October 6, 1992
Avian Glen Associates, L.P.
8250 Haverstick
Suite 290
Indianapolis, Indiana 46240
RE: Avian Glen
Carmel, Indiana
Gentlemen:
In compliance with your request, we have perfornied an inspection at the above
referenced site, reviewed copies of the soil test boring data, and reviewed available geologic
and hydrogeologic maps regarding the above referenced site. The purpose of our review
was to evaluate the groundwater elevation relative to the elevation of possible basements.
Currently the proposed elevation of the pond is 771.5. This elevation is within a
sand layer that extends to a considerable depth. Hydrologic information available from the
Indiana Department of -Natural Resources indicates that the groundwater in this area should
be anticipated to be between elevation 760 and 775. Based upon our visual observations
and the soil test boring information, it appears that the groundwater is at approximate
elevation 770. The hydrologic maps show that the groundwater gradiant in the area of the
site is toward White River and the groundwater flows to the southeast.
At this tune, it is indicated that the pond water will be allowed to fluctuate with the
groundwater. The design 100 year flood elevation is 776.7. Our evaluation and available
design data indicate that this 100 year flood elevation is attributable to surface runoff into
storm sewers within the development. Because the bottom of 4 L11C pond is within sands,
some surface water will be allowed to permeate into the ground. It is our undersuinding
that the only outflow used in computing the 100 year flood elevation was the existing outlet
pipes. Thus, because the water will be allowed to flow both out the outlet pipes and into
the ground, it is not anticipated tliat the computed 100 year Iood elevation will actually be
achieved.
Additionally, the flow of groundwater is to be southeast. It is anticipated that any
water that does permeate into the sands will flow toward the southeast. The volume of
water which is anticipated to be required to raise the pond elevation to 100 year flood
elevation does not appear adequate, to sufficiently raise the groundwater elevation to
basement level.
Offices: Snbrruface Investigation and Formdation Engineering
Cincinc ti, Ohio Construction Materials Testrrrg and Inspection
Gv,insvAlc • rI,Wavne - Lafayette • Tci c I lai;tc • Sootl: Bcn:!, lncliar.." Envrronniental Services
Avian Glen Associates, L.P.
October 6, 1992
Page Two
Therefore, we do not anticipate groundwater problems within any basements founded above
the normal pool elevation. However, in order to alleviate construction problems, it is
recommended that all bascinent floor elevations be constructed at a minimum of Nvo (2)
feet above the normal pool elevation. This will allow for installation of foundations above
the groundwater.
It is also recommended that an underdrain system and sump pump be installed
around the perimeter of the proposed basements. By installing these facilities, any surface
water which permeates along the basement backfill/natural soil interface will be able to be
removed from the basement area.
Maps also indicate that this site is one mile away from the White River at its closest
point. The eicvation difference from the surface of the site to the White River flood plain
is greater than thirty-five (35) feet. Thus, no back water of the White River is considered
during the flood periods.
Please note that this report was prepared based upon available data. However, site
specific data `could provide a more accurate evaluation of the groundwater conditions. A
comprehensive hydrogeologic study would include installation of monitoring wells and long-
term monitoring. Should elevation be critical, a site specific study should be performed.
If you have any questions regarding these matters or if we can be of further service,
please do not hesitate to contact us.
Very truly yours,
AL'T' & WI'I'ZIG ENGE TEERING, INC.
Thomas J. Co cy P.E.
TJC:kdc
Avian Glen Associates
(date
MEMORANDUM TO: J? L A ? 1 i - .
FROM: Architectural Review Committee
RE: Architectural Approval, Lot
in accordance with Article VI of the Declaration of Cove-
nants, Conditions and Restrictions of Avian Glen, dated September
21, 1992, and first recorded in the office of the Recorder of
Hamilton County, Indiana on September 22, 1992 as Instrument No.
9236482, this is to confirm that the Avian Glen Architectural
Review Committee (the "Committee") has reviewed and approved the
enclosed stamped copy of construction plans (including plot plan)
for the residence proposed to be built on Lot of Section
of Avian Glen.
Attached hereto for your reference is an additional copy of
the Avian Glen Building Policies and Procedures, which was previ-
ously delivered to all participating builders. Section 5 of this
document contains general guidelines relating to construction
specifications. Each builder is asked to keep these guidelines in
mind with respect to any item (e.g., exterior materials, colors,
landscaping, fencing, etc.) which either (i) is not specifically
set forth on the enclosed approved copy of the construction
plans, or (ii) constitutes a change from any item described on
the enclosed plans. Any builder in doubt about whether any such
non-specified or changed item will be acceptable to the Committee
is encouraged to submit such item to the Committee for specific
approval.
