HomeMy WebLinkAbout05 Miscellaneous Details & Specifications Final Construction Plans2' FROM
BUILDING
(TYP)
1"
COMPACT TO 95%
MODIFIED PROCTOR
TYPICAL PAVEMENT SECTION O
NOT TO SCALE
PROPOSED PAVEMENT
SECTION
A MIN. 4" DIA. PIPE CLEANOUT
SHALL BE INSTALLED WITHIN THREE
(3) FEET OF OUTSIDE BUILDING WALL.
A PLUG SPECIFIED BY THE PIPE
MANUFACTURER SHALL BE USED TO
ENSURE 1009 WATER TIGHTNESS.
1/8 BEND
MIN. FALL
1/4" PER FOOT
BELL HOLES SHALL BE
PROVIDED UNDER PIPE
NOTE:
JOINTS SHALL BE CUT
WITH A JOINTER HAVING A
RADIUS OF 1/4" AND FILLED
WITH JOINT FILLER.
6' -0" BETWEEN TRANSVERSE JOINTS
48' BETWEEN EXPANSION JOINTS (MAX.)
4" CONCRETE SIDEWALK ED
NO SCALE
30'
11 SURFACE
2" 9 BINDER
2" No. 53 STONE
No. 2 STONE
TRUNK LINE
1/8 BEND
SERVICE CONNECTION FOR SHALLOW SEWERS
(LESS THAN 15' DEEP)
1" C.I. LOCATOR
ROD OR MAGNETIC
TAPE INSTALLED
VARIES
COMPACTION OF GRANULAR
BACKFILL IS CRITICAL UNDER
WYE AND BEND. IF PROPER
COMPACTION CANNOT BE
ACHIEVED, PLACE A MIN. OF 6"
CLASS 'B' CONCRETE AROUND
1/8 BEND.
SERVICE WYE
1 /2" PREFORMED JOINT FILLER
WHEN ADJACENT TO BUILDING
MONOLITHIC CURB AND SIDEWALK O
NOT TO SCALE
BUILDING LATERAL
MIN. SIZE 4"
EXISTING GROUND)
RIGHT -OF -WAY LINE
MONOLITHIC CONCRETE CURB
AND SIDEWALK
3" CONCRETE BELOW
FINAL SURFACE GRADE
A
SECTION A
7.0'
H 5.0'
PLAN
CONCRETE HANDICAP RAMP 0
NO SCALE
6"
STRAIGHT CONCRETE CURB C
NOT TO SCALE
GRASS
A
BITUMINOUS PAVEMENT
18" (MIN.)
PAVEMENT
SECTION
SANITARY OR STORM SEWER
WATER MAIN
SANITARY OR
STORM SEWER
NOTE: WHEN LATERAL SEPERATION
IS 10' OR GREATER NO VERTICAL
CLEARANCE IS NEEDED.
N TS
WATER MAIN
RATED PIPE
SANITARY OR
STORM SEWER
MINIMUM CROSSOVER AND SEPARATION
REQUIREMENTS FOR WATER MAINS,
SANITARY SEWERS AND STORM SEWERS
STORM SEWER SYSTEMS
1. SCOPE OF WORK
A. The work under this section includes all storm sewers, storm water inlets, and related items, including
excavating and backfilling necessary to complete the work shown on the drawings.
2. MATERIALS
A. Storm Sewers
1. All reinforced concrete sewer pipe as specified shall conform to ASTM C -76 latest revision with
joints conforming to ASTM C -443 latest revision.
2. All plastic sewer pipe specified shall be ADS N -12 Corrugated Exterior Smooth Interior Pipe or
approved equal. The pipe shall be installed as per manufacturers recommendations.
B. Manholes
1. Precast reinforced concrete manhole sections and steps shall conform to ASTM C -478 latest
revision.
2. Casting shall be of uniform quality, free from
or other defects. They shall be smooth and
approved method. They shall be coated with
tough and tenacious when cold, not tacky or
latest revision.
