Loading...
HomeMy WebLinkAboutC5.2 Erosion Control Detailsrs 0 to 0 r; 0 N a O O N z i 4 E E O 0 0 a N 0 CZ N a w 0 F- 0 L EROSION CONTROL NOTES: 1 CONSTRUCTION ACTIVITY SHALL CONSIST OF UTILITIES, DRAINAGE SWALES, STORM SEWERS BASIN, BUILDING CONSTRUCTION AND PAVING 2. PRELIMINARY CONSTRUCTION SCHEDULE: EARTHWORK SHALL BEGIN IN STU STORM DRAINAGE STRUC RES SHALL BE CONCURRENT WITH EARTHWORK. SANITARY SEWER INSTALLATION SHALL COMMENCE UPON COMPLETION NUTILITYOINSTALLATION GRADING. WATER MAINS AND REMAIN G COMMENCE UOFINA COMPLETION GRADING AND PAVING NG SHA� INSTALLATION. OCCUR AFTER THE BUILDINGS NT ANTICIPATED COMPLETION BBY SUMMER2 05TTHIS OF THE PROJE SCHEDULE IS SUBJECT TO CHANGE. 3. LAND ALTERATION A INC O INCLUDING REGRADING, D OF VEGETATION, SHALL BE DONE IN A WAY THAT WILL MINIMIZE EROSION. 4. CONTRACTOR SHALL COMPLY WITH ALL STATE AND LOCAL ORDINANCES THAT APPLY. 5. THIS PLAN SHALL NOT BE CONSIDERED ALL INCLUSIVE AS THE CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO PREVENT SOIL SEDIMENT FROM LEAVING THE SITE. 6. ADDITIONAL ERALLSEDIMENT CONTR O SHALL BE INSTALLED IF DEEMED NECESSARY BY ON SITE INSPECTION. 7. SEDIMENT LADEN WATER SHALL BE DETAINED BY EROSION CONTROL PRACTICES AS NEEDED TO MINIMIZE SEDIMENTATION IN THE RECEIVING STREAM. NO STORM WATER SHALL BE DISCHARGED FROM THE SITE IN A MANNER THAT CAUSES EROSION AT THE POINT OF DISCHARGE. 8. WASTES AND UNUSED BUILDING MATERIALS SHALL NOT BE ALLOWED TO BE CARRIED FROM THE SITE BY STORM WATER RUNOFF. PROPER DISPOSAL OF ALL WASTES AND UNUSED BUILDING MATERIALS IS REQUIRED. 9. SEDIMENT BEING TRACKED ONTO PUBLIC OR PRIVATE ROADWAYS SHALL BE MINIMIZED. CLEARED SEDIMENT SHALL BE RETURNED TO THE SITE FOR DISPOSAL. 10. SOIL WHICH HAS B ACCUMULATED CONTROL DEVICES SHALL AND RE -DISTRIBUTED STRI UTED ON SITE AFTER EACH RAINFALL EVENT, AND AT LEAST ONCE A WEEK. 11. IF INSTALLATION TED B OF STORM OR NIGHTFALL, THE PIPE U BE INTERRUPTED ENDS SHALL TED B BE COVERED WITH FILTER FABRIC. 12. EXISTING VEGETATION SHALL BE PRESERVED IN AREAS NOT DISTURBED BY CONSTRUCTION ACTIVITY. 13. THERE ARE NO BORROW AREAS. 14. ALL APPLICABLE EROSION CONTROL MEASURES SHALL BE PLACED BEFORE ANY LAND DISTURBING ACTIVITIES. 15. SCHEDULE OF EROSION CONTROL ACTIVITIES: a) INSTALL SAND BAGS AROUND INLETS IMMEDIATELY UPON COMPLETION OF THE STRUCTURE. REMOVE SAND BAGS FOR PAVING OPERATION. REPLACE SAND BAGS AFTER PAVING IS COMPLETE. SAND BAGS SHALL REMAIN IN PLACE UNTIL VEGETATION IS ESTABLISHED ON SEEDED AREAS BEHIND THE CURB. b) THE DURATION OF TIME WHICH AN AREA REMAINS EXPOSED SHALL BE KEPT TO A PRACTICAL MINIMUM. THE AREA SHALL BE STABILIZED AS SOON AS POSSIBLE. TEMPORARY VEGETATION OR MULCHING SHALL BE USED TO PROTECT EXPOSED AREAS IF PERMANENT VEGETATION CANNOT BE SEEDED WITHIN 14 DAYS OR ACTIVITY CEASES FOR MORE THAN 21 DAYS OR AS DIRECTED BY THE ENGINEER. c) TOPSOIL REPLACEMENT SHALL TAKE PLACE FROM MARCH 1 TO OCTOBER 31. STOCKPILE TOPSOIL AT ALL OTHER TIMES OF THE YEAR. PERMANENT AND FINAL VEGETATION AND STRUCTURAL I SHALL BE INSTALLED WITHIN SEVEN (7) DAYS AFTER FINAL GRADING OR AS SOON AS POSSIBLE. 