS THE CONTRACTORS RESPONSIBILITY
TO REMOVE OR RELOCATE ITEMS WHICH INTERFERE WITH NEW
CONSTRUCTION.
1. ALL EROSION CONTROL PLANNING AND IMPLEMENTATION OF PROTECTIVE
MEASURES SHALL BE IN ACCORDANCE WITH THE STANDARDS AND PROCEDURES
OUTLINED IN THE IDEM "INDIANA STORM WATER QUALITY MANUAL".
2. THE CONTRACTOR IS RESPONSIBLE FOR THE INSTALLATION, MAINTENANCE AND
REPAIR OF ALL TEMPORARY AND PERMANENT EROSION CONTROL MEASURES
DURING EARTHMOVING OPERATIONS.
3. DURING CONSTRUCTION KEEP PAVEMENTS AND SIDEWALKS CLEAN AND WORK
AREAS IN AN ORDERLY CONDITION. CLEAN WHEELS OF VEHICLES BEFORE
LEAVING SITE TO AVOID TRACKING SOIL ONTO ROADS, WALKS, OR OTHER PAVED
AREAS.
4. IT IS THE CONTRACTOR'S RESPONSIBILITY TO CONTROL AND LIMIT THE TRACKING
OF SILT AND SEDIMENT OFFSITE. THE CONTRACTOR SHALL BROOM AND COLLECT
TRACKED SILT AND SEDIMENT IMMEDIATELY UPON DISCOVERY THE MATERIAL.
5. DO NOT COMMENCE SITE CLEARING OR EARTH MOVING OPERATIONS UNTIL
TEMPORARY EROSION AND SEDIMENTATION CONTROL MEASURES ARE IN PLACE.
6. DUST CONTROL IS THE CONTRACTOR'S RESPONSIBILITY AND SHALL INCLUDE
CONSTANT AND REPETITIVE APPLICATION OF WATERING AND STREET SWEEPING.
7. THE CONTRACTOR SHALL TEMPORARILY SEED ALL DISTURBED AREAS PLANNED
FOR A PERIOD OF INACTIVITY EXCEEDING 15 DAYS.
EROSION CONTROL
SITE UTILITIES
1. THE UNDERGROUND UTILITIES SHOWN HAVE BEEN LOCATED FROM FIELD SURVEY
INFORMATION AND EXISTING DRAWINGS. THE ENGINEER MAKES NO GUARANTEES
THAT THE UNDERGROUND UTILITIES COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN-SERVICE OR ABANDONED. THE ENGINEER FURTHER DOES NOT
WARRANT THAT THE UNDERGROUND UTILITIES SHOWN ARE IN THE EXACT
LOCATION INDICATED ALTHOUGH THE ENGINEER DOES CERTIFY THAT THEY ARE
LOCATED AS ACCURATELY AS POSSIBLE FROM THE INFORMATION MADE
AVAILABLE. THE ENGINEER HAS NOT PHYSICALLY LOCATED THE UNDERGROUND
UTILITIES.
2. CONTRACTOR SHALL VERIFY EXISTING STORM SEWER CONDITIONS, LOCATION
AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION TO ENSURE THAT THE
NEW SEWERS CAN BE CONSTRUCTED AS SHOWN ON THESE PLANS. REPORT ANY
DISCREPANCIES TO THE ENGINEER.
3. CONSTRUCTION OF ALL STORM SEWER LINES AND STRUCTURES SHALL BE IN
ACCORDANCE WITH LOCAL AND STATE CODES, RULES AND REGULATIONS.
4. IT IS THE CONTRACTOR'S RESPONSIBILITY TO NOTIFY AND COORDINATE
CONSTRUCTION WITH ALL RESPECTIVE UTILITIES.
5. EXISTING UTILITY STRUCTURES ARE SHOWN IN ACCORDANCE WITH AVAILABLE
INFORMATION. THE CONTRACTOR SHALL CONTACT ALL UTILITY COMPANIES TO
LOCATE MAINS, CONDUITS, SERVICE LINES, ETC. IN THE AFFECTED
CONSTRUCTION AREA. THE LOCATION AND PROTECTION OF UTILITY
STRUCTURES, THEIR SUPPORT AND MAINTENANCE DURING CONSTRUCTION IS
THE RESPONSIBILITY OF THE CONTRACTOR.
6. CONTRACTOR SHALL INSTALL ALL SLEEVES/CONDUITS AS REQUIRED BY THE
UTILITY COMPANIES. COORDINATE FINAL LOCATIONS WITH THE UTILITY
COMPANIES. CONTRACTOR SHALL SLEEVE ALL PIPING AT FOOTINGS AND BELOW
GRADE WALLS. SLEEVES SHALL BE WATER TIGHT. COORDINATE ALL WALL
PENETRATIONS WITH STRUCTURAL, MECHANICAL, ELECTRICAL AND PLUMBING
PLANS.
7. CONTRACTOR SHALL VERIFY WITH OWNER THE EXACT LOCATION AND DEPTH OF
ALL PRIVATE/OWNER-INSTALLED UTILITIES PRIOR TO CONSTRUCTION.
8. CONTRACTORS SHALL CONSULT ARCHITECTURAL, MECHANICAL, PLUMBING AND
ELECTRICAL PLANS FOR INVERT ELEVATIONS AND EXACT LOCATION OF
DOWNSPOUTS, WATER LINES, STORM LINES, SANITARY LINES, GAS LINES,
ELECTRICAL LINES, TELECOM LINES, TRANSFORMER PADS OR POLES, ETC.
9. SEE SITE ELECTRICAL PLANS FOR SITE LIGHTING, POWER AND TELECOM.
10. INSTALL PIPING BEGINNING AT LOW POINT, TRUE TO GRADES AND ALIGNMENT
INDICATED WITH UNBROKEN CONTINUITY OF INVERT. PLACE BELL ENDS OF PIPING
FACING UPSTREAM. INSTALL GASKETS, SEALS, SLEEVES, AND COUPLINGS
ACCORDING TO MANUFACTURER'S WRITTEN INSTRUCTIONS. REFER TO
MANUFACTURER'S WRITTEN INSTRUCTIONS FOR USE OF LUBRICANTS, CEMENTS,
AND OTHER INSTALLATION REQUIREMENTS.
11. INSTALL MANHOLES FOR CHANGES IN DIRECTION UNLESS FITTINGS ARE
INDICATED. USE FITTINGS FOR BRANCH CONNECTIONS UNLESS DIRECT TAP INTO
EXISTING SEWER IS INDICATED.
12. PVC AND HDPE STORM SEWER PIPE TO BE INSTALLED ONLY AT LOCATIONS
INDICATED AND SHALL NOT BE SUBSTITUTED FOR LOCATIONS WHERE RCP PIPE IS
SPECIFIED.
13. THE CONTRACTOR SHALL PROVIDE AT LEAST 18" OF COVER OVER ALL STORM
SEWERS, UNLESS OTHERWISE INDICATED BY PLANS.
14. WHERE WATER LINES AND SEWERS CROSS AND THE WATER LINE CANNOT BE
PLACED ABOVE OR BELOW THE SEWER WITH A MINIMUM OF 18" VERTICAL
CLEARANCE, THE SEWER MUST BE CONSTRUCTED OF WATER WORKS GRADE
DUCTILE IRON PIPE WITH MECHANICAL JOINTS OR PLASTIC PRESSURE (SDR 21)
SEWER PIPE WITH GASKETED, COMPRESSION TYPE JOINTS WITHIN 10' OF THE
WATER LINE. THE WATER LINES SHALL BE INSTALLED ABOVE THE SEWER
WHEREVER POSSIBLE.
15. WHERE WATER LINES AND SEWERS RUN PARALLEL AND A MINIMUM SEPARATION
DISTANCE OF 10' CANNOT BE MAINTAINED, THE SEWER MUST BE CONSTRUCTED
OF WATER WORKS GRADE DUCTILE IRON PIPE WITH MECHANICAL JOINTS OR
PLASTIC PRESSURE SEWER PIPE WITH GASKETED, COMPRESSION TYPE JOINTS.
16. ALL EXISTING MANHOLE AND CATCH BASIN CASTINGS, WATER OR GAS VALVE
BOXES SHALL BE ADJUSTED TO NEW FINISH GRADE ELEVATION.
17. ANY STORM DRAIN, FIELD TILE, OR UTILITY ENCOUNTERED DURING
CONSTRUCTION SHALL BE RELOCATED AND POSITIVE DRAINAGE MAINTAINED
UNLESS OTHERWISE NOTED TO REMAIN. NOTIFY ENGINEER IF ANY DRAINS ARE
ENCOUNTERED.
18. ALL PAVEMENT CUT DUE TO UTILITY INSTALLATION, CONSTRUCTION OF CURBS,
ETC., OR DAMAGE TO EXISTING PAVEMENT DURING CONSTRUCTION SHALL BE
PATCHED WITH A PAVEMENT SECTION WHICH MEETS OR EXCEEDS THE EXISTING
SECTION.
LANDSCAPING
1. PRIOR TO CONSTRUCTION, THE LANDSCAPE CONTRACTOR SHALL BE RESPONSIBLE
FOR LOCATING ALL UNDERGROUND UTILITIES & SHALL AVOID DAMAGE TO ALL UTILITIES
DURING THE COURSE OF THE WORK. THE LANDSCAPE CONTRACTOR IS RESPONSIBLE
FOR REPAIRING ANY & ALL DAMAGE TO THE UTILITIES, STRUCTURES, SITE
APPURTENANCES, ETC. WHICH OCCURS AS A RESULT OF THE LANDSCAPE
CONSTRUCTION.
2. LANDSCAPE CONTRACTOR TO VERIFY EXISTING FIELD CONDITIONS PRIOR TO THE
COMMENCEMENT OF WORK.
3. THE PLANT COUNTS INDICATED ON DRAWINGS ARE FOR LANDSCAPE ARCHITECT'S USE
ONLY. LANDSCAPE CONTRACTOR SHALL MAKE THEIR OWN PLANT QUANTITY TAKEOFFS
USING DRAWINGS, SPECIFICATIONS, AND PLANT SCHEDULE REQUIREMENTS (I.E.,
SPACING), UNLESS OTHERWISE DIRECTED BY LANDSCAPE ARCHITECT. CONTRACTOR
TO VERIFY BED MEASUREMENTS AND INSTALL APPROPRIATE QUANTITIES AS
GOVERNED BY PLANT SPACING PER SCHEDULE. PLANT MATERIAL QUANTITIES SHOWN
ON PLAN ARE MINIMUM QUANTITIES. ADDITIONAL MATERIAL MAY BE NEEDED TO MEET
SPACING REQUIREMENTS AND FIELD CONDITIONS. IN CASE OF DISCREPANCIES
BETWEEN PLAN AND PLANT LIST, THE PLAN SHALL DICTATE.
4. NO SUBSTITUTIONS OF PLANT MATERIAL WILL BE ALLOWED. IF PLANTS ARE SHOWN TO
BE UNAVAILABLE, THE CONTRACTOR SHALL NOTIFY LANDSCAPE ARCHITECT PRIOR TO
BID DATE IN WRITING.
5. DO NOT DUMP OR STORE BULK MATERIALS NEAR STRUCTURES, UTILITIES, WALKWAYS
AND PAVEMENTS, OR ON EXISTING TURF AREAS OR PLANTS.
6. PROCEED WITH PLANTING ONLY WHEN EXISTING AND FORECASTED WEATHER
CONDITIONS PERMIT PLANTING TO BE PERFORMED WHEN BENEFICIAL AND OPTIMUM
RESULTS MAY BE OBTAINED.
7. SUSPEND PLANTING OPERATIONS DURING PERIODS OF EXCESSIVE SOIL MOISTURE
UNTIL THE MOISTURE CONTENT REACHES ACCEPTABLE LEVELS TO ATTAIN THE
REQUIRED RESULTS.
8. UNIFORMLY MOISTEN EXCESSIVELY DRY SOIL THAT IS NOT WORKABLE OR WHICH IS
DUSTY.
9. DURING CONSTRUCTION KEEP PAVEMENTS AND SIDEWALKS CLEAN AND WORK AREA IN
AN ORDERLY CONDITION.
10. PROTECT STRUCTURES, UTILITIES, SIDEWALKS, PAVEMENTS, AND OTHER FACILITIES,
TREES, SHRUBS, AND PLANTINGS FROM DAMAGE CAUSED BY PLANTING OPERATIONS
AND FROM HYDROSEEDING AND HYDROMULCHING OVERSPRAY. PROMPTLY REPAIR
ANY DAMAGE CAUSED BY PLANTING OPERATIONS.
11. ESTABLISH TREE PROTECTIONS ZONES AS REQUIRED BY SPECIFICATIONS.
12. EARTHWORK CONTRACTOR SHALL INSTALL 12" OF TOPSOIL IN ALL PROPOSED BED
AREAS. CONTRACTOR SHALL COORDINATE QUANTITY AND PLACEMENT OF TOPSOIL.
SUBCONTRACTOR SHALL VERIFY DEPTH OF TOPSOIL PRIOR TO PLANT INSTALLATION.
REFER TO SPECIFICATIONS FOR TOPSOIL TESTING AND PLACEMENT REQUIREMENTS.
REPLACEMENT SOIL SHALL BE COMPRISED OF 1 PART ORIGINAL, 2 PARTS HUMUS, 1
PART COMPOSTED CATTLE MANURE, 1 PART CLEAN COARSE CUT SAND, AND 1 POUND
OF FERTILIZER (12-12-12 NPK BALANCED) PER 10 SQ. FT. - WORKED WELL INTO SOIL.
13. RECONDITION SOIL AND SEED/RE-SEED ALL AREAS DISTURBED BY CONSTRUCTION
ACTIVITIES THAT ARE NOT TO RECEIVE OTHER SURFACE TREATMENT (I.E., ASPHALT
PAVEMENT, CONCRETE SLAB, PLANTING BED ETC.). ALL DISTURBED LAWN AREAS TO
RECEIVE 4" OF TOPSOIL IN ADDITION TO SOIL AMENDMENTS AS PART OF
RECONDITIONING.
14. ALL PLANTS & PLANTING AREAS TO RECEIVE 3" MINIMUM OF SHREDDED HARDWOOD
BARK MULCH (UNLESS OTHERWISE NOTED). MULCH SHALL BE UNIFORM IN TEXTURE
AND COLOR. NO PROCESSED TREE TRIMMINGS WILL BE ALLOWED.
15. ALL DISTURBED AREAS SHALL BE SEEDED PER SPECIFICATIONS.
16. ALL GRASS AND/OR LANDSCAPING DISTURBED BY NEW CONSTRUCTION SHALL BE
RESTORED TO ORIGINAL OR BETTER CONDITION.
MAINTENANCE OF TRAFFIC
1. THE MAINTENANCE OF TRAFFIC (MOT) EFFORTS CONDUCTED BY THE CONTRACTOR
WILL INCLUDE PROVIDING, MANAGING AND MAINTAINING EQUIPMENT AND PERSONNEL
NECESSARY FOR MAINTAINING SAFE TRAFFIC CONDITIONS AT ALL TIMES DURING THE
PROJECT. TRAFFIC MAINTENANCE INCLUDES BOTH PROTECTING THE TRAVELING
PUBLIC APPROACHING THE SITE AND INCORPORATING SAFE AND EFFICIENT
CIRCULATION WITHIN THE CONSTRUCTION AREA.
2. THE CONTRACTOR SHALL FURNISH, ERECT, PLACE AND MAINTAIN TRAFFIC CONTROL
SIGNS AND DEVICES DURING THE HOURS OF CONSTRUCTION OPERATIONS AND AT ALL
OTHER TIMES IN ACCORDANCE WITH LOCAL AND INDOT STANDARDS. IN ADDITION TO
THE LOCAL AND STATE STANDARDS, THE CONTRACTOR SHALL CONSULT THE U.S. DOT,
FHA, AND MUTCD REGULATIONS REGARDING THE TYPE AND PLACEMENT OF TRAFFIC
CONTROL DEVICES.
3. THE CONTRACTOR SHALL PROVIDE ALL DEVICES NECESSARY AND INSTALL
TEMPORARY VEHICLE ROUTES, DETOURS AND RUNAROUNDS TO MAINTAIN THE
OWNER'S ONGOING ACTIVITIES. MODIFICATIONS AND TEMPORARY SHUTDOWNS FOR
THESE TRAFFIC ROUTES SHALL FIRST BE COORDINATED WITH THE OWNER.
4. DO NOT CLOSE OR OBSTRUCT STREETS, WALKS, OR OTHER ADJACENT OCCUPIED OR
USED FACILITIES WITHOUT PERMISSION FROM OWNER AND AUTHORITIES HAVING
JURISDICTION.
5. PROVIDE ALTERNATE ROUTES AROUND CLOSED OR OBSTRUCTED TRAFFIC WAYS IF
REQUIRED BY OWNER OR AUTHORITIES HAVING JURISDICTION.
6. ALL SIDEWALK CLOSURES REQUIRE A SIGNED ALTERNATIVE ROUTE FOR PEDESTRIANS.
7. MAINTAIN FIRE, AMBULANCE AND POLICE VEHICLE ACCESS TO THE BUILDINGS AT ALL
TIMES DURING CONSTRUCTION.
8. ALL REQUIRED COMMUNICATION, PERMITS OR NOTICES NEEDED BY THE LOCAL FIRE,
POLICE AND CITY OFFICES WILL REMAIN THE CONTRACTOR'S RESPONSIBILITY. THE
CONTRACTOR SHALL DETERMINE IF ANY LOCAL ROAD RESTRICTIONS ON WEIGHT OR
OTHERWISE EXISTS BEFORE DIRECTING INCOMING AND OUTGOING CONSTRUCTION
TRAFFIC.
9. SIGNS AND DEVICES SHOWN ON THE MAINTENANCE OF TRAFFIC PLAN REPRESENT THE
MINIMUM STANDARDS. ADDITIONAL SIGNS AND ADJUSTMENTS TO LOCATION MAY BE
REQUIRED TO ADDRESS CHANGING FIELD CONDITIONS.
10. PROMPTLY REMOVE TEMPORARY TRAFFIC CONTROL WHEN SIGNS AND DEVICES NO
LONGER SERVE ANY PURPOSE.
11. TEMPORARY FACILITIES, INCLUDING REROUTING PEDESTRIAN PATHS AROUND THE
WORK SITE ARE THE CONTRACTOR'S RESPONSIBILITY AND WILL BE BASED ON THE
OWNER'S NEEDS. THE CONTRACTOR SHALL COORDINATE WITH THE OWNER
REGARDING SITE ACCESS AND PEDESTRIAN MOVEMENT AROUND THE CONSTRUCTION
SITE PRIOR TO PLACING CONSTRUCTION FENCING, GATES AND EQUIPMENT OR
MATERIALS ON SITE.
12. THE LOCATION OF CONSTRUCTION LAYDOWN AREAS MUST FIRST BE APPROVED BY
THE OWNER. LAYDOWN AREAS SHALL BE FENCED AND PROTECTED FROM THE
SURROUNDING PROPERTIES.
13. CONSTRUCTION ONSITE JOB TRAILERS SHALL BE COORDINATED WITH THE OWNER.
FOR TRAILERS WITH PLUMBING, THE UNITS SHALL BE SERVED BY EITHER A PROPERLY
PERMITTED SANITARY SEWER LATERAL OR TEMPORARY WASTE STORAGE REVIEWED
AND APPROVED BY BOTH THE OWNER AND THE LOCAL AUTHORITIES.
GENERAL NOTES
TOPOGRAPHIC LEGEND
GD0.01
GENERAL NOTES AND LEGEND
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
08/19/21
ADJOINER
ADJOINER
ADJOINER
MOHAWK CROSSING
SECTION 3
P.B. 10, PG. 20-21
MOHAWK CROSSING
SECTION 2
P.B. 7, PG. 166-167
LOT 58
LOT 57
LOT 56
LOT 55
LOT 54
LOT 52
LOT 51
LOT 50
LOT 49
LOT 33
LOT 32
LOT 31
SITE
FLOOD NOTE:
8
A
B
3 4 5 6 7 12
C
D
E
F
G
H
8 34 5 6 7 12
A
B
C
D
E
F
G
H
DESCRIPTIONDATE NO REVISION RECORDDATE:DWG SCALE:DRAWN BY:CHECKED BY: APPROVED BY:PROJECT NO:SHEET OF
DRAWING NO.:BOUNDARY RETRACEMENT SURVEY303-1031"=50' AUGUST 21, 2020 TJTABSABS1 3
SV-1
NORTH 530 E. Ohio Street · Suite G - Indianapolis, IN 46204317-655-7777 · 877-746-0749www.cecinc.comFANNING HOWEY ASSOCIATES, INC.CARMEL CLAY SCHOOLSHARTMAN FIELD5201 E. MAIN STREETCARMEL, INDIANAVICINITY MAP
SUBJECT PARCEL
POINT OF COMMENCEMENT
P.OB.
E. MAIN STREET
E. 126TH STREETGRAY ROADLEGAL DESCRIPTION
08/19/21
UTILITY NOTE:
LEGEND:
8
A
B
3 4 5 6 7 12
C
D
E
F
G
H
8 34 5 6 7 12
A
B
C
D
E
F
G
H DESCRIPTIONDATENO REVISION RECORD530 E. Ohio Street · Suite G - Indianapolis, IN 46204317-655-7777 · 877-746-0749www.cecinc.comFANNING HOWEY ASSOCIATES, INC.CARMEL CLAY SCHOOLSHARTMAN FIELD5201 E. MAIN STREETCARMEL, INDIANADATE:DWG SCALE:DRAWN BY:CHECKED BY: APPROVED BY:PROJECT NO:SHEET OF
DRAWING NO.:BOUNDARY RETRACEMENT SURVEY303-103AUGUST 21, 2020 TJTABSABS2 3
SV-2
SURVEYOR'S REPORT
Reference Surveys and Plats
Reference Monuments
Record Descriptions
Evidence of Occupation
08/19/21
TBM#3 = 775.53
TBM#1 = 782.26
BENCHMARKS:
8
A
B
3 4 5 6 7 12
C
D
E
F
G
H
8 34 5 6 7 12
A
B
C
D
E
F
G
H DESCRIPTIONDATENO REVISION RECORDDATE:DWG SCALE:DRAWN BY:CHECKED BY: APPROVED BY:PROJECT NO:SHEET OF
DRAWING NO.:TOPOGRAPHIC SURVEY303-1031"=30' AUGUST 21, 2020 TJTABSABS3 3
SV-3
NORTH
530 E. Ohio Street · Suite G - Indianapolis, IN 46204317-655-7777 · 877-746-0749www.cecinc.comFANNING HOWEY ASSOCIATES, INC.CARMEL CLAY SCHOOLSHARTMAN FIELD5201 E. MAIN STREETCARMEL, INDIANASEE SHEET SV-2
FOR LEGEND
08/19/21
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L IAME.PAYN
EREGISTERE
D
IND I A N AARCHITE CT
4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
GD1.01
SITE DEMOLITION PLAN -
NORTH
30 900 30 60
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.It's Fast, It's Easy and It's the Law in the state of Indiana!
