TECHNICAL ADVISORY COMMHTEE
MINUTES
AUGUST 17, 1989
Committee Members Present: Wes Bucher, Ric Brandau, Terry Jones, Dave
Cunningham, DOCD; Randy Powell, City Engineer's Office; Jerry Liston, County
Surveyor's Office; Bart. Tharpe, PSI; Charles Eldridge,IPL; John South, SCS; Dick
Albright, County Engineer; Stan Puckett, CFD.
Goodwill Industries
Committee to consider Docket No. SU - 56 - 89 a Special Use Application for
Goodwill Industries of Central Indiana, Inc. and St. Peter United Church of
Christ, located at 3106 East Carmel Drive, Carmel. Petitioners are requesting
special use approval to construct a free standing pre - manufactured structure for
the collection of used merchandise. Parcel is zoned R - 1.
Filed by George E. Galyean of Goodwill Industries of Central Indiana, Inc.-
Petitioners present: Steve Doeson, George Galyean
Comments:
1)
2)
3)
existing drainage is adequate for proposed project
facility will not require sewer or water availability, will be using church
facilities
signage will be limited to the hours of operation and "Goodwill Donation
Center", total square footage will be limited to 3 square feet
The technical aspects of this project have been reviewed by the TAC and found them
to be satisfactory pending the above concerns being addressed.
McClure Use Variance
Committee to consider Docket No. UV - 59 - 89 a Use Variance Application for
Jerry E. & Paige N. McClure and their property located at 410 North Range
Line Road, Carmel. Petitioners are requesting a use variance to allow the
establishment of a retail flower and gift business within an area zone for
professional office. Parcel is zoned B - 5.
Filed by Paige N. McClure.
Petitioners present: Paige McClure
Comments:
1)
BPW has approved commercial curb cut for this project pending BZA
approval
page 2
.,. .... ""',,,<::;:-
..
2) all improvements (ie. curbs and paving) to be installed prior to opening
of business
3) existing drainage is adequate for proposed improvements
4) additional sewer availability will need to be approved by the BPW
The technical aspects of this project have been reviewed by the T AC and found them
to be satisfactory pending the above concerns being addressed.
Lvons Pool
Committee to consider Docket Nos. V - 64 - 89, V - 65 - 89, and V - 66 - 89
Developmental Standards Variance Applications for John and Beth Lyons and
their property located at 438 Sheffield Court, Carmel. Petitioners are requesting
variances from sections 6.3.1, 6.3.2, and 25.2.1 of the Carmel/Clay Zoning
Ordinance to allow a reduction from a 75 foot to a 30 foot front yard setback,
and to allow a swimming pool and a six (6) foot fence to be located within a
required front yard. Parcel is zoned S - 2.
Filed by John Lyons.
Petitioners present: none
Comments:
1)
2)
mounds, fences and landscaping to be located outside of all easements
PSI has a underground primary line located on the southside of Dorset
Bvld. would request no improvements in the easement
The technical aspects of this project have been reviewed by the T AC and found them
to be satisfactory pending the above concerns being addressed.
Rohrer Meadows
Committee to consider Docket No. 51- 89 P.P., a primary plat application for
Rohrer Meadows. The plat consists of 43 lots on 14.5 acres of land located on
the west side of Rohrer Road, just north of the existing Hunters Creek South
subdivision. Petitioner seeks approval to subdivide property for residential
development. Site is zoned R - 1.
Filed by Mark Boyce for c.P. Morgan
Petitioners present: Dave Sexton, Mark Boyce
Comments:
1)
2)
3)
4)
5)
6)
drainage facilities will be regulated per request of the County Surveyor
will need to obtain approval to outlet storm water into Hunters Creek
South facilities
fire hydrant location will need to be approved by the Fire Chief
Signage and Landscape plan will need to be submitted and reviewed by
DOCD
Street names will need to be approved by Fire Chief
Statement on the existing roads and proposed streets in the area
~ -::_-
page 3
7)
8)
9)
10)
11)
a 6" sub - drain for offsite swale to run from Rohrer Rd. to R.R. line, a
french drain at storm sewer outlet will be required, petitioner has agreed
to this conditional on an easement existing currently
incorporate safety ledge in pond cross - section
lower storm structure #623 to provide adequate sub - drainage
extend curb across common areas as previously approved
recommend straw bale detail to be included on detail page of plans
The technical aspects of this project have been reviewed by the T AC and found them
to be satisfactory pending the above concerns being addressed.
Fessler Insurance
Committee to consider Docket No. SU - 57 - 89 a Special Use Application for
Indiana Lumberman's Insurance Agency, Inc. d/b/a Fessler Insurance, located at
1036 South Range Line Road, Carmel. Petitioner is requesting special use
approval to remodel the existing and construct an addition containing
approximately 3200 square feet (proposal require a variance, see next agenda
item). Parcel is zoned B-3.
Filed by James J. Nelson - Attorney for Indiana Lumberman's Insurance Agency,
Inc. d/b/a Fessler Insurance.
and
Docket No. V-58 - 89 a Developmental Standards Variance Application for
Indiana Lumberman's Insurance Agency, Inc. d/b/a Fessler Insurance, located at
1036 South Range Line Road, Carmel. Petitioner is requesting a variance from
sections 14.3.3 and 14.3.5 of the Carmel/Clay Zoning Ordinance to allow a
reduction in the minimum side yard and minimum rear yard setback from 30 feet
to 20 foot and 10 foot respectively. Parcel is zoned B-3.