16. APPLY FERTILIZER AT A RATE ADEQUATE TO PROVIDE 1 LB. OF ACTUAL NITROGEN PER 1,000 SQUARE FEET. USE COMMERCIAL GRADE COMPLETE FERTILIZER i�OGEN, 50 PERCEN�DERIVED FROM OF FAST AND SLOW RELEASE N NATURAL ORGANIC SOURCES OF UREA -FORM, PHOSPHOROUS, AND IN FOLLOWING COMPOSITION: a) FERTILIZER FOR LAWNS: PROVIDE A FAST RELEASE SQ. FT. OF FERTILIZER WITH A COMPOSITION OF 1 LB PER 1, 0 ACTUAL NITROGEN, 4 PERCENT PHOSPHOROUS, AND 2 PERCENT POTASSIUM BY WEIGHT b) SLOW- RELEASE FERTILIZER FOR TREES AND SHRUBS: GRANULAR FERTILIZER CONSISTING OF 50 PERCENT NITROGEN, PHOSPHOROUS AND POTASSIUM MADE UP O COMPOSITION BY WEIGHT OF 5 PERCENT 17. ADD LIME TO TOPSOIL TO OBTAIN A pH RANGE OF 6.0 TO 7.0. LIME SHALL BE ASTM C 602, CLASS T, AGRICULTURAL LIMESTONE CONTAINING A MINIMUM OF 80 PERCENT CALCIUM CARBONATE EQUIVALENT, WITH A MINIMUM 99 PERCENT 50 (250 MICROMETER) SIEVE AND A MINIMUM 75 PERCENT PAS SING A SIEVE. 18. CONSTRUCTION TRAFFIC SHALL ENTER THE SITE AT DRIVES WHICH ARE CURRENTLY PAVED. The Catch is an inlet and catch basin filtration device developed to prevent sedimentation. Catch are available to fit virtually any drainage structure casting, and could represent a Best Management Practice for your EPA Phase 2 Program. sTEEL ERA SE OVER LOW Temporary Installation: Construction AThR projects on highways and new housing developments can result in substantial amounts of sediment during a rainstorm. Traditional practice, using silt screens, hay bales, and filter fabric under storm grates provide only limited protection. Catch-All will hold 2 cubic feet of gravel, silt, and debris, and can be moved from site -to site i OR EASY y t� STAINLESS STEEL LAND (flamed two bag) 's 'r .��Jx =are l� s POLYESTER NIESII REINFORCEMENT (Outer Layer) POLYPROPYLENE GEOTI x FILTER FABRIC (Inner Layer) Nutec Starmivater Services 6439 East 30 street Indianapilis, IN 46219 800 969-6883 A I)Lvlslofl of Nutec Supply Catch has been approved for use on many IDOT road construction projects. R Permanent Installation: Commercial and industrial sites with impervious surfaces, such ar roads and parking lots, produce stormwater run -off that may include paper refuse, cigarettes, sediment, and even some floating oils. These contaminants can quickly add up to a significant amount in catch basins or municipal systems. Without proper treatment, stormwater laden with such materials