VICINITY MAP
EXISTING NATURAL TURF INFIELD AND OUTFIELD; DEMO EXISTING NATURAL
TURF FIELD IN ITS ENTIRETY. CONTRACTOR IS TO COORDINATE TOPSOIL
REMOVAL AND STORAGE WITH OWNER / ARCHITECT PRIOR TO EXCAVATION.
LEGALLY DISPOSE OF MATERIALS OFF SITE.
EXISTING BASES AND ANCHORS; DEMO IN THEIR ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS OFF SITE.
EXISTING INFIELD, SKINNED AREAS AND WARNING TRACK; DEMO DIRT / BRICK
DUST AREAS IN THEIR ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF
SITE.
EXISTING 5' CHAIN LINK FENCING - LEFT FIELD LINE; DEMO FENCING IN ITS
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE.
EXISTING 5' CHAIN LINK FENCING - RIGHT FIELD LINE; DEMO FENCING IN ITS
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS LEGALLY OFF SITE.
EXISTING 8' CHAIN LINK FENCING; DEMO FENCING IN ITS ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS LEGALLY OFF SITE
EXISTING 5' DOUBLE GATE; DEMO EXISTING DOUBLE GATE IN IT'S ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE, SEE SHT G1.03 FOR FURTHER
INFORMATION.
EXISTING 20'+/- CANTILEVER GATE; DEMO EXISTING GATE IN ITS ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE.
EXISTING 8' SINGLE GATE; DEMO EXISTING GATE IN ITS ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS OFF SITE
EXISTING 8' DOUBLE GATE; DEMO EXISTING DOUBLE GATE IN ITS ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING 8' CHAIN LINK FENCING; CHAIN LINK FENCING WITHIN SPECIFIED
AREAS ARE TO REMAIN AND ARE TO BE PROTECTED DURING THE START OF
CONSTRUCTION TYP
EXISTING BULLPEN PITCHING MOUND; DEMO EXISTING PITCHING MOUNDS IN
THEIR ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING BULLPEN BATTING BOXES; DEMO EXISTING BATTING BOXES,
CONCRETE PAD, AND HOME PLATES IN THEIR ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS OFF SITE
EXISTING PITCHING MOUND; DEMO EXISTING PITCHERS MOUNT IN ITS
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING 23' BACKSTOP CHAIN LINK FENCING; DEMO EXISTING 23' FENCING IN
ITS ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING FOUL POLES (2); LEFT FIELD LINE FOUL POLE ( L ) TO REMAIN -
PROTECT DURING THE START OF CONSTRUCTION - RIGHT FIELD LINE FOUL POLE
( R ) DEMO IN ITS ENTIRETY AND DISPOSE OF LEGALLY OFF SITE , SEE SHT G1.03
FOR FURTHER INFORMATION
EXISTING 8' DOUBLE GATE; TO REMAIN - PROTECT DURING THE START OF
CONSTRUCTION
EXISTING BULLPEN BENCHES (2); TO REMAIN - PROTECT DURING THE
START OF CONSTRUCTION, CONTRACTOR IS TO COORDINATE STORAGE OF
ITEMS WITH OWNER PRIOR TO THE START OF CONSTRUCTION
EXISTING BATTING CAGE; DEMO EXISTING BATTING CAGE IN ITS ENTIRETY
AND LEGALLY DISPOSE OF MATERIALS OFF SITE. EXISTING CONCRETE PADS
TO REMAIN - PADS ARE TO BE CLEANED AND REPAIRED AS NEEDED -
PROTECT DURING THE START OF CONSTRUCTION.
EXISTING DUGOUTS (2); SEE ARCHITECTURAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING DUGOUT CONCRETE PAVING; TO REMAIN- CLEAN AND REPAIR PAVING
AS NEEDED - PROTECT DURING THE START OF CONSTRUCTION, SEE G1.03 FOR
FURTHER INFORMATION
EXISTING HOME PLATE; DEMO HOME PLATE AND BATTING BOXES IN THEIR
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING BLEACHERS; TO REMAIN - PROTECT DURING THE START OF
CONSTRUCTION, SEE SHT G1.0 FOR FURTHER INFORMATION
(CONCRETE HATCH) EXISTING CONCRETE PAVING; DEMO IN ITS ENTIRETY
AND LEGALLY DISPOSE OF MATERIALS OFF SITE
(DOTTED HATCH) EXISTING ASPHALT PAVING; DEMO IN ITS ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING METAL EDGING AND GRAVEL BED TO BE REMOVED IN THEIR ENTIRETY
AND MATERIALS ARE TO BE LEGALLY DISPOSED OF OFF SITE
EXISTING CONCRETE JERSEY BARRIERS (9+/-); TO BE BE RELOCATED, SEE SHT
G1.02 FOR FURTHER INFORMATION
EXISTING STADIUM LIGHTING; SEE ELECTRICAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING ELECTRICAL CONDUITS; TO REMAIN - PROTECT DURING THE
START OF CONSTRUCTION, SEE ELECTRICAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING WATER LINES, CONNECTIONS AND UTILITIES; TO REMAIN -
PROTECT DURING THE START OF CONSTRUCTION MARKED OR OTHERWISE
EXISTING FIELD IRRIGATION; EXISTING IRRIGATION HEADS (15+/-) AND
SERVICE TO VARSITY BASEBALL COMPLEX IS TO BE DISCONNECTED AND
REMOVED - CONTRACTOR IS TO MAINTAIN AND OR RE-ESTABLISH
DAMAGED OR DISCONNECTED IRRIGATION LINES SERVICING JUNIOR
VARSITY FIELD TO THE EAST OF THE VARSITY BASEBALL COMPLEX
(BLUE DASH LINE) EXISTING UNDERDRAIN SYSTEM; DEMO 160+/- LF OF
UNDERDRAIN SYSTEM IN ITS ENTIRETY AND LEGALLY DISPOSE OF
MATERIALS OFF SITE, SEE SITE CIVIL DRAWINGS FOR FURTHER
INFORMATION
EXISTING CONCRETE PAVING; TO REMAIN - PROTECT DURING
THE START OF CONSTRUCTION. ALL DAMAGED PAVING IS TO
BE RE-ESTABLISHED BACK TO LIKE NEW CONDITION PRIOR
TO THE CONCLUSION OF CONSTRUCTION EFFORTS
EXISTING SCOREBOARD; SEE ARCHITECTURAL DRAWINGS
FOR FURTHER INFORMATION
EXISTING FIBER OPTIC BOX AND LINES; TO REMAIN -
PROTECT DURING THE START OF CONSTRUCTION
EXISTING SIGNAGE; TO REMAIN - PROTECT DURING THE
START OF CONSTRUCTION
EXISTING JUNIOR VARSITY CHAIN LINK DUGOUTS, SEATING
AND PAVING; DEMO IN THEIR ENTIRETY AND DISPOSE OF
MATERIALS LEGALLY OFF SITE
EXISTING ASPHALT PAVING; TO REMAIN - PROTECT DURING
THE START OF CONSTRUCTION
EXISTING SIGNAGE; DEMO IN ITS ENTIRETY AND DISPOSE
OF MATERIALS LEGALLY OFF SITE
EXISTING SITE UTILITIES; TO REMAIN UNLESS OTHERWISE
NOTED, SEE CIVIL DRAWINGS FOR FURTHER INFORMATION
EXISTING NORWAY SPRUCE; (2) DEMO IN ITS ENTIRETY AND
DISPOSE OF MATERIALS LEGALLY OFF SITE
EXISTING JUNIOR VARSITY NATURAL TURF BASEBALL FIELD
TO REMAIN - PROTECT DURING THE START OF CONSTRUCTIONSEE ENLARGED PLAN GD1.02 - SITE DEMOLITION - SOUTHSEE ENLARGED PLAN GD1.03 - SITE DEMOLITION PLAN - VARSITY BASEBALL COMPLEX08/19/21
UPARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L IAME.PAYN
EREGISTERE
D
IND I A N AARCHITE CT
4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
GD1.02
SITE DEMOLITION PLAN -
SOUTH
30 900 30 60
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.It's Fast, It's Easy and It's the Law in the state of Indiana!
VICINITY MAP
EXISTING NATURAL TURF INFIELD AND OUTFIELD; DEMO EXISTING NATURAL
TURF FIELD IN ITS ENTIRETY. CONTRACTOR IS TO COORDINATE TOPSOIL
REMOVAL AND STORAGE WITH OWNER / ARCHITECT PRIOR TO EXCAVATION.
LEGALLY DISPOSE OF MATERIALS OFF SITE.
EXISTING BASES AND ANCHORS; DEMO IN THEIR ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS OFF SITE.
EXISTING INFIELD, SKINNED AREAS AND WARNING TRACK; DEMO DIRT / BRICK
DUST AREAS IN THEIR ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF
SITE.
EXISTING 5' CHAIN LINK FENCING - LEFT FIELD LINE; DEMO FENCING IN ITS
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE.
EXISTING 5' CHAIN LINK FENCING - RIGHT FIELD LINE; DEMO FENCING IN ITS
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS LEGALLY OFF SITE.
EXISTING 8' CHAIN LINK FENCING; DEMO FENCING IN ITS ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS LEGALLY OFF SITE
EXISTING 5' DOUBLE GATE; DEMO EXISTING DOUBLE GATE IN IT'S ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE, SEE SHT G1.03 FOR FURTHER
INFORMATION.
EXISTING 20'+/- CANTILEVER GATE; DEMO EXISTING GATE IN ITS ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE.
EXISTING 8' SINGLE GATE; DEMO EXISTING GATE IN ITS ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS OFF SITE
EXISTING 8' DOUBLE GATE; DEMO EXISTING DOUBLE GATE IN ITS ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING 8' CHAIN LINK FENCING; CHAIN LINK FENCING WITHIN SPECIFIED
AREAS ARE TO REMAIN AND ARE TO BE PROTECTED DURING THE START OF
CONSTRUCTION TYP
EXISTING BULLPEN PITCHING MOUND; DEMO EXISTING PITCHING MOUNDS IN
THEIR ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING BULLPEN BATTING BOXES; DEMO EXISTING BATTING BOXES,
CONCRETE PAD, AND HOME PLATES IN THEIR ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS OFF SITE
EXISTING PITCHING MOUND; DEMO EXISTING PITCHERS MOUNT IN ITS
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING 23' BACKSTOP CHAIN LINK FENCING; DEMO EXISTING 23' FENCING IN
ITS ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING FOUL POLES (2); LEFT FIELD LINE FOUL POLE ( L ) TO REMAIN -
PROTECT DURING THE START OF CONSTRUCTION - RIGHT FIELD LINE FOUL POLE
( R ) DEMO IN ITS ENTIRETY AND DISPOSE OF LEGALLY OFF SITE , SEE SHT G1.03
FOR FURTHER INFORMATION
EXISTING 8' DOUBLE GATE; TO REMAIN - PROTECT DURING THE START OF
CONSTRUCTION
EXISTING BULLPEN BENCHES (2); TO REMAIN - PROTECT DURING THE
START OF CONSTRUCTION, CONTRACTOR IS TO COORDINATE STORAGE OF
ITEMS WITH OWNER PRIOR TO THE START OF CONSTRUCTION
EXISTING BATTING CAGE; DEMO EXISTING BATTING CAGE IN ITS ENTIRETY
AND LEGALLY DISPOSE OF MATERIALS OFF SITE. EXISTING CONCRETE PADS
TO REMAIN - PADS ARE TO BE CLEANED AND REPAIRED AS NEEDED -
PROTECT DURING THE START OF CONSTRUCTION.
EXISTING DUGOUTS (2); SEE ARCHITECTURAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING DUGOUT CONCRETE PAVING; TO REMAIN- CLEAN AND REPAIR PAVING
AS NEEDED - PROTECT DURING THE START OF CONSTRUCTION, SEE G1.03 FOR
FURTHER INFORMATION
EXISTING HOME PLATE; DEMO HOME PLATE AND BATTING BOXES IN THEIR
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING BLEACHERS; TO REMAIN - PROTECT DURING THE START OF
CONSTRUCTION, SEE SHT G1.0 FOR FURTHER INFORMATION
(CONCRETE HATCH) EXISTING CONCRETE PAVING; DEMO IN ITS ENTIRETY
AND LEGALLY DISPOSE OF MATERIALS OFF SITE
(DOTTED HATCH) EXISTING ASPHALT PAVING; DEMO IN ITS ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING METAL EDGING AND GRAVEL BED TO BE REMOVED IN THEIR ENTIRETY
AND MATERIALS ARE TO BE LEGALLY DISPOSED OF OFF SITE
EXISTING CONCRETE JERSEY BARRIERS (9+/-); TO BE BE RELOCATED, SEE SHT
G1.02 FOR FURTHER INFORMATION
EXISTING STADIUM LIGHTING; SEE ELECTRICAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING ELECTRICAL CONDUITS; TO REMAIN - PROTECT DURING THE
START OF CONSTRUCTION, SEE ELECTRICAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING WATER LINES, CONNECTIONS AND UTILITIES; TO REMAIN -
PROTECT DURING THE START OF CONSTRUCTION MARKED OR OTHERWISE
EXISTING FIELD IRRIGATION; EXISTING IRRIGATION HEADS (15+/-) AND
SERVICE TO VARSITY BASEBALL COMPLEX IS TO BE DISCONNECTED AND
REMOVED - CONTRACTOR IS TO MAINTAIN AND OR RE-ESTABLISH
DAMAGED OR DISCONNECTED IRRIGATION LINES SERVICING JUNIOR
VARSITY FIELD TO THE EAST OF THE VARSITY BASEBALL COMPLEX
(BLUE DASH LINE) EXISTING UNDERDRAIN SYSTEM; DEMO 160+/- LF OF
UNDERDRAIN SYSTEM IN ITS ENTIRETY AND LEGALLY DISPOSE OF
MATERIALS OFF SITE, SEE SITE CIVIL DRAWINGS FOR FURTHER
INFORMATION
EXISTING CONCRETE PAVING; TO REMAIN - PROTECT DURING
THE START OF CONSTRUCTION. ALL DAMAGED PAVING IS TO
BE RE-ESTABLISHED BACK TO LIKE NEW CONDITION PRIOR
TO THE CONCLUSION OF CONSTRUCTION EFFORTS
EXISTING SCOREBOARD; SEE ARCHITECTURAL DRAWINGS
FOR FURTHER INFORMATION
EXISTING FIBER OPTIC BOX AND LINES; TO REMAIN -
PROTECT DURING THE START OF CONSTRUCTION
EXISTING SIGNAGE; TO REMAIN - PROTECT DURING THE
START OF CONSTRUCTION
EXISTING JUNIOR VARSITY CHAIN LINK DUGOUTS, SEATING
AND PAVING; DEMO IN THEIR ENTIRETY AND DISPOSE OF
MATERIALS LEGALLY OFF SITE
EXISTING ASPHALT PAVING; TO REMAIN - PROTECT DURING
THE START OF CONSTRUCTION
EXISTING SIGNAGE; DEMO IN ITS ENTIRETY AND DISPOSE
OF MATERIALS LEGALLY OFF SITE
EXISTING SITE UTILITIES; TO REMAIN UNLESS OTHERWISE
NOTED, SEE CIVIL DRAWINGS FOR FURTHER INFORMATION
EXISTING NORWAY SPRUCE; (2) DEMO IN ITS ENTIRETY AND
DISPOSE OF MATERIALS LEGALLY OFF SITE
EXISTING JUNIOR VARSITY NATURAL TURF BASEBALL FIELD
TO REMAIN - PROTECT DURING THE START OF CONSTRUCTION
SEE ENLARGED PLAN GD1.01 - SITE DEMOLITION PLAN - NORTH
SEE ENLARGED PLAN GD1.03 - SITE DEMOLITION PLAN - VARSITY BASEBALL COMPLEX08/19/21
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L IAME.PAYN
EREGISTERE
D
IND I A N AARCHITE CT
4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
GD1.03
SITE DEMOLITION PLAN -
VARSITY BASEBALL COMPLEX
30 900 30 60
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.It's Fast, It's Easy and It's the Law in the state of Indiana!
VICINITY MAP
EXISTING NATURAL TURF INFIELD AND OUTFIELD; DEMO EXISTING NATURAL
TURF FIELD IN ITS ENTIRETY. CONTRACTOR IS TO COORDINATE TOPSOIL
REMOVAL AND STORAGE WITH OWNER / ARCHITECT PRIOR TO EXCAVATION.
LEGALLY DISPOSE OF MATERIALS OFF SITE.
EXISTING BASES AND ANCHORS; DEMO IN THEIR ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS OFF SITE.
EXISTING INFIELD, SKINNED AREAS AND WARNING TRACK; DEMO DIRT / BRICK
DUST AREAS IN THEIR ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF
SITE.
EXISTING 5' CHAIN LINK FENCING - LEFT FIELD LINE; DEMO FENCING IN ITS
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE.
EXISTING 5' CHAIN LINK FENCING - RIGHT FIELD LINE; DEMO FENCING IN ITS
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS LEGALLY OFF SITE.
EXISTING 8' CHAIN LINK FENCING; DEMO FENCING IN ITS ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS LEGALLY OFF SITE
EXISTING 5' DOUBLE GATE; DEMO EXISTING DOUBLE GATE IN IT'S ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE, SEE SHT G1.03 FOR FURTHER
INFORMATION.
EXISTING 20'+/- CANTILEVER GATE; DEMO EXISTING GATE IN ITS ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE.
EXISTING 8' SINGLE GATE; DEMO EXISTING GATE IN ITS ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS OFF SITE
EXISTING 8' DOUBLE GATE; DEMO EXISTING DOUBLE GATE IN ITS ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING 8' CHAIN LINK FENCING; CHAIN LINK FENCING WITHIN SPECIFIED
AREAS ARE TO REMAIN AND ARE TO BE PROTECTED DURING THE START OF
CONSTRUCTION TYP
EXISTING BULLPEN PITCHING MOUND; DEMO EXISTING PITCHING MOUNDS IN
THEIR ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING BULLPEN BATTING BOXES; DEMO EXISTING BATTING BOXES,
CONCRETE PAD, AND HOME PLATES IN THEIR ENTIRETY AND LEGALLY
DISPOSE OF MATERIALS OFF SITE
EXISTING PITCHING MOUND; DEMO EXISTING PITCHERS MOUNT IN ITS
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING 23' BACKSTOP CHAIN LINK FENCING; DEMO EXISTING 23' FENCING IN
ITS ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING FOUL POLES (2); LEFT FIELD LINE FOUL POLE ( L ) TO REMAIN -
PROTECT DURING THE START OF CONSTRUCTION - RIGHT FIELD LINE FOUL POLE
( R ) DEMO IN ITS ENTIRETY AND DISPOSE OF LEGALLY OFF SITE , SEE SHT G1.03
FOR FURTHER INFORMATION
EXISTING 8' DOUBLE GATE; TO REMAIN - PROTECT DURING THE START OF
CONSTRUCTION
EXISTING BULLPEN BENCHES (2); TO REMAIN - PROTECT DURING THE
START OF CONSTRUCTION, CONTRACTOR IS TO COORDINATE STORAGE OF
ITEMS WITH OWNER PRIOR TO THE START OF CONSTRUCTION
EXISTING BATTING CAGE; DEMO EXISTING BATTING CAGE IN ITS ENTIRETY
AND LEGALLY DISPOSE OF MATERIALS OFF SITE. EXISTING CONCRETE PADS
TO REMAIN - PADS ARE TO BE CLEANED AND REPAIRED AS NEEDED -
PROTECT DURING THE START OF CONSTRUCTION.
