C402 Erosion Control Details
PART 1 EXECUTION 1.1 IMPLEMENTATION AND MAINTENANCE PROCEDURE AT BEGINNING OF SITE WORK A. Prior to general stripping topsoil and excavating, install silt fence where indicated. B. Construct erosion control devices where indicated on drawings during rough grading as grading progresses. C. Topsoil must be present to ensure growth. D. Temporarily seed basin slopes, topsoil stockpiles, and areas disturbed by construction. 1. Seeding times and rates: a. May 15 to September 15; Annual Ryegrass at 40 lbs. /acre. b. August 15 to November 15; Rye (grain) or wheat at 2 bushels /acre. c. March 1 to May 15; Oats at 3 bushels /acre. 2. Fertilizer: Commercial analysis 12/12/12 applied at a rate of 600# /acre. a. Apply lime to raise PH to the level needed for species being seeded. b. Work fertilizer and lime into the soil to a depth of 2 -3 IN. 3. All Hydroseeding shall be in accordance with the preceding requirements. 4. Reseed as required until good stand of gross is achieved. 1.2 DURING CONSTRUCTION PERIOD A. Maintain basins, dikes, traps, stone filters, silt fences, etc. B. Inspect regularly especially after rainstorms. C. Repair or replace damaged or missing items. D. After rough grading, sow temporary grass cover over exposed earth areas not draining into a protected device. E. Construct inlets as soon as possible. 1. Install silt fence or straw bale barriers or 1/2" slotted barrel at each new inlet, as necessary to control erosion. F. Provide necessary swales and dikes to direct water towards a protected device. G. Do not disturb existing vegetation (grass and trees) outside limits of construction. H. Remove sediment from behind silt fences when sediment reaches one fourth fabric height. I. Topsoil and fine grade slopes and swales, etc. Seed and mulch as soon as possible in areas as they become ready. 1.3 NEAR COMPLETION OF CONSTRUCTION A. Eliminate erosion control devices except inlet protection. B. Grade to finished or existing grades. C. Fine grade remaining earth areas disturbed by construction activities. D. Topsoil must be a minimum of 4" to ensure growth. F. Permanent seed: March 1 to May 15 and August 10 to October 15. (Dates may vary at discretion of Landscape Architect depending on weather conditions.) G. Soil Preparation. Soil surface must be free of rocks, debris, and other foreign materials. 2. Soils must have proper moisture control to assure proper germination and growth. 3. Soil surface must be compacted to a depth of at least 6 inches. 4. Soil preparation depends on soil conditions at time of seeding. Various tools may be necessary to achieve surface finish. 5. Surface of soil shall be level and large voids eliminated to applying fertilizer, lime and seed. H. Applying fertilizer, lime and seed. 1. Work fertilizer and lime into soil to a depth of 2 3 inches. 2. Apply seed carefully and cover seed with 1/4 inch soil, apply seed carefully and avoid covering seed more than 1/4 inch. 3. Apply mulch at rate of 2 tons per acre following seeding. 4. Water as necessary to ensure adequate moisture for germination and growth. 5. Reseed as necessary until a good stand of grass is achieved. I. Products 1. Fertilizer: Commercial analysis 12/12/12 or equivalent applied at a rate of 600 pounds per acre. 2. Lime: Apply agricultural lime to raise PH to the level needed for species being seeded. Soil test may be required to determine rate. 3. Swales /Slopes: Blended mixture of seed shall be applied at the rate of 110 pounds per acre. The mix shall consist of 40 pounds Mustang turf -type Tall Fescue, 30 pounds Banff or Wabash Kentucky Bluegrass, 30 4. Graded areas adjacent to pavement: Blended mixture of seed shall be applied at a rote of 90 pounds per acre. The mixture shall consist of 35 pounds Mustang turf -type Tall Fescue, 30 pounds Fiesta Perennial 5. Apply mulch straw at rate of 2 tons per acres immediately after seeding. The straw must be evenly distributed loosely over the entire area. "Slabs" of straw must be redistributed or it will kill young seedlings. On large open areas the mulch must be secured to soil by a tack or mechanical means to prevent wind action on mulch. 3.4 MAINTENANCE A. Reseed all areas that don't take. B. Apply a maintenance fertilizer within 6 months of acquiring a good stand. C. Avoid traffic on area until area is well protected and stable. D. Water as necessary to ensure adequate growth and development. *Maintenance fertilizer apply 200 lbs of 12 -12 -12 or equivalent. Stabilization Practice: Permanent Seeding Dormant Seeding Temporary Seeding Sodding Mulching SEASONAL SOIL PROTECTION CHART MAR, A C F APR. E MAY JUN. JUL. AUG SEP. I iii /I/ /I/ 1 OCT. NOV. B DEC. A KENTUCKY BLUEGRASS 40 lbs /acre: CREEPING RED FESCUE 40 lbs/acre; PLUS 2 TONS STRAW MULCH /ACRE, OR ADD ANNUAL RYEGRASS 20 lbs /acre. B KENTUCKY BLUEGRASS 60 lbs /acre; CREEPING RED FESCUE 60 lbs/acre; PLUS 2 TONS STRAW MULCH /ACRE, OR ADD ANNUAL RYEGRASS 30 lbs/acre. C SPRING OATS 3 BUSHEL /ACRE. D WHEAT OR RYE 2 BUSHEL /ACRE E ANNUAL RYEGRASS 40 lbs/acre. (1 lb /1000 sq. ft.) F SOD G STRAW MULCH 2 TONS /ACRE /l IRRIGATION NEEDED DURING JUNE, JULY, AND /OR SEPTEMBER. IRRIGATION NEEDED FOR 2 TO 3 WEEKS AFTER APPLYING SOD. NOTE: RULE 5 REQUIRES ALL DISTURBED GROUND TO BE IMMEDIATELY STABILIZED WiTH GRASS AND /OR MULCH IF CONSTRUCTION ACTIVITIES ARE TO CEASE FOR 15 DAYS OR MORE. Land Disturbing Activities Pre construction actions Construction access Demolition Clearing and Grubbing Stripping Topsoil Rough Grading Surface Drainage Excavation Utility Excavation Sanitary Sewer Storm Sewer Water Finish Grading Topsoil Replacement Landscaping TENTATIVE SCHEDULE START DATE 10 -04 -04 10 -04 -04 10 -04 -04 10 -04 -04 10 -11 -04 10 -18 -04 11 -01 -04 11 -15 -04 11 -08 -04 12 -13 -04 02 -14 -05 02 -21 -05 02 -28 -05 DURATION (WEEKS) 1 1 2 2 1 3 3 2 4 2 2 2 2 *NOTE TO CONTRACTOR SCHEDULE PROVIDED PER AGENCY REQUIREMENTS MORE DETAILED SCHEDULE TO BE PROVIDED BY CONTRACTOR. e Erosion and Sediment Control Sequence 1. Assign an on -site person with the daily responsibility and authority to ensure that erosion /sediment control practices are installed according to this sequence schedule. 2. Contact Indiana Underground Planned Protection Systems, Inc. "Holey Maley for underground Utility locations. (1- 800 382 -5544) 3. Before opening up the site, first evaluate, mark and protect important trees and associated root zones, unique areas to be preserved (i.e. wetlands), or existing vegetation suitable for use as filter strips (especially in perimeter areas). 4. Install silt fence around the perimeter of the site as shown. 5. Install an adequate and stable construction entrance exit drive from the construction site to keep mud and sediment off public roads. Dust shall be kept to a minimum by utilizing sprinkling, Calcium Chloride, vegetative cover, spray on adhesives or other approved methods. 