can pollute streams, lakes, and near -shore waters. The unique design of the reusable steel frame of Catch provides an overflow capacity greater than the open area of the grate it fits under. This means little chance for water to back up or pool, even between scheduled cleanings. The durable, reinforced sediment bag can be cleaned numerous times and is easily replaced in the field. The entire unit is installed below grade and no rebar, clips, or straps are exposed on the surface. With a top flange less than 1/8" thick, the additional height exposure of the grate is minimal. Catch can be an important supplement for catch basins and underground stormwater storage systems that are usually difficult to access for cleaning. Catch are available to fit virtually any drainage structure casting. GENERAL NOTES' FRAME. Top flange fabricated from IYix1WAr angle. Base rtn fabricated from IJ 'xlf'x16' channel. Handles and suspension brackets fabricated from IWxY: flat stock- Ali domestic steel conforming to ASTM -A35. SEDIMENT BAG Bag fabricated from 4 oz./s4Yd. non -woven polypropylene geotextile reinforced with polyester mesh. Bag secured to base rim with a stainless steel strop and Lock. GENERAL NOTES FRAME Top flange fabricated from IhNlYex/fr angle. Bose rim fabricated from 11¢'xlf'xW channel. Handles and suspension brsckets fabricated from l xWY flat stock. All domestic steel conformhg to ASTM -A36. SEDIMENT BAG. Bag fabricated from 4 ozJsq.yd non-woven polypropylene ecuur d to base rim with a reinforced ainl ss steel 8 and lock. INLET BASKET MAINTENANCE REQUIREMENTS 1. INSPECT THE STRUCTURE AFTER EACH STORM EVENT, REMOVING SEDIMENT AND MAKING NEEDED REPAIRS IMMEDIATELY. 2. WHEN THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZES, REMOVE AND PROPERLY DISPOSE OF ANY UNSTABLE SEDIMENT AND CONSTRUCTION MATERIAL, AND RE- STABILIZE. 3. FOLLOW MANUFACTURER'S RECOMMENDATIONS FOR INSTALLATION AND MAINTENANCE. FILTER FABRIC NON WOVEN GEOTEXTILE FABRIC FLOW 1 a I I I __l EXTEND FABRIC WIRE TO 4" BELOW SURFACE WIRE WOOD POST SILT FENCE CONSTRUCTION NOT TO SCALE NOTE: POSTS SHALL HAVE A MINIMUM LENGTH OF 36 INCHES PLUS BURIAL DEPTH. POST MATERIAL SHALL BE WOOD, STEEL, OR SYNTHETIC, AND SHALL BE OF SUFFICIENT STRENGTH TO RESIST DAMAGE DURING INSTALLATION AND TO SUPPORT APPLIED LOADS. FABRIC SHALL BE A WOVEN GEOTEXTILE FABRIC CONSISTING OF STRONG, ROT RESISTANT, MATERIALS RESISTANT TO DETERIORATION FROM ULTRAVIOLET AND HEAT EXPOSURE. SILT FENCE INSTALLATION REQUIREMENTS SITE PREPARATION 1. PLAN FOR THE FENCE TO BE AT LEAST 10 ft. FROM THE TOE OF THE SLOPE TO PROVIDE A SEDIMENT STORAGE AREA. 2. PROVIDE ACCESS TO THE AREA IF SEDIMENT CLEANOUT WILL BE NEEDED. OUTLET CONSTRUCTION (OPTIONAL) 1. DETERMINE