Filed by James J. Nelson - Attorney for Indiana Lumberman's Insurance Agency,
Inc. d/b/a Fessler Insurance.
Petitioners present: Jim Nelson, Chris White, Li - Ching Wu
Comments:
1)
2)
will need to obtain additional sewer and water availability from the BPW
staff has a concern with the subdivision of the property, in regards to the
legality of this splitting per our current ordinance, staff will research this
concern
The technical aspects of this project have been reviewed by the TAC and found them
to be satisfactory pending the above concerns being addressed.
page 4
,... -- ...-::.'1'
American Awtre2ates
Committee to consider Docket No. SU - 60 - 89 a Special Use Application for
the American Aggregates Corporation and two parcels located on the west side
of North Gray Road between East 106th Street on the north and East 96th
Street on the south. Petitioner is requesting special use approval to extract sand
and gravel from the real estate and to construct thereon an artificial lake or
pond. Parcel A is zoned S - 1 and S - 2. Parcel B is zoned S - 1 and S - 2.
Filed by James J. Nelson - Attorney for the American Aggregates Corporation.
Petitioners present: Jim Nelson, Mark Boyce, Richard Henderson
Comments:
1)
2)
3)
4)
SCS would recommend erosion control practices to be implemented during
the extraction process and afterwards during development of the ground
County Highway would request the dedication of a 50' half ROW on Gray
Road
staff will need to research and discuss the 300' buffer requirement in
regards where the setback should be established (district vs. use)
staff questions parking requirement, petitioner states no employee parking
will be located onsite
The technical aspects of this project have been reviewed by the TAC and found them
to be satisfactory pending the above concerns being addressed.
Shady Brook Rezone
Committee to consider Docket No. 42 - 89 Z, a rezone application for 180.86
acres of land located south of 106th street, east of Mi~higan Road and west of
Shelbourne Road. Site is currently zoned S - 1. Rezone request is to zone this
property to B-3 and S - 2 for a commercial and residential development project.
Filed by Jim Nelson for Shady Brook Development Co.
Petitioners present: Jim Nelson, Ursel Cox, Terry Quillman, Bill Fehribach, George
Sweet
Public present: Judy Hagen, Sue Dillon, Marilyn Anderson
Comments:
1)
2)
3)
4)
Drainage plan has been conceptually approved by Ham Co SCS and Co
Surveyor
Highway plans are being reviewed by Ham. Co. Highway Dept. in
conjunction. with A & F Engineering
Water currently exists to site and sewer availability is projected to be
available in the end of 1990
Residential area shown is conceptual plan to be finalized at the time of
primary platting
The technical aspects of this project have been reviewed by the T AC and found them
to be satisfactory pending the above concerns being addressed.
-- ~~..... .
..
page 5
TooJries Cookies
Committee to consider Docket No. 52 - 89 ADLS,an Architectural Design,
Lighting and Signage application for Toogies Cookies. Petitioner seeks approval
for the construction of a 15,178 sq. ft. building to house a retail and
manufacturing facility located on lot 2 of North American Park. Site is zoned
B-2 and 1- 1 and is located in the 421 Overlay Zone.
Filed by Jim Nelson for RMC Corp. .
Petitioners present: Jim Nelson, Bill Schertzinger, Rochelle Cohen, Stu Huckleberry
Comments:
1)
2)
3)
4)
5)
6)
7)
additional detail will be required in regards to the dry retention facility
in the SW comer of the site
petitioner will hook onto sewers as soon as available
commitment in recordable form for sidewalks along Michigan Rd. will be
requested at the time a sidewalk plan is developed along the Michigan Rd.
Corridor
erosion control plan and details will need to be submitted and reviewed
siamese to be located next to existing hydrant on north property line
at all property lines the footcandle spread cannot exceed .1 ftcdle
non - opposition to annexation in recordable form will need to be
submitted
The technical aspects of this project have been reviewed by the T AC and found them
to be satisfactory pending the above concerns being addressed.
HAMILTON CROSSING WEST SIDE BLDG. 1
Petitioner present: Mark Disney, Stu Huckleberry
Comments:
1)
2)
3)
4)
5)
6)
at the time this development is split off and sold the storm drainage
system would need to become a regulated drain (42" pipe along east side
of road) in a recordable letter of commitment
DOCD has requested a curb cut (access point) between this parcel and
the one to the south (location to be determined at the time the parcel
to the south develops)
petitioner will need to obtain approval to outlet stormwater into the J.R.
Collins drain
need an updated erosion control plan approved by SCS
sidewalks are to be installed per BPW requirements, staff would request
an overall plan for the sidewalks to be developed
prior to c/o on this bdlg. fencing/screening may need to be installed along
the north side of this phase 1 in conjunction with and depending upon
the timing of phase 2 will need to be approved by staff
.. ..........--.....:::.
p-
page 6
""
PSI would request updated plans to be forwarded showing service locations
and any overall plan for the remaining acreage
A concern has been raised in regards to the type of materials being used
for the storm sewer system and facilities - City Engineer and County
Surveyor will need to approve these prior to construction
The technical aspects of this project have been reviewed by the T AC and found them
to be satisfactory pending the above concerns being addressed.
7)
8)
"