EXISTING DUGOUTS (2); SEE ARCHITECTURAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING DUGOUT CONCRETE PAVING; TO REMAIN- CLEAN AND REPAIR PAVING
AS NEEDED - PROTECT DURING THE START OF CONSTRUCTION, SEE G1.03 FOR
FURTHER INFORMATION
EXISTING HOME PLATE; DEMO HOME PLATE AND BATTING BOXES IN THEIR
ENTIRETY AND LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING BLEACHERS; TO REMAIN - PROTECT DURING THE START OF
CONSTRUCTION, SEE SHT G1.0 FOR FURTHER INFORMATION
(CONCRETE HATCH) EXISTING CONCRETE PAVING; DEMO IN ITS ENTIRETY
AND LEGALLY DISPOSE OF MATERIALS OFF SITE
(DOTTED HATCH) EXISTING ASPHALT PAVING; DEMO IN ITS ENTIRETY AND
LEGALLY DISPOSE OF MATERIALS OFF SITE
EXISTING METAL EDGING AND GRAVEL BED TO BE REMOVED IN THEIR ENTIRETY
AND MATERIALS ARE TO BE LEGALLY DISPOSED OF OFF SITE
EXISTING CONCRETE JERSEY BARRIERS (9+/-); TO BE BE RELOCATED, SEE SHT
G1.02 FOR FURTHER INFORMATION
EXISTING STADIUM LIGHTING; SEE ELECTRICAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING ELECTRICAL CONDUITS; TO REMAIN - PROTECT DURING THE
START OF CONSTRUCTION, SEE ELECTRICAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING WATER LINES, CONNECTIONS AND UTILITIES; TO REMAIN -
PROTECT DURING THE START OF CONSTRUCTION MARKED OR OTHERWISE
EXISTING FIELD IRRIGATION; EXISTING IRRIGATION HEADS (15+/-) AND
SERVICE TO VARSITY BASEBALL COMPLEX IS TO BE DISCONNECTED AND
REMOVED - CONTRACTOR IS TO MAINTAIN AND OR RE-ESTABLISH
DAMAGED OR DISCONNECTED IRRIGATION LINES SERVICING JUNIOR
VARSITY FIELD TO THE EAST OF THE VARSITY BASEBALL COMPLEX
(BLUE DASH LINE) EXISTING UNDERDRAIN SYSTEM; DEMO 160+/- LF OF
UNDERDRAIN SYSTEM IN ITS ENTIRETY AND LEGALLY DISPOSE OF
MATERIALS OFF SITE, SEE SITE CIVIL DRAWINGS FOR FURTHER
INFORMATION
EXISTING CONCRETE PAVING; TO REMAIN - PROTECT DURING
THE START OF CONSTRUCTION. ALL DAMAGED PAVING IS TO
BE RE-ESTABLISHED BACK TO LIKE NEW CONDITION PRIOR
TO THE CONCLUSION OF CONSTRUCTION EFFORTS
EXISTING SCOREBOARD; SEE ARCHITECTURAL DRAWINGS
FOR FURTHER INFORMATION
EXISTING FIBER OPTIC BOX AND LINES; TO REMAIN -
PROTECT DURING THE START OF CONSTRUCTION
EXISTING SIGNAGE; TO REMAIN - PROTECT DURING THE
START OF CONSTRUCTION
EXISTING JUNIOR VARSITY CHAIN LINK DUGOUTS, SEATING
AND PAVING; DEMO IN THEIR ENTIRETY AND DISPOSE OF
MATERIALS LEGALLY OFF SITE
EXISTING ASPHALT PAVING; TO REMAIN - PROTECT DURING
THE START OF CONSTRUCTION
EXISTING SIGNAGE; DEMO IN ITS ENTIRETY AND DISPOSE
OF MATERIALS LEGALLY OFF SITE
EXISTING SITE UTILITIES; TO REMAIN UNLESS OTHERWISE
NOTED, SEE CIVIL DRAWINGS FOR FURTHER INFORMATION
EXISTING NORWAY SPRUCE; (2) DEMO IN ITS ENTIRETY AND
DISPOSE OF MATERIALS LEGALLY OFF SITE
EXISTING JUNIOR VARSITY NATURAL TURF BASEBALL FIELD
TO REMAIN - PROTECT DURING THE START OF CONSTRUCTIONSEE ENLARGED PLAN GD1.02 - SITE DEMOLITION PLAN - SOUTH08/19/21
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L IAME.PAYN
EREGISTERE
D
IND I A N AARCHITE CT
4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
GD1.04
SITE DEMOLITION PLAN -
JUNIOR VARSITY BASEBALL
COMPLEX PHOTO DETAILS
EXISTING STADIUM LIGHTING POLES AND BASES TO REMAIN - SEE ELECTRICAL
DRAWINGS FOR FURTHER INFORMATION
EXISTING STORAGE BUILDING TO REMAIN - REFER TO ARCHITECTURAL
DRAWINGS FOR FURTHER INFORMATION
(CONCRETE HATCH) EXISTING PAVING - ALONG ALL FOUR SIDES OF EXISTING
STORAGE BUILDING TO BE REMOVED
8' DOUBLE CHAIN LINK GATE TO BE REMOVED
EXISTING JUNIOR VARSITY DUGOUTS ( 2 ) , FENCING AND PAVING TO BE
REMOVED
EXISTING WATER PUMP / MECHANICAL AREA TO REMAIN - PROTECT DURING
CONSTRUCTION
EXISTING NORWAY SPRUCES TO REMAIN - PROTECT DURING CONSTRUCTION
EXISTING FIBER OPTIC BOX TO TO REMAIN - PROTECT DURING CONSTRUCTION
(CONCRETE HATCH) EXISTING CONCRETE PAVING TO BE REMOVED
EXISTING 8' SINGLE GATE AND FENCING TO BE REMOVED
EXISTING DRAIN - SEE CIVIL DRAWINGS FOR FURTHER INFORMATION
24' x 12'+/- EXISTING BLEACHERS TO REMAIN - REFER TO PLANS FOR EXISTNG
BLEACHER LOCATIONS
BACKSTOP CHAIN LINK FENCE TO BE REMOVED - ALONGSIDE HOME DUGOUTS
TO BE REMOVED
* GENERAL NOTE ; SEE SITE DEMOLITION PLANS FOR FURTHER
INFORMATION
* GENERAL NOTE ; PAGE READS FROM TOP OF PAGE - RIGHT TO LEFT
12' x 8'+/- EXISTING BLEACHERS TO REMAIN - REFER TO PLANS FOR EXISTING
BLEACHER LOCATIONS
EXISTING 8' FENCING AND RIGHT FIELD FOUL
POLE TO BE REMOVED
40 1200 40 80
08/19/21
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L IAME.PAYN
EREGISTERE
D
IND I A N AARCHITE CT
4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
GD1.04
SITE DEMOLITION PLAN -
JUNIOR VARSITY BASEBALL
COMPLEX PHOTO DETAILS
EXISTING STADIUM LIGHTING POLES AND BASES TO REMAIN - SEE ELECTRICAL
DRAWINGS FOR FURTHER INFORMATION
EXISTING STORAGE BUILDING TO REMAIN - REFER TO ARCHITECTURAL
DRAWINGS FOR FURTHER INFORMATION
(CONCRETE HATCH) EXISTING PAVING - ALONG ALL FOUR SIDES OF EXISTING
STORAGE BUILDING TO BE REMOVED
8' DOUBLE CHAIN LINK GATE TO BE REMOVED
EXISTING JUNIOR VARSITY DUGOUTS ( 2 ) , FENCING AND PAVING TO BE
REMOVED
EXISTING WATER PUMP / MECHANICAL AREA TO REMAIN - PROTECT DURING
CONSTRUCTION
EXISTING NORWAY SPRUCES TO REMAIN - PROTECT DURING CONSTRUCTION
EXISTING FIBER OPTIC BOX TO TO REMAIN - PROTECT DURING CONSTRUCTION
(CONCRETE HATCH) EXISTING CONCRETE PAVING TO BE REMOVED
EXISTING 8' SINGLE GATE AND FENCING TO BE REMOVED
EXISTING DRAIN - SEE CIVIL DRAWINGS FOR FURTHER INFORMATION
24' x 12'+/- EXISTING BLEACHERS TO REMAIN - REFER TO PLANS FOR EXISTNG
BLEACHER LOCATIONS
BACKSTOP CHAIN LINK FENCE TO BE REMOVED - ALONGSIDE HOME DUGOUTS
TO BE REMOVED
* GENERAL NOTE ; SEE SITE DEMOLITION PLANS FOR FURTHER
INFORMATION
* GENERAL NOTE ; PAGE READS FROM TOP OF PAGE - RIGHT TO LEFT
12' x 8'+/- EXISTING BLEACHERS TO REMAIN - REFER TO PLANS FOR EXISTING
BLEACHER LOCATIONS
EXISTING 8' FENCING AND RIGHT FIELD FOUL
POLE TO BE REMOVED
40 1200 40 80
08/19/21
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L IAME.PAYN
EREGISTERE
D
IND I A N AARCHITE CT
4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
GD1.05
SITE DEMOLITION PLAN -
VARSITY BASEBALL COMPLEX
PHOTO DETAILS
EXISTING 5' FENCING AND (20'+/-) CANTILEVER GATE - ALONG RIGHT FIELD LINE
TO BE REMOVEDEXISTING RIGHT FIELD LINE BULLPEN - SEATING BENCH TO REMAIN - PROTECT
DURING CONSTRUCTION - CONTRACTOR IS TO COORDINATE STORAGE WITH
OWNER PRIOR TO THE START OF CONSTRUCTION
EXISTING LEFT FIELD LINE BULLPEN - SEATING TO REMAIN - PROTECT DURING
CONSTRUCTION - CONTRACTOR IS TO COORDINATE STORAGE WITH OWNER
PRIOR TO THE START OF CONSTRUCTION
EXISTING 8' DOUBLE GATE AND FENCING TO REMAIN - PROTECT DURING THE
START OF CONSTRUCTION
VISITORS SIDE 8' SINGLE GATE AND BACKSTOP TO BE REMOVED
EXISTING 5' GATE TO BE REMOVED
EXISTING CHAIN LINK FENCING ALONG HOME AND VISITOR DUGOUTS - FENCING
WITH PADS, AND LAWN TO BE REMOVED
EXISTING LEFT FIELD LINE FENCING, 5' DOUBLE GATE, AND PAVING TO BE
REMOVED
EXISTING 5' FENCING TO REMAIN - STRAIGHT SECTION OF FENCING TO REMAIN -
PROTECT DURING THE START OF CONSTRUCTION
EXISTING FENCING, GATE AND ENTRY PAVING TO REMAIN - PROTECT DURING
THE START OF CONSTRUCTION
EXISTING FENCING WITH PADS, LAWN AND 8' SINGLE GATE TO BE REMOVED
EXISTING JERSEY BARRIERS TO BE RELOCATED TO JV COMPLEX - SEE SITE
LAYOUT PLAN G1.02 FOR FURTHER INFORMATION
EXISTING BATTING TUNNEL TO BE
PROTECTED - COORDINATE STORAGE
WITH OWNER PRIOR TO THE START OF
CONSTRUCTION
EXISTING BATTING CAGES ( 2 ) ; 75' x 18' -
TO BE REMOVED IN ITS ENTIRETY
EXISTING 5' GATES ( 2 ) TO BE REMOVED
EXISTING 23' BACKSTOP FENCING TO BE
REMOVED
* GENERAL NOTE ; SEE SITE DEMOLITION PLANS FOR FURTHER
INFORMATION
* GENERAL NOTE ; PAGE READS FROM TOP OF PAGE - RIGHT TO LEFT
EXISTING 5' FENCING - RIGHT FIELD LINE TO BE REMOVED
EXISTING 8' FENCING AND RIGHT FIELD
FOUL POLE TO BE REMOVED
HOME SITE DUGOUTS TO REMAIN - SEE
ARCHITECTURAL DRAWINGS FOR
FURTHER INFORMATION
HOME DUGOUT FENCING - BOTH HOME
AND VISITORS SIDES TO BE REMOVED
23' BACKSTOP FENCING AND ( 2 ) 8' SINGLE
GATES TO BE REMOVED
EXISTING BLEACHERS TO REMAIN -
PROTECT DURING CONSTRUCTION -
CLEAN PRIOR TO THE CONCLUSION OF
CONSTRUCTION EFFORTS
EXISTING PRESS BOX - SEE
ARCHITECTURAL DRAWING FOR FURTHER
INFORMATION
40 1200 40 80
08/19/21
MATCH LINE (NORTH/SOUTH)
3
3
4
4
4
4
6
6
77
TBM#3 = 775.53
ADJOINER
MODIFY EXISTING CONCRETE
PAVED SWALE IN THIS AREA TO
MATCH PROPOSED GRADES
3
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
GD1.06
30 900 30 60
DEMOLITION KEYNOTES
1. RELOCATE PORTION OF EXISTING ELECTRICAL LINE AS REQUIRED
TO INSTALL PROPOSED STORM SEWER.
2. REMOVE EXISTING STORM DRAIN.
3. REMOVE PORTION OF EXISTING STORM PIPE WHICH INTERFERES
WITH PROPOSED CONSTRUCTION.
4. PROTECT EXISTING FIBER OPTIC LINE TO REMAIN IN PLACE.
5. PROTECT EXISTING WATER PUMP TO REMAIN IN PLACE.
6. PROTECT EXISTING ELECTRICAL LINE TO REMAIN IN PLACE.
7. PROTECT EXISTING LIGHT POLE TO REMAIN IN PLACE.
8. ADJUST UTILITY BOX TO NEW FINISH GRADE AND LOWER
EXISTING UTILITY AS REQUIRED TO MEET MINIMUM COVER
REQUIREMENTS. RELOCATE IF NECESSARY, COORDINATE WITH
UTILITY OWNER.
9. CONTRACTOR TO REMOVE EXISTING UNDERDRAIN SYSTEM
LOCATED WITHIN THE VARSITY FIELD.
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE
PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE
ENGINEER MAKES NO GUARANTEES THAT THE UNDERGROUND
UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION.
REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN
APPROVED STORM WATER MANAGEMENT PERMIT.
5. UTILITY RELOCATIONS REQUIRED BY THE PROJECT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER. UTILITY LINE RELOCATIONS
REQUIRED FOR ROAD PROJECTS THAT RESULT IN A CONFLICT WITH
PROPOSED DEVELOPMENT SHALL BE THE DEVELOPERS
RESPONSIBILITY TO RESOLVE WITH THE UTILITY. EXISTING POLE
LINES REQUIRED TO BE RELOCATED TO WITHIN ONE FOOT OF
PROPOSED RIGHT-OF-WAY LINE.
6. DAMAGE TO THE EXISTING RIGHT-OF-WAY SHALL
RESTORED/REPAIRED TO THE SATISFACTION OF THE CITY AT THE
COMPLETION OF THE PROJECT. THE CONTRACTOR IS ENCOURAGED
TO INSPECT THE RIGHT-OF-WAY WITH THE CITY PRIOR TO THE START
OF CONSTRUCTION TO DOCUMENT THE EXISTING CONDITION OF THE
RIGHT-OF-WAY.
7. DEMOLITION ITEMS INCLUDE BUT ARE NOT LIMITED TO DEMOLITION
ITEMS INDICATED ON THIS PLAN. IT IS THE CONTRACTORS
RESPONSIBILITY TO REMOVE OR RELOCATE ALL ITEMS WHICH
INTERFERE WITH NEW CONSTRUCTION.
GENERAL NOTES
SITE UTILITY DEMOLITION
PLAN - NORTH
DEMOLITION LEGEND
APPROXIMATE LIMITS OF UTILITY OR SEWER LINE
REMOVAL
08/19/21
8
MATCH LINE (NORTH/SOUTH)
1
1
2
3
4
4
5
7
7
7
7
7
7
8
4
4
9
9
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
GD1.07
30 900 30 60
DEMOLITION KEYNOTES
1. RELOCATE PORTION OF EXISTING ELECTRICAL LINE AS REQUIRED
TO INSTALL PROPOSED STORM SEWER.
2. REMOVE EXISTING STORM DRAIN.
3. REMOVE PORTION OF EXISTING STORM PIPE WHICH INTERFERES
WITH PROPOSED CONSTRUCTION.
4. PROTECT EXISTING FIBER OPTIC LINE TO REMAIN IN PLACE.
5. PROTECT EXISTING WATER PUMP TO REMAIN IN PLACE.
6. PROTECT EXISTING ELECTRICAL LINE TO REMAIN IN PLACE.
7. PROTECT EXISTING LIGHT POLE TO REMAIN IN PLACE.
8. ADJUST UTILITY BOX TO NEW FINISH GRADE AND LOWER
EXISTING UTILITY AS REQUIRED TO MEET MINIMUM COVER
REQUIREMENTS. RELOCATE IF NECESSARY, COORDINATE WITH
UTILITY OWNER.
9. CONTRACTOR TO REMOVE EXISTING UNDERDRAIN SYSTEM
LOCATED WITHIN THE VARSITY FIELD.
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE
PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE
ENGINEER MAKES NO GUARANTEES THAT THE UNDERGROUND
UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION.
REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN
APPROVED STORM WATER MANAGEMENT PERMIT.
5. UTILITY RELOCATIONS REQUIRED BY THE PROJECT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER. UTILITY LINE RELOCATIONS
REQUIRED FOR ROAD PROJECTS THAT RESULT IN A CONFLICT WITH
PROPOSED DEVELOPMENT SHALL BE THE DEVELOPERS
RESPONSIBILITY TO RESOLVE WITH THE UTILITY. EXISTING POLE
LINES REQUIRED TO BE RELOCATED TO WITHIN ONE FOOT OF
PROPOSED RIGHT-OF-WAY LINE.
6. DAMAGE TO THE EXISTING RIGHT-OF-WAY SHALL
RESTORED/REPAIRED TO THE SATISFACTION OF THE CITY AT THE
COMPLETION OF THE PROJECT. THE CONTRACTOR IS ENCOURAGED
TO INSPECT THE RIGHT-OF-WAY WITH THE CITY PRIOR TO THE START
OF CONSTRUCTION TO DOCUMENT THE EXISTING CONDITION OF THE
RIGHT-OF-WAY.
7. DEMOLITION ITEMS INCLUDE BUT ARE NOT LIMITED TO DEMOLITION
ITEMS INDICATED ON THIS PLAN. IT IS THE CONTRACTORS
RESPONSIBILITY TO REMOVE OR RELOCATE ALL ITEMS WHICH
INTERFERE WITH NEW CONSTRUCTION.
GENERAL NOTES
SITE UTILITY DEMOLITION
PLAN - SOUTHWEST
DEMOLITION LEGEND
APPROXIMATE LIMITS OF UTILITY OR SEWER LINE
REMOVAL
08/19/21
8
MATCH LINE (NORTH/SOUTH)
1
1
2
3
4
5
7
7
7
3
3
3
2
8
4
4
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
GD1.08
SITE UTILITY DEMOLITION
PLAN - SOUTHEAST
30 900 30 60
DEMOLITION KEYNOTES
1. RELOCATE PORTION OF EXISTING ELECTRICAL LINE AS REQUIRED
TO INSTALL PROPOSED STORM SEWER.
2. REMOVE EXISTING STORM DRAIN.
3. REMOVE PORTION OF EXISTING STORM PIPE WHICH INTERFERES
WITH PROPOSED CONSTRUCTION.
4. PROTECT EXISTING FIBER OPTIC LINE TO REMAIN IN PLACE.
5. PROTECT EXISTING WATER PUMP TO REMAIN IN PLACE.
6. PROTECT EXISTING ELECTRICAL LINE TO REMAIN IN PLACE.
7. PROTECT EXISTING LIGHT POLE TO REMAIN IN PLACE.
8. ADJUST UTILITY BOX TO NEW FINISH GRADE AND LOWER
EXISTING UTILITY AS REQUIRED TO MEET MINIMUM COVER
REQUIREMENTS. RELOCATE IF NECESSARY, COORDINATE WITH
UTILITY OWNER.
9. CONTRACTOR TO REMOVE EXISTING UNDERDRAIN SYSTEM
LOCATED WITHIN THE VARSITY FIELD.
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE
PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE
ENGINEER MAKES NO GUARANTEES THAT THE UNDERGROUND
UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION.
REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN
APPROVED STORM WATER MANAGEMENT PERMIT.
5. UTILITY RELOCATIONS REQUIRED BY THE PROJECT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER. UTILITY LINE RELOCATIONS
REQUIRED FOR ROAD PROJECTS THAT RESULT IN A CONFLICT WITH
PROPOSED DEVELOPMENT SHALL BE THE DEVELOPERS
RESPONSIBILITY TO RESOLVE WITH THE UTILITY. EXISTING POLE
LINES REQUIRED TO BE RELOCATED TO WITHIN ONE FOOT OF
PROPOSED RIGHT-OF-WAY LINE.
6. DAMAGE TO THE EXISTING RIGHT-OF-WAY SHALL
RESTORED/REPAIRED TO THE SATISFACTION OF THE CITY AT THE
COMPLETION OF THE PROJECT. THE CONTRACTOR IS ENCOURAGED
TO INSPECT THE RIGHT-OF-WAY WITH THE CITY PRIOR TO THE START
OF CONSTRUCTION TO DOCUMENT THE EXISTING CONDITION OF THE
RIGHT-OF-WAY.
7. DEMOLITION ITEMS INCLUDE BUT ARE NOT LIMITED TO DEMOLITION
ITEMS INDICATED ON THIS PLAN. IT IS THE CONTRACTORS
RESPONSIBILITY TO REMOVE OR RELOCATE ALL ITEMS WHICH
INTERFERE WITH NEW CONSTRUCTION.
GENERAL NOTES
DEMOLITION LEGEND
APPROXIMATE LIMITS OF UTILITY OR SEWER LINE
REMOVAL
08/19/21
TBM#1 = 782.26
A110F: DECORATIVE RESINOUS FLOORINGB: DECORATIVE RESINOUS FLOORINGW: MASONRY - PAINT CODE 4.223C: PLYWOOD - PAINT CODE 6.31
A111F: DECORATIVE RESINOUSE FLOORINGB: DECORATIVE RESINOUS FLOORINGW: MASONRY - PAINT CODE 4.223C: PLYWOOD - PAINT CODE 6.31
REMOVE EXISTING DOUBLEDOOR, INFILL OPENING WITH CMUTO MATCH EXISTING. PAINT WALLTO MATCH ADJACENT FINISH.
A110 A111UPUP
PRESSBOXA103 SEE ENLARGED G1.01 - SITE LAYOUT PLAN - NORTH PARKING LOT
SEE ENLARGED G1.01 - SITE LAYOUT PLAN - NORTH PARKING LOT
SEE ENLARGED G1.02 - SITE LAYOUT PLAN - BASEBALL COMPLEX
SEE ENLARGED G1.02 - SITE LAYOUT PLAN - BASEBALL COMPLEX
SEE ENLARGED G1.03 - SITE LAYOUT PLAN - VARSITY TURF FIELD
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
PROPOSED SITE LEGEND
HEAVY DUTY ASPHALT PAVEMENT
6" CONCRETE SIDEWALK / PAD
4" MONOLITHIC WALK AND CURB
4" CONCRETE SIDEWALK
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE PROVIDED
BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE ENGINEER MAKES NO
GUARANTEES THAT THE UNDERGROUND UTILITIES SHOWN COMPRISE ALL
SUCH UTILITIES IN THE AREA, EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE PROJECT
AREA INCLUDING UNDERGROUND UTILITY CONDITIONS, LOCATION AND DEPTH
PRIOR TO ANY OTHER SITE CONSTRUCTION. REPORT ANY DISCREPANCIES TO
THE ENGINEER.
GENERAL NOTES
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L I AME.PAY
N
EREGISTERE
D
IND I A N AARCHITE CT4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
G1.0
OVERALL SITE PLAN
SITE KEYNOTES
REFURBISHED EXISTING STORAGE BUILDING; SEE ARCHITECTURAL DRAWINGS
FOR FURTHER INFORMATION
RENOVATED VARSITY BASEBALL FIELD DUGOUTS; SEE ARCHITECTURAL
DRAWINGS FOR FURTHER INFORMATION
NEW VARSITY BASEBALL COMPLEX PREFABRICATED PRESS BOX, SEE
ARCHITECTURAL DRAWINGS FOR FURTHER INFORMATION
NEW OUTBUILDING - RESTROOM ADDITION, SEE ARCHITECTURAL DRAWINGS
FOR FURTHER INFORMATION
NEW JUNIOR VARSITY BASEBALL COMPLEX BLEACHERS, SEE ARCHITECTURAL
DRAWINGS FOR FURTHER INFORMATION
NEW JUNIOR VARSITY BASEBALL FIELD HOME AND AWAY DUGOUTS, SEE
ARCHITECTURAL DRAWINGS FOR FURTHER INFORMATION
MASONRY ENTRY AND GATE, SEE ARCHITECTURAL DRAWINGS FOR FURTHER
INFORMATION
VICINITY MAP
40 1200 40 80
08/19/21
TBM#3 = 775.53
ADJOINER
CONSULTANT
CARMEL CLAY SCHOOLS
WWW.FHAI.COM
ARCHITECT
317-848-0966
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
CARMEL HIGH
SCHOOL
5201 E MAIN STREET
CARMEL, IN 46033
HARTMAN FIELD
IMPROVEMENTS
DESIGN DEVELOPMENT
REV.
NO. DESCRIPTION DATE
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 02/17/2021
DRAWN BY: EB
PROJECT
220127.00
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
W IL L I AME.PAY
N
EREGISTERE
D
IND I A N AARCHITE CT
4169
STATE OF
No.
