HomeMy WebLinkAboutThieneman Construction/UTL/$31,124/106th Pumping Station Expansion CO#1106th Street Pump Station Expansion City of Carmel
451.8039.001
EXHIBIT F
CHANGE ORDER
Change Order No._________________
Date: ___________________________
Contract Date:____________________
Name of Project: 106th Street Pump Station Expansion
Owner: _______________________________________________________________
Contractor: ____________________________________________________________
The following changes are hereby made to the Agreement:
Description of Change in Work: __________________________________________
Original Contract Price:$_________________________
Previous Changes to Contract Price:$_________________________
Current Contract Price adjusted by previous
Change Order(s):$_________________________
The Contract Price due to this Change
Order will be $__________________________
The new Contract Price including this
Change Order will be: $__________________________
Change to Contract Time:
The Contract Time will be
The date for completion of all work will be __________________________________. (Date)
Requested by: __________________________________ ___________________
(Owner)(Date)
Recommended by: ______________________________ ___________________
(Consulting Engineer)(Date)
Accepted by:___________________________________ ___________________
(Contractor)(Date)
Approved by: __________________________________ ___________________
(Name and Title)(Date)
4/08/25
1
2/26/2025
7/25/2023
City of Carmel, Indiana
Thieneman Construction
See attached log
6,536,000
31,124
6,567,124
101
4/8/25
March 15th, 2025
0
6,536,000
Changes due to found conditions and extra scope addition.
by:
Price due t
increased
increased by ________ calendar days.
Justification:
Original Contra
JONES & HENRY ENGINEERS, L
Philip Teague, PE
By Sergey Grechukhin at 3:43 pm, Apr 08, 2025
Docusign Envelope ID: F8269C36-A963-47A6-BC0B-BD47BD82C79F
PROPOSED CHANGE ORDER LOG
Approved / Accepted
Rejected
THIENEMAN CONSTRUCTION Notice in - waiting on TCI to justify claim
Outstanding - waiting on J&H and/or City of Carmel response
City of Carmel - 106th Street Pump Station Expansion Project
TCI Job # 2315
2/26/2025
A = Approved
D = Denied
001 TBD Existing pump station duct bank pressure grouting $5,090.00 $5,090.00 10 A Actual cost approx. $ 2,000 more than estimated. TCI is covering the difference.11/29/2023
002 TBD Unforeseen Concrete Debris near new 42" RCP $7,723.00 $7,723.00 3 A 11/30/2023
TBD City of Carmel repairs to duct bank box $1,850.00 ($1,850.00)0 A City made these repairs to the conduit box 4/26/2024
003 TBD Credit for wall not poured due to RFI no.3 response $8,646.00 ($8,646.00)0 A 11/30/2023
004 TBD Provide & Install additional manhole 2A $10,988.00 $10,988.00 5 A Includes credit for eliminating external/internal drop. Revised 12/1 to include bolt down casting 11/30/2023
005 TBD Valve Change due to Lead Times $48,274.00 ($48,274.00)0 A 2/26/2024
006 TBD Generator Tap Box Changes $8,946.00 $8,946.00 14 A 2/26/2024
007 TBD Existing 36" sewer concrete collar mods to new wall (concrete)$0.00 $0.00 $0.00 0 A TCI will complete this work at NO COST. Approx. value = $ 5,000 NA
008 TBD Unforeseen utilities on West side near Manholes $33,704.00 $33,704.00 5 A 2 unforeseen utilities and 1 gas main much closer to new work; Actual cost listed 4/26/2024
009 TBD ART Square footage reduction in for future screen area $8,400.00 ($8,400.00)0 A 7/24/2024
010 TBD Additional bypass for City work to line another section upstream $29,229.00 $29,229.00 15 Original budget of $ 31,080 was approved in November 2024 1/23/2025
011 TBD New Omni Site Crystall Ball $2,614.30 $2,614.30 0 1/17/2025
$0.00
$0.00
$0.00
$0.00
TOTALS $ 98,294 $ 67,170 $ 31,124 -$
Original Contract Amount 6,536,000$
Changes To Date
New Approved Contract Amount 6,536,000$
Recap Amount 6,536,000$
DescriptionC.O.#PCO #DaysAdd ($)Deduct ($)Total ($)
Total Executed
Changes To
Date
Notes Submitted
Date
Page 1 Carmel 106th Street Pump Station Expansion # 2315 - Change Order Log - 2-26-25.xlsx
Docusign Envelope ID: F8269C36-A963-47A6-BC0B-BD47BD82C79F
Approved and Adopted this day of , 20 .
CITY OF CARMEL, INDIANA
By and through its Board of Public Works and Safety
BY:
Laura Campbell, Presiding Officer
Date:
James Barlow, Member
Date:
Alan Potasnik, Member
Date:
ATTEST:
Jacob Quinn, Clerk
Date:
Docusign Envelope ID: F8269C36-A963-47A6-BC0B-BD47BD82C79F
NOT PRESENT
April
4/16/2025
25
4/16/2025
4/16/2025
16