THE APPROPRIATE LOCATION FOR A REINFORCED, STABILIZED BYPASS FLOW OUTLET (UNLESS THE FENCE IS DESIGNED TO RETAIN ALL RUNOFF FROM A 2 YEAR FREQUENCY, 24 HR DURATION STORM EVENT) 2. SET THE OUTLET ELEVATION SO THAT WATER DEPTH CANNOT EXCEED 1 %229 ft. AT THE LOWEST POINT ALONG THE FENCE LINE. 3. LOCATE THE OUTLET WEIR SUPPORT POSTS NO MORE THAN 4 ft. APART, AND INSTALL A HORIZONTAL BRACE BETWEEN THEM. (WEIR HEIGHT SHOULD BE NO MORE THAN 1 ft. DEEP, 5 ft. WIDE, AND F ft. LONG ON LEVEL GRADE. 4. EXCAVATE THE FOUNDATION FOR THE OUTLET SPLASH PAD TO MINIMUMS OF 1 ft. AND WATER DEPTH NO MORE THAN 1 1 /2 ft. ANYWHERE ELSE ALONG THE FENCE.) 5. FILL THE EXCAVATED FOUNDATION WITH INDOT CA NO. 1 STONE, BEING CAREFUL THAT THE FINISHED SURFACE BLENDS WITH THE SURROUNDING AREA, ALLOWING NO OVERFILL. 6. STABILIZE THE AREA AROUND THE RAD. FENCE CONSTRUCTION 1. ALONG THE ENTIRE INTENDED FENCE LINE, DIG AN 8 in. DEEP FLAT BOTTOMED OR V- SHAPED TRENCH. 2. ON THE DOWNSIDE SLOPE OF THE TRENCH, DRIVE THE WOOD OR STEEL SUPPORT POSTS AT LEAST 1 ft. INTO THE GROUND (THE DEEPER THE BETTER!), SPACING THEM NO MORE THAN 8 ft. APART IF THE FENCE IS SUPPORTED BY WIRE OR 6 ft. IF EXTRA STRENGTH rABRIC IS USED WITHOUT SUPPORT WIRE. ADJUST SPACING, IF NECESSARY, TO ENSURE THAT POSTS ARE SET AT THE LOW POINTS ALONF THE FENCE LINE. (NOTE: IF THE FENCE HAS PRE ATTACHED POSTS OR STAKES, DRIVE THEM DEEP ENOUGH SO THE FABRIC IS SATISFACTORILY IN THE TRENCH AS DESCRIBED IN STEP 6). 3. FASTEN SUPPORT WIRE FENCE (IF THE MANUFACTUER RECOMMENDS ITS USE) TO THE UPSLOPE SIDE OF THE POSTS, EXTENDING IT 8 in. INTO THE TRENCH. 4. RUN A CONTINUOUS LENGTH OF GEOTEXTILE FABRIC IN FRONT (UPSLOPE) OF THE SUPPORT WIRE AND POSTS, AVOIDING JOINTS, PARTICULARLY AT LOW POINTS IN THE FENCE LINE. 5. IF A JOINT IS NECESSARY, NAIL THE OVERLAP TO THE NEAREST POST WITH LATH. 6. PLACE THE BOTTOM 1 ft. OF FABRIC IN THE 8 in. DEEP TRENCH, EXTENDING THE REMAING 4 in. TOWARD THE UPSLOPE SIDE. 7. BACKFILL NE TRENCH WITH COMPACTED EARTH OR GRAVEL. NOTE: IF USING A PRE PACKED COMMERCIAL SILT FENCE RATHER THAN CONSTRUCTING ONE, FOLLOW MANUFACTURER'S INSTALLATION INSTRUCTIONS. SILT FENCE MAINTENANCE REQUIREMENTS 1. INSPECT THE SILT FENCE PERIODICALLY AND AFTER EACH STORM EVENT. 2. IF FABRIC TEARS, STARTS TO DECOMPOSE, OR IN ANY WAY BECOMES INEFFECTIVE, REPLACE THE AFFECTED PORTION IMMEDIATELY. 3. REMOVE DEPOSITED SEDIMENT WHEN iT REACHES HALF THE HEIGHT OF THE FENCE AT ITS LOWEST POINT OR IS CAUSING THE FABRIC TO BULGE. 4. TAKE CARE TO AVOID UNDERMINING THE FENCE DURING CLEAN OUT. 5. AFTER THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZED REMOVE THE FENCE AND SEDIMENT DEPOSITS, BRING THE DISTURBED AREA TO GRADE, AND STABILIZE. z t• CHANNEL SLOPE SHALL BE 0.3% GRADE (min.) NORTH AMERICAN GREEN S75 EROSION CONTROL MAT STAPLE PATTERN C DIVERSION SWALE MAINTENANCE REQUIREMENTS 1. INSPECT DIVERSION SWALES FOLLOWING STORM EVENTS DURING AND AFTER VEGETATIVE ESTABLISHMENT; MAKE NEEDED REPAIRS IMMEDIATELY. 