G1.01
SITE LAYOUT PLAN -
NORTH PARKING LOT
SEE ENLARGED PLAN G1.02 - SITE LAYOUT PLAN - BASEBALL COMPLEX
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.Call 48 hours or 2 working days before you dig.It's Fast, It's Easy and It's the Law in the state of Indiana!
SITE KEYNOTES
(DOTTEDHATCH)HEAVYDUTYASPHALTPAVEMENTWITHPETROMATENVIRO
PAVINGFABRIC- INSTALLPERMANUF.GUIDANCEANDRECOMMENDATIONS,
SEEDETAIL#13SHTG4.0
STANDARDCONCRETECURBING/RETAININGCURBWALL;VARIESINHEIGHT,
SEECIVILDRAWINGSANDDETAIL#14SHTG4.OFORFURTHERINFORMATION
(HONEYCOMBHATCH)4"CONCRETEWALK,SEEDETAILS#3, #7	SHTG4.0
MONOLITHICCURBANDWALK,SEEDETAIL#1SHTG4.0
ADAACCESSIBLECURBRAMPTYPE "A",SEEDETAIL#12SHTG4.0
(NEW )WALKTOEXISTINGWALK,SEEDETAILS#2SHTG4.0
EXISTING ACCESSIBLE RAMP TO REMAIN , PROTECT DURING CONSTRUCTION
EXISTING ASPHALT PAVING TO REMAIN , PROTECT DURING CONSTRUCTION
EXISTING LAWN; SEE L1.0 FOR FURTHER INFORMATION
CURB TAPER, SEE DETAIL #17 SHT. G4.0
EXISTING VARSITY SCOREBOARD; SEE ARCHITECTURAL DRAWINGS FOR
FURTHER INFORMATION
SEE DETAIL #15 & #16 SHT. G4.0
(NEW) STOP SIGNS (2)
(NEW) 8' ORNAMENTAL FENCING, SEE ARCHITECTURAL DRAWINGS AND
DETAIL #11 SHT G4.0 FOR FURTHER INFORMATION
1' WIDE x12'+/- LONG WHITE PAINTED STOP BAR
4" WIDE WHITE PAINTED LINE, TYP AT CAR 9X20 +/- PARKING SPACES AND ADA
PARKING SPACES
CJ -TYPICAL CONTRACTION JOINS, SEE DETAILS #6 & #7 SHT G4.0
EJ - TYPICAL EXPANSION JOINTS, SEE DETAILS #6 & #7 SHT G4.0
ACCESSIBLE CROSSWALK: 4" BLUE PAINTED DIAGONAL LINES, SEE DETAIL #10
SHT G4.O
(NEW) MASONRY COLUMN ENTRY AND FENCING, SEE ARCHITECTURAL
DRAWINGS FOR FURTHER INFORMATION
EXISTING FENCING TO REMAIN, PROTECT DURING THE START OF
CONSTRUCTION, SEE G1.03 FOR FURTHER INFORMATION
NEW 8' CHAIN LINK FENCING WITH YELLOW PLASTIC FENCE CAP TO MATCH
EX. TYP, SEE DETAILS #4, #6, & #7 SHT G4.01 AND PROJECT MANUAL FOR
FUTHER INFORMATION
NEW 8' HIGH DOUBLE FENCE GATE TO MATCH EXISTING, SEE DETAIL #4 SHT
G4.02
NEW 5'-7" HIGH MACRO BOX SLIDE GATE; COLOR (BLACK), 50' MAX
OPENING, BY PRO ACCESS SYSTEMS WITH HARDWARE AND ACCESSORIES
PER MANUF. WRITTEN RECOMMENDATIONS. PROVIDE A SLIDE DRIVE 40
WITH HYDRAULIC GATE OPERATOR - 1 HP, OPERATING AT ONE FOOT PER
SECOND. BATTERY BACKUP TO BE PROVIDED. GATE OPERATOR TO
FUNCTION WITH AN OPEN, STOP, CLOSE BUTTON - THE BUTTON IS TO BE
LOCATED ON THE INSIDE OF THE COMPLEX FENCING. SAFETY FEATURES TO
COMPLY WITH UL-325 PHOTO EYES, AND MILLER EDGES, AS WELL AS LOOP
DETECTORS IMBEDDED WITHIN PROPOSED CONCRETE PAVEMENT. GATE IS
TO BE LOCKABLE FROM THE INSIDE OF COMPLEX FENCING. SEE DETIAL #5B
SHT. G4.02 FOR GATE
NEW 8' HIGH SINGLE FENCE GATE TO MATCH EXISTING, SEE DETAIL #4
SHT G4.02
NEW 5' HIGH FENCING WITH YELLOW PLASTIC FENCE CAP TO MATCH
EXISTING, SEE DETAILS #4, #6 & #7 SHT G4.01 AND PROJECT MANUAL FOR
FURTHER INFORMATION
NEW 5' HIGH DOUBLE FENCE GATE TO MATCH EXISTING,
SEE DETAIL #4 SHT G4.02
EXISTING STADIUM LIGHTING; SEE ELECTRICAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING FOUL LINE POLES; (1) LEFT FIELD FOUL POLE TO BE CLEANED,
REPAINTED . RIGHT FIELD FOUL POLE IS TO BE DEMOLISHED AND DISPOSED
OF LEGALLY OFF SITE - INSTALL NEW RIGHT FIELD FOUL POLE PER DETAIL #3
G4.02
(NEW) JV BACKSTOP FENCING; 25' CHAINLINK FENCING ATTACHED TO
EXISTING BACKSTOP FENCING, SEE DETAIL #6 & #7 SHT G4.01
(NEW) TENSION NETTING SYSTEM AND ACCESSORIES; 40' HIGH x 80' LONG
NETTING. TENSION NETTING SYSTEM FOUNDATIONS ARE TO BE
CONSTRUCTED AND INSTALLED PER MANUFACTURES RECOMMENDATIONS.
HEAVY DUTY PAVEMENT AT EXISTING PAVING, SEE DETAIL #18 SHT G4.0
RELOCATED EX. CONCRETE JERSEY BARRIER STOCKPILE PITS (9+/-).
(2) CANTILEVER BATTING TUNNELS; STANDARD BLACK POWDER COATED
FINISH - 75' LENGTH - END BAY WIDTH 20'-11" - MIDDLE BAY WIDTH @ 18'-9" -
INSTALL PER MANUF. GUIDANCE AND RECONMONDATIONS. BATTING CAGE
FOUNDATIONS ARE TO BE CONSTRUCTED AND INSTALLED PER MANUF.
RECOMMENDATIONS. EXISTING CONCRETE PADS TO REMAIN- CLEAN AND
REPAIR AS NEEDED, PROTECT EXISTING CONCRETE PADS DURING THE
START OF CONSTRUCTION, SEE DETAIL #6 SHT G4.02
(CONCRETE HATCH) 6" CONCRETE WALK, SEE DETAILS #4 , #7 SHT G4.0
PARKING BUMPERS: PROVIDE PRECAST CONCRETE PARKING BUMPERS -
6' IN LENGTH IN SPECIFIED ( YELLOW ) AND ( HANDICAPPED BLUE ) IN
QUANTITIES AND WITHIN SPECIFIED LOCATIONS AS NOTED ON DRAWINGS.
EACH PARKING BUMPER IS TO BE INSTALLED ON AT-GRADE OF ASPHALT
PAVEMENT - AND SHOULD BE MANUFACTURED WITH TWO HOLES TO
ACCOMMODATE THE INSTALLATION OF REBAR, SEE PROJECT MANUAL
FOR FURTHER INFORMATION.
TYPICAL CONCRETE STOOP: SEE STRUCTURAL DRAWINGS FOR FURTHER
INFORMATION
( 6 TOTAL ) SIX SPACE BIKE RACKS SHALL BE ORIGINAL APEX "INVERTED U"
BIKE PARKING WITH EMBEDMENT TYPE INSTALLATION AS MANUF. BY
SITESCAPES 402-421-9479 IN COLOR AND FINISH AS SELECTED BY
ARCHITECT ( BLACK ) TYP, SEE DETAIL #19 SHT. G4.0
NEW 7'-7" TALL , 46' MAX OPENING, MACRO BOX SLIDE GATE BY PRO
ACCESS SYSTEMS WITH HARDWARE AND ACCESSORIES PER MANUF.
WRITTEN RECOMMENDATIONS, COLOR IS TO MATCH EXISTING FENCING
( BLACK ). PROVIDE A SLIDE DRIVE 40 WITH HYDRAULIC GATE
OPERATOR - 1 HP, OPERATING AT ONE FOOT PER SECOND. BATTERY
BACKUP TO BE PROVIDED. GATE OPERATOR TO FUNCTION WITH AN
OPEN, STOP, CLOSE BUTTON - THE BUTTON IS TO BE LOCATED ON THE
INSIDE OF THE COMPLEX FENCING. SAFETY FEATURES TO COMPLY
WITH UL-325 PHOTO EYES, AND MILLER EDGES, AS WELL AS LOOP
DETECTORS IMBEDDED WITHIN PROPOSED CONCRETE PAVEMENT.
GATE IS TO BE LOCKABLE FROM THE INSIDE OF COMPLEX FENCING.
SEE DETIAL #5A SHT. G4.02 FOR GATE
NEW KNOX LOCK BOXES (3 TOTAL); PROVIDE ( 1 ) KNOX LOCK BOX AT
SPECIFIED GATE LOCATION
SEE SU1.02 FOR SANITARY CONNECTION
EXISTING CONCRETE PAVING TO REMAIN, PROTECT
DURING CONSTRUCTION
EXISTING FENCING TO REMAIN, PROTECT DURING
CONSTRUCTION
PROPOSED SITE LEGEND
HEAVY DUTY ASPHALT PAVEMENT
6" CONCRETE SIDEWALK / PAD
4" MONOLITHIC WALK AND CURB
4" CONCRETE SIDEWALK
PARKING SUMMARY
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE PROVIDED
BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE ENGINEER MAKES NO
GUARANTEES THAT THE UNDERGROUND UTILITIES SHOWN COMPRISE ALL
SUCH UTILITIES IN THE AREA, EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE PROJECT
AREA INCLUDING UNDERGROUND UTILITY CONDITIONS, LOCATION AND DEPTH
PRIOR TO ANY OTHER SITE CONSTRUCTION. REPORT ANY DISCREPANCIES TO
THE ENGINEER.
GENERAL NOTES
30 900 30 60
VICINITY MAP
08/19/21
A110A1111
1
2
3
SITE KEYNOTES
(DOTTEDHATCH)HEAVYDUTYASPHALTPAVEMENTWITHPETROMATENVIRO
PAVINGFABRIC- INSTALLPERMANUF.GUIDANCEANDRECOMMENDATIONS,
SEEDETAIL#13SHTG4.0
STANDARDCONCRETECURBING/RETAININGCURBWALL;VARIESIN HEIGHT,
SEECIVILDRAWINGSANDDETAIL#14SHTG4.OFORFURTHERINFORMATION
(HONEYCOMBHATCH)4"CONCRETEWALK,SEEDETAILS#3, #7	SHTG4.0
MONOLITHICCURBANDWALK,SEEDETAIL#1SHTG4.0
ADAACCESSIBLECURBRAMPTYPE "A",SEEDETAIL#12SHTG4.0
(NEW )WALKTOEXISTINGWALK,SEEDETAILS#2SHTG4.0
EXISTING ACCESSIBLE RAMP TO REMAIN , PROTECT DURING CONSTRUCTION
EXISTING ASPHALT PAVING TO REMAIN , PROTECT DURING CONSTRUCTION
EXISTING LAWN; SEE L1.0 FOR FURTHER INFORMATION
CURB TAPER, SEE DETAIL #17 SHT. G4.0
EXISTING VARSITY SCOREBOARD; SEE ARCHITECTURAL DRAWINGS FOR
FURTHER INFORMATION
SEE DETAIL #15 & #16 SHT. G4.0
(NEW) STOP SIGNS (2)
(NEW) 8' ORNAMENTAL FENCING, SEE ARCHITECTURAL DRAWINGS AND
DETAIL #11 SHT G4.0 FOR FURTHER INFORMATION
1' WIDE x12'+/- LONG WHITE PAINTED STOP BAR
4" WIDE WHITE PAINTED LINE, TYP AT CAR 9X20 +/- PARKING SPACES AND ADA
PARKING SPACES
CJ -TYPICAL CONTRACTION JOINS, SEE DETAILS #6 & #7 SHT G4.0
EJ - TYPICAL EXPANSION JOINTS, SEE DETAILS #6 & #7 SHT G4.0
ACCESSIBLE CROSSWALK: 4" BLUE PAINTED DIAGONAL LINES, SEE DETAIL #10
SHT G4.O
(NEW) MASONRY COLUMN ENTRY AND FENCING, SEE ARCHITECTURAL
DRAWINGS FOR FURTHER INFORMATION
EXISTING FENCING TO REMAIN, PROTECT DURING THE START OF
CONSTRUCTION, SEE G1.03 FOR FURTHER INFORMATION
NEW 8' CHAIN LINK FENCING WITH YELLOW PLASTIC FENCE CAP TO MATCH
EX. TYP, SEE DETAILS #4, #6, & #7 SHT G4.01 AND PROJECT MANUAL FOR
FUTHER INFORMATION
NEW 8' HIGH DOUBLE FENCE GATE TO MATCH EXISTING, SEE DETAIL #4 SHT
G4.02
NEW 5'-7" HIGH MACRO BOX SLIDE GATE; COLOR (BLACK), 50' MAX
OPENING, BY PRO ACCESS SYSTEMS WITH HARDWARE AND ACCESSORIES
PER MANUF. WRITTEN RECOMMENDATIONS. PROVIDE A SLIDE DRIVE 40
WITH HYDRAULIC GATE OPERATOR - 1 HP, OPERATING AT ONE FOOT PER
SECOND. BATTERY BACKUP TO BE PROVIDED. GATE OPERATOR TO
FUNCTION WITH AN OPEN, STOP, CLOSE BUTTON - THE BUTTON IS TO BE
LOCATED ON THE INSIDE OF THE COMPLEX FENCING. SAFETY FEATURES TO
COMPLY WITH UL-325 PHOTO EYES, AND MILLER EDGES, AS WELL AS LOOP
DETECTORS IMBEDDED WITHIN PROPOSED CONCRETE PAVEMENT. GATE IS
TO BE LOCKABLE FROM THE INSIDE OF COMPLEX FENCING. SEE DETIAL #5B
SHT. G4.02 FOR GATE
NEW 8' HIGH SINGLE FENCE GATE TO MATCH EXISTING, SEE DETAIL #4
SHT G4.02
NEW 5' HIGH FENCING WITH YELLOW PLASTIC FENCE CAP TO MATCH
EXISTING, SEE DETAILS #4, #6 & #7 SHT G4.01 AND PROJECT MANUAL FOR
FURTHER INFORMATION
NEW 5' HIGH DOUBLE FENCE GATE TO MATCH EXISTING,
SEE DETAIL #4 SHT G4.02
EXISTING STADIUM LIGHTING; SEE ELECTRICAL DRAWINGS FOR FURTHER
INFORMATION
EXISTING FOUL LINE POLES; (1) LEFT FIELD FOUL POLE TO BE CLEANED,
REPAINTED . RIGHT FIELD FOUL POLE IS TO BE DEMOLISHED AND DISPOSED
OF LEGALLY OFF SITE - INSTALL NEW RIGHT FIELD FOUL POLE PER DETAIL #3
G4.02
(NEW) JV BACKSTOP FENCING; 25' CHAINLINK FENCING ATTACHED TO
EXISTING BACKSTOP FENCING, SEE DETAIL #6 & #7 SHT G4.01
(NEW) TENSION NETTING SYSTEM AND ACCESSORIES; 40' HIGH x 80' LONG
NETTING. TENSION NETTING SYSTEM FOUNDATIONS ARE TO BE
CONSTRUCTED AND INSTALLED PER MANUFACTURES RECOMMENDATIONS.
HEAVY DUTY PAVEMENT AT EXISTING PAVING, SEE DETAIL #18 SHT G4.0
RELOCATED EX. CONCRETE JERSEY BARRIER STOCKPILE PITS (9+/-).
(2) CANTILEVER BATTING TUNNELS; STANDARD BLACK POWDER COATED
FINISH - 75' LENGTH - END BAY WIDTH 20'-11" - MIDDLE BAY WIDTH @ 18'-9" -
INSTALL PER MANUF. GUIDANCE AND RECONMONDATIONS. BATTING CAGE
FOUNDATIONS ARE TO BE CONSTRUCTED AND INSTALLED PER MANUF.
RECOMMENDATIONS. EXISTING CONCRETE PADS TO REMAIN- CLEAN AND
REPAIR AS NEEDED, PROTECT EXISTING CONCRETE PADS DURING THE
START OF CONSTRUCTION, SEE DETAIL #6 SHT G4.02
(CONCRETE HATCH) 6" CONCRETE WALK, SEE DETAILS #4 , #7 SHT G4.0
PARKING BUMPERS: PROVIDE PRECAST CONCRETE PARKING BUMPERS -
6' IN LENGTH IN SPECIFIED ( YELLOW ) AND ( HANDICAPPED BLUE ) IN
QUANTITIES AND WITHIN SPECIFIED LOCATIONS AS NOTED ON DRAWINGS.
EACH PARKING BUMPER IS TO BE INSTALLED ON AT-GRADE OF ASPHALT
PAVEMENT - AND SHOULD BE MANUFACTURED WITH TWO HOLES TO
ACCOMMODATE THE INSTALLATION OF REBAR, SEE PROJECT MANUAL
FOR FURTHER INFORMATION.
TYPICAL CONCRETE STOOP: SEE STRUCTURAL DRAWINGS FOR FURTHER
INFORMATION
( 6 TOTAL ) SIX SPACE BIKE RACKS SHALL BE ORIGINAL APEX "INVERTED U"
BIKE PARKING WITH EMBEDMENT TYPE INSTALLATION AS MANUF. BY
SITESCAPES 402-421-9479 IN COLOR AND FINISH AS SELECTED BY
ARCHITECT ( BLACK ) TYP, SEE DETAIL #19 SHT. G4.0
NEW 7'-7" TALL , 46' MAX OPENING, MACRO BOX SLIDE GATE BY PRO
ACCESS SYSTEMS WITH HARDWARE AND ACCESSORIES PER MANUF.
WRITTEN RECOMMENDATIONS, COLOR IS TO MATCH EXISTING FENCING
( BLACK ). PROVIDE A SLIDE DRIVE 40 WITH HYDRAULIC GATE
OPERATOR - 1 HP, OPERATING AT ONE FOOT PER SECOND. BATTERY
BACKUP TO BE PROVIDED. GATE OPERATOR TO FUNCTION WITH AN
OPEN, STOP, CLOSE BUTTON - THE BUTTON IS TO BE LOCATED ON THE
INSIDE OF THE COMPLEX FENCING. SAFETY FEATURES TO COMPLY
WITH UL-325 PHOTO EYES, AND MILLER EDGES, AS WELL AS LOOP
DETECTORS IMBEDDED WITHIN PROPOSED CONCRETE PAVEMENT.
GATE IS TO BE LOCKABLE FROM THE INSIDE OF COMPLEX FENCING.
SEE DETIAL #5A SHT. G4.02 FOR GATE
NEW KNOX LOCK BOXES (3 TOTAL); PROVIDE ( 1 ) KNOX LOCK BOX AT
SPECIFIED GATE LOCATION
SEE SU1.02 FOR SANITARY CONNECTION
EXISTING CONCRETE PAVING TO REMAIN, PROTECT
DURING CONSTRUCTION
EXISTING FENCING TO REMAIN, PROTECT DURING
CONSTRUCTION
PROPOSED SITE LEGEND
HEAVY DUTY ASPHALT PAVEMENT
6" CONCRETE SIDEWALK / PAD
4" MONOLITHIC WALK AND CURB
4" CONCRETE SIDEWALK
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE PROVIDED
BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE ENGINEER MAKES NO
GUARANTEES THAT THE UNDERGROUND UTILITIES SHOWN COMPRISE ALL
SUCH UTILITIES IN THE AREA, EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE PROJECT
AREA INCLUDING UNDERGROUND UTILITY CONDITIONS, LOCATION AND DEPTH
PRIOR TO ANY OTHER SITE CONSTRUCTION. REPORT ANY DISCREPANCIES TO
THE ENGINEER.
GENERAL NOTES
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
ADDENDUM #1 6/01/20211
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L I AME.PAY
N
EREGISTERE
D
IND I A N AARCHITE CT4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
ADDENDUM #2 6/07/20212
ADDENDUM #3 6/11/20213
G1.02
SITE LAYOUT PLAN - BASEBALL
COMPLEXES
30 900 30 60
VICINITY MAP
SEE ENLARGED PLAN G1.01 - SITE LAYOUT PLAN - NORTH PARKING LOT
08/19/21
57'-0"UP6'-5 1/2" 6'-3"ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L I AME.PAY
N
EREGISTERE
D
IND I A N AARCHITECT4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
G1.03
VARSITY BASEBALL FIELD TURF
LAYOUT PLAN
30 900 30 60
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.It's Fast, It's Easy and It's the Law in the state of Indiana!
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN
THE PROJECT AREA INCLUDING UNDERGROUND UTILITY
CONDITIONS, LOCATION AND DEPTH PRIOR TO ANY OTHER
SITE CONSTRUCTION. REPORT ANY DISCREPANCIES TO THE
ENGINEER.
GENERAL NOTES
CONSTRUCT 6" X 18" DEEP REINFORCED CONCRETE CURB AND 2X4" TREATED
NAILER STRIP AROUND PERIMETER OF SYNTHETIC TURF. SEE DETAIL #2 SHT
G4.01.