6. Identify construction staging area, material storage area, concrete washout areas, dumpster area. Each area shall properly protected and delineated prior to construction. 7. Prior to the start of construction activities, pump down the water level of the existing pond to two feet below normal pool elevation. This will aid in preventing turbid water from entering the storm sewer system. Repeat this step following all rain events once the pond has settled. If rain events persist to the point of turbid water reaching the outlet, stormwater clarification additives are to be used (Floc Log by Applied Polymer Systems, Inc. or approved equal). Follow manufacturer's instructions. 8. Once erosion and sediment control measures are in place, begin land clearing followed immediately by grading. Do not leave large areas unprotected for more than 7 days. 9. Start mass earthwork including topsoil striping and stockpile. 10. Start building pad and road grading. 11. As the grading progress, install fabric inlet bafflers to storm inlets, and additional silt fencing to prevent sediment from going off site or into the retention pond. 12. Install the main runoff conveyance system with inlet and outlet protection devices to convey storm runoff through the site without creating gullies and to prevent damage to open channels. Sides of Swales, mounds and ponds to be seeded and mulched upon completion. Temporary seeding shall be required for all swales and disturbed areas that can not be final seeded within a time period that will prevent slope erosion. For temporary seeding, the contractor shall utilize a fast growing seed of either oats, annual rye grass, wheat or rye depending on time of year. Disturbed areas shall be kept to a minimum at all times. 13. As soon as the storm drain system is functional, install drain inlet protections, which trap sediment on -site in shallow pools while allowing high water flows to enter the system. 14. Install sanitary sewers and other utilities. 15. Complete roadway and parking lot grading followed by aggregate layers and curbing. 16. Immediately after grading, apply surface stabilization practices on all graded areas, using permanent measures in accordance with the erosion control plan. However, if weather delays permanent stabilization, temporary seeding and /or mulching may be necessary as a stop -qap measure. Also stabilize (using temporary seeding /mulching or other suitable means) any disturbed area where active construction will not take place for 15 working days. 17. After construction and final grading, landscape and permanently stabilize all disturbed sites, including borrow and disposal areas. Also remove temporary runoff control structures and any unstable sediment around them, and vegetate those areas. 18. Maintain all erosion and sediment control practices until all disturbed areas are permanently stabilized. CONSTRUCTION /STORMWATER POLLUTION PREVENTION PLAN ASSESSMENT OF CONSTRUCTION PLAN ELEMENTS (SECTION A) Al PLAN INDEX SHOWING LOCATIONS OF REQUIRED ITEMS: SEE COVER SHEET A2 11x17 INCH PLAT SHOWING BUILDING LOT NUMBERS AND ROAD LAYOUT /NAMES: SITE LOCATION: LONGITUDE 8613'6"W, LATITUDE 39'57'55 "N A3 NARRATIVE DESCRIBING PROJECT NATURE AND PURPOSE: THIS IS A PROPOSED GOVERNMENT USE DEVELOPMENT CONSISTING OF 4.82 AC. THE CONSTRUCTION WILL CONSIST OF A PARKING LOTS, WALKWAYS, ENCLOSED STORM SEWERS, AND ENTRY DRIVES. THE LAND DISTURBING ACTIVITIES SHALL BE AS SHOWN ON THE DRAWINGS INCLUDED WITH THIS SUBMITTAL. CONSTRUCTION SEQUENCE: (SEE SCHEDULE OF EROSION AND SEDIMENT CONTROL SEQUENCE ON THIS SHEET.) A4 VICINITY MAP SHOWING PROJECT LOCATION: SEE SHEET C101 A5 LEGAL DESCRIPTION OF THE PROJECT SITE: SEE COVER SHEET A6 LOCATION OF ALL LOTS AND PROPOSED SITE IMPROVEMENTS: SEE SHEETS C201 AND C501. A7 HYDROLOGIC UNIT CODE: EAGLE CREEK LONG BRANCH IRISHMAN RUN 05120201120080 A8 NOTATION OF ANY STATE OR FEDERAL WATER QUALITY PERMITS: NONE. A9 SPECIFIC POINTS WHERE STORMWATER DISCHARGE WILL LEAVE THE SITE: STORM WATER IS COLLECTED ON SITE AND FLOWS TO THE EXISTING RETENTION POND. THE POND OUTLETS TO LONG BRANCH CREEK. A10 LOCATION NAME OF ALL WETLANDS. LAKES WATER COURSES ON AND ADJACENT TO THE SITE: NONE All IDENTIFY ALL RECEMNG WATERS: LONG BRANCH CREEK Al2 IDENTIFICATION OF POTENTIAL DISCHARGE TO GROUNDWATER: NONE A13 100 YEAR FLOODPLAINS, FLOODWAYS. AND FLOODWAY FRINGES: NONE A14 PRE CONSTRUCTION AND POST CONSTRUCTION ESTIMATE OF PEAK DISCHARGE: Q10 PRE) 6.34 cfs TO POND Q10 Post) 15.2 cfs TO POND 0100 PRE) 9.36 cfs TO POND 0100 POST) 22.4 cfs TO POND Q100 POST) 25.6 cfs FROM POND FOR ENTIRE SCHOOL PROPERTY (77.3 ACRES) A15 ADJACENT LAND USE. INCLUDING UPSTREAM WATERSHED: SEE SHEET C101 A16 LOCATIONS AND APPROXIMATE BOUNDARIES OF ALL DISTURBED AREAS: SEE SHEETS C101, C201, C301, C401 A17 IDENTIFICATION OF EXISTING VEGETATIVE COVER: SEE SHEET C102 A18 SOILS MAP INCLUDING DESCRIPTIONS AND LIMITATIONS: SEE SHEET C101 A19 LOCATION. SIZE AND DIMENSIONS OF PROPOSED STORMWATER SYSTEMS: SEE SHEETS C501 A20 PLAN FOR ANY OFF -SITE CONSTRUCTION ACTMTIES ASSOCIATED WITH THIS PROJECT: NONE A21 LOCATIONS OF PROPOSED SOIL STOCKPILES. BORROW AND /OR DISPOSAL AREAS: NONE A22 EXISTING SITE TOPOGRAPHY AT AN INTERVAL APPROPRIATE TO SHOW DETAILED DRAINAGE PATTERNS: SEE SHEET C102 A23 PROPOSED FINAL TOPOGRAPHY AT AN INTERVAL APPROPRIATE TO SHOW DETAILED DRAINAGE PATTERNS: SEE SHEET C301 ASSESSMENT OF STORMWATER POLLUTION PREVENTION PLAN CONSTRUCTION COMPONENT (SECTION B) B1 DESCRIPTION OF POTENTIAL POLLUTANT SOURCES ASSOCIATED WITH CONSTRUCTION ACTMTIES: POTENTIAL POLLUTANT SOURCES DURING CONSTRUCTION INCLUDE DISTURBED SOILS, CONCRETE WASH -OUT, FUEL OIL, GASOLINE, TRASH, FERTIUZERS, AND HERBICIDES. B2 SEQUENCE DESCRIBING STORMWATER QUALITY MEASURE IMPLEMENTATION RELATIVE TO LAND DISTURBING ACTIVITIES: SEE SCHEDULE OF EROSION AND SEDIMENT CONTROL SEQUENCES ON THIS SHEET. B3 STABLE CONSTRUCTION ENTRANCE LOCATIONS AND SPECIFICATIONS: SEE SHEET C401 ADDITIONAL STORMWATER POLLUTION PREVENTION MEASURES DESCRIPTION AND PURPOSE TO PREVENT OR REDUCE THE AMOUNT OF CONTAMINATION TO STORMWATER RESULTING FROM VEHICLE AND EQUIPMENT MAINTENANCE BY MAINTAINING A "DRY AND CLEAN SITE THE BEST PRACTICE WOULD BE TO PERFORM MAINTENANCE ACTIVITIES AT AN OFFSITE FACILITY WHENEVER POSSIBLE. IF THIS OPTION IS NOT FEASIBLE, THEN WORK SHOULD BE PERFORMED ONLY IN DESIGNATED AREAS, WHILE PROVIDING ADEQUATE COVER FOR MATERIALS STORED OUTSIDE, ROUTINELY CHECKING FOR LEAKS AND SPILLS, AND CONTAINING AND CLEANING UP ALL SPILLS IMMEDIATELY. SUITABLE APPLICATIONS THESE PROCEDURES ARE APPLICABLE FOR ALL CONSTRUCTION PROJECTS WHERE AN ONSITE STAGING YARD AREA IS NECESSARY FOR THE STORAGE AND MAINTENANCE OF HEAVY CONSTRUCTION EQUIPMENT AND VEHICLES. LIMITATIONS VEHICLE AND EQUIPMENT MAINTENANCE SHOULD ONLY BE PERFORMED ONSITE WHEN IT IS IMPRACTICAL TO SEND THEM OFFSITE FOR MAINTENANCE AND REPAIR. TRANSPORTING VEHICLES AND /EQUIPMENT OFFSITE SHOULD BE DONE ONLY AT THE STABIUZED CONSTRUCTION ENTRANCE /EXIT. VEHICLE STORAGE AND EQUIPMENT MAINTENANCE PROVIDES FOR A POTENTIALLY SIGNIFICANT SOURCE OF STORMWATER POLLUTION. ONSITE ACTIVITIES THAT CAN CONTAMINATE STORMWATER INCLUDE GENERAL MAINTENANCE SUCH AS CHANGING OR REPLACEMENT OF FLUIDS AND FILTERS, ENGINE REPAIR AND SERVICE, AND OUTDOOR EQUIPMENT STORAGE OR PARKING (FROM SOURCES SUCH AS THE ENGINE, OIL FUEL, OR HYDRAULIC FLUID LEAKS). IMPLEMENTATION IF MAINTENANCE MUST OCCUR ONSITE, WORK SHOULD BE DONE ONLY iN DESIGNATED AREAS LOCATED AWAY FROM DRAINAGE COURSES. DEDICATED MAINTENANCE AREAS SHOULD BE PROTECTED FROM STORMWATER INFILTRATION AND RUNOFF. THE MAINTENANCE AREA SHOULD BE LOCATED AT LEAST 50 FEET FROM DOWNSTREAM DRAINAGE FACILITIES, WATERWAYS, AND FLOOD PLAINS. STORE AN ADEQUATE AMOUNT OF SPILL CLEANUP MATERIALS ONSITE WHERE THEY CAN BE READILY ACCESSIBLE. DRIP PANS OR ABSORBENT PADS SHOULD BE USED DURING VEHICLE AND EQUIPMENT MAINTENANCE WORK THAT INVOLVES FLUIDS, UNLESS THE MAINTENANCE WORK IS PERFORMED OVER AN IMPERMEABLE SURFACE WITHIN THE DEDICATED MAINTENANCE AREA USE ABSORBENT MATERIALS ON SMALL SPILL AREAS. REMOVE THE CONTAMINATED ABSORBENT MATERIALS PROMPTLY AND DISPOSE OF THEM PROPERLY. ALL FUELING TRUCKS AND FUELING AREAS SHALL HAVE SPILL KiTS AND /OR USE OTHER ADEQUATE SPILL PROTECTION DEVICES. INSPECT ONSITE VEHICLES AND EQUIPMENT DAILY AT THE BEGINNING OF EACH DAY FOR LEAKS AND REPAIR IMMEDIATELY. KEEP VEHICLES AND EQUIPMENT CLEAN; DO NOT ALLOW EXCESSIVE BUILD -UP OF OiL GREASE OR SILT MATERIALS THAT MAY CONTAMINATE OTHER PORTIONS OF THE SiTE. EMPLOYEES AND SUBCONTRACTORS SHALL BE TRAINED IN PROPER MAINTENANCE AND SPILL MEDIATION PROCEDURES. PROPERLY DISPOSE OF USED OILS, FLUIDS, LUBRICANTS, AND SPILL CLEANUP MATERIALS PER LOCAL AND STATE LAWS. SEPARATE AND RECYCLE WASTES SUCH AS GREASES, USED OiL, HYDRAULIC FLUID, OIL FILTERS, ANTIFREEZE, CLEANING SOLVENTS, BATTERIES, AND TRANSMISSION FLUIDS. IF THESE MATERIALS ARE STORED ONSITE, PROVIDE ADEQUATE SECONDARY CONTAINMENT AND COVERS. DO NOT PLACE USED OIL IN AN UNAPPROVED DUMPSTER, POUR INTO A STORM DRAIN OR WATERCOURSE, OR POUR ONTO THE GROUND. DRIP PANS OR PLASTIC SHEETING SHOULD BE PLACED UNDER ALL VEHICLES AND EQUIPMENT PLACED ON WATERWAY DOCKS, BARGES, OR OTHER STRUCTURES LOCATED OVER WATER BODIES WHEN THE VEHICLE OR EQUIPMENT IS ANTICIPATED TO BE IDLE FOR MORE THAN ONE HOUR. DO NOT BURY OR BURN USED TIRES. SOLiD WASTE MANAGEMENT DESCRIPTION AND PURPOSE SOLID WASTE MANAGEMENT PROCEDURES AND PRACTICES ARE DESIGNED TO PREVENT OR REDUCE THE POTENTIAL FOR DISCHARGE OF POLLUTANTS TO STORMWATER FROM SOUD OR CONSTRUCTION WASTE BY PROVIDING DESIGNATED WASTE COLLECTION AREAS AND CONTAINERS, ENSURING REGULAR DISPOSAL, AND TRAINING OF EMPLOYEES AND SUBCONTRACTORS. SUiTAB! E APPLICATIONS THIS PRACTICE IS APPLICABLE FOR CONSTRUCTION SiTES WHERE THE FOLLOWING WASTES ARE GENERATED OR STORED: SOLID WASTE GENERATED FROM DEMOLITION ACTIVITIES SUCH AS TREES OR SHRUBS, DEMOLITION OF EXISTING STRUCTURES, AND NEW BUILDING CONSTRUCTION MATERIALS INCLUDING CONCRETE, MASONRY, WOOD, METAL, GLASS, RUBBER, STYROFOAM, PAPER, PLASTIC, PIPE, ELECTRICAL COMPONENTS, AND PACKAGING MATERIALS. DOMESTIC WASTES INCLUDE: FOOD CONTAINERS, BEVERAGE CONTAINERS, COFFEE CUPS, PAPER BAGS, PLASTIC WRAPPERS, STYROFOAM, AND CIGARETTES CONSTRUCTION WASTES INCLUDING BRICK, MORTAR, TIMBER, STEEL AND METAL SCRAPS, PIPE AND ELECTRICAL CUTTINGS, NONHAZARDOUS EQUIPMENT PARTS, STYROFOAM AND OTHER MATERIALS SEND TRANSPORT AND PACKAGE CONSTRUCTION MATERIALS IMPLEMENTATION THE FOLLOWING STEPS WILL AID IN KEEPING THE SITE CLEAN AND REDUCE THE POTENTIAL FOR STORMWATER POLLUTION: SELECT A DESIGNATED WASTE COLLECTION AREA ONSITE THAT IS DOWNSTREAM FROM THE STORMWATER COLLECTION SYSTEM AND AT LEAST 50 FEET AWAY FROM ALL WATERWAYS AND FLOOD PLAINS. INFORM THE TRASH HAULING CONTRACTOR THAT ONLY WATERTIGHT DUMPSTERS FOR ONSITE USE WILL BE ACCEPTED. INSPECT DUMPSTERS WHEN THEY REACH THE SITE FOR LEAKS. REJECT ANY DUMPSTER THAT IS NOT WATERTIGHT OR IS DEFECTIVE. PROVIDE AN ADEQUATE NUMBER OF CONTAINERS WITH LiDS OR COVERS TO KEEP RAINWATER OUT AND TO PREVENT LOSS OF MATERIALS DUE TO WINDY CONDITIONS. ALLOW FOR ADDITIONAL DUMPSTERS OR MORE FREQUENT PICKUPS DURING THE DEMOLITION PHASE OF CONSTRUCTION TO INSURE TRASH MATERIALS DO NOT GET STORED ON THE GROUND. HAVE SiTE TRASH COLLECTED DAILY. DURING RAINY AND WINDY CONDITIONS IT MAY BE NECESSARY TO COLLECT TRASH MORE THAN ONCE A DAY. REMOVE SOLID WASTE MATERIALS PROMPTLY FROM THE SiTE SINCE EROSION AND SEDIMENT CONTROL MEASURES TEND TO COLLECT TRASH WHICH HINDERS THE EFFECTIVENESS OF THE EROSION CONTROL MEASURES. INSURE THAT TOXIC LIQUID WASTES SUCH AS USED OILS, SOLVENTS, AND PAINTS AND CHEMICALS SUCH AS ACIDS, PESTICIDES, ADDITIVES, AND CURING COMPOUNDS ARE NOT DISPOSED OF IN DUMPSTERS DESIGNATED FOR CONSTRUCTION DEBRIS BUT ARE PROPERLY DISPOSED OF ACCORDING TO LOCAL AND STATE LAWS. DO NOT WASH OUT DUMPSTERS ON THE CONSTRUCTION SITE. DUMPSTER CLEANING SHOULD BE THE RESPONSIBILITY OF THE TRASH HAUUNG CONTRACTOR. ARRANGE FOR REGULAR WASTE COLLECTION BEFORE DUMPSTERS OVERFLOW. DO NOT PILE MATERIAL ABOVE THE DUMPSTER SIDE OR ALLOW MATERIAL TO DRAPE OVER THE SIDES. IMMEDIATELY CLEAN UP DUMPSTER SHOULD A SPILL OCCUR. MAKE SURE THAT CONSTRUCTION WASTE IS COLLECTED, REMOVED, AND DISPOSED OF IN A TIMELY MANOR BY AN AUTHORIZED DISPOSAL CONTRACTOR. EQUIPMENT FUELING INSPECT AND VERIFY THAT PRACTICES ARE IN PLACE PRIOR TO THE START OF EACH ASSOCIATED ACTIVITY. WHILE ACTMTIES ARE IN PROGRESS, INSPECT EACH PRACTICE WEEKLY TO VERIFY CONTINUED IMPLEMENTATION. KEEP ADEQUATE SUPPLIES OF SPILL CLEANUP MATERIALS ONSITE. INSURE THAT ALL EMPLOYEES ARE AWARE OF MATERIAL STORAGE LOCATIONS AND ACCESS CAN BE OBTAINED TO THE MATERIALS. MAINTAIN FLUID WASTE CONTAINERS IN LEAK PROOF CONDITION. REMOVE AND REPLACE ANY CONTAINERS FOUND TO BE DEFECTIVE. VEHICLES AND EQUIPMENT SHOULD BE INSPECTED AT THE START OF EACH DAY. IMMEDIATELY REPAIR ALL LEAKS. iT IS PREFERRED THAT THE PROBLEM VEHICLE OR EQUIPMENT BE REMOVED FROM THE PROJECT SITE FOR REPAIRS TO MINIMIZE ONSITE IMPACTS. INSPECT EQUIPMENT FOR DAMAGED HOSES AND LEAKY GASKETS DAILY. IMMEDIATELY REPAIR OR REPLACE FAULTY COMPONENTS. DESCRIPTION AND PURPOSE VEHICLE AND EQUIPMENT FUEUNG PROCEDURES AND PRACTICES ARE DESIGNED TO PREVENT FUEL SPILLS OR LEAKS AND REDUCE OR ELIMINATE CONTAMINATION OF SOILS AND STORMWATER. THIS CAN BE ACCOMPLISHED BY USING OFFSITE FACILMES, FUEUNG IN DESIGNATED ONSITE AREAS ONLY, ENCLOSING OR COVERING STORED MATERIAL, UTILIZING SPILL CONTROLS, AND TRAINING EMPLOYEES AND SUBCONTRACTORS IN PROPER FUEUNG PROCEDURES. LIMITATION ONSITE VEHICLE AND EQUIPMENT FUEUNG SHOULD ONLY BE DONE WHEN IT IS NOT FEASIBLE TO SEND VEHICLES AND EQUIPMENT OFFSITE FOR FUELING. VEHICLES AND EQUIPMENT ENTERING AND EXITING THE SITE SHOULD ALWAYS BE DONE AT THE STABIUZED CONSTRUCTION ENTRANCE /EXIT. IMPLEMENTATION. THE USE OF OFFSITE FUELING STATIONS IS ENCOURAGED WHENEVER FEASIBLE. THESE FACILITIES ARE EQUIPPED