HomeMy WebLinkAboutCRC-06-27-02CARMEL REDEVELOPMENT COMMISSION Meeting
Thursday, June 27, 2002
President Rick Roesch called the meeting to order at 4:06 p.m. Commission members
present were Ed Burke and Ron Carter, constituting a quorum. Luci Snyder arrived at
4:09 p.m. Also present were Chris McComas, Brian Shapiro, Steve Engelking, Les Olds,
Trent Newport, Lance Stahley, Kelli Lawrence. Phyllis Morrissey, support staff.
Mr. Roesch stated we are here today to discuss the traffic flow, the designs around the
Shapiro project, the site that’s under construction. We have some problems and things to
consider and we have contractors on site . Cash flow considerations also which need to
be addressed.
Mr. Olds referred to a document prepared earlier which noted the different scopes of
work connected with the project. Of these scopes, some have been completed, Shapiro
was authorized to complete scopes #1, 2, and 7. the additional scope of work (#4) was not
part of the project agreement although the work needed to be done. The CRC has
authorized the building of the north park of the parking lot. What’s happened is that this
document we prepared, based on Civil Designs’ document which included Fire Dept
Drive, the adding of the additional lane, the Veterans Way comes up
Mr. McComas discovered that Veterans Way is not included in the project agreement. Mr.
Olds said if it is not done at this time, then the curb cut for it exits out on the grass. That
is what started the conversation and why today’s meeting was called, to determine the
Commission’s position on Veterans Way and where the costs currently based on the
scopes of work, #1, 2 and 7.
Mr. McComas distributed a spreadsheet with the different areas of work and the costs
associated with each area and then explained the details.
Discussion followed at some length.
It was noted that item IV-B [Bank storm work] for $7,920 proposed cost will be paid by
the City, via the Engineer’s Department.
Mr. Roesch said if we don’t do the items on the list at this time, we will have to go
through the bidding process.
The Police Department mechanical screen wall was discussed. Mr. Carter noted we just
secured the mechanicals outside City Hall and he felt the others should be also. It was
decided to complete the wall at this time. Mr. McComas will complete a design for it and
come back for approval, with the construction cost not to exceed $15,000.
Further discussion followed.
At the conclusion of the discussion, Mr. Roesch called for a motion to approve all areas
of work on the spreadsheet and the proposed cost except for V-A for $20,500 [the Street
furniture and street light for Veterans Way which will be done later] for a total cost of
$330,439. So moved by Mr. Burke. For clarification, Mr. Carter asked if this was all
going to be done by Shapiro’s contractors with no public contractors involved at this
time. It was noted this is correct. Following a second by Mr. Carter, the motion was
unanimously approved.
There being no other business before the Commission, Mr. Burke moved the meeting be
adjourned. Following a second by Ms. Snyder, the motion was unanimously approved
and the meeting adjourned at 4:45 p.m.