HomeMy WebLinkAboutVINE-HEALTHCARE-ENGINEERING-COST-ESTIMATE 1
October 28, 2019
Carmel City Engineer
One Civic Square
Carmel, IN 46032
Re: Vine Healthcare
40 North Rangeline Road
Carmel, IN - KWA project No. 1805-008
ENGINEER’S COST ESTIMATE
Dr. Scott Antoine is the managing partner of Vine Real Estate Investments LLC, and Mr.
Steve Moed with SLM Homes is developer’s representative and the General Contractor.
The proposed project will require the site earthwork, erosion control measures during
construction, and the installation of storm sewer for the installation of the redevelopment
of the property. These estimates are based on the Development Plan which has been
revised as of September 27, 2019.
The developer/general contractor will be forwarding the following performance
guarantees/bonds, separately, upon approval of this estimate. This letter is in response
to the engineers request for an Engineer’s estimate for determining performance
guarantees to be produced by the developer in the form of a letter of credit from a
lending institution or developer’s insurance surety bond.
Letters of Credit or Surety bonds shall be 100% of the amount of the following
Engineer's Cost Estimate. The following are the Certified Engineers Cost Estimates for
determining the surety bond for the required items within the project:
Erosion Control
Description Quantity Unit Price Total
Silt Fence 534 lf. $3.07 / lf $1,640
Temporary & Permanent Seeding 2,775 sq.ft. $0.12 / sq. ft. $335
Concrete washout dumpster 6 month $333.00 ea. $2,000
Temporary Inlet protection 3 $175 ea. $525
Erosion Control Blanket 550 sq.ft. $1.00 / sq. ft. $550
Rain garden 1 $3,000 ea. $2,000
Install Construction Exit 144 sq.yds $4.50 /sq.yd. $650
Total $7,700
2
Improvements in Right-of-way
Description Quantity Unit Price Total
Sidewalk & ADA ramps 14 sq.yd. $64.26 / sq. yd. $900
Storm sewer structure 1 $7,000.00 ea. $6,760
Storm sewer 8 $50 / ft. $400
Backfill & Pavement repair
Curb cut asphalt 35 sq.yd. $60 / sq. yd. $2,100
Curb cut curbs 26 ft. $30 /ft. $780
Total $10,940
These estimates are expressly for use by the Carmel City Engineers Office to determine
the cost estimate of the bonds for Erosion Control measures on private property and for
use by the client to provide permit bond(s) in the amount of the Engineer’s estimate to
be submitted for review and approval to Carmel Engineering.
If you have any questions, require any additional documentation, or comments, please
do not hesitate to contact our office at any time and we will respond rapidly with any
request.
Respectfully,
Keeler-Webb Associates
Adam DeHart, PS, EMT-P, CEPSC, CESWWI
Project Manager
James P. McCann, P.E.
Project Engineer
VINE-HEALTHCARE-ENGINEERING-COST-ESTIMATE