(WITHIN DOTTED HATCH) INSTALL STANDARD GREEN PLAYING FIELD
SYNTHETIC TURF WITH SAND/ECOFILL ( BROWN ) MATERIAL MIX IN LIGHT
SHADED AREAS AS NOTED ON SHT G1.04 GRAPHIC PLAN - OVER 6" MIN. FREE
DRAINING AGGREGATE. SEE DETAILS #2 & #3 SHT G4.01 FOR TURF SYSTEM
(WITHIN DARK SHADED AREAS) INFIELD AND SKINNED AREAS; INSTALL TAN
SYNTHETIC TURF WITH 1 34" PILE HEIGHT OF SAND/ECOFILL ( BROWN ) MATERIAL
MIX IN DARK SHADED AREAS AS NOTED ON SHT G1.04 GRAPHIC PLAN - OVER 6"
MIN. FREE DRAINING AGGREGATE. SEE DETAIL #2 G4.01 FOR TURF SYSTEM
INSTALL TAN WARNING TRACK SYNTHETIC TURF WITH 1 34" PILE HEIGHT OF
SAND/WALNUT GROUNDS INFILL IN DARK SHADED AND HATCHED AREAS AS
NOTED ON SHT G1.04 GRAPHIC PLAN OVER 6" MIN. FREE DRAINING AGGREGATE,
SEE DETAILS #2 & #3 G4.01 FOR TURF SYSTEM
INSTALL WHITE SYNTHETIC TURF BASELINE AND HOMEPLATE SYNTHETIC TURF
MARKINGS AS NOTED AND AS PER NFHS GUIDELINES. INSTALL REMOVABLE
SHP-RBA-SCHUTT BURY-ALL HOME PLATE OVER SYNTHETIC TURF PERMANENT
MARKINGS - INSTALL SHBBP-44-SHUTT GROUND ANCHOR MOUNTS AS MANUF. BY
SPORTSFIELD SPECIALTIES 312-933-9680, SEE DETAIL #10 SHT G4.01, DETAILS #2
& #8 SHT G4.02
INSTALL WHITE SYNTHETIC SURFACING PERMANENT BASES IN LOCATIONS AND
AS REQUIRED BY NFHS GUIDELINES. INSTALL REMOVABLE SHBBPL-SCHUTT
JACK CORBETT MLB HOLLYWOOD BASES - INSTALL SHBBP-44-SHUTT GROUND
ANCHOR MOUNTS AS MANUF. BY SPORTSFIELD SPECIALTIES 312-99-9680 , SEE
DETAIL #5 SHT G4.01 AND DETAIL #9 G4.02 - INSTALL PER MANUF.
RECOMMENDATIONS
INSTALL PORTABLE PITCHERS MOUND WITH PITCHING RUBBER IN LOCATIONS
AS NOTED. PORTABLE PITCHING MOUNDS SHALL BE PPGIT (LGPRTPTCH-GR-SYN)
"PORTA-PITCH" AS MANUF. BY SPORTSFIELD SPECIALTIES 312-933-9680 OR THE
"PERFECT MOUND" #330-920-019 AS MANUFACTURED BY BEACON ATHLETICS
800-747-5985. SYNTHETIC TURF IS TO MATCH INFIELD AND SKINNED AREAS WITH
1 3
4" PILE HEIGHT OF SAND/ECOFILL ( BROWN ) MATERIAL MIX, SEE DETAIL #7
G4.02
INSTALL PORTABLE DOUBLE BULLPEN MOUNDS WITH PITCHING RUBBER PER
NFHS GUIDELINES. SYNTHETIC TURF IS TO MATCH INFIELD AND SKINNED AREAS
WITH 1 34" PILE HEIGHT OF SAND/ECOFILL ( BROWN ) MATERIAL MIX, SEE DETAIL
#9 SHT G4.01, AND DETAIL #1 G4.02
(CONCRETE HATCH) IN LOCATIONS WHERE NEW SIDEWALK AND FENCING ABUTS
SYNTHETIC TURF THICKEN CONCRETE SLAB TO 8 x 18 FOR ATTACHMENT OF
NAILER BOARD. SEE DETAIL #3 SHT G4.01
EXISTING FENCING TO REMAIN TYP. CONTRACTOR IS TO COORDINATE REMOVAL,
STORAGE AND RE-INSTALL OF EXISTING ( BLUE ) WINDSCREEN FENCE COVER
WITH OWNER PRIOR TO THE START OF CONSTRUCTION
CARMEL GREYHOUNDS FIELD LOGO IN COLOR AND SIZE AS SELECTED BY
OWNER, SEE DETAIL #11 G4.01
(MAGENTA DASH DOT LINE) NFHS REGULATED
TURF BASEBALL FIELD LAYOUT, SEE G1.03
BASEBALL FIELD DIMENSIONS AND FIELD
DIMENSIONS KEY FOR FURTHER INFORMATION,
SEE DETAIL #9 G4.01 FOR FURTHER INFORMATION
4" WIDE WHITE TUFTED SYNTHETIC FABRIC
STRAIGHT POLE TO POLE TENSION NET SYSTEM ; @
40' H X 80' LONG : TNPPSG - CUSTOM POLE TO POLE
TENSION NETTING SYSTEM AS MANUF. BY
SPORTSFIELD SPECIALTIES 312-933-9680, SYSTEM
INCLUDES POWDER COATED BLACK STEEL POLES
WITH WELDED TABS, CABLING, HARDWARE PER
DRAWINGS AND SPECIFICATIONS AND BLACK #36
NYLON NETTING WITH 1-3/4" SQUARE MESH AND ROPE
BOUND PERIMETER - INSTALL PER MANUF.
RECOMMENDATIONS. TENSION NETTING SYSTEM
FOUNDATIONS ARE TO BE CONSTRUCTED PER MANUF.
RECOMMENDATIONS.
MASONRY BACKSTOP ; INSTALL TNPPUC - CUSTOM
POLE TO POLE TENSION NETTING SYSTEM, INCLUDES
POWDER COATE BLACK STEEL POLES WITH WELDED
TABS, CABLING, HARDWARE PER DRAWINGS AND
SPECIFIECATIONS AND BLACK ULTRA CROSS
KNOTLESS DYNEEMA NETTING WITH 1-3/4" SQUARE
MESH AND A ROPE BOUND PERIMETER WITHIN
MASONRY BACKSTOP WALL .TENSION NETTING
SYSTEM FOUNDATIONS ARE TO BE CONSTRUCTED
PER MANUF. RECOMMENDATIONS, SEE DETAIL #1 SHT
G4.01 AND ARCHITECTURAL DRAWINGS FOR
FURTHER INFORMATION
EXISTING FOUL POLES ( 2 ); LEFT FIELD LINE EXISTING
FLAGPOLE - CLEAN, REPAINT AND MAKE LIKE NEW TO
MATCH EXISTING (FLUORESCENT YELLOW) COLOR.
RIGHT FIELD EXISTING FLAGPOLE TO BE DEMOLISHED
AND DISPOSED OF LEGALLY OFF SITE - PROVIDE NEW
FLAGPOLE PER DETAIL #3 G4.02
PLYO TRAINING WALL; TO BE PROVIDED AND
INSTALLED BY OWNER - COORDINATE INSTALLATION
WITH OWNER PRIOR TO CONSTRUCTION
NEW 5' CHAIN LINK FENCING WITH YELLOW FENCING
CAP, SEE DETAIL #8 SHT G4.01
* GENERAL NOTE - PROVIDE ALTERNATE FOR
SHOCKPAD, SEE PROJECT MANUAL FOR
FURTHER INFORMATION
* GENERAL NOTE - IF ALTERNATE SHOCKPAD IS
SELECTED - SYNTHETIC TURF INFILL RATIO IS
TO BE 70% SAND ( 3 LBS ) /
30% 'ECOFILL' ( 2 LBS )
97'-3"
66'-5"
320'-0"
390'-0"
18'-1"
13'-0"
6'-0"
3'-0"
Hartman Field - Varsity Baseball Complex
VICINITY MAP
08/19/21
8A1.05UP6'-5 1/2"6'-3"ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L I AME.PAY
N
EREGISTERE
D
IND I A N AARCHITECT4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
G1.04
VARSITY BASEBALL FIELD TURF
GRAPHIC PLAN
SITE KEYNOTES
HOME PLATE; WHITE SYNTHETIC TURF COLOR, SEE SHT G1.03 FOR FURTHER
INFORMATION
PERMANENT BASE MARKINGS; WHITE SYNTHETIC TURF COLOR, SEE SHT G1.03
FOR FURTHER INFORMATION
FOUL LINES; WHITE SYNTHETIC TURF COLOR, SEE SHT G1.03 FOR FURTHER
INFORMATION
INFIELD AND SKINNED AREAS; TAN SYNTHETIC TURF COLOR, SEE SHT G1.03 FOR
FURTHER INFORMATION
WARNING TRACK; TAN SYNTHETIC TURF COLOR, SEE SHT G1.03 FOR FURTHER
INFORMATION
INFIELD LAWN AND OUTFIELD LAWN; ALTERNATING STANDARD GREEN & DARK
GREEN SYNTHETIC TURF COLOR PANELS, SEE SHT G1.03 FOR FURTHER
INFORMATION
SIDELINE AREAS; TAN SYNTHETIC TURF COLOR, SEE SHT G1.03 FOR FURTHER
INFORMATION
STANDARD GREEN SYNTHETIC TURF COLOR, SEE SHT G1.03 FOR FURTHER
INFORMATION
REPLACEABLE VELCRO BATTERS/CATCHERS BOXES; WITH TAN SYNTHETIC TURF
COLOR WITH WHITE OUTLINING, SEE SHT G1.03 FOR FURTHER INFORMATION
DOUBLE BULLPEN PORTA-PITCH SYNTHETIC MOUND SYSTEM; TAN SYNTHETIC
TURF COLOR TO MATCH INFIELD AND SKINNED AREAS, SEE SHT G1.03 FOR
FURTHER INFORMATION
BULLPEN BATTING BOX; TAN SYNTHETIC TURF COLOR WITH WHITE OUTLINE, SEE
SHT G1.03 FOR FURTHER INFORMATION
CARMEL GREYHOUNDS FIELD LOGO; SEE SHT G1.03 FOR FURTHER
INFORMATION
REPLACEABLE 2ND AND 3RD BASE SLIDING LANES; VELCRO SYNTHETIC TURF PIECE
- TAN SYNTHETIC TURF COLOR, SEE SHT G1.03 FOR FURTHER INFORMATION
REPLACEABLE 1ST BASE LEAD OFF ZONE; VELCRO SYNTHETIC TURF PIECE -
TAN SYNTHETIC TURF COLOR, SEE SHT G1.03 FOR FURTHER INFORMATION
PERMANENT PITCHING CIRCLE; 4" WHITE OUTLINE WITH TAN SYNTHETIC TURF
COLOR WITHIN CIRCLE, SEE SHT G1.03 FOR FURTHER INFORMATION
BATTING CAGE ARTIFICIAL TURF; STANDARD GREEN SYNTHETIC TURF COLOR,
SEE SHT G1.03 FOR FURTHER INFORMATION
TUFTED ON DECK CIRCLE MARKING; 4" WHITE SYNTHETIC TURF, SEE SHT G1.03
FOR FURTHER INFORMATION
RENOVATED DUGOUTS; SEE ARCHITECTURAL DRAWINGS FOR FURTHER
INFORMATION
NEW 5' FENCING WITH ACCESSORIES, HARDWARE AND CORRUGATED YELLOW
FENCE CAP
20 600 20 40 INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.It's Fast, It's Easy and It's the Law in the state of Indiana!
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN
THE PROJECT AREA INCLUDING UNDERGROUND UTILITY
CONDITIONS, LOCATION AND DEPTH PRIOR TO ANY OTHER
SITE CONSTRUCTION. REPORT ANY DISCREPANCIES TO THE
ENGINEER.
GENERAL NOTES
VICINITY MAP
08/19/21
TBM#2 = 791.71
TBM#3 = 775.53
ADJOINER
TBM#1 = 782.26
ADJOINER
ADJOINER
ADJOINER
TBM#4 = 779.85
TBM#2 = 781.44
E. MAI N STREET
1
2
WTR
SAN
WTR
WTR
SAN SANWTR
SAN SAN SANWT
RST-108
ST-102 ST-104
ST-103
ST-107 ST-112
ST-105
ST-113
ST-109
ST-111
ST-101
ST-110
ST-106 ST-114
ST-108A
CONSTRUCTION LIMITS
CONSTRUCTION LIMITS
CONSTRUCTION LIMITS
CONSTRUCTION LIMITS
CONSTRUCTION LIMITS
CONSTRUCTION LIMITS
BUILDING INFORMATION
FINISH FLOOR ELEV.= 779.75
MIN. LOWEST ADJACENT GRADE = 779.25
MIN. FLOOD PROTECTION GRADE = 778.52
EAST BASIN PROPOSED CONDITIONS
CONTRIBUTING DRAINAGE AREA = 13.83
10 YR. DISCHARGE = 10.72 CFS
10 YR. STAGE ELEV.= 774.85
10 YR. STORAGE VOLUME = 0.77 AC/FT
100 YR. DISCHARGE = 12.14 CFS
100 YR. STAGE ELEV.= 776.52
100 YR. STORAGE VOLUME REQUIRED = 2.30 AC/FT
100 YR. STORAGE VOLUME PROVIDED = 6.0 AC/FT
UNDERGROUND DETENTION CHAMBERS (SC-740)
CONTRIBUTING DRAINAGE AREA = 3.16 ACRES
MINIMUM FINISH GRADE ELEV. = 783.00
TOP OF STONE = 782.50
TOP OF CHAMBERS = 781.50
BOTTOM OF CHAMBERS = 779.00
BOTTOM OF STONE = 778.50
21 ROWS OF 27 CHAMBERS = 47,355 CFT.
10 YR. DISCHARGE = 1.02 CFS
10 YR. STAGE ELEV.= 780.06
10 YR. STORAGE VOLUME = 0.49 AC/FT
100 YR. DISCHARGE = 2.03 CFS
100 YR. STAGE ELEV.= 781.20
100 YR. STORAGE VOLUME REQUIRED = 0.85 AC/FT
100 YR. STORAGE VOLUME PROVIDED = 1.09 AC/FT
WEST BASIN PROPOSED CONDITIONS
CONTRIBUTING DRAINAGE AREA = 17.29
10 YR. DISCHARGE = 7.08 CFS
10 YR. STAGE ELEV.= 777.13
10 YR. STORAGE VOLUME = 0.83 AC/FT
100 YR. DISCHARGE = 7.49 CFS
100 YR. STAGE ELEV.= 779.14
100 YR. STORAGE VOLUME REQUIRED = 3.07 AC/FT
100 YR. STORAGE VOLUME PROVIDED = 3.07 AC/FT
2
2
3
3
3
3
3
2
ST-202ST-201
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
EXIST. STORAGE BUILDING (WEST SIDE)
FINISH FLOOR ELEV.= 782.20
PROPOSED RESTROOM BUILDING (EAST SIDE)
FINISH FLOOR ELEV.= 780.87
4
OVERTOPPING FLOOD
ELEVATION: 780.50±
OVERTOPPING FLOOD
ELEVATION: 782.50±
OVERTOPPING FLOOD
ELEVATION: 778.50±
OVERTOPPING FLOOD
ELEVATION: 781.10±
CARMEL SCHOOL ARM OF
THE UG MITCHNER DRAIN
30.0'
30.0'
30' REGULATED
DRAINAGE EASEMENT
BENCHMARKS:
60 1800 60 120
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana! G2.0
OVERALL GRADING PLAN
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN
WERE PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC.
THE ENGINEER MAKES NO GUARANTEES THAT THE
UNDERGROUND UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES
IN THE AREA, EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE
CONSTRUCTION. REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. THE MINIMUM FLOOD PROTECTION GRADE OF ALL STRUCTURES
FRONTING A POND OR OPEN DITCH SHALL BE NO LESS THAN 2
FEET ABOVE ANY ADJACENT 100-YR LOCAL OR REGIONAL FLOOD
ELEVATIONS, WHICHEVER IS GREATER, FOR ALL WINDOWS,
DOORS, PIPE ENTRANCES, WINDOW WELLS, AND ANY OTHER
STRUCTURE MEMBER WHERE FLOODWATERS CAN ENTER A
BUILDING.
GENERAL NOTES
CONSULTANT
Carmel Clay Schools
WWW.FHAI.COM
ARCHITECT
317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTSNOT FOR CONSTRUCTIONConstruction Documents
REV.
NO. DESCRIPTION DATE
TAC SUBMITTAL 02/17/2021A
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: March 1, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
GRADING PLAN LEGEND
EXISTING SPOT ELEVATION
MATCH EXISTING GRADE
TOP OF CURB
BOTTOM OF CURB
EDGE OF PAVEMENT
FLOWLINE
EXISTING CONTOUR W/ ELEVATION
PROPOSED CONTOUR W/ ELEVATION
PROPOSED SPOT ELEVATION
PROPOSED SURFACE DRAINAGE FLOW ARROW
FLOOD ROUTING PATH
100-YEAR OVERFLOW PATHS/PONDING AREAS
MEG
TC
BC
EP
750.65
FL
USGS BENCHMARK INFORMATION
GRADING KEYNOTES
1. CONTRACTOR TO COORDINATE WITH OWNERS
REPRESENTATIVE ON LOW SPOT REGRADING. FINAL AREAS
TO BE DETERMINED PRIOR TO CONSTRUCTION. SOD TO BE
STRIPPED PRIOR TO GRADING ACTIVITY.
2. PROPOSED SWALE @ 1.0% MIN. SLOPE
3. BOTTOM OF DRY BASIN @ 1.0% MIN. SLOPE
4. FLOOD ROUTING PATH FROM THE PROJECT SITE WHEN THE
100 YEAR FLOOD IS EXCEEDED.
08/19/21
TBM#3 = 775.53
MATCH LINE (NORTH/SOUTH)
ST-105
RIM. = 780.00
ST-108
RIM. = 784.24
ST-106
RIM. = 778.90 ST-110
INV. 777.76 (W)
ST-114
INV. 775.00 (W)ST-107
RIM. = 780.89
ST-109
RIM. = 780.80
ST-112
RIM. = 780.44
ST-111
RIM. = 778.56
781.06
TC 780.96
BC 780.46
779.60779.33
780.96
779.60
779.60
779.50
MEG 779.80
780.04
780.91
MEG 779.53
MEG 779.67
TC 780.96
BC 780.46
TC 780.39
BC 779.89780.49
781.06
781.06
781.06
780.95
TC 780.96
BC 780.46
TC 780.96
BC 780.46
781.06 781.06
MEG 780.47
MEG 781.21
ST-113
RIM. = 780.17
MODIFY EXISTING CONCRETE
PAVED SWALE IN THIS AREA TO
MATCH PROPOSED GRADES
UNDERGROUND DETENTION CHAMBERS (SC-740)
ST-108A
1
TC 780.96
BC 780.46
TC 780.96
BC 780.46
780.46780.46
MEG 780.30
MEG 780.22
MEG 779.86
MEG 779.80
780.33
780.45
MEG 779.71 MEG 779.65
MEG 779.53
FL 779.022
3
3
3
3
FL 773.55
FL 776.82
FL 771.50
FL 777.76
EAST BASIN PROPOSED CONDITIONS
CONTRIBUTING DRAINAGE AREA = 13.83
10 YR. DISCHARGE = 10.72 CFS
10 YR. STAGE ELEV.= 774.85
10 YR. STORAGE VOLUME = 0.77 AC/FT
100 YR. DISCHARGE = 12.14 CFS
100 YR. STAGE ELEV.= 776.52
100 YR. STORAGE VOLUME = 2.30 AC/FT
WEST BASIN PROPOSED CONDITIONS
CONTRIBUTING DRAINAGE AREA = 17.29
10 YR. DISCHARGE = 7.08 CFS
10 YR. STAGE ELEV.= 777.13
10 YR. STORAGE VOLUME = 0.83 AC/FT
100 YR. DISCHARGE = 7.49 CFS
100 YR. STAGE ELEV.= 779.14
100 YR. STORAGE VOLUME = 3.07 AC/FT
BUILDING INFORMATION
FINISH FLOOR ELEV.= 779.75
MIN. LOWEST ADJACENT GRADE = 779.25
MIN. FLOOD PROTECTION GRADE = 778.52
781.13
780.81
780.74
BENCHMARKS:
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
G2.01
GRADING PLAN - NORTH
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
USGS BENCHMARK INFORMATION
30 900 30 60
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN
WERE PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC.
THE ENGINEER MAKES NO GUARANTEES THAT THE
UNDERGROUND UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES
IN THE AREA, EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE
CONSTRUCTION. REPORT ANY DISCREPANCIES TO THE ENGINEER.
GENERAL NOTES
GRADING PLAN LEGEND
EXISTING SPOT ELEVATION
MATCH EXISTING GRADE
TOP OF CURB
BOTTOM OF CURB
TOP OF WALL
BOTTOM OF WALL
FINISH FLOOR
FLOWLINE
EXISTING CONTOUR W/ ELEVATION
PROPOSED CONTOUR W/ ELEVATION
PROPOSED SPOT ELEVATION
PROPOSED SURFACE DRAINAGE FLOW ARROW
MEG
TC
BC
FF
750.65
FL
TW
BW
GRADING KEYNOTES
1. CONTRACTOR TO COORDINATE WITH OWNERS
REPRESENTATIVE ON LOW SPOT REGRADING. APPROXIMATE
AREAS HAVE BEEN DELINEATED WITHIN THE JV OUTFIELD.
FINAL AREAS TO BE DETERMINED PRIOR TO CONSTRUCTION.
SOD TO BE STRIPPED PRIOR TO GRADING ACTIVITY.
2. PROPOSED SWALE @ 1.0% MIN. SLOPE
3. BOTTOM OF DRY BASIN @ 1.0% MIN. SLOPE
08/19/21
MATCH LINE (NORTH/SOUTH)
WTR
SAN
WTR
WTR
SAN
SAN
WTR
SAN SAN SANWT
R
ST-103
RIM. = 780.05
ST-101
INV. 777.83 (N)
ST-104
RIM. = 778.96
779.80
780.15
780.15
779.87
779.81
781.79
781.59
781.21
781.63
780.05
779.86
779.86780.05
780.05
780.05
779.68
779.60
784.75
784.43
BW 779.44
784.25
784.77
784.06
783.85
UNDERGROUND DETENTION CHAMBERS (SC-740)
CHAMBER AREA = 196' x 102'
MINIMUM FINISH GRADE ELEV. = 783.00
TOP OF STONE = 782.50
TOP OF CHAMBERS = 781.50
BOTTOM OF CHAMBERS = 779.00
BOTTOM OF STONE = 778.50
21 ROWS OF 27 CHAMBERS = 47,355 CFT.
CONTRIBUTING DRAINAGE AREA = 3.16 ACRES
10 YR. DISCHARGE = 1.02 CFS
10 YR. STAGE ELEV.= 780.06
10 YR. STORAGE VOLUME = 0.49 AC/FT
100 YR. DISCHARGE = 2.03 CFS
100 YR. STAGE ELEV.= 781.20
100 YR. STORAGE VOLUME = 0.85 AC/FT
MEG 783.15
MEG 784.39
782.90
MEG 784.13 1
1
779.30
779.20
TW 781.27
781.27
BW 779.33
TW 781.27
ST-102
RIM. = 781.90
780.15BW 780.31
BW 780.34 TW 781.27
TW 781.27
BW 779.79
TW 781.27
779.60
BW 779.49
TW 781.27
BW 780.42
BW 780.60TW 782.75
TW 781.27
BW 781.00TW 782.75
BW 781.49
BW 782.18
TW 782.90
TW 783.04
BW 782.02
782.00 782.18
FF 782.20
FF 782.20
FF 780.87FF 780.87
781.30 780.85
780.33
780.75
780.75
780.54
781.79
TW 783.10783.10
782.71
784.71
784.64784.70
784.84
784.77
784.44
MEG 784.49
MEG 784.34
MEG 784.10
MEG 784.71
784.78
MEG 784.80
MEG 784.91
MEG 784.71
MEG 784.90
784.99
784.66
784.74
784.70
784.78
784.80
784.80
784.69
784.69
MEG 784.68
784.73
780.26
779.83
FL 778.80
785.78
784.95
784.95 784.95
784.95
784.81
784.70
784.81 784.70
784.70
784.81
FL 784.07 2
2
2
FL 777.83FL 777.83
EXIST. STORAGE BUILDING (WEST SIDE)
FINISH FLOOR ELEV.= 782.20
PROPOSED RESTROOM BUILDING (EAST SIDE)
FINISH FLOOR ELEV.= 780.87
FL 781.17 FL 781.90
MEG 786.70MEG 786.70
784.20784.30
784.35 784.32
ST-202
INV. 781.17 (W)ST-201
INV. 781.90 (E)
BENCHMARKS:
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
USGS BENCHMARK INFORMATION
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
G2.02
GRADING PLAN - SOUTHWEST
30 900 30 60
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN
WERE PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC.
