HomeMy WebLinkAboutMAYFLOWER-ALT-ENGINEERING-COST-ESTIMATE 1
November 6, 2019rev
Carmel City Engineer
One Civic Square
Carmel, IN 46032
Re: Mayflower Alt, LLC
9801 Mayflower Park Drive
Carmel, IN - KWA project No. 1903-016
ENGINEER’S COST ESTIMATE
Mr. Seth Alt is the managing partner of Mayflower Alt LLC, and is developer’s
representative and the General Contractor. The proposed project will require the site
earthwork, erosion control measures during construction, and the installation of storm
sewer for the installation of the new retail commercial development. These estimates
are based on the Development Plan which has been revised as of November 4, 2019.
The developer/general contractor will be forwarding the following performance
guarantees/bonds, separately, upon approval of this estimate. This letter is in response
to the engineers request for an Engineer’s estimate for determining performance
guarantees to be produced by the developer in the form of a letter of credit from a
lending institution or developer’s insurance surety bond.
Letters of Credit or Surety bonds shall be 100% of the amount of the following
Engineer's Cost Estimate. The following are the Certified Engineers Cost Estimates for
determining the surety bond for the required items within the project:
Erosion Control
Description Quantity Unit Price Total
Silt Fence 2,100 lf. $3.07 / lf $6,450
Temporary & Permanent Seeding 53,946 sq.ft. $0.05 / sq. ft. $2,697
Native Stormwater Seeding 12,720 sq.ft. $0.05 / sq. ft. $636
Concrete washout dumpster 6 month $333.00 ea. $2,000
Temporary Inlet protection 8 $175 ea. $1,400
Erosion Control Blanket 10,850 sq.ft. $1.00 / sq. ft. $10,850
Outlet Protection 14. tons $70/ton $1,005
Rain garden 1 $5,000 ea. $5,000
CDS-3030-C-6 1 $18,400 ea. $18,400
Install Construction Exit 333 sq.yds $4.50 /sq.yd. $1,500
Pond Aerator Fountain 1 $3,000 ea. $3,000
Pond Protection signage 1 $400 ea. $400
Total $53,338
2
These estimates are expressly for use by the Carmel City Engineers Office to determine
the cost estimate of the bonds for Erosion Control measures on private property and for
use by the client to provide permit bond(s) in the amount of the Engineer’s estimate to
be submitted for review and approval to Carmel Engineering.
If you have any questions, require any additional documentation, or comments, please
do not hesitate to contact our office at any time and we will respond rapidly with any
request.
Respectfully,
Keeler-Webb Associates
Adam DeHart, PS, EMT-P, CEPSC, CESWWI
Project Manager
James P. McCann, P.E.
Project Engineer
MAYFLOWER-ALT-ENGINEERING-COST-ESTIMATErev2