TO HANDLE FUELING AND SPILLS PROPERLY. PERFORMING THIS WORK OFFSITE MAY BE MORE ECONOMICAL BY EUMiNATiNG THE NEED FOR A SEPARATE DESIGNATED FUELING AREA AND CONTAINMENT MEASURES ONSITE. DISCOURAGE EMPLOYEES FROM "TOPPING -OFF" FUEL TANKS TO PREVENT UNNECESSARY SPILLS. ABSORBENT SPILL CLEANUP MATERIALS AND SPILL KITS SHALL BE AVAILABLE IN ONSITE FUELING AREAS AND ON MOBILE FUELING TRUCKS. PROPERLY DISPOSE OF USED MATERIALS AFTER USE. ABSORBENT PADS OR DRIP PANS SHOULD BE USED DURING VEHICLE AND EQUIPMENT FUELING UNLESS THE FUELING IS PERFORMED OVER AN IMPERVIOUS SURFACE WITHIN A DEDICATED FUELING AREA. ABSORBENT MATERIALS FOR SMALL SPILLS SHALL BE USED. DO NOT WASH OR BURY THE SPILL MATERIAL AS THIS ONLY RESULTS IN ADDITIONAL REMEDIATiON REQUIREMENTS. REMOVE THE CONTAMINATED ABSORBENT MATERIALS PROMPTLY AND DISPOSE OF PROPERLY ACCORDING TO LOCAL AND STATE LAWS. AVOID FUELING OF CONSTRUCTION EQUIPMENT AT VARIOUS LOCATIONS AROUND THE SITE. TRANSPORT THE VEHICLE OR EQUIPMENT TO DESIGNATED ONSITE FUELING AREAS WHERE ADEQUATE PREVENTION AND SPILL CONTAINMENT MATERIALS ARE LOCATED. EMPLOYEES AND SUBCONTRACTORS SHOULD BE TRAINED IN PROPER FUEUNG AND CLEANUP PROCEDURES. DEDICATED FUELING AREAS SHOULD BE PROTECTED FROM STORMWATER INFILTRATION AND RUNOFF, AND SHOULD BE LOCATED AT LEAST 50 FT AWAY FROM DOWNSTREAM DRAINAGE FACILITIES, WATERWAYS, AND FLOOD PLAINS. FUELING MUST BE PERFORMED IN A LEVEL AREA. PROTECT FUELING AREAS WiTH BERMS OR DIKES TO PREVENT INFILTRATION, RUNOFF, AND TO CONTAIN SPILLS. NOZZLES USED IN VEHICLE AND EQUIPMENT FUELING SHOULD BE EQUIPPED WITH AN AUTOMATIC SHUTOFF TO CONTROL SPILLS AND DRIPS. FUELING OPERATIONS SHOULD BE MONITORED BY THE FUELING OPERATOR AT ALL TIMES. FEDERAL SLATE, AND LOCAL REQUIREMENTS SHOULD BE OBSERVED FOR ANY TEMPORARY ABOVE GROUND STORAGE TANKS. INSPECTION AND MAINTENANCE VEHICLES AND EQUIPMENT SHOULD BE INSPECTED DAILY FOR LEAKS. LEAKS SHOULD BE REPAIRED IMMEDIATELY PREFERABLY WiTH THE PROBLEM VEHICLE OR EQUIPMENT REMOVED FROM THE PROJECT SITE FOR REPAIR. MAINTAIN ADEQUATE SUPPLIES OF SPILL CLEANUP MATERIALS ONSITE AND INSURE ALL PERSONEL KNOW THEIR STORAGE LOCATION. IMMEDIATELY CLEAN UP SPILLS AND PROPERLY DISPOSE OF CONTAMINATED SOIL AND CLEANUP MATERIALS ACCORDING TO LOCAL AND STATE LAWS. COLLECTION, STORAGE, AND DISPOSAL OF MATERIALS LITTERING ON THE PROJECT SITE IS PROHIBITED. TO PREVENT CLOGGING OF THE STORM DRAINAGE SYSTEM LITTER AND DEBRIS SHOULD BE REMOVED FROM DRAINAGE GRATES, TRASH RACKS, AND DITCHES DAILY. TRASH RECEPTACLES SHOULD BE PROVIDED IN THE CONSTRUCTION STAGING AREAS, FIELD TRAILER AREAS, AND AREAS UTILIZED FOR LUNCH AND BREAK PERIODS. DOMESTIC TRASH FROM WORK AREAS WiTHIN THE CONSTRUCTION LIMITS OF THE SITE SHOULD BE COLLECTED AND PLACED IN WATERTIGHT DUMPSTERS WEEKLY AT A MINIMUM. DOMESTIC TRASH SHOULD BE COLLECTED FROM THE SiTE REGARDLESS OF THE SOURCE. COLLECTED UTTER AND DEBRIS SHOULD NOT BE PLACED IN OR NEXT TO THE STORMWATER DRAINAGE SYSTEMS OR WATERWAYS. DUMPSTERS OF SUFFICIENT SIZE AND QUANTITY SHOULD BE PROVIDED TO CONTAIN THE SOLID WASTE GENERATED BY THE PROJECT. DUMPSTERS SHOULD BE REMOVED FROM THE PROJECT SITE ONCE THEY BECOME FULL AND THE CONTENTS DISPOSED OF BY THE TRASH HAULING CONTRACTOR. CONSTRUCTION DEBRIS AND WASTE SHOULD BE REMOVED FROM THE SITE WEEKLY OR MORE FREQUENTLY AS REQUIRED. THE CONTRACTOR SHOULD USE THEIR BEST JUDGEMENT IN ANTICIPATING WHEN A DUMPSTER WILL BE FULL AND SCHEDULE A PICKUP iN ADVANCE OF THE DUMPSTER BEiNG FULL TO PREVENT OVER TOPPING OF THE DUMPSTER OR PLACEMENT OF EXCESS MATERIAL ON THE GROUND. CONSTRUCTION MATERIAL VISIBLE TO THE PUBLIC SHOULD BE STORED OR STACKED IN AN ORDERLY MANNER AWAY FROM THE STORM DRAINAGE SYSTEM, WATERWAYS, AND FLOOD PLAIN. STORMWATER RUNOFF SHOULD BE DIVERTED FROM STORED SOLID WASTE THROUGH THE USE OF BERMS, DIKES, OR OTHER TEMPORARY DIVERSION STRUCTURES OR THROUGH THE USE OF MEASURES TO ELEVATE THE WASTE COLLECTION DUMPSTER. SOLiD WASTE STORAGE AREAS SHOULD NOT BE LOCATED IN AREAS PRONE TO FLOODING OR PONDING AND SHOULD BE LOCATED AT LEAST 50 FT FROM STORM DRAINAGE SYSTEMS AND WATERWAYS. INSPECTION AND MAINTENANCE INSPECT AND VERIFY THAT ACTIVITY-BASED PRACTICES ARE IN PLACE PRIOR TO THE START OF CONSTRUCTION IN THAT AREA. INSPECT EACH PRACTICE WEEKLY TO VERIFY IMPLEMENTATION. INSPECT CONSTRUCTION WASTE COLLECTION AREA REGULARLY TO INSURE ALL WASTE MATERIALS ARE BEING DISPOSED OF PROPERLY. ARRANGE FOR REGULAR WASTE COLLECTION WITH A TRASH HAUUNG CONTRACTOR. CONCRETE AND MASONRY WASHOUT AREAS THE FOLLOWING STEPS WILL HELP REDUCE STORMWATER POLLUTION FROM CONCRETE AND MASONRY WASTES: DISCUSS THE CONCRETE MANAGEMENT TECHNIQUES DESCRIBED, SUCH AS HANDLING OF CONCRETE WASTE AND WASHOUT AREAS WITH THE READY -MIX CONCRETE SUPPLIER BEFORE ANY DELIVERIES ARE MADE. DISCUSS MASONRY WASTE MANAGEMENT TECHNIQUES WITH THE MASONRY CONTRACTORS FOR THE CONTROL OF CEMENT MIXER WASHOUT AREAS. INCORPORATE REQUIREMENTS FOR CONCRETE AND MASONRY WASTE MANAGEMENT INTO MATERIAL SUPPLIER AND SUBCONTRACTOR AGREEMENTS. STORE DRY AND LIQUID MATERIALS IN A COVERED AREA AWAY FROM DRAINAGE AREAS. PREVENT MASONRY SAND STOCKPILE FROM WASHING INTO STREETS, STORM DRAINAGE SYSTEMS, AND WATERWAYS. AVOID MIXING EXCESS AMOUNTS OF FRESH CONCRETE OR MORTAR. PERFORM WASHOUT OF CONCRETE TRUCKS OFFSITE OR iN DESIGNATED AREAS ONLY. PERFORM MORTAR MIXER WASHOUT IN ONE DESIGNATED AREA FOR THE DURATION OF THE PROJECT. DO NOT WASH OUT CONCRETE TRUCKS OR MORTAR MIXERS INTO STORM DRAINS, OPEN DiTCHES, STREETS, OR WATERWAYS. DO NOT ALLOW EXCESS CONCRETE OR MORTAR TO BE DUMPED ONSITE, EXCEPT IN DESIGNATED AREAS. FOR ONSITE WASHOUT AREAS: LOCATE WASHOUT AREA AT LEAST 50 FEET FROM STORM DRAINS, OPEN DITCHES, OR WATERWAYS. DO NOT ALLOW RUNOFF TO LEAVE THE DESIGNATED AREA BY CONSTRUCTING A TEMPORARY PIT OR BERMED AREA LARGE ENOUGH FOR LIQUID AND SOLID WASTE. -WASH OUT WASTES INTO THE TEMPORARY PIT WHERE THE CONCRETE CAN SET, BE BROKEN UP, AND BE DISPOSED OF PROPERLY. -AVOID CREATING UNNECESSARY RUNOFF BY NI WATER f 0 D CR DRAINING WA E FROM THE WASHOUT AREA INTO A BERMED, LEVEL AREA WHEN WASHING CONCRETE TO REMOVE FINE PARTICLES AND EXPOSE THE AGGREGATE. DO NOT WASH SWEEPINGS FROM EXPOSED AGGREGATE CONCRETE INTO THE STREET OR STORM DRAIN SYSTEM. COLLECT AND RETURN SWEEPINGS TO AGGREGATE BASE STOCKPILE OR DISPOSE OF PROPERLY. B4 SEDIMENT CONTROL MEASURES FOR SHEET FLOW AREAS: SEE SHEET C401 B5 SEDIMENT CONTROL MEASURES FOR CONCENTRATED FLOW AREAS: CONCENTRATED FLOW AREAS ARE INCORPORATED INTO THE STORM SEWER SYSTEM. INLETS ARE PROTECTED FROM SEDIMENT VIA SILT FENCING, AND INLET CONTROL MEASURES AS LISTED ON SHEET C401. B6 STORM SEWER INLET PROTECTION MEASURE LOCATIONS AND SPECIFICATIONS: SEE SHEETS C401 -C402 B7 RUNOFF CONTROL MEASURES: RUNOFF CONTROL MEASURES INCLUDE RIPRAP, SiLT FENCING, AND INLET CONTROL MEASURES AS SHOWN ON SHEETS C401 -C402. CONSTRUCTION DETAILS AND SPECIFICATIONS FOR THESE MEASURES ARE INCLUDED ON THIS SHEET. B8 STORMWATER OUTLET