10' MIN
WATER
blow holes, porosity, hard spots, shrinkage distortion
well cleaned by shot blasting or by some other
asphalt paint which shall result in a smooth coating,
brittle. They shall be gray iron meeting ASTM A -48
3. Joints: Manhole sections shall be jointed with rubber type gaskets. The rubber type gaskets shall
meet ASTM C -443 latest revision.
C. Underground Detention System
1. All structures shall be part of StormTech SC -740 detention system and shall be installed per
manufacturer's recommendations.
3. APPLICATION
A. Permits and Codes: The intent of this section of the specifications is that the Contractor's bid on the
work covered herein shall be based upon the drawings and specifications but that the work shall comply
with all applicable codes and regulations as amended by any waivers. The Contractor shall furnish all
bonds necessary to get permits for cuts and connections to existing sewers.
B. Local Standards: The term "Local Standards" as used herein means the standards of design and
construction of the respective municipal department or utility company.
C. Existing Improvements: The Contractor shall maintain in operating condition all active utilities, sewers and
other drains encountered in the sewer installation. Tne Contractor shall repair to the satisfaction of the
Owner any damage to existing active improvements.
D. Workmanship: This work shall conform to all local, state and national codes and to be approved by all
local and state agencies having jurisdiction.
E. Trenching: Lay all pipe in open trenches, except when the local authority gives written permission for
tunneling. Open the trench sufficiently ahead of pipe laying to reveal any obstructions. The min. width
of trench shall be 1.25 times the outside dia. of pipe. Sheet and brace trench as necessary to protect
workmen and adjacent structures. All trenching to comply with Occupational Safety and Health
Administration Standards. Keep trenches free from water while construction is in progress. Under no
circumstances shall pipe or appurtenances be laid in standing water. Conduct the discharge from trench
de- watering to drains or natural drainage channels.
F. Special Supports: Whenever, in the opinion of the Engineer, the soil at or below the pipe grade is
unsuitable for supporting sewers and appurtenances specified in this section, such special support, in
addition to those shown or specified, shall be provided as the Engineer may direct, and the contract will
be adjusted.
G. Backfilling: Backfill shall be placed as shown in the plans. Note that PVC HDPE pipe shall be covered
with 12" minimum of #8 stone. Compact this backfill thoroughly, taking care not to disturb the pipe.
Backfill under and within 5 feet of walks, parking areas, driveways and streets shall be "B" Borrow or
equivalent granular material only and thoroughly compacted by approved methods.
H. Manhole Inverts: Construct manhole flow channels of concrete sewer pipe or brick, smoothly finished and
of semicircular section conforming to the inside diameter of the connecting sewers. Make changes in size
or grade gradually and changes indirection by true curves. Provide such channels for all connecting
sewers at each manhole.
I. Subdrains: All subdrains shall be of the size shown on the plans and shall be constructed to the grades
shown. All drains constructed off -site as part of the outlet drain will be located as shown.
J. Utilities: It shall be the responsibility of the Contractor to verity all existing utilities and conditions
pertaining to his work. It shall also be the Contractor's responsibility to contact the owners of the
various utilities before work is started. The Contractor shall notify in writing the Owner and the Engineer
of any changes, errors or omissions found on these plans or in the field before work is started or
resumed.
CLEANOUT ADAPTER
THREADED PLUG
12" 0 POURED
CONCRETE COLLAR
STANDARD CLEANOUT DETAIL
N TS
EARTHWORK
1. SCOPE OF WORK
A. Extent: The work required under this section consists of all excavating, filling, rough grading and related
items necessary to complete the work indicated on the drawings and described in the specifications. The
Contractor shall notify in writing the Owner and the Engineer of any changes, errors or omissions found on
the plans or in the field, before work is started or resumed.
1. In general, the items of work to be performed under this section shall include clearing and grubbing,
removal of trees and stumps, stripping and storage of topsoil, fill compaction and rough grading of
entire site. All trees shall be removed unless otherwise noted in plans or directed by Owner.
2. Excavated material that is suitable may be used for fills. All unsuitable material and all surplus
excavated material not required shall be removed from the site. The location of dump and length of
haul shall be the Contractor's responsibility.
3. Provide and place any additional fill material from off the site as may be necessary to produce the
grades required. Fill obtained from off site shall be of kind and quality as specified for fills herein
and the source approved by the Owner.