THE ENGINEER MAKES NO GUARANTEES THAT THE
UNDERGROUND UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES
IN THE AREA, EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE
CONSTRUCTION. REPORT ANY DISCREPANCIES TO THE ENGINEER.
GENERAL NOTES
GRADING PLAN LEGEND
EXISTING SPOT ELEVATION
MATCH EXISTING GRADE
TOP OF CURB
BOTTOM OF CURB
TOP OF WALL
BOTTOM OF WALL
FINISH FLOOR
FLOWLINE
EXISTING CONTOUR W/ ELEVATION
PROPOSED CONTOUR W/ ELEVATION
PROPOSED SPOT ELEVATION
PROPOSED SURFACE DRAINAGE FLOW ARROW
MEG
TC
BC
FF
750.65
FL
TW
BW
GRADING KEYNOTES
1. CONTRACTOR TO COORDINATE WITH OWNERS
REPRESENTATIVE ON LOW SPOT REGRADING. APPROXIMATE
AREAS HAVE BEEN DELINEATED WITHIN THE JV OUTFIELD.
FINAL AREAS TO BE DETERMINED PRIOR TO CONSTRUCTION.
SOD TO BE STRIPPED PRIOR TO GRADING ACTIVITY.
2. PROPOSED SWALE @ 1.0% MIN. SLOPE
3. BOTTOM OF DRY BASIN @ 1.0% MIN. SLOPE
08/19/21
1
MATCH LINE (NORTH/SOUTH)
WTR
WTR
SAN SANWTR
ST-103
RIM. = 780.05
ST-101
INV. 777.83 (N)
ST-104
RIM. = 778.96
779.80
780.15
780.15
779.87
779.81
781.79
781.59
779.61
779.60
781.21
781.63
780.05
779.86
779.86780.05
780.05
780.05
779.68
779.60
779.51
BW 779.44
784.25
784.06
783.85
UNDERGROUND DETENTION CHAMBERS (SC-740)
CHAMBER AREA = 196' x 102'
MINIMUM FINISH GRADE ELEV. = 783.00
TOP OF STONE = 782.50
TOP OF CHAMBERS = 781.50
BOTTOM OF CHAMBERS = 779.00
BOTTOM OF STONE = 778.50
21 ROWS OF 27 CHAMBERS = 47,355 CFT.
CONTRIBUTING DRAINAGE AREA = 3.16 ACRES
10 YR. DISCHARGE = 1.02 CFS
10 YR. STAGE ELEV.= 780.06
10 YR. STORAGE VOLUME = 0.49 AC/FT
100 YR. DISCHARGE = 2.03 CFS
100 YR. STAGE ELEV.= 781.20
100 YR. STORAGE VOLUME = 0.85 AC/FT
782.90
1
1
1
1
1
1
1
779.30
779.20
TW 781.27
781.27
BW 779.33
TW 781.27
ST-102
RIM. = 781.90
780.15BW 780.31
BW 780.34 TW 781.27
TW 781.27
BW 779.79
TW 781.27
779.60
BW 779.49
TW 781.27
BW 780.42
BW 780.60TW 782.75
TW 781.27
BW 781.00TW 782.75
BW 781.49
BW 782.18
TW 782.90
TW 783.04
BW 782.02
782.00 782.18
FF 782.20
FF 782.20
FF 780.87FF 780.87
781.30 780.85
780.33
780.75
780.75
780.54
781.79
TW 783.10783.10
782.71
780.26
779.83
FL 778.80
779.75
784.70
784.70
2
2
3
FL 778.99
FL 777.83FL 777.83
3
EXIST. STORAGE BUILDING (WEST SIDE)
FINISH FLOOR ELEV.= 782.20
PROPOSED RESTROOM BUILDING (EAST SIDE)
FINISH FLOOR ELEV.= 780.87
FL 781.17
MEG 786.70
784.20
784.32
ST-202
INV. 781.17 (W)
BENCHMARKS:
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
USGS BENCHMARK INFORMATION
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
G2.03
GRADING PLAN - SOUTHEAST
30 900 30 60
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN
WERE PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC.
THE ENGINEER MAKES NO GUARANTEES THAT THE
UNDERGROUND UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES
IN THE AREA, EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE
CONSTRUCTION. REPORT ANY DISCREPANCIES TO THE ENGINEER.
GENERAL NOTES
GRADING PLAN LEGEND
EXISTING SPOT ELEVATION
MATCH EXISTING GRADE
TOP OF CURB
BOTTOM OF CURB
TOP OF WALL
BOTTOM OF WALL
FINISH FLOOR
FLOWLINE
EXISTING CONTOUR W/ ELEVATION
PROPOSED CONTOUR W/ ELEVATION
PROPOSED SPOT ELEVATION
PROPOSED SURFACE DRAINAGE FLOW ARROW
MEG
TC
BC
FF
750.65
FL
TW
BW
GRADING KEYNOTES
1. CONTRACTOR TO COORDINATE WITH OWNERS
REPRESENTATIVE ON LOW SPOT REGRADING. APPROXIMATE
AREAS HAVE BEEN DELINEATED WITHIN THE JV OUTFIELD.
FINAL AREAS TO BE DETERMINED PRIOR TO CONSTRUCTION.
SOD TO BE STRIPPED PRIOR TO GRADING ACTIVITY.
2. PROPOSED SWALE @ 1.0% MIN. SLOPE
3. BOTTOM OF DRY BASIN @ 1.0% MIN. SLOPE
08/19/21
TBM#3 = 775.53
ADJOINER
CW
SF SFSF
SF SF SF
SFSF
PT
1
1
1
1
2
3
3
3
2
4
5
6
7
3
8
8
1
1
1
ST-108
ST-107
ST-106
ST-109
ST-111
ST-110
ST-112
ST-114
ST-105
ST-113
CONSTRUCTION LIMITS
CONSTRUCTION LIMITS
CONSTRUCTION LIMITS
6
6 6
ST-108A
MATCH LINE (NORTH/SOUTH)
2
2
2
9
1
2
1
MECHANICAL BMP
AQUASWIRL XC-7
BENCHMARKS:
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
G2.04
EROSION CONTROL
PLAN - NORTH
USGS BENCHMARK INFORMATION
EROSION CONTROL LEGEND
CW
PT
SF
30 900 30 60
EROSION CONTROL NOTES
1. ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES MY BE
REQUIRED BY THE INSPECTOR.
2. DURING CONSTRUCTION KEEP PAVEMENTS AND SIDEWALKS CLEAN
AND WORK AREAS IN AN ORDERLY CONDITION. CLEAN WHEELS OF
VEHICLES BEFORE LEAVING THE SITE TO AVOID TRACKING SOIL
ONTO ROADS, WALKS, OR OTHER PAVED AREAS.
3. ALL PROPOSED EROSION AND SEDIMENT CONTROL SHALL BE IN
CONFORMANCE WITH CHAPTER 600 OF THE CITY OF CARMEL
STORMWATER TECHNICAL STANDARDS MANUAL, LATEST EDITION.
DISCREPANCIES BETWEEN THE PLANS AND THE MANUAL SHALL NOT
ALLEVIATE THE CONTRACTOR FROM ADHERING TO THE
REQUIREMENTS AS SET FORTH IN THE MANUAL.
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE
PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE
ENGINEER MAKES NO GUARANTEES THAT THE UNDERGROUND
UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION.
REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. SEE EROSION CONTROL DETAILS ON SHEET G4.2
5. NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN
APPROVED STORM WATER MANAGEMENT PERMIT.
6. UTILITY RELOCATIONS REQUIRED BY THE PROJECT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER. UTILITY LINE RELOCATIONS
REQUIRED FOR ROAD PROJECTS THAT RESULT IN A CONFLICT
WITH PROPOSED DEVELOPMENT SHALL BE THE DEVELOPERS
RESPONSIBILITY TO RESOLVE WITH THE UTILITY. EXISTING POLE
LINES REQUIRED TO BE RELOCATED TO WITHIN ONE FOOT OF
PROPOSED RIGHT-OF-WAY LINE.
7. DAMAGE TO THE EXISTING RIGHT-OF-WAY SHALL
RESTORED/REPAIRED TO THE SATISFACTION OF THE CITY AT THE
COMPLETION OF THE PROJECT. THE CONTRACTOR IS
ENCOURAGED TO INSPECT THE RIGHT-OF-WAY WITH THE CITY
PRIOR TO THE START OF CONSTRUCTION TO DOCUMENT THE
EXISTING CONDITION OF THE RIGHT-OF-WAY.
GENERAL NOTES
EROSION CONTROL KEYNOTES
1. SEDIMENT BAG INLET PROTECTION
2. TEMPORARY SEEDING
3. EROSION CONTROL BLANKET
4. CONCRETE WASHOUT
5. PORTABLE TOILETS
6. SILT FENCE
7. CONSTRUCTION ENTRANCE
8. ROCK DONUT
9. RIPRAP OUTLET CONTROL
08/19/21
SFSFSFSFSF SFSF
SF
SF
WTR
SAN
WTR
WTR
SAN
SAN
WTR
SAN SAN SANWTR SF SFSFS
F
SFSF
1
1
2
6
6
6 6
6
8
3
2
ST-104
ST-102
ST-103
ST-101
CONSTRUCTION LIMITS
CONSTRUCTION LIMITS
6
6
UNDERGROUND
DETENTION
CHAMBERS
MATCH LINE (NORTH/SOUTH)
ST-202
ST-201
9
3
8
ISOLATOR ROW BMP
2
BENCHMARKS:
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
G2.05
EROSION CONTROL
PLAN - SOUTHWEST
USGS BENCHMARK INFORMATIONEROSION CONTROL LEGEND
CW
PT
SF
30 900 30 60
EROSION CONTROL NOTES
1. ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES MY BE
REQUIRED BY THE INSPECTOR.
2. DURING CONSTRUCTION KEEP PAVEMENTS AND SIDEWALKS CLEAN
AND WORK AREAS IN AN ORDERLY CONDITION. CLEAN WHEELS OF
VEHICLES BEFORE LEAVING THE SITE TO AVOID TRACKING SOIL
ONTO ROADS, WALKS, OR OTHER PAVED AREAS.
3. ALL PROPOSED EROSION AND SEDIMENT CONTROL SHALL BE IN
CONFORMANCE WITH CHAPTER 600 OF THE CITY OF CARMEL
STORMWATER TECHNICAL STANDARDS MANUAL, LATEST EDITION.
DISCREPANCIES BETWEEN THE PLANS AND THE MANUAL SHALL NOT
ALLEVIATE THE CONTRACTOR FROM ADHERING TO THE
REQUIREMENTS AS SET FORTH IN THE MANUAL.
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE
PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE
ENGINEER MAKES NO GUARANTEES THAT THE UNDERGROUND
UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION.
REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. SEE EROSION CONTROL DETAILS ON SHEET G4.2
5. NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN
APPROVED STORM WATER MANAGEMENT PERMIT.
6. UTILITY RELOCATIONS REQUIRED BY THE PROJECT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER. UTILITY LINE RELOCATIONS
REQUIRED FOR ROAD PROJECTS THAT RESULT IN A CONFLICT
WITH PROPOSED DEVELOPMENT SHALL BE THE DEVELOPERS
RESPONSIBILITY TO RESOLVE WITH THE UTILITY. EXISTING POLE
LINES REQUIRED TO BE RELOCATED TO WITHIN ONE FOOT OF
PROPOSED RIGHT-OF-WAY LINE.
7. DAMAGE TO THE EXISTING RIGHT-OF-WAY SHALL
RESTORED/REPAIRED TO THE SATISFACTION OF THE CITY AT THE
COMPLETION OF THE PROJECT. THE CONTRACTOR IS
ENCOURAGED TO INSPECT THE RIGHT-OF-WAY WITH THE CITY
PRIOR TO THE START OF CONSTRUCTION TO DOCUMENT THE
EXISTING CONDITION OF THE RIGHT-OF-WAY.
GENERAL NOTES
EROSION CONTROL KEYNOTES
1. SEDIMENT BAG INLET PROTECTION
2. TEMPORARY SEEDING
3. EROSION CONTROL BLANKET
4. CONCRETE WASHOUT
5. PORTABLE TOILETS
6. SILT FENCE
7. CONSTRUCTION ENTRANCE
8. ROCK DONUT
9. RIPRAP OUTLET CONTROL
08/19/21
BENCHMARKS:
SF
SF
SF
WTR
WTR
SAN SANWTR SF SFSFS
F
SF
1
1
2
3
6
6
6
8
3
3
2
2
ST-104
ST-102
ST-103
ST-101
CONSTRUCTION LIMITS
6
6
UNDERGROUND
DETENTION
CHAMBERS
MATCH LINE (NORTH/SOUTH)
3
ST-202
9
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
G2.06
EROSION CONTROL
PLAN - SOUTHEAST
USGS BENCHMARK INFORMATIONEROSION CONTROL LEGEND
CW
PT
SF
30 900 30 60
EROSION CONTROL NOTES
1. ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES MY BE
REQUIRED BY THE INSPECTOR.
2. DURING CONSTRUCTION KEEP PAVEMENTS AND SIDEWALKS CLEAN
AND WORK AREAS IN AN ORDERLY CONDITION. CLEAN WHEELS OF
VEHICLES BEFORE LEAVING THE SITE TO AVOID TRACKING SOIL
ONTO ROADS, WALKS, OR OTHER PAVED AREAS.
3. ALL PROPOSED EROSION AND SEDIMENT CONTROL SHALL BE IN
CONFORMANCE WITH CHAPTER 600 OF THE CITY OF CARMEL
STORMWATER TECHNICAL STANDARDS MANUAL, LATEST EDITION.
DISCREPANCIES BETWEEN THE PLANS AND THE MANUAL SHALL NOT
ALLEVIATE THE CONTRACTOR FROM ADHERING TO THE
REQUIREMENTS AS SET FORTH IN THE MANUAL.
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE
PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE
ENGINEER MAKES NO GUARANTEES THAT THE UNDERGROUND
UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION.
REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. SEE EROSION CONTROL DETAILS ON SHEET G4.2
5. NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN
APPROVED STORM WATER MANAGEMENT PERMIT.
6. UTILITY RELOCATIONS REQUIRED BY THE PROJECT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER. UTILITY LINE RELOCATIONS
REQUIRED FOR ROAD PROJECTS THAT RESULT IN A CONFLICT
WITH PROPOSED DEVELOPMENT SHALL BE THE DEVELOPERS
RESPONSIBILITY TO RESOLVE WITH THE UTILITY. EXISTING POLE
LINES REQUIRED TO BE RELOCATED TO WITHIN ONE FOOT OF
PROPOSED RIGHT-OF-WAY LINE.
7. DAMAGE TO THE EXISTING RIGHT-OF-WAY SHALL
RESTORED/REPAIRED TO THE SATISFACTION OF THE CITY AT THE
COMPLETION OF THE PROJECT. THE CONTRACTOR IS
ENCOURAGED TO INSPECT THE RIGHT-OF-WAY WITH THE CITY
PRIOR TO THE START OF CONSTRUCTION TO DOCUMENT THE
EXISTING CONDITION OF THE RIGHT-OF-WAY.
GENERAL NOTES
EROSION CONTROL KEYNOTES
1. SEDIMENT BAG INLET PROTECTION
2. TEMPORARY SEEDING
3. EROSION CONTROL BLANKET
4. CONCRETE WASHOUT
5. PORTABLE TOILETS
6. SILT FENCE
7. CONSTRUCTION ENTRANCE
8. ROCK DONUT
9. RIPRAP OUTLET CONTROL
08/19/21
PROJECT SITE
PROJECT SITE
E. MAIN STREET
E. 126TH STREET GRAY ROADHAZEL DELL PARKWAYYsnA
YoxA
YmsB2
YmsB2
YoxB2
YmsB2
YoxA
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
G2.07
STORMWATER POLLUTION
PREVENTION PLAN
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
08/19/21
AREA INLET
SEDIMENT BAG DETAIL
SILT FENCE DETAIL
METAL PINS OR STAPLES TO
SECURE THE POLYETHYLENE
LINING TO THE STRAW BALES
WOOD OR METAL STAKES
TO SECURE THE STRAW
BALES (2 PER STRAW
BALE)
STRAW BALE (ALTERNATIVE
MATERIALS OR PRODUCTS
MAY BE USED TO PROVIDE
STRUCTURAL
CONTAINMENT.
ALTERNATIVE MATERIALS
OR PRODUCTS WILL
REQUIRE DESIGN
MODIFICATION.)
PLAN VIEW
NOT TO SCALE
L = INSIDE LENGTH (10' MIN)
W = INSIDE WIDTH (10' MIN)
POLYETHYLENE LINING
(10 MIL); THE LINING
SHALL EXTEND OVER
THE STRAW BALES.
COMPACTED SOIL
MATERIAL
SECTION A-A
NOT TO SCALE
EXCAVATION
SANDBAGS OR OTHER
APPROPRIATE ANCHORING
SYSTEM TO
SECURE THE POLYETHYLENE
LINING
ASs =
T L = TOP LENGTH OF
EXCAVATION (10' MIN)
B L = BOTTOM LENGTH OF
EXCAVATION
T W = TOP WIDTH OF
EXCAVATION (10' MIN)
B W = BOTTOM WIDTH OF
EXCAVATION
ASS = ANCHORING SYSTEM
TYPE AND SPACING
D = REQUIRED DEPTH TO CONTAIN
WASHOUT INCLUDING 12"
RAINFALL PLUS 12" FREEBOARD
POLYETHYLENE
LINING (10 MIL)
SECTION B-B
NOT TO SCALE
SANDBAGS OR OTHER
APPROPRIATE ANCHORING SYSTEM
TO SECURE THE POLYETHYLENE
LINING
WOOD OR METAL STAKES
TO SECURE THE STRAW
BALES (2 PER STRAW
BALE)
L=10'
STRAW BALES ENTRENCHED 4
INCHES INTO THE SOIL
D = 2'
A A
W=10'
TL=10'
BW=8'
TW=10'
BL=8'
PLAN VIEW
NOT TO SCALE
ABOVE GRADE SYSTEM BELOW GRADE SYSTEM
STANDARD WASHOUT DETAIL
B
CONSTRUCTION ENTRANCE
4
2
5
1
3A
3B
NOTE:
REFER TO GENERAL STAPLE PATTERN GUIDE FOR
CORRECT STAPLE PATTERN RECOMMENDATIONS FOR
SLOPE INSTALLATIONS.
1. PREPARE SOIL BEFORE INSTALLING BLANKETS, INCLUDING APPLICATION OF LIME,
FERTILIZER, AND SEED. NOTE: WHEN USING CELL-O-SEED DO NOT SEED PREPARED
AREA. CELL-O-SEED MUST BE INSTALLED WITH PAPER SIDE DOWN.
2. BEGIN AT THE TOP OF THE SLOPE BY ANCHORING THE BLANKET IN 6" DEEP X 6" WIDE
TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING.
3. ROLL THE BLANKETS (A.) DOWN OR (B.) HORIZONTALLY ACROSS THE SLOPE.
4. THE EDGES OF PARALLEL BLANKETS MUST BE STAPLED WITH APPROXIMATELY 2"
OVERLAP.
5. WHEN BLANKETS MUST BE SPLICED DOWN THE SLOPE, PLACE BLANKETS END OVER
END (SHINGLE STYLE) WITH APPROXIMATELY 4" OVERLAP. STAPLE THROUGH
OVERLAPPED AREA, APPROXIMATELY 12" APART.
EROSION CONTROL BLANKET SLOPE INSTALLATION
2' 2'MIN.1' MIN.
MAINTENANCE:
NO SCALE
ROCK DONUT DETAIL
GEOTEXTILE 8oz/SYD. MIN.
CONC. HEADWALL
SEE PLAN
FABRIC SECURING PINS
COMPACTED SUBGRADE
TOE WALL
12"24" 12"6"NO SCALE
COMPACTED SUBGRADE
GEOTEXTILE
8 OZ./SYD. MIN.
2' (TYP.)24" MAX.12" MIN.1'-0"END SECTION
RIPRAP OUTLET CONTROL DETAIL
G2.08
EROSION CONTROL DETAILS
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
08/19/21
G4.0
SITE DETAILS
CONSULTANT
CARMEL CLAY SCHOOLS
WWW.FHAI.COM
ARCHITECT
317-848-0966
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
CARMEL HIGH
SCHOOL
5201 E MAIN STREET
CARMEL, IN 46033
HARTMAN FIELD
IMPROVEMENTS
DESIGN DEVELOPMENT
REV.
NO. DESCRIPTION
DATE
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 02/17/2021
DRAWN BY: EB
PROJECT
220127.00
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
W IL L I AME.PAY
N
EREGISTERE
D
IND I A N AARCHITE CT
4169
STATE OF
No.
ADDENDUM #2 6/07/20212
08/19/21
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L I AME.PAY
N
EREGISTERE
D
IND I A N AARCHITE CT4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
G4.01
SITE DETAILS - VARSITY
SYNTHETIC TURF FIELD
NEW BRACE RAIL
2.375" O.D.INTERMEDIATE
RAILS
CORNER, END &
PULL POST
TOP AND BRACE
GRADE
USE FABRIC UNDER 10' HT.
2.875" O.D.
BOTTOM TENSION WIRE
CORNER, END
POST
LEAF WIDTH:
LESS THAN 6'
GATE FRAME
GATE POST FOR
2.875"O.D.
NEW TOP RAIL
10'-0" MAX. LINE POST10'-0" MAXIMUM
FABRIC WIDTH
SEE PLANS
1 1/2"MAX.