PROTECTION SPECIFICATIONS: SEE SHEETS C401 -C402 AND DETAIL EC-16 ON THIS SHEET. B9 GRADE STABILIZATION STRUCTURE LOCATIONS AND SPECIFICATIONS: PLEASE SEE SHEETS C401 -C4O2 B10 LOCATION. DIMENSIONS, SPECIFICATIONS AND CONSTRUCTION DETAILS FOR EACH STORMWATER QUALITY MEASURE: SEE SHEET C401 AND ASSOCIATED EROSION CONTROL DETAILS ON THIS SHEET. B11 TEMPORARY SURFACE STABILIZATION METHODS APPROPRIATE FOR EACH SEASON: SEE SHEET C401 AND IMPLEMENTATION AND MAINTENANCE PROCEDURE ON THIS SHEET B12 PERMANENT SURFACE STABILIZATION SPECIFICATIONS: SEE SHEET C401 IMPLEMENTATION AND MAINTENANCE PROCEDURE ON THIS SHEET e B13 MATERIAL HANDLING AND SPILL PREVENTION PLAN: EXPECTED CONSTRUCTION MATERIALS ON SITE MAY INCLUDE VEHICLE LUBRICANTS, OILS, VEHICULAR FUELS, CONCRETE WASH -OUT, MULCH, PAINTS AND SOLVENTS, PESTICIDES, HERBICIDES, FERTILIZER, AND TRASH. FUELS, OILS, AND GASOLINE CAN LEAK OR BE SPILLED FROM TRUCKS AND CONSTRUCTION EQUIPMENT WHICH COULD FIND THEIR WAY TO MUD CREEK. SMALL SPILLS AND LEAKS OF THESE MATERIALS ONTO NON -PAVED AREAS WILL BE SHOVELED INTO CONTAINERS OR DUMPSTERS FOR PROPER DISPOSAL. SPILLS OF PAINTS, SOLVENTS, FERTILIZER, AND OR PESTICIDES SHALL BE ADDRESSED PER MANUFACTURERS INSTRUCTIONS AND PER PRODUCTS MATERIAL SAFETY DATA SHEET (MSDS). CONCRETE WASH -OUT TO BE OPERATED IN DESIGNATED CONSTRUCTION STAGING AREA ONLY. FUELING TRUCKS WILL BE EQUIPPED WiTH SPILL PREVENTION KITS FOR SMALLER FUEL SPILLS. ALL VEHICULAR MAINTENANCE SHALL BE PERFORMED IN THE SAME DESIGNATED AREA THROUGHOUT THE CONSTRUCTION TIME FRAME. IF POSSIBLE, VEHICULAR MAINTENANCE SHALL BE DONE OFF -SITE AT FACILITIES THAT ARE DESIGNED TO HANDLE ANY MATERIAL SPILLAGE. THIS SHALL INCLUDE FUELING OF VEHICLES WHENEVER POSSIBLE. THE CARMEL CLAY FIRE DEPARTMENT (317) 571 -2600 OR 911, INDIANA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT, OFFICE OF EMERGENCY RESPONSE (800)- 233 -7745, SHALL BE NOTIFIED IMMEDIATELY FOR LARGER SPILLS OR LEAKS. THE NATIONAL RESPONSE CENTER (800)- 424 -8802 SHALL BE NOTIFIED AND PROVIDED WITH THE FOLLOWING INFORMATION: TIME OF SPILL LOCATION OF SPILL, MATERIAL, SOURCE OF SPILL, APPROXIMATE VOLUME AND LENGTH OF SPILLAGE, WEATHER CONDITIONS AT TIME OF SPILL, PERSONAL PRESENT AT TIME OF SPILL, AND ALL ACTION TAKEN FOR POST SPILL CLEANUP. CONTRACTOR SHALL CONTACT A WASTE RECOVERY AGENCY IMMEDIATELY FOR REMOVAL OF CONTAMINATES AND COORDINATION OF MONITORING THE SITE DURING CLEANUP UNTIL ALL OF THE HAZARDOUS MATERIAL HAS BEEN REMOVED. CONTRACTOR SHALL COOPERATE WiTH IDEM DURING AND AFTER THE SPILL TO INSURE ALL REQUIRED CLEANUP AND FILING REPORTS ARE PROPERLY SUBMITTED. THE DEVELOPER SHALL BE CONTINUALLY INFORMED OF ANY CONTAMINATION CONCERNS OCCURRING ON THE SITE. THE CONSTRUCTION MANAGER SHALL KEEP ON SITE A LIST OF QUALIFIED CONTRACTORS FOR SPILL REMEDIATION. ALL SITE PERSONNEL, INCLUDING MAINTENANCE EMPLOYEES, SHALL BE MADE AWARE OF PROPER SPILL PREVENTION AND REMEDIATION TECHNIQUES. ALL MATERIALS USED TO ABSORB SPILLS SHALL BE PROPERLY DISPOSED OF IN AN APPROVED MANOR WILL LOCAL AND STATE LAWS. DO NOT FLUSH SPILL MATERIALS WITH WATER UNLESS DIRECTED TO DO SO BY A GOVERNING AGENCY. IT IS IMPORTANT THAT ALL MANUFACTURER'S INSTRUCTIONS BE FOLLOWED WHEN USING OR APPLYING ALL FERTILIZERS, HERBICIDES, AND PESTICIDES. B14 MONITORING AND MAINTENANCE GUIDELINES FOR EACH PROPOSED POLLUTION PREVENTION MEASURE: REFER TO MAINTENANCE GUIDELINES SHOWN FOR EACH EROSION CONTROL MEASURE THIS SHEET. B15 EROSION AND SEDIMENT CONTROL SPECIFICATIONS FOR INDIVIDUAL BUILDING LOTS: NOT APPLICABLE ASSESSMENT OF STORMWATER POLLUTION PREVENTION POST CONSTRUCTION COMPONENT (SECTION C) e Cl DESCRIPTION OF POTENTIAL POLLUTANT SOURCES ASSOCIATED WITH THE PROPOSED LAND USE: POTENTIAL POLLUTANT SOURCES POST CONSTRUCTION INCLUDE DISTURBED SOILS FROM SUBSEQUENT DEVELOPMENT, FERTILIZERS, HERBICIDES, PESTICIDES AND OTHER LAWN TREATMENT APPLICATIONS, SPILLS OR OVERFILLS AT THE FUELING STATION, AND ASSORTED FUELS, OiLS AND LIQUIDS ASSOCIATED WiTH VEHICULAR TRAFFIC THROUGHOUT THE DEVELOPMENT. C2 SEQUENCE DESCRIBING STORMWATER QUALITY MEASURE IMPLEMENTATION: THE STORMWATER QUALITY MEASURE IMPLEMENTATION SHALL BE SUBSTANTIALLY COMPLETE UPON COMPLETION OF THE CONSTRUCTION ACTiTIES FOR THE PROPOSED PROJECT. ADDITIONAL STORMWATER QUALITY MEASURES WiLL BE IMPLEMENTED AT THE DEVELOPMENT OF SUBSEQUENT CONSTRUCTION PHASES. PRE CONSTRUCTION ACTIONS, CONSTRUCTION ACCESS, DEMOLITION, AND CLEARING AND GRUBBING WILL BEGIN THE FIRST WEEK OF CONSTRUCTION. STRIPPING TOPSOIL WILL BEGIN THE SECOND WEEK OF CONSTRUCTION. ROUGH GRADING WILL BEGIN THE THIRD WEEK. SURFACE DRAINAGE EXCAVATION WILL BEGIN THE FIFTH WEEK. UTILITY INSTALLATION WILL BEGIN SOON AFTER. TEMPORARY SEEDING WILL BE PLACED IMMEDIATELY AFTER COMPLETION OF A DISTURBED AREA, OR IMMEDIATELY PRIOR TO ANY PROLONGED BREAK (GREATER THAN SEVEN DAYS) FOR A GIVEN DISTURBED AREA. C3 DESCRIPTION OF PROPOSED POST CONSTRUCTION STORMWATER QUALITY MEASURES: POST CONSTRUCTION STORMWATER QUALITY MEASURES WILL CONSIST OF VEGETATIVE COVER ON THE DISTURBED AREAS, AN OIL WATER SEPERATOR CONNECTED TO THE INLET AT THE FUEL ISLAND, CATCH BASINS TO REDUCE SEDIMENT FROM PARKING AREAS, AND THE EXISTING RETENTION POND. C4 LOCATION, DIMENSIONS. SPECIFICATIONS, AND CONSTRUCTION DETAILS OF EACH STORMWATER QUALITY MEASURE: THE STORMWATER QUALITY MEASURES FOR POST CONSTRUCTION ACTMTES ARE INDICATED WITHIN THESE CONSTRUCTION DOCUMENTS. REFER TO SHEET C401 FOR EROSION CONTROL MEASURES TO BE IMPLEMENTED WITHIN THE PROJECT SITE, AND SHEET C501 FOR STORM SEWER IMPROVEMENTS INTENDED TO SERVE THE POST CONSTRUCTED AREA. DIMENSIONS, SPECIFICATIONS AND CONSTRUCTION DETAILS FOR THESE STORMWATER QUALITY MEASURES ARE INCLUDED WITHIN THE AFOREMENTIONED SERIES OF CONSTRUCTION DOCUMENTS. C5 DESCRIPTION OF MAINTENANCE GUIDELINES FOR POST CONSTRUCTION STORMWATER QUALITY MEASURES: BUILDING AND GROUNDS PERSONNEL WILL PROVIDE MAINTENANCE ACTIVITIES FOR THE POST CONSTRUCTION WATER QUALITY MEASURES. MAINTENANCE ACTMTIES WILL BE COMPLETED AS DESCRIBED BELOW. ALL INLET CASTINGS WILL BE INSPECTED MONTHLY. DEBRIS AND TRASH AROUND OR OBSTRUCTING INLETS WILL BE REMOVED. CATCH BASINS WILL BE INSPECTED QUARTERLY. TRASH, STICKS, DEBRIS, AND SEDIMENT WILL BE REMOVED TO ENSURE PROPER PERFORMANCE OF THE CATCH BASIN. GRASS AREAS SURROUNDING INLETS WILL BE MAINTAINED ON A REGULAR MOWING CYCLE. TRASH AND DEBRIS WILL BE REMOVED FROM SEEDED AND PAVED AREAS. DAMAGE TO INLET CASTINGS, INLET STRUCTURES, STORM STRUCTURES, OR CATCH BASINS SHOULD BE REPAIRED AS SOON AS POSSIBLE. 