4. The Contractor shall accept the site as he finds it and shall remove all trash, rubbish and debris from
the site prior to starting excavation.
2. BENCHMARKS
A. Maintain carefully all bench marks, monuments and other reference points; if disturbed or destroyed,
Contractor shall contact Engineer.
3. REMOVAL OF TREES
A. Remove all trees and stumps from
B. All brush, stumps, wood and other
areas off of the site. Disposal by
applicable).
entire site unless otherwise directed by Owner.
refuse from the trees shall be buried on site or removed to disposal
burning shall not be permitted unless proper permits are obtained (where
4. HANDLING OF TOPSOIL
A. Remove all organic material from the areas to be occupied by buildings, roads, walks and parking areas.
Pile and store topsoil at a location where it will not interfere with construction operations. Topsoil shall be
reasonable free from subsoil, debris, weeds, grass, stones, etc.
B. After completion of site grading and subsurface utility installation, topsoil shall be replaced in areas
designated on the erosion control plan for seeding and /or sodding. Any remaining topsoil shall be used for
finished grading around structures and landscaping areas.
5. DISPOSITION OF UTILITIES
A. Rules and regulations governing the respective utilities shall be observed in executing all work under this
section.
B. If active utilities are encountered but not shown on the drawings, the Engineer shall be advised before work
is continued.
C. Inactive and abandoned utilities encountered in excavating and grading operations shall be reported to the
Engineer. They shall be removed, plugged or capped as directed by the Utility Company or the Engineer.
D. It shall be the responsibility of each contractor to verity all existing utilities and conditions pertaining to his
phase of the work. It shall also be the Contractor's responsibility to contact the owners of the various
utilities before work is started.
6. SITE GRADING
Grades: Contractor shall perform all cutting, filling, compacting of fills and rough grading required to bring
entire project area to grade as shown on the drawings.
B. Rough Grading: The tolerance for paved areas shall not exceed 0.10 feet plus or minus above the
established subgrade. All other areas shall not exceed 0.10 feet plus or minus the established grade. All
banks and other breaks in grade shall be rounded at the top and bottom.
C. Compaction Requirements:
1. All building pad areas shall be compacted to standards specified by local and /or state building codes.
2. Compaction requirements of paved areas shall be 95% of maximum dry density.
7. EARTH WORK BALANCE
A. The Contractor shall confirm all earthwork quantities prior to start of construction. If an excess or shortage
of earth is encountered, the Contractor shall confirm with the Owner and Engineer the requirements for
stockpiling, removal or importing of earth.
Minor adjustments to the grades may be required to earthwork balances when minor excess material or
shortages are encountered. It is recognized by the parties hereto that the calculations of the Engineer in
accordance with the American Society of Civil Engineers Standards for such calculations. Further, that these
calculations are subject to the interpretations of soil borings as the physical limits in finish grade and
compaction permitted the Contractor, and that all of these parameters may cause either an excess or
shortage of actual earthwork materials to complete the project. If such an actual minor excess or shortage
of actual earthwork materials occurs, the Contractor shall contact the Engineer to determine if adjustments
can be made to correct the imbalance of earth.
A.
NO.
2/24/04
DATE
PARKING LOT /DRIVE
1. SCOPE OF WORK
A. The work required under this section includes all concrete and bituminous paving and related items
necessary to complete the work indicated on the drawings and described in the specifications, including
but not limited to:
1. All drives, parking areas within the contract limits.
2. Curbs and concrete ramps.
3. Sidewalks and concrete slabs.
2. MATERIALS
A. Concrete: Concrete shall be ready -mixed concrete and shall be a mixture of proportioned fine and
coarse aggregates with Portland cement and water. Minimum cement content shall be 6 bags per
cubic yard of concrete and maximum water content shall be 5.5 U. S. gallons per sack of cement,
including moisture in the aggregate. Slump for normal weight concrete shall be a maximum of 4
inches and a minimum of 2 inches. The slump of machine placed concrete shall be no less than 1
1/4 inches nor more than 3 inches. Standard test ASTM C -143 shall be used to measure slump.
