HomeMy WebLinkAboutASPR Clay TerracePage 1
PROJECT DATA FOR OFFICE USE ONLY
(to be completed by submitter) Please answer all pertinent questions SBC project number Filing date
DOCUMENTS REQUIRED FOR FILING
1. One Application for Construction Design Release, together with correct filing fees. (See Fee Schedule)
2. One complete filing (paper or e-mail). This filing will not be returned to the applicant. A set of drawings identical to those released by the Office of the State Building
Commissioner shall be maintained on the project site. Weight limit of each submitted package is 30 pounds.
A. Site plan showing dimensioned location of building to all property lines and to all existing buildings on the property, as well as width of any streets, access
roadways or easements bordering the property.
B. Foundation and basement plans and details.
C. Dimensioned floor plans for all floors.
D. Fire and life safety plan showing graphically or by legend the location and rating of building elements such as area separation walls, smoke barriers, fire-resistive
corridor walls, stair enclosures, shaft enclosures and horizontal exists.
E. Wall elevations of all exterior walls including adjacent ground elevation.
F. Sections and details of walls, floors and roof, showing dimensions, materials.
G. Structural plans and elevations showing size and location of all members, truss designs showing all connection details, and stress calculations.
H. Room finish schedule showing finishes for walls, ceilings and floors in all rooms, stairways, hallways and corridors.
I. Door schedule showing material, size, thickness and fire-resistive rating for all doors.
J. Electrical plans, diagrams, details and grounding of service entrance and power or lighting information required for energy conservation.
K. Plumbing plans showing location of fixtures, risers, drains, and piping isometrics.
L. Mechanical plans showing location and size of ductwork, equipment, fire dampers, smoke dampers and equipment schedules showing capacity.
M. Fire protection plans showing type of system, location of sprinkler heads, standpipes, hose connections, fire pumps, riser and hanger details.
PROJECT DESCRIPTION (Must Be Complete) FLOOR AREAS ESTIMATED COSTS
Scope of work:
New building Addition × Remodeling
Total existing (if applicable)
2075 Sq. ft.
Is this construction the result of fire or
Natural disaster?
Yes × No
Sewer :
× Existing Proposed
× Public Private None
Addition (if applicable)
none Sq. ft.
Addition (if applicable)
$
Fire suppression system in building
× Full Partial None
Detailed suppression system plans/specs
Provided × To follow
Remodeled (if applicable)
2075 Sq. ft.
Remodeling (if applicable)
$150.00 Category H
If partial, specify where*
Located in flood plain (check county
plan commission) Yes × No
Total building area square feet Total project cost
$
Building construction type and occupancy classification
Type IIB fully sprinklered, Occupancy M
Building height (stories)*
One
Number of buildings this submittal
(Describe if necessary)* One
Volume cubic feet
(Fee category E only)
Indiana rehabilitation standard (Rule 8) used? Evaluation documents provided?
Yes × No Yes × No
Use of conversion rule (Rule 13) proposed?
Yes × No
Does project include: (Check if yes)
Elevator or lift Combustible fibers storage Fireworks storage Explosives storage
High-piled storage Boiler or pressure vessel Hazardous or flammable materials storage
Describe proposed use of facility IN DETAIL including types of flammable or combustible materials stored or handled
Landlord’s work to prepare existing retail space for incoming tenant GameStop. Tenant will follow separately for additional work required for occupancy
Describe IN DETAIL previous or current use of facility (if existing facility)* This was a retail space, previous tenant was Casual Corner.
Number of persons employed
(max/shift) N/A
General comments* Number of persons (public)
N/A
GENERAL INFORMATION
Has work at this location ever been filed?
X Yes No Unknown
Does project include use of a master plan design release or a factory built modular or mobile structure?
Yes X No
What year and month?
Unknown
Previous SBC Project Number
Unknown
Name of Manufacturer Master Plan / Modular Number
Has construction started?
Yes × No
If yes, has notice of violation or investigation been issued?
Yes No
If no, probable construction starting date?
May 01, 2009
*NOTE: USE SEPARATE SHEET IF ADDITIONAL SPACE IS REQUIRED.