CE'RTfFfcATEOF'SUBSTANTIAL"COMPlETION(CenttaIPark) ~~.,__....n_
Project:
Carmel Clay Central Park
1010111'" Street
Indianapolis, IN 46280
Date of Issuance: 28 December 2006
To:
Geupel Demars Hagerman
7930 Castleway Drive
Indianapolis, IN 46250-7710
Project No.: 2003-018
Contract For:
Contract Date:
Project or Dasignated Portion shall include:
All Architectural, Civil, Landscaping, Structural, Mechanical, Plumbing, Fire Protection Electrical, Aquatic and Food
Service building and s"e elements I "ems for the Carmel Clay Central Park, Project which consist of the three (3)
major Sub-Certificate of Substantial Completion Fonms: 1) Manon Family Recreation Center, 2) Monon Family
Aquatic Center, 3) Central Park Site Development, as per the Contract Documents. Also included are all: Field
Sketches (SK's), Request for Information (RFI's), Field Orders (FO's), Field Meeting Notes I Minutes,
Memorandum, Architect's Field Reports and all Architects I Owners I Architect's Consultantsl City of Carmel
punchlists to date.
The Work perfonmed under this Contract has been reviewed and found to be substantially complete. The Date of
Substantial Completion of the Project or portion thereof designated above is hereby established as 28 December
2006.
The date of commencement of warranties for items on the attached list will be the date of final payment unless
otherwise agreed to in writing. Which is also the date of commencement of applicable warranties required by the
Contract Documents, except as stated below:
Refer to each Sub-Certificate for additional infonmation.
. )
DEFINITION OF DATE OF SUBSTANTIAL COMPLETION
,
The Date of Substantial Completion of the Work or designated portion thereof, is the Date certified by the Architect I
when construction is sufficiently complete, in accordance with the ContractDocuments, so tha Owner can occupy I
or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract ,
Documents. I
Williams Associates Architects, Ltd.
E-Mail Williams@Williams-Architects.com
.,.
A list of items to be completed or corrected, prepared by the Contractor and verified and amended by the
Architect is attached to the fore mentioned and below noted Sub Certification of Substantial Completion
accordingiy. The failure to include any items on such list does not aiter the responsibility of the Contractor to
complete all Work in accordance with the Contract Documents.
Williams Architects
ARCHITECT
~ /~~~ _;r
~
~r: ""':'r'}~ ~('0
2) I
I
I
I
The attached Sub Certificates of Substantial Completion will consist of: 1) Monon Family Recreation Center.
Monon Outdoor Family Aquatic Center. 3) Central Park Site Development.
28 December 2006
DATE
I
I
I
. ~days from the I
. .... 1
Ih.e~ Contractor will complete or correCt the Work on the list of items attached hereto within
above Date of S'ubstantiaICompleliori: -
Geuoel Oemars Haaerman
CONTRACTOR
BY~~a<MP,J) D~~~~\O~ i
SQ. VrLou. ,,^,,<L.. I
The Owner accepts the Work or designated portion thereof as substantially complete and will assume full !
possession thereof at 5:00 O.m. (time) on 28 December 2006 (date).
Carmel Clav Park & Recreation
OWNER .
/~ Q ~;j(j'),cC.,
BY O:'h.,....j rPr ...~j ,".J 0 "- -r
I'J.. - :1- <is-a (,
DATE
The responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities. damage to the Work
and insurance shall be as follows:
(Note: Owner's & Contractor's legal and insurance counsel should determine and review insurance requirements
and coverage; Contractor shall secure consent of Surety Company, if any.)
G:I2003\2003-Q18 Carmel Clay\Certlficate of Substantial Complellon\CSCOO1.Mairl.doc
Williams Associates Architects. Ltd.
E-Mail Williams@Williams.Architects.com
WilliAMS
ARCHITECTS
ARCHITECTS PLANNERS
450 East Gundersen Drive
Carol Stream, illinois 60188
Phone 630-221-1212
Fax 630-221-1220
Williams-Architecls.com
a Architect's Copy
a Construction Manager's Copy
a Owner's Copy
a Field Copy
SUB-CERTIFICATE OF SUBSTANTIAL COMPLETION (Monon Community Recreation Center)
Project:
Carmel Clay Central Park
1010 111th Street
Indianapolis, IN 46280
Date of Issuance: 28 Decem ber 2006
To:
Geupel DeMars Hagerman
7930 Castleway Drive
Indianapolis, IN 46250-7710
Project No.: 2003-018
Contract For:
Contract Date:
Project or Designated Portion shall include:
All Architectural, Civil, Landscaping, Structural, Mechanical, Plumbing, Fire Protection Electrical, Aquatic and Food Service
building and site elements I items for the Mo~on Community Recreation Center, as per the Contract Documents. Also
included are all: Field Sketches (SK's), Request for Information (RFI's), Field Orders (Fa's), Field Meeting Notes I Minutes,
Memorandum, Architect's Field Reports and all Architects I Owners I Architect's Consultantsl City of Carmel Punchlists to
date.
The Work. performed under this Contract has been reviewed and found to be substantially complete. The Date of Substantial
Completion of the Project or portion thereof designated above is hereby established as 28 December 2006.