POST
1.90" O.D.
1.66" O.D.SCHED. 40
SCHED. 40
SCHED. 40
SCHED. 40
SCHED. 40
EX. LINE POST
THERMALLY FUSED TO GALVANIZED (ZINC COATED) STEEL PIPE.
THERMALLY FUSED TO ZINC COATED WIRE. ALL POSTS, RAILS
CHAIN LINK FENCE FABRIC SHALL HAVE BLACK PVC COATING
AND BRACING SHALL ALSO HAVE BLACK PVC COATING,
NOTE:
FABRIC 10' AND OVER
4" O.D.
4" O.D.
4" O.D.
1.90" O.D.
1.66" O.D.SCHED. 40
SCHED. 40
SCHED. 40
SCHED. 40
SCHED. 40
IN AREAS WHERE PRACTICE BOARD IS ATTACHED TO FENCING INSERT 3-1/2" O.D.NOTE:SS-40 SLEEVE INSIDE OF THE 4" PIPE AND END AND PLUG WELD
FINISH GRADE
NEW BOTTOM RAILTHIS SECTION
ON CORNER END
OR GATE POST
NEW
FABRIC
SLEEVE EXISTING POST
SEE PLANS
ECONOMY FENCE CAP
BEACON ATHLETICS
PRE-SLIT POLY TUBING
4-1/2" DIA, FULLY UV- PROTECTED
51°
'
138°'48°'08/19/21
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L I AME.PAY
N
EREGISTERE
D
IND I A N AARCHITE CT4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
ADDENDUM #2 6/07/20212
G4.02
SITE DETAILS - VARSITY
SYNTHETIC TURF FIELD
DOUBLE WIDE GATES
HINGE HINGE
LATCH
GATE PLAN
LATCH
HINGE
GATE PLAN
SINGLE WIDE GATES
WIDTH
SEE PLANS WIDTH
SEE PLANS
ECONOMY FENCE CAP
BEACON ATHLETICS
PRE-SLIT POLY TUBING
4-1/2" DIA, FULLY UV- PROTECTED
SEE DETAILS #6 & #7 G4.01
08/19/21
TBM#2 = 791.71
TBM#3 = 775.53
TBM#1 = 782.26
WTR
SAN
WTR
WTR
SAN SANWTR
SANSAN SANWTRST-106
ST-110ST-111
ST-114
ST-113
ST-112
ST-109
ST-107
ST-105
ST-104
ST-102
ST-103
ST-108
ST-108A
UNDERGROUND
DETENTION
CHAMBERS
ST-101ST-202ST-201
STORM STRUCTURE TABLE
STR.
NO.
101
102
103
104
105
106
107
108A
108
109
110
111
112
113
114
201
202
STRUCTURE
???
Type "C" Manhole
Inlet Type "A"
Inlet Type "E"
Type "C" Manhole
Inlet Type "E"
Type "C" Manhole
Type "C" Manhole
Type "C" Manhole
Type "C" Manhole
???
Inlet Type "E"
Type "C" Manhole
Type "C" Manhole
???
???
???
CASTING TYPE
???
R-1772
R-4342
R-4215-C
R-1772
R-4215-C
R-4342
R-1772
R-1772
R-4342
???
R-4215-C
R-1772
R-1772
???
???
???
RIM
779.30
781.90
780.05
778.96
780.00
778.90
780.89
783.00
784.24
780.80
778.89
778.56
780.44
780.17
777.33
783.03
782.30
INCOMING PIPE DATA
(DIRECTION) [FROM STR]
15" HDPE Pipe 776.96 (S) [101]
15" HDPE Pipe 776.77 (W) [102]
12" HDPE Pipe 776.77 (S) [103]
18" HDPE Pipe 776.25 (S) [104]
12" HDPE Pipe 776.52 (N) [106]
12" HDPE Pipe 778.40 (S) [108A]
12" HDPE Pipe 776.14 (W) [107]
15" HDPE Pipe 777.99 (SW) [108]
12" HDPE Pipe 776.76 (E) [110]
18" HDPE Pipe 775.91 (S) [105]
15" HDPE Pipe 775.91 (W) [109]
12" HDPE Pipe 775.91 (N) [111]
24" HDPE Pipe 775.23 (W) [112]
24" HDPE Pipe 775.00 (W) [113]
12" HDPE Pipe 781.17 (W) [201]
OUTGOING PIPE DATA
(DIRECTION) [TO STR]
15" HDPE Pipe 777.83 (N) [102]
15" HDPE Pipe 776.86 (E) [104]
12" HDPE Pipe 777.10 (N) [104]
18" HDPE Pipe 776.67 (N) [105]
18" HDPE Pipe 776.15 (N) [112]
12" HDPE Pipe 776.69 (S) [107]
12" HDPE Pipe 776.42 (E) [109]
12" HDPE Pipe 778.50 (N) [108]
15" HDPE Pipe 778.40 (NE) [109]
15" HDPE Pipe 776.04 (E) [112]
12" HDPE Pipe 777.76 (W) [111]
12" HDPE Pipe 776.66 (S) [112]
24" HDPE Pipe 775.81 (E) [113]
24" HDPE Pipe 775.13 (E) [114]
12" HDPE Pipe 781.90 (E) [202]
OUTGOING
PIPE L.F.
290'
29'
108'
143'
80'
57'
93'
18'
136'
46'
32'
65'
193'
42'
44'
OUTGOING
PIPE SIZE
15" HDPE Pipe
15" HDPE Pipe
12" HDPE Pipe
18" HDPE Pipe
18" HDPE Pipe
12" HDPE Pipe
12" HDPE Pipe
12" HDPE Pipe
15" HDPE Pipe
15" HDPE Pipe
12" HDPE Pipe
12" HDPE Pipe
24" HDPE Pipe
24" HDPE Pipe
12" HDPE Pipe
OUTGOING
GRADE
0.30%
0.30%
0.30%
0.30%
0.30%
0.30%
0.30%
0.57%
0.30%
0.30%
3.13%
1.16%
0.30%
0.30%
1.65%
CONNECT TO
STR.
102
104
104
105
112
107
109
108
109
112
111
112
113
114
202
REMARKS
End Section - -
End Section - -
Aquaswirl XC-7 Per Manufacturer
End Section - -
ACO Trench Drain Per Manufacturer
End Section -
End Section -
-
-
ALL STORM SEWER CASTINGS SHALL BE MARKED "DUMP NO WASTE DRAINS TO WATERWAYS"
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
SU1.0
OVERALL SITE UTILITY PLAN
THE STORM SEWER SYSTEM SHALL BE CONSTRUCTED PER DESIGN SPECIFIED AND
AS APPROVED BY THE CITY OF CARMEL ON THE FINAL APPROVED CONSTRUCTION
PLANS. DEVIATIONS FROM THE APPROVED DESIGN SHALL BE PERMITTED DUE TO
SPECIAL CIRCUMSTANCES OR DIFFICULTY DURING CONSTRUCTION AND WILL
REQUIRE PRIOR FIELD APPROVAL FROM A DESIGNATED REPRESENTATIVE OF THE
CITY OF CARMEL IN ADDITION TO SUPPLEMENTAL APPROVAL BY THE DESIGN
ENGINEER. AN EXPLANATION OF ANY SUCH DEVIATION SHALL BE INCLUDED AS A
REQUIREMENT ON AS-BUILT/RECORD DRAWINGS SUBMITTED FOR RELEASE OF
PERFORMANCE GUARANTEES. APPROVED DESIGN SLOPES IDENTIFIED AS
GENERATING VELOCITIES OF 2.5 FPS OR LESS, OR 10 FPS OR GREATER (AT FULL
FLOW CAPACITY) SHALL REQUIRE AS-BUILT CERTIFICATION AT THE TIME OF
CONSTRUCTION, PRIOR TO BACKFILLING THE PIPE. THE CONTRACTOR IS INSTRUCTED
AS-BUILT EACH SECTION OF STORM PIPE AS IT IS BEING INSTALLED TO ENSURE
COMPLIANCE WITH THE DESIGN PLANS AND AS APPROVED BY THE CITY OF CARMEL.
STORM SEWER NOTE
UTILITY PLAN LEGEND
PROPOSED 2" PVC WATER LINE
PROPOSED 8" PVC SANITARY SEWER PIPE
WTR
SAN
60 1800 60 120
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE
PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE
ENGINEER MAKES NO GUARANTEES THAT THE UNDERGROUND
UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION.
REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. SEE SHEET G2.1 FOR GRADING PLAN.
5. THE PROPOSED STORM SEWER SYSTEM FOR THIS PROJECT WILL
BE PRIVATE OWNED.
6. NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN
APPROVED STORM WATER MANAGEMENT PERMIT.
7. UTILITY RELOCATIONS REQUIRED BY THE PROJECT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER. UTILITY LINE RELOCATIONS
REQUIRED FOR ROAD PROJECTS THAT RESULT IN A CONFLICT WITH
PROPOSED DEVELOPMENT SHALL BE THE DEVELOPERS
RESPONSIBILITY TO RESOLVE WITH THE UTILITY. EXISTING POLE
LINES REQUIRED TO BE RELOCATED TO WITHIN ONE FOOT OF
PROPOSED RIGHT-OF-WAY LINE.
8. DAMAGE TO THE EXISTING RIGHT-OF-WAY SHALL
RESTORED/REPAIRED TO THE SATISFACTION OF THE CITY AT THE
COMPLETION OF THE PROJECT. THE CONTRACTOR IS
ENCOURAGED TO INSPECT THE RIGHT-OF-WAY WITH THE CITY
PRIOR TO THE START OF CONSTRUCTION TO DOCUMENT THE
EXISTING CONDITION OF THE RIGHT-OF-WAY.
9. IT IS THE CONTRACTORS RESPONSIBILITY TO REMOVE OR
RELOCATE ANY EXISTING UTILITY LINES WHICH INTERFERE WITH
NEW STORM SEWER INSTALLATION.
GENERAL NOTES
08/19/21
TBM#3 = 775.53
ADJOINER
MATCH LINE (NORTH/SOUTH)
ST-108
RIM. = 784.24'
INV. 778.40 (NE)
INV. 778.40 (S)
ST-107
RIM. = 780.89'
INV. 776.52 (N)
INV. 776.42 (E)
ST-112
RIM. = 780.44'
INV. 775.91 (S)
INV. 775.91 (W)
INV. 775.91 (N)
INV. 775.81 (E)
ST-105
RIM. = 780.00'
INV. 776.25 (S)
INV. 776.15 (N)
ST-113
RIM. = 780.17'
INV. 775.23 (W)
INV. 775.13 (E)
ST-109
RIM. = 780.80'
INV. 776.14 (W)
INV. 776.04 (E)
INV. 777.99 (SW)
ST-106
INV. 776.69 (S)
ST-114
INV. 775.00 (W)
ST-110
INV. 777.76 (W)
ST-111
RIM. = 778.56'
INV. 776.66 (S)
INV. 776.76 (E)
1
4
1
2
56
7
6
5
9
4
7
1
2
7
3
1
7
7
1
ST-108A
RIM. = 783.00'
INV. 778.50 (N)6
MODIFY EXISTING CONCRETE
PAVED SWALE IN THIS AREA TO
MATCH PROPOSED GRADES
19
19
19
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
SU1.01
SITE UTILITY PLAN - NORTH
THE STORM SEWER SYSTEM SHALL BE CONSTRUCTED PER DESIGN SPECIFIED AND
AS APPROVED BY THE CITY OF CARMEL ON THE FINAL APPROVED CONSTRUCTION
PLANS. DEVIATIONS FROM THE APPROVED DESIGN SHALL BE PERMITTED DUE TO
SPECIAL CIRCUMSTANCES OR DIFFICULTY DURING CONSTRUCTION AND WILL
REQUIRE PRIOR FIELD APPROVAL FROM A DESIGNATED REPRESENTATIVE OF THE
CITY OF CARMEL IN ADDITION TO SUPPLEMENTAL APPROVAL BY THE DESIGN
ENGINEER. AN EXPLANATION OF ANY SUCH DEVIATION SHALL BE INCLUDED AS A
REQUIREMENT ON AS-BUILT/RECORD DRAWINGS SUBMITTED FOR RELEASE OF
PERFORMANCE GUARANTEES. APPROVED DESIGN SLOPES IDENTIFIED AS
GENERATING VELOCITIES OF 2.5 FPS OR LESS, OR 10 FPS OR GREATER (AT FULL
FLOW CAPACITY) SHALL REQUIRE AS-BUILT CERTIFICATION AT THE TIME OF
CONSTRUCTION, PRIOR TO BACKFILLING THE PIPE. THE CONTRACTOR IS INSTRUCTED
AS-BUILT EACH SECTION OF STORM PIPE AS IT IS BEING INSTALLED TO ENSURE
COMPLIANCE WITH THE DESIGN PLANS AND AS APPROVED BY THE CITY OF CARMEL.
STORM SEWER NOTE
30 900 30 60
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE
PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE
ENGINEER MAKES NO GUARANTEES THAT THE UNDERGROUND
UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION.
REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. SEE SHEET G2.1 FOR GRADING PLAN.
5. THE PROPOSED STORM SEWER SYSTEM FOR THIS PROJECT WILL
BE PRIVATE OWNED.
6. NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN
APPROVED STORM WATER MANAGEMENT PERMIT.
7. UTILITY RELOCATIONS REQUIRED BY THE PROJECT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER. UTILITY LINE RELOCATIONS
REQUIRED FOR ROAD PROJECTS THAT RESULT IN A CONFLICT WITH
PROPOSED DEVELOPMENT SHALL BE THE DEVELOPERS
RESPONSIBILITY TO RESOLVE WITH THE UTILITY. EXISTING POLE
LINES REQUIRED TO BE RELOCATED TO WITHIN ONE FOOT OF
PROPOSED RIGHT-OF-WAY LINE.
8. DAMAGE TO THE EXISTING RIGHT-OF-WAY SHALL
RESTORED/REPAIRED TO THE SATISFACTION OF THE CITY AT THE
COMPLETION OF THE PROJECT. THE CONTRACTOR IS
ENCOURAGED TO INSPECT THE RIGHT-OF-WAY WITH THE CITY
PRIOR TO THE START OF CONSTRUCTION TO DOCUMENT THE
EXISTING CONDITION OF THE RIGHT-OF-WAY.
9. IT IS THE CONTRACTORS RESPONSIBILITY TO REMOVE OR
RELOCATE ANY EXISTING UTILITY LINES WHICH INTERFERE WITH
NEW STORM SEWER INSTALLATION.
GENERAL NOTES
UTILITY KEYNOTES
1. PROPOSED 12" HDPE STORM SEWER PIPE
2. PROPOSED 15" HDPE STORM SEWER PIPE
3. PROPOSED 18" HDPE STORM SEWER PIPE
4. PROPOSED 24" HDPE STORM SEWER PIPE
5. PROPOSED STORM FLARED END SECTION
6. PROPOSED STORM MANHOLE
7. PROPOSED STORM INLET
8. PROPOSED STORM TRENCH DRAIN
9. PROPOSED MECHANICAL STORMWATER QUALITY BMP
10. PROPOSED 1"x 12" FLAT PIPE UNDERDRAIN
11. PROPOSED 6" PVC PERIMETER DRAIN @ 0.5%
12. PROPOSED 12" PVC PERIMETER DRAIN @ 0.5%
13. CONNECT FORCE MAIN TO EXISTING SANITARY SEWER
14. 608 LF OF 2" WATER LINE
15. SANITARY LIFT STATION - SEE DETAIL 4 ON SHEET P3.01
16. 783 LF OF SANITARY FORCE MAIN - SEE PLUMBING PLAN
SHEET P2.01 FOR SIZE.
17. PROPOSED SANITARY DOG HOUSE MANHOLE WITH FLAT TOP
18. EXISTING SANITARY LINE - PER RECORD DRAWINGS
19. PROPOSED STORM SEWER POTENTIAL CONFLICT WITH
EXISTING UTILITY. CONTRACTOR TO VERIFY TOP AND
BOTTOM ELEVATIONS OF EXISTING UTILITY PRIOR TO
CONSTRUCTION.
20. ADJUST UTILITY BOX TO NEW FINISH GRADE AND LOWER
EXISTING UTILITY AS REQUIRED TO MEET MINIMUM COVER
REQUIREMENTS. RELOCATE IF NECESSARY, COORDINATE
WITH UTILITY OWNER.
21. CONNECT PROPOSED WATER LINE TO EXISTING WATER LINE
AT WATER METER LOCATION.
UTILITY PLAN LEGEND
PROPOSED 2" PVC WATER LINE
PROPOSED 8" PVC SANITARY SEWER PIPE
WTR
SAN
08/19/21
MATCH LINE (NORTH/SOUTH)
WTR
SAN
WTR
WTR
SAN
SAN
WTR
SANSAN SANWT
R
ST-102
RIM. = 781.90'
INV. 776.96 (S)
INV. 776.86 (E)
ST-104
RIM. = 778.96'
INV. 776.77 (W)
INV. 776.77 (S)
INV. 776.67 (N)
ST-103
RIM. = 780.05'
INV. 777.10 (N)
ST-101
INV. 777.83 (N)
2
5
7
6
1
8
3
10
11
11
10
12
12
13
14 14
15
16
16
18
16
16
2
398 L.F. OF 6" PERFORATED
PVC @ 0.50% MIN. SLOPE
11
11
INV. = 783.65 (6" PER. PVC)
INV. = 783.65 (6" PER. PVC)
INV. = 780.46(6" PER. PVC)
109 L.F. OF 6" PERFORATED
PVC @ 0.50% MIN. SLOPE
INV. = 781.00 (6" PER. PVC)
298 L.F. OF 12" PERFORATED
PVC @ 0.50% MIN. SLOPE
385 L.F. OF 12" PERFORATED
PVC @ 0.50% MIN. SLOPE
11
356 L.F. OF 6" PERFORATED
PVC @ 0.50% MIN. SLOPE
INV. = 781.87 (6" PER. PVC)
INV. = 781.62 (12" PER. PVC)
INV. = 779.70 (12" PER. PVC)
INV. = 781.19 (12" PER. PVC)
UNDERGROUND DETENTION CHAMBERS (SC-740)
CHAMBER AREA = 196' x 102'
MINIMUM FINISH GRADE ELEV. = 783.00
TOP OF STONE = 782.50
TOP OF CHAMBERS = 781.50
BOTTOM OF CHAMBERS = 779.00
BOTTOM OF STONE = 778.50
21 ROWS OF 27 CHAMBERS = 47,355 CFT.
INV. 778.50 (N)6
19
19
19
19
19
19
19
20
20
ST-202
INV. 781.17 (W)ST-201
INV. 781.90 (E)
17
16
21
14
14
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
SU1.02
SITE UTILITY PLAN - SOUTHWEST
30 900 30 60
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE
PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE
ENGINEER MAKES NO GUARANTEES THAT THE UNDERGROUND
UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION.
REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. SEE SHEET G2.1 FOR GRADING PLAN.
5. THE PROPOSED STORM SEWER SYSTEM FOR THIS PROJECT WILL
BE PRIVATE OWNED.
6. NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN
APPROVED STORM WATER MANAGEMENT PERMIT.
7. UTILITY RELOCATIONS REQUIRED BY THE PROJECT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER. UTILITY LINE RELOCATIONS
REQUIRED FOR ROAD PROJECTS THAT RESULT IN A CONFLICT WITH
PROPOSED DEVELOPMENT SHALL BE THE DEVELOPERS
RESPONSIBILITY TO RESOLVE WITH THE UTILITY. EXISTING POLE
LINES REQUIRED TO BE RELOCATED TO WITHIN ONE FOOT OF
PROPOSED RIGHT-OF-WAY LINE.
8. DAMAGE TO THE EXISTING RIGHT-OF-WAY SHALL
RESTORED/REPAIRED TO THE SATISFACTION OF THE CITY AT THE
COMPLETION OF THE PROJECT. THE CONTRACTOR IS
ENCOURAGED TO INSPECT THE RIGHT-OF-WAY WITH THE CITY
PRIOR TO THE START OF CONSTRUCTION TO DOCUMENT THE
EXISTING CONDITION OF THE RIGHT-OF-WAY.
9. IT IS THE CONTRACTORS RESPONSIBILITY TO REMOVE OR
RELOCATE ANY EXISTING UTILITY LINES WHICH INTERFERE WITH
NEW STORM SEWER INSTALLATION.
GENERAL NOTES
THE STORM SEWER SYSTEM SHALL BE CONSTRUCTED PER DESIGN SPECIFIED AND
AS APPROVED BY THE CITY OF CARMEL ON THE FINAL APPROVED CONSTRUCTION
PLANS. DEVIATIONS FROM THE APPROVED DESIGN SHALL BE PERMITTED DUE TO
SPECIAL CIRCUMSTANCES OR DIFFICULTY DURING CONSTRUCTION AND WILL
REQUIRE PRIOR FIELD APPROVAL FROM A DESIGNATED REPRESENTATIVE OF THE
CITY OF CARMEL IN ADDITION TO SUPPLEMENTAL APPROVAL BY THE DESIGN
ENGINEER. AN EXPLANATION OF ANY SUCH DEVIATION SHALL BE INCLUDED AS A
REQUIREMENT ON AS-BUILT/RECORD DRAWINGS SUBMITTED FOR RELEASE OF
PERFORMANCE GUARANTEES. APPROVED DESIGN SLOPES IDENTIFIED AS
GENERATING VELOCITIES OF 2.5 FPS OR LESS, OR 10 FPS OR GREATER (AT FULL
FLOW CAPACITY) SHALL REQUIRE AS-BUILT CERTIFICATION AT THE TIME OF
CONSTRUCTION, PRIOR TO BACKFILLING THE PIPE. THE CONTRACTOR IS INSTRUCTED
AS-BUILT EACH SECTION OF STORM PIPE AS IT IS BEING INSTALLED TO ENSURE
COMPLIANCE WITH THE DESIGN PLANS AND AS APPROVED BY THE CITY OF CARMEL.
STORM SEWER NOTE
UTILITY KEYNOTES
1. PROPOSED 12" HDPE STORM SEWER PIPE
2. PROPOSED 15" HDPE STORM SEWER PIPE
3. PROPOSED 18" HDPE STORM SEWER PIPE
4. PROPOSED 24" HDPE STORM SEWER PIPE
5. PROPOSED STORM FLARED END SECTION
6. PROPOSED STORM MANHOLE
7. PROPOSED STORM INLET
8. PROPOSED STORM TRENCH DRAIN
9. PROPOSED MECHANICAL STORMWATER QUALITY BMP
10. PROPOSED 1"x 12" FLAT PIPE UNDERDRAIN
11. PROPOSED 6" PVC PERIMETER DRAIN @ 0.5%
12. PROPOSED 12" PVC PERIMETER DRAIN @ 0.5%
13. CONNECT FORCE MAIN TO EXISTING SANITARY SEWER
14. 608 LF OF 2" WATER LINE
15. SANITARY LIFT STATION - SEE DETAIL 4 ON SHEET P3.01
16. 783 LF OF SANITARY FORCE MAIN - SEE PLUMBING PLAN
SHEET P2.01 FOR SIZE.