0: 11994t945011100401Cad1EVCDs1C402- C403.dwg, 10/2812004 3:34:24 PM, mwag z 0 0 L.LJ Drown Checked Approved Scale Sheet Dote to W 0: Z 0 C9 I- L 0 ce S 0 MAW DJO DAL 1 =30' CONSULTANTS w o: 0 z 0 z wz U) N Lx Lx D U) 0 a J z J U) 0 0 1 z W 2 z 0 fY w C402 08/30/04 Project number PIC 0940501 -101 CONTROL DETAILS BID DOCUMENTS ONLY, PENDING AGENCY APPROVAL CHANGES PER TAC REVIEW 2 *O /6 /9 10/28/0 i E r ARCHITECTURE fl t x. 7172 GRAHAM ROAD CIVIL ENGINEERS k LANDSCAPE ARCHITECTURE aspr��5`� INDIANAPOLIS, INDIANA 46250 S'R p; LAND PLANNING p F (317) 842 -6777 FAX (317) 841-4798 LAND SURVEYORS sz d f 3 E —Mail cripe©cripe.biz TRANSPORTATION ENGINEERS GIS Architects Engineers 126th AND SHELBORNE ROAD CARMEL, INDIANA 46033 WEST SIDE TRANSPORTAI i ot: J n eISTE/94ctk dr■ No.10200269 i s 1 '0 s STATE OF i /ONAL 4/ /iiiiliiiiitO -N Drawn By: MAW Checked By: DJO Mauranoe DAL Soda 0 Scala 1' NA' am mom Sheet C Dote 08-30 -04 Project timber 94501 -10040 PART 1 EXECUTION 1.1 IMPLEMENTATION AND MAINTENANCE PROCEDURE AT BEGINNING OF SITE WORK A. Prior to general stripping topsoil and excavating, install silt fence where indicated. B. Construct erosion control devices where indicated on drawings during rough grading as grading progresses. C. Topsoil must be present to ensure growth. D. Temporarily seed basin slopes, topsoil stockpiles, and areas disturbed by construction. 1. Seeding times and rates: a. May 15 to September 15; Annual Ryegrass at 40 lbs. /acre. b. August 15 to November 15; Rye (grain) or wheat at 2 bushels /acre. c. March 1 to May 15; Oats at 3 bushels /acre. 2. Fertilizer: Commercial analysis 12/12/12 applied at a rate of 600# /acre. a. Apply lime to raise PH to the level needed for species being seeded. b. Work fertilizer and lime into the soil to a depth of 2 -3 IN. 3. All Hydroseeding shall be in accordance with the preceding requirements. 4. Reseed as required until good stand of gross is achieved. 1.2 DURING CONSTRUCTION PERIOD A. Maintain basins, dikes, traps, stone filters, silt fences, etc. B. Inspect regularly especially after rainstorms. C. Repair or replace damaged or missing items. D. After rough grading, sow temporary grass cover over exposed earth areas not draining into a protected device. E. Construct inlets as soon as possible. 1. Install silt fence or straw bale barriers or 1/2" slotted barrel at each new inlet, as necessary to control erosion. F. Provide necessary swales and dikes to direct water towards a protected device. G. Do not disturb existing vegetation (grass and trees) outside limits of construction. H. Remove sediment from behind silt fences when sediment reaches one fourth fabric height. I. Topsoil and fine grade slopes and swales, etc. Seed and mulch as soon as possible in areas as they become ready. 1.3 NEAR COMPLETION OF CONSTRUCTION A. Eliminate erosion control devices except inlet protection. B. Grade to finished or existing grades. C. Fine grade remaining earth areas disturbed by construction activities. D. Topsoil must be a minimum of 4" to ensure growth. F. Permanent seed: March 1 to May 15 and August 10 to October 15. (Dates may vary at discretion of Landscape Architect depending on weather conditions.) G. Soil Preparation. Soil surface must be free of rocks, debris, and other foreign materials. 2. Soils must have proper moisture control to assure proper germination and growth. 3. Soil surface must be compacted to a depth of at least 6 inches. 4. Soil preparation depends on soil conditions at time of seeding. Various tools may be necessary to achieve surface finish. 5. Surface of soil shall be level and large voids eliminated to applying fertilizer, lime and seed. H. Applying fertilizer, lime and seed. 1. Work fertilizer and lime into soil to a depth of 2 3 inches. 2. Apply seed carefully and cover seed with 1/4 inch soil, apply seed carefully and avoid covering seed more than 1/4 inch. 3. Apply mulch at rate of 2 tons per acre following seeding. 4. Water as necessary to ensure adequate moisture for germination and growth. 5. Reseed as necessary until a good stand of grass is achieved. I. Products 1. Fertilizer: Commercial analysis 12/12/12 or equivalent applied at a rate of 600 pounds per acre. 2. Lime: Apply agricultural lime to raise PH to the level needed for species being seeded. Soil test may be required to determine rate. 3. Swales /Slopes: Blended mixture of seed shall be applied at the rate of 110 pounds per acre. The mix shall consist of 40 pounds Mustang turf -type Tall Fescue, 30 pounds Banff or Wabash Kentucky Bluegrass, 30 4. Graded areas adjacent to pavement: Blended mixture of seed shall be applied at a rote of 90 pounds per acre. The mixture shall consist of 35 pounds Mustang turf -type Tall Fescue, 30 pounds Fiesta Perennial 5. Apply mulch straw at rate of 2 tons per acres immediately after seeding. The straw must be evenly distributed loosely over the entire area. "Slabs" of straw must be redistributed or it will kill young seedlings. On large open areas the mulch must be secured to soil by a tack or mechanical means to prevent wind action on mulch. 3.4 MAINTENANCE A. Reseed all areas that don't take. B. Apply a maintenance fertilizer within 6 months of acquiring a good stand. C. Avoid traffic on area until area is well protected and stable. D. Water as necessary to ensure adequate growth and development. *Maintenance fertilizer apply 200 lbs of 12 -12 -12 or equivalent. Stabilization Practice: Permanent Seeding Dormant Seeding Temporary Seeding Sodding Mulching SEASONAL SOIL PROTECTION CHART MAR, A C F APR. E MAY JUN. JUL. AUG SEP. I iii /I/ /I/ 1 OCT. NOV. B DEC. A KENTUCKY BLUEGRASS 40 lbs /acre: CREEPING RED FESCUE 40 lbs/acre; PLUS 2 TONS STRAW MULCH /ACRE, OR ADD ANNUAL RYEGRASS 20 lbs /acre. B KENTUCKY BLUEGRASS 60 lbs /acre; CREEPING RED FESCUE 60 lbs/acre; PLUS 2 TONS STRAW MULCH /ACRE, OR ADD ANNUAL RYEGRASS 30 lbs/acre. C SPRING OATS 3 BUSHEL /ACRE. D WHEAT OR RYE 2 BUSHEL /ACRE E ANNUAL RYEGRASS 40 lbs/acre. (1 lb /1000 sq. ft.) F SOD G STRAW MULCH 2 TONS /ACRE /l IRRIGATION NEEDED DURING JUNE, JULY, AND /OR SEPTEMBER. IRRIGATION NEEDED FOR 2 TO 3 WEEKS AFTER APPLYING SOD. NOTE: RULE 5 REQUIRES ALL DISTURBED GROUND TO BE IMMEDIATELY STABILIZED WiTH GRASS AND /OR MULCH IF CONSTRUCTION ACTIVITIES ARE TO CEASE FOR 15 DAYS OR MORE. Land Disturbing Activities Pre construction actions Construction access Demolition Clearing and Grubbing Stripping Topsoil Rough Grading Surface Drainage Excavation Utility Excavation Sanitary Sewer Storm Sewer Water Finish Grading Topsoil Replacement Landscaping TENTATIVE SCHEDULE START DATE 10 -04 -04 10 -04 -04 10 -04 -04 10 -04 -04 10 -11 -04 10 -18 -04 11 -01 -04 11 -15 -04 11 -08 -04 12 -13 -04 02 -14 -05 02 -21 -05 02 -28 -05 DURATION (WEEKS) 1 1 2 2 1 3 3 2 4 2 2 2 2 *NOTE TO CONTRACTOR SCHEDULE PROVIDED PER AGENCY REQUIREMENTS MORE DETAILED SCHEDULE TO BE PROVIDED BY CONTRACTOR. e Erosion and Sediment Control Sequence 1. Assign an on -site person with the daily responsibility and authority to ensure that erosion /sediment control practices are installed according to this sequence schedule. 2. Contact Indiana Underground Planned Protection Systems, Inc. "Holey Maley for underground Utility locations. (1- 800 382 -5544) 3. Before opening up the site, first evaluate, mark and protect important trees and associated root zones, unique areas to be preserved (i.e. wetlands), or existing vegetation suitable for use as filter strips (especially in perimeter areas). 