The date of commencement of warranties for items on the attached list will be the date of final payment unless otherwise
agreed to in writing, which is also the date of commencement of applicable warranties required by the Contract Documents,
except as stated in the attached document Appendix A.
DEFINITION OF DATE OF SUBSTANTIAL COMPLETION
The Date of Substantial Completion of the Work or designated portion thereof, is the Date certified by the Architect when
construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the
Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.
Williams Associates Architects, Ltd.
E-Mail Wiliiams@Williams-Architects.com
A list of items to be completed or corrected, prepared by the Contractor and verified and amended by the Architect is
attached to the forementioned and below noted Sub Certification of Substantial Completion accordingly. The failure to
include any items on such list does not alter the responsibility of the Contractor to complete all Work. in accordance with the
Contract Documents.
Williams Architects
ARCHITECT
~--:- ~ ~,-'''''""
ft """"f'llJ.s-,. t DATE
The Contractor will complete or correct the Work on the list of items attached hereto within 30 days from the above Date of
S~U~bUNSDTtea~nDtia~I~C~Dr~mHPlaeatieDrmn, an .B.y.Z.... -/-//----------.---
_ _ __ ___ ___ ~L -' o5121/~7
DATE I
The Owner accepts the Work or designated portion thereof as substantially complete and will assume full possession thereof
at 5:00 D.m. (time) Dn 28 December 2006 (date),
Carmel Clav Park & Recreation
OWNER
l~jJ '7/ (1)1,-,
BY
t.,-- ;1..1 -0')
DATE
The responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work and
insurance shall be as follows:
(Note: ONner's & Contractor's legal and insurance counsel should determine and review insurance requirements and
coverage; Contractor shall secure consent of Surety Company, if any)
G:\2003\2003-018 Carmel Clay\Certificate of Substantial Completion\CSG-MCRC.doc
,
~
Williams Associates Architects, Ltd.
E-Mail Willlams@Williams-Architects.com
WllUAMS
ARCHITECTS
ARCHITECTS PLANNERS
450 East Gundersen Drive
Carol Stream, Illinois 60166
Phone 630-221-1212
Fax 630'221-1220
Williams-Architects. com
o Architect's Copy 0 Construction Manager's Copy 0 Owner Representative's Copy 0 Owner's Copy
SUB-CERTIFICATE OF SUBSTANTIAL COMPLETION (Manon Family Aquatic Center)
Project:
Carmel Clay Central Park
1010 111th Street
Indianapolis, IN 46260
Date of Issuance: 28 December 2006
To:
Geupel DeMars Hagerman
7930 CasUeway Drive
Indianapolis, IN 46250-7710
Project No.: 2003-018
Contract For:
Contract Date:
Project or Designated Portion shall include:
All Architectural, Civil, Landscaping, Structural, Mechanical, Plumbing, Fire Protection Electrical, Aquatic and Food
Service building and site elements / items for the Monon Family Aquatic Center, as per the Contract Documents. Also
included are all: Field Sketches (SK's), Request for Information (RFI's), Field Orders (FO's), Field Meeting Notes I
Minutes, Memorandum, Architect's Field Reports and all Architects I Owners I Architect's Consultantsl City of Carmel
Punch lists to date.
The Work performed under this Contract has been reviewed and found to be substantially complete. The Date of
Substantial Completion of the Project or portion thereof designated above is hereby established as
28 December 2006
The date of commencement of warranties for items on the attached list will be the date affinal payment unless otherwise
agreed to in writing, which is also the date of commencement of applicable warranties required by the Contract
Documents, except as stated in the attached document Appendix A.
DEFINITION OF DATE OF SUBSTANTIAL COMPLETION
The Date of Substantial Completion of the Work or designated portion thereof, is the Date certified by the Architect when
construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the
Work or designated portion thereof for the use for which it is intended. as expressed in the Contract Documents.
Williams Associates Architects, Ltd.
E-Mail Williams@Williams-Architects.com
.r-'-'--_.
A list of items to be completed or corrected, prepared by the Contractor and verified and amended by the Architect is
attached to the fore mentioned and below noted Sub Certification of Substantial Completion accordingly. The failure to
include any items on such list does not alter the responsibility of the Contractor to complete all Work. in accordance with
the Contract Documents. See Appendix A
Williams Architects
ARCHITECT
28 December 2006
DATE
The Contractor will complete or correct the Work on
Date of Substantial Completion.
items attached hereto within .1Q...days from the above
-- - ..GeuDel,DeMars,Haaerman-
CONTRACTOR
BY
JULt Z, 2007
DATE '
The Owner accepts the Work or designated portion thereof as substantially complete and will assume full possession
thereof at 5'00 D m. (time) on 28 December 2006 (date).
Carmel Clav Park & Recreation
OWNER
( ~~"~ 07fCl) ~q~
BY
7.- '}. -0'1
DATE
The responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work and
insurance shall be as follows:
(Note: Owner's & Contractor's legal and insurance counsel should determine and review insurance requirements and
coverage; Contractor shall secure consent of Surety Company, if any)