2. CHECK DITCH OUTLET AND ROAD CROSSINGS FOR BLOCKAGE, SEDIMENT, BANK INSTABILITY AND PIPING OR SCOUR HOLES; REMOVE ANY BLOCKAGE, AND MAKE PIPING REPAIRS IMMEDIATELY. 3. REMOVE SIGNIFICANT SEDIMENT AND DEBRIS FROM THE CHANNEL TO MAINTAIN DESIGN CROSS- SECTION AND GRADE AND TO PREVENT SPOT EROSION. 4. TEMPORARY ROCK CHECK DAMS SHALL BE CONSTRUCTED EN CONDIRIONSR TEMPORARY ROCK CHECK DAMS, BE ESTABLISHED DUE TO WEATHER OR OTHER UNFORESEEN IF REQUIRED SHALL BE REMOVED ONLY WHEN THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZED. DIVERSION SWALE DETAIL NOT TO SCALE NOTE: SEE EROSION CONTROL MAT DETAIL sheet C5.3 FOR ADDITIONAL INFORMATION 1 CLEAN -OUT LEVEL SET STAKE AT GRAVEL FACE 2' (MIN) SEDIMENT TRAP SPILLWAY INSTALLATION REQUIREMENTS EMBANKMENT: 1. LOCATE THE TRAP AS NEAR THE SEDIMENT SOURCE AS TOPOGRAPHY ALLOWS. 2. DIVERT RUNOFF FROM ALL DISTURBED AREAS AWAY FROM THE TRAP SITE. 3. CLEAR, GRUB, AND STRIP ALL VEGETATION AND ROOT MAT FROM THE EMBANKMENT AREA. 4. USING STABLE MINERAL SOIL FREE OF ROOTS, ROCKS, BRUSH AND DEBRIS, PLACE FILL IN 9 -in. LIFTS (MAX.) 5. COMPACT EACH LIFT SO THE SIDE SLOPES ARE 2:1 OR FLATTER (3:1 RECOMMENDED FOR BACKSLOPE TO IMPROVE STABILITY OF STONE SPILLWAY). 6. OVERFILL THE EMBANKMENT TO 6 in. ABOVE THE DESIGN ELEVATION TO ALLOW FOR SETTLING. OUTLET SECTION: 1. EXCAVATE A TRAPEZOIDAL STONE OUTLET SECTION FROM THE COMPACTED EMBANKMENT. 2. INSTALL GEOTEXTILE FABRIC, EXTENDING IT UP THE SIDES TO THE TOP OF NE EMBANKMENT. 3. PLACE SPECIFIES STONE TO THE LINES AND GRADES, WORKING SMALLER STONES INTO VOIDS TO ACHIEVE A DENSE MAS. THE SPILLWAY CREST SHOULD BE LEVEL WITH THE WIDTH SPECIFIED (MIN. 4 ft.); SPILLWAY DEPTH SHOULD BE 1 /2 ft. MINIMUM, MEASURED FROM THE HIGHEST STONES IN THE SPILLWAY TO NE TOP OF THE DAM. 4. KEEP THE BASE OF THE OUTLET STONE SECTION AT LEAST 2 ft. THICK THROUGH THE LEVEL SECTION AND THE DOWNSTREAM FACE OF THE DAM. 5. EXTEND THE OUTLET APRON BELOW THE TOE OF THE DAM ON LEVEL GRADE UNTIL STABILE CONDITIONS ARE REACHED. 6. MAKE THE EDGES AND END OF THE STONE APRON SECTION FLUSH WITH THE SURROUNDING GROUND (NO OVERFALL SHOULD EXIST.) 7. COVER THE INSIDE FACE OF THE STONE OUTLET SECTION WITH A 1 ft. LAYER OF INDOT CA No. 5. 8. STABILIZE THE EMBANKMENT. 9. SET A STAKE AT ONE -HALF THE DESIGN DEPTH TO MARK THE CLEANOUT LEVEL. SEDIMENT TRAP SPILLWAY MAINTENANCE REQUIREMENTS 1. INSPECT TEMPORARY SEDIMENT TRAPS AFTER EACH STORM EVENT, AND IMMEDIATELY REPAIR ANY EROSION AND PIPING HOLES. 