17. PROPOSED SANITARY DOG HOUSE MANHOLE WITH FLAT TOP
18. EXISTING SANITARY LINE - PER RECORD DRAWINGS
19. PROPOSED STORM SEWER POTENTIAL CONFLICT WITH
EXISTING UTILITY. CONTRACTOR TO VERIFY TOP AND
BOTTOM ELEVATIONS OF EXISTING UTILITY PRIOR TO
CONSTRUCTION.
20. ADJUST UTILITY BOX TO NEW FINISH GRADE AND LOWER
EXISTING UTILITY AS REQUIRED TO MEET MINIMUM COVER
REQUIREMENTS. RELOCATE IF NECESSARY, COORDINATE
WITH UTILITY OWNER.
21. CONNECT PROPOSED WATER LINE TO EXISTING WATER LINE
AT WATER METER LOCATION.
UTILITY PLAN LEGEND
PROPOSED 2" PVC WATER LINE
PROPOSED 8" PVC SANITARY SEWER PIPE
WTR
SAN
08/19/21
MATCH LINE (NORTH/SOUTH)
WTR
WTR
SAN SANWTR
ST-102
RIM. = 781.90'
INV. 776.96 (S)
INV. 776.86 (E)
ST-104
RIM. = 778.96'
INV. 776.77 (W)
INV. 776.77 (S)
INV. 776.67 (N)
ST-103
RIM. = 780.05'
INV. 777.10 (N)
ST-101
INV. 777.83 (N)
2
5
7
6
1
8
3
11
10
12
12
14 14
15
16
16
2
298 L.F. OF 12" PERFORATED
PVC @ 0.50% MIN. SLOPE
385 L.F. OF 12" PERFORATED
PVC @ 0.50% MIN. SLOPE
356 L.F. OF 6" PERFORATED
PVC @ 0.50% MIN. SLOPE
INV. = 781.87 (6" PER. PVC)
INV. = 781.62 (12" PER. PVC)
INV. = 779.70 (12" PER. PVC)
UNDERGROUND DETENTION CHAMBERS (SC-740)
CHAMBER AREA = 196' x 102'
MINIMUM FINISH GRADE ELEV. = 783.00
TOP OF STONE = 782.50
TOP OF CHAMBERS = 781.50
BOTTOM OF CHAMBERS = 779.00
BOTTOM OF STONE = 778.50
21 ROWS OF 27 CHAMBERS = 47,355 CFT.
19
19
19
19
19
19
19
20
20
ST-202
INV. 781.17 (W)
14
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana!
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
SU1.03
SITE UTILITY PLAN - SOUTHEAST
30 900 30 60
1. SEE DRAWING GD0.1 FOR GENERAL NOTES AND ADDITIONAL
LEGEND.
2. TOPOGRAPHIC CONDITIONS AND EXISTING UTILITIES SHOWN WERE
PROVIDED BY CIVIL ENVIRONMENTAL CONSULTANTS, INC. THE
ENGINEER MAKES NO GUARANTEES THAT THE UNDERGROUND
UTILITIES SHOWN COMPRISE ALL SUCH UTILITIES IN THE AREA,
EITHER IN SERVICE OR ABANDONED.
3. CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS IN THE
PROJECT AREA INCLUDING UNDERGROUND UTILITY CONDITIONS,
LOCATION AND DEPTH PRIOR TO ANY OTHER SITE CONSTRUCTION.
REPORT ANY DISCREPANCIES TO THE ENGINEER.
4. SEE SHEET G2.1 FOR GRADING PLAN.
5. THE PROPOSED STORM SEWER SYSTEM FOR THIS PROJECT WILL
BE PRIVATE OWNED.
6. NO EARTH DISTURBING ACTIVITY MAY COMMENCE WITHOUT AN
APPROVED STORM WATER MANAGEMENT PERMIT.
7. UTILITY RELOCATIONS REQUIRED BY THE PROJECT SHALL BE THE
RESPONSIBILITY OF THE DEVELOPER. UTILITY LINE RELOCATIONS
REQUIRED FOR ROAD PROJECTS THAT RESULT IN A CONFLICT WITH
PROPOSED DEVELOPMENT SHALL BE THE DEVELOPERS
RESPONSIBILITY TO RESOLVE WITH THE UTILITY. EXISTING POLE
LINES REQUIRED TO BE RELOCATED TO WITHIN ONE FOOT OF
PROPOSED RIGHT-OF-WAY LINE.
8. DAMAGE TO THE EXISTING RIGHT-OF-WAY SHALL
RESTORED/REPAIRED TO THE SATISFACTION OF THE CITY AT THE
COMPLETION OF THE PROJECT. THE CONTRACTOR IS
ENCOURAGED TO INSPECT THE RIGHT-OF-WAY WITH THE CITY
PRIOR TO THE START OF CONSTRUCTION TO DOCUMENT THE
EXISTING CONDITION OF THE RIGHT-OF-WAY.
9. IT IS THE CONTRACTORS RESPONSIBILITY TO REMOVE OR
RELOCATE ANY EXISTING UTILITY LINES WHICH INTERFERE WITH
NEW STORM SEWER INSTALLATION.
GENERAL NOTES
THE STORM SEWER SYSTEM SHALL BE CONSTRUCTED PER DESIGN SPECIFIED AND
AS APPROVED BY THE CITY OF CARMEL ON THE FINAL APPROVED CONSTRUCTION
PLANS. DEVIATIONS FROM THE APPROVED DESIGN SHALL BE PERMITTED DUE TO
SPECIAL CIRCUMSTANCES OR DIFFICULTY DURING CONSTRUCTION AND WILL
REQUIRE PRIOR FIELD APPROVAL FROM A DESIGNATED REPRESENTATIVE OF THE
CITY OF CARMEL IN ADDITION TO SUPPLEMENTAL APPROVAL BY THE DESIGN
ENGINEER. AN EXPLANATION OF ANY SUCH DEVIATION SHALL BE INCLUDED AS A
REQUIREMENT ON AS-BUILT/RECORD DRAWINGS SUBMITTED FOR RELEASE OF
PERFORMANCE GUARANTEES. APPROVED DESIGN SLOPES IDENTIFIED AS
GENERATING VELOCITIES OF 2.5 FPS OR LESS, OR 10 FPS OR GREATER (AT FULL
FLOW CAPACITY) SHALL REQUIRE AS-BUILT CERTIFICATION AT THE TIME OF
CONSTRUCTION, PRIOR TO BACKFILLING THE PIPE. THE CONTRACTOR IS INSTRUCTED
AS-BUILT EACH SECTION OF STORM PIPE AS IT IS BEING INSTALLED TO ENSURE
COMPLIANCE WITH THE DESIGN PLANS AND AS APPROVED BY THE CITY OF CARMEL.
STORM SEWER NOTE
UTILITY KEYNOTES
1. PROPOSED 12" HDPE STORM SEWER PIPE
2. PROPOSED 15" HDPE STORM SEWER PIPE
3. PROPOSED 18" HDPE STORM SEWER PIPE
4. PROPOSED 24" HDPE STORM SEWER PIPE
5. PROPOSED STORM FLARED END SECTION
6. PROPOSED STORM MANHOLE
7. PROPOSED STORM INLET
8. PROPOSED STORM TRENCH DRAIN
9. PROPOSED MECHANICAL STORMWATER QUALITY BMP
10. PROPOSED 1"x 12" FLAT PIPE UNDERDRAIN
11. PROPOSED 6" PVC PERIMETER DRAIN @ 0.5%
12. PROPOSED 12" PVC PERIMETER DRAIN @ 0.5%
13. CONNECT FORCE MAIN TO EXISTING SANITARY SEWER
14. 608 LF OF 2" WATER LINE
15. SANITARY LIFT STATION - SEE DETAIL 4 ON SHEET P3.01
16. 783 LF OF SANITARY FORCE MAIN - SEE PLUMBING PLAN
SHEET P2.01 FOR SIZE.
17. PROPOSED SANITARY DOG HOUSE MANHOLE WITH FLAT TOP
18. EXISTING SANITARY LINE - PER RECORD DRAWINGS
19. PROPOSED STORM SEWER POTENTIAL CONFLICT WITH
EXISTING UTILITY. CONTRACTOR TO VERIFY TOP AND
BOTTOM ELEVATIONS OF EXISTING UTILITY PRIOR TO
CONSTRUCTION.
20. ADJUST UTILITY BOX TO NEW FINISH GRADE AND LOWER
EXISTING UTILITY AS REQUIRED TO MEET MINIMUM COVER
REQUIREMENTS. RELOCATE IF NECESSARY, COORDINATE
WITH UTILITY OWNER.
21. CONNECT PROPOSED WATER LINE TO EXISTING WATER LINE
AT WATER METER LOCATION.
UTILITY PLAN LEGEND
PROPOSED 2" PVC WATER LINE
PROPOSED 8" PVC SANITARY SEWER PIPE
WTR
SAN
08/19/21
SEE STRUCTURE DATA TABLE FOR
CASTING TYPE AND ELEVATION FINISH GRADE
ASPHALTIC
MASTIC OR BUTYL
RUBBER SEAL
BETWEEN JOINTS
PRECAST CONCRETE ADJUSTING
RINGS AS NEEDED (12" OF RINGS MAX.)
ECCENTRIC CONE OR REDUCER
CAP AS REQUIRED BY SITE
CONDITIONS. CONE TOP TO
MATCH ADJUSTING RING PROFILE.
48" DIA. 5"16"TYP.PRECAST CONCRETE
SECTIONS
PREFORMED HOLE TO MAX.
OF PIPE O.D. + 6" W/ NON
SHRINK CEMENT GROUT
BENCHWALLS AT MIN. 1/2" PER
FOOT SLOPE. BENCHWALLS TO
BE CONSTRUCTED TO SPRING
LINE OF PIPE.
MANHOLE BASE SET ON
6" OF #8 OR #2 STONECOMPACTED
SUBGRADE
PLASTIC ENCAPSULATED
STEEL MANHOLE STEPS
O-RING GASKET
ASPHALTIC MASTIC
OR BUTYL RUBBER
SEAL AT JOINTS
BASE 6" OR 8"
PER SECTION
3"#4 BAR @ 12" o.c.
EACH WAY
(STEEL MESH
AREA = 0.12 SQ.
IN./SQ. FT.)
STORM MANHOLE TYPE "C" DETAIL
1/2" = 1'-0"
24" DIA.
SEE STRUCTURE DATA
TABLE FOR PIPE SIZE
AND INVERT ELEV.
NOTES:
1. MANHOLE CONFORMS TO ASTM C478, JOINTS CONFORM TO ASTM C443.
2. ALL STORM SEWER CASTINGS SHALL BE MARKED "DUMP NO WASTE DRAINS TO WATERWAYS".
3. SEE UTILITY PLAN FOR STORM SEWER STRUCTURE DATA TABLE.VARIES16" MIN.12" TO 15""A"
PIPE SIZE
24" X 24"
STRUCTURE SIZING CHART
"F" 30" X 30"
"M" 24" X 36"
1" = 1'-0"
STORM INLET DETAIL
INSIDE
DIMENSIONS
INLET
TYPE
8"6"
CLASS "A" PRECAST REINFORCED
CONCRETE BOX
SEE STRUCTURE DATA
TABLE FOR PIPE SIZE
AND INVERT ELEV.
INSIDE DIMENSION
* SEE SIZING CHART ABOVE
SEE STRUCTURE DATA TABLE FOR
CASTING TYPE AND ELEVATION
BASE SET ON 6" OF
#8 OR #2 STONE
COMPACTED
SUBGRADEINSIDE DIMENSION* SEE SIZING CHART ABOVEMAX. NUMBER OF
SIDES OF THE
INLET WITH PIPES
3
18" TO 24"
315" TO 18"
3
NOTES:
1. ALL STORM SEWER CASTINGS SHALL BE MARKED "DUMP NO WASTE
DRAINS TO WATERWAYS".
2. SEE UTILITY PLAN FOR STORM SEWER STRUCTURE DATA TABLE.
FOR PIPE LOCATED IN AND
WITHIN 5' OF PAVED AREAS
FOR PIPE LOCATED
IN GRASSED AREAS
STORM SEWER (PVC & HDPE) TRENCH DETAIL
NO SCALE
NOTES:
1. ALL BEDDING & INITIAL BACKFILL
SHALL BE INSTALLED IN 6" TO 12"
BALANCED LIFTS.
2. A MIN. 9" CLEARANCE EACH SIDE
OR PIPE FOR 42" DIA. AND LESS.
Bc MIN.4"12"MIN. 1.25 O.D.+12"
MIN. 6" TOPSOIL
OUTSIDE PAVEMENT LIMITS
PAVEMENT SECTION
REGULAR BACKFILL -
GREATER THAN 5' FROM
EDGE OF PAVEMENT
COMPACTED 90%
REGULAR BACKFILL-
GREATER THAN 5' FROM
EDGE OF PAVEMENT
COMPACTED TO 90%
#8 CRUSHED STONE OR
EQUIVALENT CLASS 1
MATERIAL HAND TAMPED
OR WALKED INTO PLACE
"B" BORROW (INDOT SPEC.) OR
EQUIVALENT GRANULAR
MATERIAL COMPACTED TO 95%
STANDARD PROCTER DENSITY
STORM SEWER / WATER LINE CROSSING DETAIL
NONE
NO SCALE
1 1/2" RAD.WALLDIAMETER
R-1E 1 1/2" RAD.
WALL
1/32 TAPER PER
INCH PER SIDE
WALL R-1
E WALL DIA.+1ADIAMETER
HORIZONTAL FLARE
VERTICAL FLARE
SECTION BB
R-2
BSKIRT
DIAMETERA
B
D
B
C WALLDIAMETER SECTION AA
G or T (TONGUE-INLET END)WALL (GROOVE-OUTLET END)
A
52249 98 84 26 72 24 6550 4 5 48 28
35
39
21
21
21
21
PORTIONS OF A.S.T.M. SPECIFICATION C76.
NOTE: MANUFACTURER OF END SECTION IS IN ACCORDANCE WITH APPLICABLE
78
84
7
8
6
7
6 60
66
72
6
7
54 5
5
5
6
4
14430
16350
24
24
78
78
308750
10630
12520
24
34
8040 27
60
78
78
65
99
99
114
120
79
85
99
99
99
100
6196
102
108
67
73
90 55
44
41 24
24
8
9
2436
38
35 24
24
32 24
6
7
7
6
SIZE SCHEDULE
46
48
38
30
25
19
34
35
39
46
2 3 27
36
42
4
4
30
33
3
3
3
3
3
3
2 21
24 3
15
18
2
2
2
2
2
2
48 10 1930
4100
5380
15
21
2190
3150
12
13
63
63
54
58
9 1280
1520 9
740
990
6
9
35
43
27
27
WALL DIA.
12 2
G or T
1
A WT. SEC
530 4 24
B
28 73 54
97
98
73
97
72
78
37
43
60
66
31
34
73
73
73
73
22 42
48 25
30
36
16
19
41417
27
24 20
22
23
18 15
17
5
5
5
5
1316
16 14
15
12 11
12
4
4
3
4
72
C D DIA.+1E
24 13
R-2R-1
10 9
SKIRT
3
PRECAST FLARED END SECTION DETAIL
SLOPE
MIN.
NOTE: CLEANOUTS IN PAVED AREAS TO BE ACCESSIBLE VIA YARD
BOXES OR EXTENDED FLUSH WITH THE PAVING. CO VER SHOULD BE
THREADED TYPE, WATER TIGHT AND CAPPED.
1/2" = 1'-0"
EXTERIOR CLEANOUT DETAILVARIESFINISH GRADE
STORM SEWER
(SIZE SHOWN ON PLANS)
SAME SIZE AS MAIN
LINE (MAX. 8"
REQUIRED ON
STORM SEWERS)
1'-0" 1'-0"
MIN.6"1/2"HEAVY DUTY CLEANOUT
CASTING - JAY R. SMITH 4253
SERIES OR EQUAL
CONCRETE COLLAR
(CONCRETE SHALL
NOT BE IN
CONTACT w/ PIPE)
PRECAST CONCRETE
SECTIONS
MANHOLE BASE SET ON
6" OF #8 OR #2 STONECOMPACTED SUBGRADE
OUTLET CONTROL STR 108 DETAIL
NOT TO SCALE
24" DIA.
SEE SCHEDULE
FOR CASTING TYPE
ELEV: 784.24
FINISH
GRADEASPHALTIC MASTIC OR
BUTYL RUBBER SEAL
BETWEEN JOINTS
8" REDUCER CAP
16"PLASTIC ENCAPSULATED
STEEL MANHOLE STEPS
O-RING GASKET ASPHALTIC
MASTIC OR BUTYL RUBBER
SEAL AT JOINTS
12" THICK STEEL PLATE
RESTRICTOR
12" HDPE INFLUENT
INV. = 778.4012" HDPE OUTLET
INV. = 778.40
2' SUMPREQ'D.BASE 6" OR 8"
PER SECTION
#4 BAR @ 12" o.c.
EACH WAY
(STEEL MESH
AREA = 0.12 SQ.
IN./SQ. FT.)12" HDPEINFLUENTPIPE12" H
D
P
E
OUT
L
E
T
PI PE12" THICK STEEL PLATE
RESTRICTOR
1/2" THICK STEEL PLATE
ANGLE BRACKET (TYP.)
MANHOLE BTM
INV. = 776.40
TOP OF PLATE
ELEV = 782.41 (100-YR)
6" DIA. CIRCULAR ORIFICE
INV. = 778.40
6" CIRCULAR ORIFICE
INV. = 780.50
ACO TRENCH DRAIN CHANNEL DETAIL
SU3.01
SITE UTILITY DETAILS
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
08/19/21
SU3.02
SITE UTILITY DETAILS
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
08/19/21
NOT TO SCALE
12" MIN.18" MIN.3:1 MA
X
.
3:1 MAX.
TOP OF BANK
TYPICAL SWALE CROSS SECTION
BOTTOM OF SWALE AT
1.0% MIN. SLOPE
BOTTOM OF DRY BASIN ELEVATION VARIES.
24" OUTLET PIPE INVERT = 771.47
4:1 M
A
X
.
PROPOSED EAST DRY BASIN - TYPICAL CROSS SECTION
WIDTH VARIES
BOTTOM SLOPE 1.0% MIN.
EXISTING GRADE
4:1 MAX
.
PROPOSED GRADE
PROPOSED GRADE
EXISTING GRADE
10 YR. STAGE ELEV. = 774.85
100 YR. STAGE ELEV. = 776.52
EXISTING TOP OF BANK = 779.25
BOTTOM OF DRY BASIN ELEVATION VARIES.
15" OUTLET PIPE INVERT = 774.24
EXISTING WEST DRY BASIN - TYPICAL CROSS SECTION
WIDTH VARIES
BOTTOM SLOPE 1.0% MIN.
EXISTING GRADE
EXISTING GRADE
10 YR. STAGE ELEV. = 777.13
100 YR. STAGE ELEV. = 779.14
EXISTING TOP OF BANK = 779.25
SU3.03
SITE UTILITY DETAILS
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
08/19/21
24" SUMP
SU3.04
SITE UTILITY DETAILS
ARCHITECT
Carmel Clay Schools
CONSULTANT
Construction Documents
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 East Main Street
Carmel, Indiana 46033
CARMEL HARTMAN
FIELD IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: May 12, 2021
DRAWN BY: HHW
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
REV.
NO. DESCRIPTION DATE
08/19/21
TBM#1 = 782.26
REMOVE EXISTING DOUBLEDOOR, INFILL OPENING WITH CMUTO MATCH EXISTING. PAINT WALLTO MATCH ADJACENT FINISH.
A1.06
4
A1.06
2
A1.063
2'-8" 8'-4" 2'-8"2'-8"13'-8"UPUP
PRESSBOXA103 A103SYNTHETIC TURF BASEBALL FIELD
LAWN
LAWN
LAWN
LAWN
LAWN
NATURAL TURF BASEBALL FIELD
PROPOSED HEAVY DUTY PAVING
PROTECT
EXISTING
FENCE TO
REMAIN
PROTECT
EXISTING
FENCE TO
REMAIN
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L I AME.PAY
N
EREGISTERE
D
IND I A N AARCHITE CT4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
L1.0
SITE LANDSCAPING PLAN
40 1200 40 80
INLETS, VALVES, AND MARKS MADE UPON THE GROUND BY
ALSO BE OTHER EXISTING UNDERGROUND UTILITIES FOR
WHICH THERE IS NO ABOVE GROUND EVIDENCE OR FOR
EXACT LOCATIONS OF EXISTING UNDERGROUND UTILITIES
SHALL BE VERIFIED BY CONTRACTOR PRIOR TO ANY AND
WHICH NO ABOVE GROUND EVIDENCE WAS OBSERVED. THE
OTHERS) AND ARE SPECULATIVE IN NATURE. THERE MAY
ALL CONSTRUCTION.
THE LOCATIONS OF ALL EXISTING UNDERGROUND UTILITIES
EVIDENCE (INCLUDING, BUT NOT LIMITED TO, MANHOLES,
SHOWN ON THE PLAN ARE BASED UPON ABOVE GROUND
CAUTION !!
Know what'sbelow.
before you dig.Call
R
Call 811 or 1-800-382-5544 Before You Begin Any Digging Project.
Call 48 hours or 2 working days before you dig.
It's Fast, It's Easy and It's the Law in the state of Indiana! VICINITY MAP
08/19/21
ARCHITECT
CARMEL CLAY SCHOOLS
REV.
NO. DESCRIPTION DATE
CONSULTANT
DESIGN DEVELOPMENT
WWW.FHAI.COM317-848-0966
350 E NEW YORK ST# 300, INDIANAPOLIS, IN 46204
COPYRIGHT 2021 BY FANNING/HOWEY ASSOCIATES, INC.
5201 E MAIN STREET
CARMEL, IN 46033
CARMEL
HARTMAN FIELD
IMPROVEMENTS
PROJECT NUMBER: 220127.00
PROJECT ISSUE DATE: 05/12/2021
DRAWN BY:EB
PROJECT
220127.00
W IL L I AME.PAY
N
EREGISTERE
D
IND I A N AARCHITE CT4169
STATE OF
No.
WWW.TLF-ENGINEERS.COM317-334-1500
3901 W 86TH ST #200, INDIANAPOLIS, IN 46268
L1.01
SITE LANDSCAPE DETAILS
•
•
•
•
•
•
•
•
•
•
•
•
08/19/21
08/19/21