Compressive strength of concrete at 28 days shall be 4000 psi. All exterior concrete shall have air
entrainment of 5% to 8% by volume per ASTM C -260. Re- tempering of delivered concrete will not be
allowed. Concrete shall be composed of
1. Portland Cement: Conforming to ASTM C -150, Type I A or Type III A.
2. Aggregates: Conforming to ASTM C -33.
3. Water: Shall be clear and free from injurious amounts of oils, acids, alkalies, organic materials,
or other deleterious substances.
B. Welded Steel Wire Fabric: Where required for concrete reinforcement shall conform to ASTM A185.
C. Premoulded Joint Filler. Shall be of non extruding type meeting ASTM D -544 except that premoulded
juint filler used in concrete walk construction may be either non extruding or resilient.
D. Bituminous Pavement Materials: All materials proposed for the construction of bituminous pavements
shall comply with the Indiana Department of Transportation Specifications, per latest revision.
E. Compacted Aggregate Subbase: If required, shall be crushed stone or gravel. Crushed gravel shall be
a minimum of 35% crushed material. Chert shall be limited to a maximum of 8% of the total.
Material shall be free from an excess of flat, elongated, thinly laminated, soft or disintegrated pieces:
and shall be free from fragments coated with dirt. Compacted aggregate shall be graded in
accordance with INDOT Specifications for the type specified.
3. APPLICATION
A. Grading: Do any necessary grading in addition to that performed in accordance with Earthwork Section
to bring subgrades, after final compaction, to the required grades and sections for site improvements.
B. Preparation of Subgrade: Remove spongy and otherwise unsuitable material and replace with stable
material. No traffic will be allowed on prepared subgrade prior to paving.
C. Compaction of Subgrade: The first 6 inches below the subgrade shall be compacted to at least 100%
of the maximum dry density as determined by the provisions of AASHO T -99. Water shall be
prevented from standing on the compacted subgrade.
D. Utility Structures: Check for correct elevation of all manhole covers, valve boxes and similar structures
located within areas to be paved, and make, or have made, any necessary adjustments in such
structures.
E. Placing Concrete
1 Subgrade: Place concrete only on a moist, compacted subgrade or base free from loose
material. Place no concrete on a muddy or frozen subgrade.
2. Forms: All forms shall be free from warp, tight enough to prevent leakage and substantial
enough to maintain their shape and position without springing or settling, when concrete is
placed. Forms shall be clean and smooth immediately before concreting.
3. Placing Concrete: Concrete shall be deposited so as to require as little rehandling as
practicable. When concrete is to be placed at an atmospheric temperature of 35 degrees F. or
less, paragraph 702.10 of the Indiana Department of Transportation
Specifications latest revisions shall be followed.
F. Concrete Curb
1. Expansion Joints:
spacing of 100 fee
2. Contraction Joints:
feet on center.
3. Finish: Tamp and
square corners to
Shall be 1/2 inch thick premoulded at ends of all returns and at a maximum
t.
Unless otherwise provided, contraction joints shall be sawed joints spaced 10
screed concrete as soon as placed, and fill any honey combed places. Finish
1/4 inch radius and other corners to radii shown.
G. Concrete Walks and Exterior Steps
1. Slopes: Provide 1/4 inch per foot cross slope. Make adjustments on slopes at walk
intersections as necessary to provide proper drainage.
2. Dimensions: Walks and steps shall be one course construction and of widths and details shown
on the drawings.
3. Finish: Screed concrete and trowel with a steel trowel to a hard dense surface after surface
water has disappeared. Apply medium broom finish and scribe transverse joints at 6 foot
spacing. Provide 1/2 inch expansion joints where sidewalks intersect, and at a maximum spacing
of 48 feet between expansion joints.
MISCELLANEOUS REVISIONS PER CITY OF CARMEL REVIEW
REVISIONS
MISCELLANEOUS DETAILS
SPECIFICATIONS
PARCEL #9 CITY CENTER
DATE JANUARY 30, 2004
CHECKED TEN
APPROVED TEN
RLH
TEN
APFR
Transportation
Development Consultants
X11' S. BARMAN NR- BEECH GROVE. IN 46107 (31
SHEET
I_ F