SWPP Bond Cost Estimates
Engineer's Opinion of Probable Costs Stormwater Erosion / Sediment Controls Valvoline Instant Oil Change 9835 N. Michigan Road - Carmel, IN 9/13/2019 Stormwater Erosion / Sediment Controls Item Unit TotalNo.Description Quantity Units Price Price 1 Temporary Stone Construction Access 1 Each 1,750.00$ 1,750$ 2 Permanent Seeding/Straw Mulch 1814 Square 1.50$ 2,721$ Yards 3 Storm Inlet Protection - "Flexstorm"3 Each 200$ 600$ 4 Concrete Washout 1 Each 400$ 400$ 5 Silt Fencing 807 Linear 2.05$ 1,654$ Feet 6 Silt Sock 18 Linear 7.00$ 126$ Feet 7 BMP Structure - 4' Dia. First Defense Unit 1 Each 12,500$ 12,500$ Subtotal 19,751$ Estimated Total Surety Costs =19,751$