4. Install silt fence around the perimeter of the site as shown. 5. Install an adequate and stable construction entrance exit drive from the construction site to keep mud and sediment off public roads. Dust shall be kept to a minimum by utilizing sprinkling, Calcium Chloride, vegetative cover, spray on adhesives or other approved methods. 6. Identify construction staging area, material storage area, concrete washout areas, dumpster area. Each area shall properly protected and delineated prior to construction. 7. Prior to the start of construction activities, pump down the water level of the existing pond to two feet below normal pool elevation. This will aid in preventing turbid water from entering the storm sewer system. Repeat this step following all rain events once the pond has settled. If rain events persist to the point of turbid water reaching the outlet, stormwater clarification additives are to be used (Floc Log by Applied Polymer Systems, Inc. or approved equal). Follow manufacturer's instructions. 8. Once erosion and sediment control measures are in place, begin land clearing followed immediately by grading. Do not leave large areas unprotected for more than 7 days. 9. Start mass earthwork including topsoil striping and stockpile. 10. Start building pad and road grading. 11. As the grading progress, install fabric inlet bafflers to storm inlets, and additional silt fencing to prevent sediment from going off site or into the retention pond. 12. Install the main runoff conveyance system with inlet and outlet protection devices to convey storm runoff through the site without creating gullies and to prevent damage to open channels. Sides of Swales, mounds and ponds to be seeded and mulched upon completion. Temporary seeding shall be required for all swales and disturbed areas that can not be final seeded within a time period that will prevent slope erosion. For temporary seeding, the contractor shall utilize a fast growing seed of either oats, annual rye grass, wheat or rye depending on time of year. Disturbed areas shall be kept to a minimum at all times. 13. As soon as the storm drain system is functional, install drain inlet protections, which trap sediment on -site in shallow pools while allowing high water flows to enter the system. 14. Install sanitary sewers and other utilities. 15. Complete roadway and parking lot grading followed by aggregate layers and curbing. 16. Immediately after grading, apply surface stabilization practices on all graded areas, using permanent measures in accordance with the erosion control plan. However, if weather delays permanent stabilization, temporary seeding and /or mulching may be necessary as a stop -qap measure. Also stabilize (using temporary seeding /mulching or other suitable means) any disturbed area where active construction will not take place for 15 working days. 17. After construction and final grading, landscape and permanently stabilize all disturbed sites, including borrow and disposal areas. Also remove temporary runoff control structures and any unstable sediment around them, and vegetate those areas. 18. Maintain all erosion and sediment control practices until all disturbed areas are permanently stabilized. CONSTRUCTION /STORMWATER POLLUTION PREVENTION PLAN ASSESSMENT OF CONSTRUCTION PLAN ELEMENTS (SECTION A) Al PLAN INDEX SHOWING LOCATIONS OF REQUIRED ITEMS: SEE COVER SHEET A2 11x17 INCH PLAT SHOWING BUILDING LOT NUMBERS AND ROAD LAYOUT /NAMES: SITE LOCATION: LONGITUDE 8613'6"W, LATITUDE 39'57'55 "N A3 NARRATIVE DESCRIBING PROJECT NATURE AND PURPOSE: THIS IS A PROPOSED GOVERNMENT USE DEVELOPMENT CONSISTING OF 4.82 AC. THE CONSTRUCTION WILL CONSIST OF A PARKING LOTS, WALKWAYS, ENCLOSED STORM SEWERS, AND ENTRY DRIVES. THE LAND DISTURBING ACTIVITIES SHALL BE AS SHOWN ON THE DRAWINGS INCLUDED WITH THIS SUBMITTAL. CONSTRUCTION SEQUENCE: (SEE SCHEDULE OF EROSION AND SEDIMENT CONTROL SEQUENCE ON THIS SHEET.) A4 VICINITY MAP SHOWING PROJECT LOCATION: SEE SHEET C101 A5 LEGAL DESCRIPTION OF THE PROJECT SITE: SEE COVER SHEET A6 LOCATION OF ALL LOTS AND PROPOSED SITE IMPROVEMENTS: SEE SHEETS C201 AND C501. A7 HYDROLOGIC UNIT CODE: EAGLE CREEK LONG BRANCH IRISHMAN RUN 05120201120080 A8 NOTATION OF ANY STATE OR FEDERAL WATER QUALITY PERMITS: NONE. A9 SPECIFIC POINTS WHERE STORMWATER DISCHARGE WILL LEAVE THE SITE: STORM WATER IS COLLECTED ON SITE AND FLOWS TO THE EXISTING RETENTION POND. THE POND OUTLETS TO LONG BRANCH CREEK. A10 LOCATION NAME OF ALL WETLANDS. LAKES WATER COURSES ON AND ADJACENT TO THE SITE: NONE All IDENTIFY ALL RECEMNG WATERS: LONG BRANCH CREEK Al2 IDENTIFICATION OF POTENTIAL DISCHARGE TO GROUNDWATER: NONE A13 100 YEAR FLOODPLAINS, FLOODWAYS. AND FLOODWAY FRINGES: NONE A14 PRE CONSTRUCTION AND POST CONSTRUCTION ESTIMATE OF PEAK DISCHARGE: Q10 PRE) 6.34 cfs TO POND Q10 Post) 15.2 cfs TO POND 0100 PRE) 9.36 cfs TO POND 0100 POST) 22.4 cfs TO POND Q100 POST) 25.6 cfs FROM POND FOR ENTIRE SCHOOL PROPERTY (77.3 ACRES) A15 ADJACENT LAND USE. INCLUDING UPSTREAM WATERSHED: SEE SHEET C101 A16 LOCATIONS AND APPROXIMATE BOUNDARIES OF ALL DISTURBED AREAS: SEE SHEETS C101, C201, C301, C401 A17 IDENTIFICATION OF EXISTING VEGETATIVE COVER: SEE SHEET C102 A18 SOILS MAP INCLUDING DESCRIPTIONS AND LIMITATIONS: SEE SHEET C101 A19 LOCATION. SIZE AND DIMENSIONS OF PROPOSED STORMWATER SYSTEMS: SEE SHEETS C501 A20 PLAN FOR ANY OFF -SITE CONSTRUCTION ACTMTIES ASSOCIATED WITH THIS PROJECT: NONE A21 LOCATIONS OF PROPOSED SOIL STOCKPILES. BORROW AND /OR DISPOSAL AREAS: NONE A22 EXISTING SITE TOPOGRAPHY AT AN INTERVAL APPROPRIATE TO SHOW DETAILED DRAINAGE PATTERNS: SEE SHEET C102 A23 PROPOSED FINAL TOPOGRAPHY AT AN INTERVAL APPROPRIATE TO SHOW DETAILED DRAINAGE PATTERNS: SEE SHEET C301 ASSESSMENT OF STORMWATER POLLUTION PREVENTION PLAN CONSTRUCTION COMPONENT (SECTION B) B1 DESCRIPTION OF POTENTIAL POLLUTANT SOURCES ASSOCIATED WITH CONSTRUCTION ACTMTIES: POTENTIAL POLLUTANT SOURCES DURING CONSTRUCTION INCLUDE DISTURBED SOILS, CONCRETE WASH -OUT, FUEL OIL, GASOLINE, TRASH, FERTIUZERS, AND HERBICIDES. B2 SEQUENCE DESCRIBING STORMWATER QUALITY MEASURE IMPLEMENTATION RELATIVE TO LAND DISTURBING ACTIVITIES: SEE SCHEDULE OF EROSION AND SEDIMENT CONTROL SEQUENCES ON THIS SHEET. B3 STABLE CONSTRUCTION ENTRANCE LOCATIONS AND SPECIFICATIONS: SEE SHEET C401 ADDITIONAL STORMWATER POLLUTION PREVENTION MEASURES DESCRIPTION AND PURPOSE TO PREVENT OR REDUCE THE AMOUNT OF CONTAMINATION TO STORMWATER RESULTING FROM VEHICLE AND EQUIPMENT MAINTENANCE BY MAINTAINING A "DRY AND CLEAN SITE THE BEST PRACTICE WOULD BE TO PERFORM MAINTENANCE ACTIVITIES AT AN OFFSITE FACILITY WHENEVER POSSIBLE. IF THIS OPTION IS NOT FEASIBLE, THEN WORK SHOULD BE PERFORMED ONLY IN DESIGNATED AREAS, WHILE PROVIDING ADEQUATE COVER FOR MATERIALS STORED OUTSIDE, ROUTINELY CHECKING FOR LEAKS AND SPILLS, AND CONTAINING