The Building Policies and Procedures also contains informa-
tion regarding compliance with subdivision grading plans; mainte-
nance of lots during construction; basements and crawl spaces;
stone base construction driveways; dusk-to-dawn lighting; street
trees; sidewalks; and tree preservation areas. Each builder is
asked to review these provisions before beginning construction.
Any questions about the Building Policies and Procedures may be
directed to the Committee by calling 259-6213.
Thank you again for building at Avian Glen.
8250 Nawersrnck fioad, Suite 290, lelddnn.molis, f-,dona 46249 3 r7.25q-6273 FAX. J!7-259-S2,5
SCHEDULE A
AVIAN GLEN. BUILDING POLICIES AND PROCEDURES
The Avian Glen Architectural Review Committee (the "Commit-
tee") has been established pursuant to the Avian Glen Declaration
of Covenants, Conditions and Restrictions in order to preserve
property values and maintain a harmonious and compatible rela-
tionship among the homes in Avian Glen. In performing this role,
the Committee will use its best efforts to apply the following
standards in a fair, consistent and predictable manner and to
minimize any delays or other inconvenience to builders in having
their plans approved prior to construction.
1. Avian Glen Architectural Review Committee. All improve-
ments of any kind (including, without limitation, residences,
accessory buildings, decks, gazebos, walkways, patios, porches,
terraces, pools, fences, walls, antennas and landscaping) must be
approved in writing in advance by the Committee pursuant to
Article VI of the Avian Glen Declaration of Covenants, Conditions
and Restrictions. Initially, the Committee will be comprised of
representatives of the Developer. Builders are asked to submit
two (2) sets of plans (including plot plans) to the Committee for
approval prior to application for a building permit and the
beginning of construction. One copy, if approved, will be so
stamped and returned to the builder. The plot plan must show in
reasonable detail the manner in which the builder will provide
for surface water drainage on the lot. Also, reference must be
made in the plans to the location and manner in which any sump
pump discharge will be handled on the lat.
2. Minimum Residence Sizes. The Committee will require
that the minimum square footage of finished living area (i.e.,
exclusive of decks, patios, porches, terraces, garages and base-
ments) for a one-story or "ranch" style dwelling be 210D square
feet. Minimum square footage of finished living area for a
multi-story dwelling will be 1300 square feet on the ground floor
and 2300 square feet in the aggregate.
3. Compliance with Subdivision Grading Plan. Builders must
comply with the over-all grading plan for Avian Glen project
(copies of which are available to builders in the office of the
Developer) when establishing the finished floor elevations on and
performing the final grading of the lots, and builders may not
interfere with the general drainage plan for the project by
filling or diverting existing rear or side-yard swales. Builders
will be solely responsible for providing for positive storm
drainage for the entire lot and for not adversely affecting
adjoining lots.
4. Maintenance of Lots During Construction. Builders will
be responsible for the maintenance of lots during the construc-
tion period. Specifically, builders must periodically mow lots
and keep them free of trash and other debris and keep trash and
other debris from blowing or being deposited onto other areas of
the project. Paring construction operations, builders are asked
to use all reasonable efforts to keep building sites and adjacent
streets in as neat, clean and orderly condition as is practica-
ble. Builders will be responsible for removing all excess dirt
from building sites and may not deposit any dirt on any property
owned by Developer without Developer's prior written consent in
each case. In the event of the failure by a builder to comply
with its obligations under this Paragraph A or the preceding
Paragraph 3, Developer may, after written notice and reasonable
opportunity to cure, perform such obligations on behalf of the
builder and collect from the builder the reasonable costs there-
of.
S. Architectural Review Committee Guidelines. In order to
provide builders with some guidance on the manner in which the
Committee will review plans and specifications submitted by
builders, the following information is provided:
Location. Location of dwellings on any lot must con-
form to the appropriate front, rear and side setbacks,
as shown on the Plat or specified in the Plat Covenants
and Restrictions.
Variation. Architectural
will be governed so as
models from being built c
will be made to vary each
excessive duplication.
style and exterior treatment
to prevent similar styles or
i adjacent lots. Every effort
architectural style, avoiding
Exterior Materials. Exterior building materials will
generally be.restricted to "natural" materials. No
artificial materials such as aluminum, vinyl or prefin-
ished masonite will be acceptable. Though the Committee
will generally prefer natural cedar lap siding, the
reasonable use of T-111 siding will be permitted at
Avian Glen.
Colors. All exterior brick, siding and trim color
selections will be reviewed to ensure that color
schemes are reasonably conventional and harmonious with
the surrounding area.
