Loading...
HomeMy WebLinkAboutGeneral Construction Sequence 02-25-05 , . General Construction Sequence 1. Prior to earth disturbance activities, appropriate erosion and sedimentation controls will be in place to prevent sediment from leaving the subject property. 2. Seed any former cropland areas that do not have a permanent dense vegetative cover. Install the proposed 25-foot tree planting area along the northern and western perimeters. 3. Install interceptor channel downslope of areas to be stripped. Interceptor channel will be extended as overburden stripping progresses. 4. Commence overburden removal. 5. Concurrent with the beginning of overburden removal, commence construction of the berm along 106th Street to provide a sediment barrier. This berm should be seeded (temporary or permanent depending on the weather) immediately upon completion. Silt fence will be installed, if necessary, until berm outslopes are stabilized. 6. Continue overburden removal activities. 7. Seed all berms and other affected areas that are not active mining areas as soon as final grade is attained. 8. Temporary erosion and sediment controls, such as the channels and silt fences, will remain in place until the contributing drainage areas are stabilized. These controls may be removed after the upslope areas are vegetated or the drainage area is eliminated by the progression of mining activities. 9. Upon completion of all mining activities, final grade side slopes not inundated at no steeper than 3 to 1 (horizontal to vertical). 10. Concurrent with reclamation sloping and grading activities, install rock stabilization along the lake water level. 11. Revegetate site in accordance with the plans as described on Drawing 2, Erosion and Sedimentation Control and Planting Plan - Post Mining, which is contained in the Mueller Property North Sand and Gravel Operation Erosion and Sediment Control Report, located on page 6-4 of this Construction Plan. Revised 2/25/05 " SPL Avg PWL Avg ~ SKELLY and LOY, Inc. Noise Measurement Data Sheet 110 100 90 80 70 60 50 40" , ~ IlfJ ii,. !~ dli ~' (~ !1~ ).~ Site Descri tion: Suction Dredge @ 50' Client: Martin Marietta Materials, Inc. Location: Carmel Sand & Gravel Plant Noise Source: Suction Dredge Distance: 50 feet Date: 9/17/2003 Time: 3:23:00 PM Employee: AJD/NW 1/1 Octave Sound Pressure Level 31.5 Hz 63 Hz 125 Hz n 70 70 102.7 101.7 101.7 ''IN MI N I M '" N I 10 ~ ~ Noise Meter ID: RION na-2ge (SN 10790042) Field Calibration Date: 9/17/2003 Notes: SPL and Sound Power Level PWL Results in dB 250 Hz 500 Hz 1k Hz 2k Hz 4k Hz 63.5 61.9 65 63.4 56.7 95.2 93.6 96.7 95.1 88.4 8kHz 50 81.7 ~ <lilo Sf'LA'Il I --.- PWL Avg ~ II ill 1 ~I 1 . '" M N I o 10 N N I o g N I ~ N :r x N N I x .... N :r x '" ~ 1l ~ ~VW ~ "~ ~ \~ <2> t(r MARTIN MARIETTA MATERIALS, INC. MUELLER PORPERTY SOUTH SAND AND GRAVEL OPERATION March 2004 Mueller Property South - Sand & Gravel Timeline Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 1 2 3 I 4 I 1 2 3 4 I 1 I 2 3 I 4 I 1 2 3 4 I 1 2 3 4 1 2 3 4 Overburden Removal ~ ~ Blue Woods Creek Relocation Minina 1111 . J.C -- Reclamation Notes: Hypothetical timeline for Mueller Property South Sand and Gravel only. Actual commencement of activities is contingent upon approval of the proposed surface mining operation. Actual work will commence within approximately 180 days after receiving approval of the proposed application. Actual mining duration dependent on local market conditions once activities begin. 3/17/20048:45 AM