HomeMy WebLinkAboutChange Order #3/ENG/$3,943/United Construction Services/20-ENG-06 Haverstick MU PathCity of Carmel Project 20-ENG-06
Haverstick Rd. MU Path
CHANGE ORDER #3
Added two hydrant extensions for locations where Water Main is greater than 5’ depth per direction
from Carmel Water.
Contract Price prior to this Change Order $899,043.79
Contract Price will be increase by this Change Order $3,943.00
New Contract Price including this Change Order $902,986.79
Amount Adjusted Contract
Price
Cumulative % Change
from Original Contract
Original Contract $885,000.00 N/A N/A
CO 01 $8,930.85 $893,930.85 1.01%
CO 02 $5,112.94 $899,043.79 1.59%
CO 03 $3,943.00 $902,986.79 2.03%
By Sergey Grechukhin at 4:52 pm, Dec 09, 2024
Docusign Envelope ID: 9276DBCF-8D4E-4A99-A43B-B8FE7E0471CE
AR-1
Version 2024-09-23
CITY OF CARMEL
TO: CONTRACT CHANGE ORDER NO.: 3
DATE: 11/15/2024
PROJECT NAME:20-ENG-06 Haverstick Rd. MUT Path
CITY REQ. NO.:
CITY PO NO.: 110089
CITY PO DATE: _
I. You are directed to make the following changes in this Contract:
Supply and install two hydrant extensions for Carmel Water hydrants where Main is 5’
depth or greater.
SCHEDULED ADJUSTMENT
ITEM AMOUNT (+) OR (-) DAYS
II. The following referenced Documents further describe the changes outlined in Paragraph I, and
are to be considered a part of this Change Order: R.F.P.: ________ W.D.C. No.: _______
Other:__Change_Order_03_____________________________________________________
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $__899,043.79___________
Contract Price will be increased/decreased by this Change Order $__3,943.00______________
New Contract Price including this Change Order $__902,986.79____________
Contract Time Prior to this Change Order _N/A__ Days _N/A_ Completion Date
Net increased/decreased resulting from this Change Order__N/A Days
Current Contract Time including this Change Order__N/A Days _N/A___ Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are
Recommended
The Above Changes Are
Accepted:
Approved:
Clark Dietz, Inc. United Construction Services, LLC
ENGINEER CONTRACTOR Laura Campbell, Presiding
Officer
8900 Keystone Crossing 347 South Broadway
Address Address James Barlow, Member
Suite 475
Alan Potasnik, Member
Indianapolis, IN 46240 Pendleton, IN 46064
City/State/Zip City/State/Zip Brad Pease, PE, City Engineer
By:
____________________
By:
______________________
ATTEST:
Phone:_219-775-1427_____ Phone:__765-238-1989____
Jacob Quinn, Clerk
Date:__11/15/24_________ Date: _______ Date: _______ 11/15/24
Docusign Envelope ID: 9276DBCF-8D4E-4A99-A43B-B8FE7E0471CE
12/18/2024
Project No.:20-ENG-06
Description:Haverstick Rd. MU Path
Type:Change Conditions
Summary:Added Hydrant Extensions for Main Greater than 5-ft. Depth
Change Order Description:
Awarded Project Amount:$885,000.00
Authorized Project Amount:$899,043.79
Change Order Amount:$3,943.00
Revised Project Amount:$902,986.79
Item No.Unit Unit Price Quantity
84*EA 1,971.50$ 2.00
NOTES:
This Change includes added work for procuring and installing hydrant extensions on two Carmel Water hydrants where the
Water Main is greater than 5' depth per the direction of Carmel Water.
Description Amount
Hydrant Extension, 5 Ft. or Greater $3,943.00
Quantity Changes:
DateContractor
$3,943.00
Docusign Envelope ID: 9276DBCF-8D4E-4A99-A43B-B8FE7E0471CE
Submitted To Phone/Fax Date
City of Carmel Attn: Chris Ogg 317-571-2441 10/29/2024
Street Job Name
1 Civic Square Haverstick Path 96th to 99th
City, State and Zip Code Job Location
Carmel, IN 46032 Haverstick Road
Architect/Engineer Date of Plans Project Number Job Phone
Clark Dietz 8/9/2023 20-ENG-06
We hereby submit bids for:
Cost to add 2 hydrant extensions per Carmel Water, Main was deeper than typical 5' depth
COST ITEM QUANTITY PRICE
Labor
Superintendent 8 HRS @ $96 768.00$
Laborer 8 HRS @ $67 536.00$
1,304.00$
Equipment
18000 lbs excavator 8 HRS @ $158 1,264.00$
1,264.00$
Materials
Hydrant Extensions $625 each @ 2 1,250.00$
1,250.00$
Allowable Markup on Materials 10%125.00$
Respectfully Submitted: 3,943.00$
United Construction Services, LLC
Proposal Request Reply
347 S Broadway St., Pendleton, IN 46064
General Contractor
Phone: (765)278-6246
APPROVEDDocusign Envelope ID: 9276DBCF-8D4E-4A99-A43B-B8FE7E0471CE