Garages. All garages must conform to the above exteri-
or material requirements and must have automatic garage
door openers for each garage door. All homes must have
a minimum two-car attached garage.
Roofs. Roof materials must be asphalt shingle or any
other natural roofing material.
Windows. All windows and window treatments must gener-
ally-be wood.
Vents. Vent stacks and roof ventilators must generally
be placed to the rear roof elevations.
Fireplaces. Chimneys must be enclosed in a masonry
chase.
Gutters and Drains. Gutters and down-spouts must be
constructed on all homes, draining to a proper drainage
swale. If necessary for proper drainage or to avoid
soil erosion, downspouts will be required to be buried.
Basements and Crawl SRaces. All foundations will be
either basement or crawl space design. In general,
slab foundation construction will not be approved. All
drainage from sump pumps must be discharged directly to
a lake or to a drainage the and may not drain to the
street or any drainage swale. Casual water will not be
permitted to stand on any lot. Under no circumstances
may downspouts, sump pumps or any storm water facility
be connected to any part of the sanitary sewer system
or designed or built in a manner that adversely affects
drainage on adjoining lots.
-2-
Driveways. All driveways must be asphalt, concrete or
other approved materials. At the beginning of construc-
tion of each home, the builder will be asked to install
a stone base in the driveway area in order to minimize
the spread of construction dirt and mud into project
roadway areas.
Mail Boxes. All mail boxes must be approved by the
Committee and must be of a generally uniform type and
construction.
Dusk to Dawn Lighting. A dusk to dawn pole yard light
must be installed. as part of the home construction
within the front yard of each residence. Placement
may be made at the builder's discretion to enhance the
appearance of the residence and community security.
Landscaping. The front yards of all homes must be
landscaped, and general plans for all landscaping that
will be visible from the street must be submitted to and
approved by the Committee prior to installation. In
order to comply with platting requirements imposed by
the City of Carmel, as part of the construction of each
home, a minimum of two trees (of 1 1/2 inch caliper or
larger) must be planted by the builder within the front
yard area of each lot. All front yards and at least the
front fifteen (15) feet in depth of side yards must be
sodded or properly hydroseeded.
Sidewalks. Builders must install sidewalks in accord-
ance with the requirements and standards of the Carmel
Subdivision Control ordinance along all interior streets
in the project upon which the lot abuts. Sidewalks
must be completed on or before the substantial comple-
tion of the home. If a builder should default on its
obligation relating to sidewalks, Developer may, after
written notice to the builder and a reasonable opportu-
nity to cure, perform such obligation on behalf of
builder and collect from builder the reasonable costs
thereof.
Awnings. No metal, fiberglass, canvas or similar type
material awnings or patio covers will be permitted with-
out specific Committee approval.
Pools. No above-ground pools will be permitted at Avian
Glen.
Fencing. Special care will be aken by the Committee in
reviewing any proposed fencing on a lot to ensure that
the fence will not create an unreasonable hindrance or
obstruction to any other lot in the project. In gener-
al, all fencing must be brick, ornamental iron or alumi-
num, treated wood or vinyl-coated chain link (dark
green, brown or black in color) and must not be higher
than six (6) feet from ground level. Fencing in rear or
side yard areas of lake lots, however, should generally
not exceed 42 inches in height and should be of a see-
through material. The Committee will focus carefully on
any fencing proposed to be located near the project's
perimeter or main entrances to ensure that the project's
appearance from streets is not adversely affected. In
no event will any stockade, horizontal wood, galvanized
chain link, wire, solid aluminum or PVC fences be per-
mitted in any part of the project. No fencing may
extend forward of any front corner of a residence.
-3-
6. Tree Preservation. Each builder will receive a copy of
the Tree Preservation Plan which the Developer was required to
establish for the project. The following Phase 1 lots are af-
fected by this plan: 29, 30, 31, 32, 39, 40, 41, 45, 46, 47, 48,
49, 50, 51, 54, 55, 56, 57, 58, 59, 60, 61, 78, 79 and 82.
Living trees of 4 inches caliper or larger located within desig-
nated Tree Preservation Areas may not be removed by builders or
homeowners without the prior written consent of the Committee in
each case; provided, however, that such consent will not be
required for trees located within the footprint of the home to be
constructed on a lot or within any driveway areas.
7. Modifications. These Building Policies and Procedures
are subject to modification from time to time in the reasonable
discretion of the Developer. The Developer will use all reasona-
ble efforts to monitor the compliance by builders and homeowners
with these policies and procedures, but the Developer will not be
responsible or liable to any builder or owner for any other
builder's or owner's violation thereof.
July 1992