2. REMOVE SEDIMENT WHEN IT HAS ACCUMULATED TO ONE -HALF THE DESIGN DEPTH. 3. REPLACE SPILLWAY GRAVEL FACING IF CLOGGED. 4. INSPECT VEGETATION, AND RE -SEED IF NECESSARY. 5. CHECK THE SPILLWAY DEPTH PERIODICALLY TO ENSURE A MINIMUM OF 1 FT. DEPTH FROM THE LOWEST POINT OF THE SETTLED EMBANKMENT TO HIGHEST POINT OF THE SPILLWAY CREST, AND FILL ANY LOW AREAS TO MAINTAIN DESIGN ELEVATION. NOTE: KEY STONE INTO CHANNEL BANKS AND EXTEND IT BEYOND THE ABUTMENTS A MINIMUM OF 18" (0.5m) TO PREVENT FLOW AROUND DAM. FLOW NOTE: CHECK DAMS TO BE INSTALLED ONLY IF NEEDED TO CONTROL DITCH EROSION. SEE DITCH MAINTENANCE NOTE #4. FILTER FABRIC 5` CROSS- SECTION 4' (MIN.) SEDIMENT TRAP AND SPILLWAY DETAIL NOT TO SCALE 18" (0.5m) A s F 6" (1 w �'f� 2 /.y r i1' i I/ •41 /r l1 at VIEW LOOKING UPSTREAM SECT A A 'L' THE DISTANCE SUCH THAT POINTS 'A' AND `B' ARE OF EQUAL ELEVATION. FILTER FABRIC SPACING BETWEEN CHECK DAMS ROCK CHECK DAM NOT TO SCALE 1:1 SIDE SLOPE (MAX.) 24" (0.6m) 5 APRON (MIN.) OVERFILL 6" FOR SETTLEMENT -2: SIDE SLOPE (MAX.) ROCK CHECK DAM INSTALLATION REQUIREMENTS 1. EXCAVATE A CUTOFF TRENCH INTO THE DITCH BANKS, AND EXTEND IT A MINIMUM OF 18 in. BEYOND THE ABUTMEN TS. 2. PLACE THE ROCK IN THE CUTOFF TRENCH AND CHANNEL TO THE LINES AND DIMENSIONS SHOWN IN DETAIL, CENTER MAXIMUM OF 2 ft. HIGH YET 9 in. BELOW WHERE THE DAM ABUTS THE CHANNEL BANKS. 3. EXTEND THE ROCK AT LEAST 18 in. BEYOND THE CHANNEL BANKS TO KEEP OVERFLOW WATER FROM UNDERCUTTING THE DAM AS IT RE- ENTERS THE CHANNEL. 4. INSTALL AS MANY DAMS AS NECESSARY TO SATISFY THE SPACING REQUIREMENT SHOWN IN DETAIL. 5. STABILIZE THE CHANNEL ABOVE THE UPPERMOST DAM. 6. RECOGNIZING THAT WATER WILL FLOW OVER AND AROUND THE LOWERMOST DAM, PROTECT THE CHANNEL DOWNSTREAM FROM IT WITH AN EROSION RESISTANT LINING FOR A DISTANCE OF 6 ft. UNLESS THE CHANNEL IS PROTECTED THROUGH OTHER MEANS. ROCK CHECK DAM MAINTENANCE REQUIREMENTS 1. INSPECT CHECK DAMS AND THE CHANNEL AFTER EACH STORM EVENT, AND REPAIR ANY DAMAGE IMMEDIATELY. 2. IF SIGNIFICANT EROSION OCCURS BETWEEN DAMS, INSTALL A RIPRAP LINER IN THAT PORTION OF THE CHANNEL. 3. REMOVE SEDIMENT ACCUMULATED BEHIND EACH DAM AS NEEDED TO MAINTAIN CHANNEL CAPACITY, TO ALLOW DRAINAGE THROUGH THE DAM, AND TO PREVENT LARGE FLOWS FROM DISPLACING SEDIMENT. 4. ADD ROCK TO THE DAMS AS NEEDED TO MAINTAIN DESIGN HEIGHT AND CROSS SECTION. 5. WHEN THE DAMS ARE NO LONGER NEEDED, REMOVE THE ROCK AND STABILIZE CHANNEL, USING AN EROSION- RESISTANT LINING IF NECESSARY. Z t p g.1;63 Z r:14 e“' nve r *p Z Z~ E Z 04 a� L w ~A d a g l Z N 4 e t'- 0 a' r et 0 c� 0 Cl) O Z 70 vs 0 65 ZQ 0 ic a cc (1.1 W d z a DATE: DRAWN BY: CHK'D BY: JOB NO. 12/05/03 WJT KMB 1N2003.0744 REVISIONS /3\ GENERAL 03/2 SHEET NO. C5.2 OF I N 2003.0744.073.C52 •C53