AND CLEANING UP ALL SPILLS IMMEDIATELY. SUITABLE APPLICATIONS THESE PROCEDURES ARE APPLICABLE FOR ALL CONSTRUCTION PROJECTS WHERE AN ONSITE STAGING YARD AREA IS NECESSARY FOR THE STORAGE AND MAINTENANCE OF HEAVY CONSTRUCTION EQUIPMENT AND VEHICLES. LIMITATIONS VEHICLE AND EQUIPMENT MAINTENANCE SHOULD ONLY BE PERFORMED ONSITE WHEN IT IS IMPRACTICAL TO SEND THEM OFFSITE FOR MAINTENANCE AND REPAIR. TRANSPORTING VEHICLES AND /EQUIPMENT OFFSITE SHOULD BE DONE ONLY AT THE STABIUZED CONSTRUCTION ENTRANCE /EXIT. VEHICLE STORAGE AND EQUIPMENT MAINTENANCE PROVIDES FOR A POTENTIALLY SIGNIFICANT SOURCE OF STORMWATER POLLUTION. ONSITE ACTIVITIES THAT CAN CONTAMINATE STORMWATER INCLUDE GENERAL MAINTENANCE SUCH AS CHANGING OR REPLACEMENT OF FLUIDS AND FILTERS, ENGINE REPAIR AND SERVICE, AND OUTDOOR EQUIPMENT STORAGE OR PARKING (FROM SOURCES SUCH AS THE ENGINE, OIL FUEL, OR HYDRAULIC FLUID LEAKS). IMPLEMENTATION IF MAINTENANCE MUST OCCUR ONSITE, WORK SHOULD BE DONE ONLY iN DESIGNATED AREAS LOCATED AWAY FROM DRAINAGE COURSES. DEDICATED MAINTENANCE AREAS SHOULD BE PROTECTED FROM STORMWATER INFILTRATION AND RUNOFF. THE MAINTENANCE AREA SHOULD BE LOCATED AT LEAST 50 FEET FROM DOWNSTREAM DRAINAGE FACILITIES, WATERWAYS, AND FLOOD PLAINS. STORE AN ADEQUATE AMOUNT OF SPILL CLEANUP MATERIALS ONSITE WHERE THEY CAN BE READILY ACCESSIBLE. DRIP PANS OR ABSORBENT PADS SHOULD BE USED DURING VEHICLE AND EQUIPMENT MAINTENANCE WORK THAT INVOLVES FLUIDS, UNLESS THE MAINTENANCE WORK IS PERFORMED OVER AN IMPERMEABLE SURFACE WITHIN THE DEDICATED MAINTENANCE AREA USE ABSORBENT MATERIALS ON SMALL SPILL AREAS. REMOVE THE CONTAMINATED ABSORBENT MATERIALS PROMPTLY AND DISPOSE OF THEM PROPERLY. ALL FUELING TRUCKS AND FUELING AREAS SHALL HAVE SPILL KiTS AND /OR USE OTHER ADEQUATE SPILL PROTECTION DEVICES. INSPECT ONSITE VEHICLES AND EQUIPMENT DAILY AT THE BEGINNING OF EACH DAY FOR LEAKS AND REPAIR IMMEDIATELY. KEEP VEHICLES AND EQUIPMENT CLEAN; DO NOT ALLOW EXCESSIVE BUILD -UP OF OiL GREASE OR SILT MATERIALS THAT MAY CONTAMINATE OTHER PORTIONS OF THE SiTE. EMPLOYEES AND SUBCONTRACTORS SHALL BE TRAINED IN PROPER MAINTENANCE AND SPILL MEDIATION PROCEDURES. PROPERLY DISPOSE OF USED OILS, FLUIDS, LUBRICANTS, AND SPILL CLEANUP MATERIALS PER LOCAL AND STATE LAWS. SEPARATE AND RECYCLE WASTES SUCH AS GREASES, USED OiL, HYDRAULIC FLUID, OIL FILTERS, ANTIFREEZE, CLEANING SOLVENTS, BATTERIES, AND TRANSMISSION FLUIDS. IF THESE MATERIALS ARE STORED ONSITE, PROVIDE ADEQUATE SECONDARY CONTAINMENT AND COVERS. DO NOT PLACE USED OIL IN AN UNAPPROVED DUMPSTER, POUR INTO A STORM DRAIN OR WATERCOURSE, OR POUR ONTO THE GROUND. DRIP PANS OR PLASTIC SHEETING SHOULD BE PLACED UNDER ALL VEHICLES AND EQUIPMENT PLACED ON WATERWAY DOCKS, BARGES, OR OTHER STRUCTURES LOCATED OVER WATER BODIES WHEN THE VEHICLE OR EQUIPMENT IS ANTICIPATED TO BE IDLE FOR MORE THAN ONE HOUR. DO NOT BURY OR BURN USED TIRES. SOLiD WASTE MANAGEMENT DESCRIPTION AND PURPOSE SOLID WASTE MANAGEMENT PROCEDURES AND PRACTICES ARE DESIGNED TO PREVENT OR REDUCE THE POTENTIAL FOR DISCHARGE OF POLLUTANTS TO STORMWATER FROM SOUD OR CONSTRUCTION WASTE BY PROVIDING DESIGNATED WASTE COLLECTION AREAS AND CONTAINERS, ENSURING REGULAR DISPOSAL, AND TRAINING OF EMPLOYEES AND SUBCONTRACTORS. SUiTAB! E APPLICATIONS THIS PRACTICE IS APPLICABLE FOR CONSTRUCTION SiTES WHERE THE FOLLOWING WASTES ARE GENERATED OR STORED: SOLID WASTE GENERATED FROM DEMOLITION ACTIVITIES SUCH AS TREES OR SHRUBS, DEMOLITION OF EXISTING STRUCTURES, AND NEW BUILDING CONSTRUCTION MATERIALS INCLUDING CONCRETE, MASONRY, WOOD, METAL, GLASS, RUBBER, STYROFOAM, PAPER, PLASTIC, PIPE, ELECTRICAL COMPONENTS, AND PACKAGING MATERIALS. DOMESTIC WASTES INCLUDE: FOOD CONTAINERS, BEVERAGE CONTAINERS, COFFEE CUPS, PAPER BAGS, PLASTIC WRAPPERS, STYROFOAM, AND CIGARETTES CONSTRUCTION WASTES INCLUDING BRICK, MORTAR, TIMBER, STEEL AND METAL SCRAPS, PIPE AND ELECTRICAL CUTTINGS, NONHAZARDOUS EQUIPMENT PARTS, STYROFOAM AND OTHER MATERIALS SEND TRANSPORT AND PACKAGE CONSTRUCTION MATERIALS IMPLEMENTATION THE FOLLOWING STEPS WILL AID IN KEEPING THE SITE CLEAN AND REDUCE THE POTENTIAL FOR STORMWATER POLLUTION: SELECT A DESIGNATED WASTE COLLECTION AREA ONSITE THAT IS DOWNSTREAM FROM THE STORMWATER COLLECTION SYSTEM AND AT LEAST 50 FEET AWAY FROM ALL WATERWAYS AND FLOOD PLAINS. INFORM THE TRASH HAULING CONTRACTOR THAT ONLY WATERTIGHT DUMPSTERS FOR ONSITE USE WILL BE ACCEPTED. INSPECT DUMPSTERS WHEN THEY REACH THE SITE FOR LEAKS. REJECT ANY DUMPSTER THAT IS NOT WATERTIGHT OR IS DEFECTIVE. PROVIDE AN ADEQUATE NUMBER OF CONTAINERS WITH LiDS OR COVERS TO KEEP RAINWATER OUT AND TO PREVENT LOSS OF MATERIALS DUE TO WINDY CONDITIONS. ALLOW FOR ADDITIONAL DUMPSTERS OR MORE FREQUENT PICKUPS DURING THE DEMOLITION PHASE OF CONSTRUCTION TO INSURE TRASH MATERIALS DO NOT GET STORED ON THE GROUND. HAVE SiTE TRASH COLLECTED DAILY. DURING RAINY AND WINDY CONDITIONS IT MAY BE NECESSARY TO COLLECT TRASH MORE THAN ONCE A DAY. REMOVE SOLID WASTE MATERIALS PROMPTLY FROM THE SiTE SINCE EROSION AND SEDIMENT CONTROL MEASURES TEND TO COLLECT TRASH WHICH HINDERS THE EFFECTIVENESS OF THE EROSION CONTROL MEASURES. INSURE THAT TOXIC LIQUID WASTES SUCH AS USED OILS, SOLVENTS, AND PAINTS AND CHEMICALS SUCH AS ACIDS, PESTICIDES, ADDITIVES, AND CURING COMPOUNDS ARE NOT DISPOSED OF IN DUMPSTERS DESIGNATED FOR CONSTRUCTION DEBRIS BUT ARE PROPERLY DISPOSED OF ACCORDING TO LOCAL AND STATE LAWS. DO NOT WASH OUT DUMPSTERS ON THE CONSTRUCTION SITE. DUMPSTER CLEANING SHOULD BE THE RESPONSIBILITY OF THE TRASH HAUUNG CONTRACTOR. ARRANGE FOR REGULAR WASTE COLLECTION BEFORE DUMPSTERS OVERFLOW. DO NOT PILE MATERIAL ABOVE THE DUMPSTER SIDE OR ALLOW MATERIAL TO DRAPE OVER THE SIDES. IMMEDIATELY CLEAN UP DUMPSTER SHOULD A SPILL OCCUR. MAKE SURE THAT CONSTRUCTION WASTE IS COLLECTED, REMOVED, AND DISPOSED OF IN A TIMELY MANOR BY AN AUTHORIZED DISPOSAL CONTRACTOR. EQUIPMENT FUELING INSPECT AND VERIFY THAT PRACTICES ARE IN PLACE PRIOR TO THE START OF EACH ASSOCIATED ACTIVITY. WHILE ACTMTIES ARE IN PROGRESS, INSPECT EACH PRACTICE WEEKLY TO VERIFY CONTINUED IMPLEMENTATION. KEEP ADEQUATE SUPPLIES OF SPILL CLEANUP MATERIALS ONSITE. INSURE THAT ALL EMPLOYEES ARE AWARE OF MATERIAL STORAGE LOCATIONS AND ACCESS CAN BE OBTAINED TO THE MATERIALS. MAINTAIN FLUID WASTE CONTAINERS IN LEAK PROOF CONDITION. REMOVE AND REPLACE ANY CONTAINERS FOUND TO BE DEFECTIVE. VEHICLES AND EQUIPMENT SHOULD BE INSPECTED AT THE START OF EACH DAY. IMMEDIATELY REPAIR ALL LEAKS. iT IS PREFERRED THAT THE PROBLEM VEHICLE OR EQUIPMENT BE REMOVED FROM THE PROJECT SITE FOR REPAIRS TO MINIMIZE ONSITE IMPACTS. INSPECT EQUIPMENT FOR DAMAGED HOSES AND LEAKY GASKETS DAILY. IMMEDIATELY REPAIR OR REPLACE FAULTY COMPONENTS. DESCRIPTION AND PURPOSE VEHICLE AND EQUIPMENT FUEUNG PROCEDURES AND PRACTICES ARE DESIGNED TO PREVENT FUEL SPILLS OR LEAKS AND REDUCE OR ELIMINATE CONTAMINATION OF SOILS AND STORMWATER. THIS CAN BE ACCOMPLISHED BY USING OFFSITE FACILMES, FUEUNG IN DESIGNATED ONSITE AREAS ONLY, ENCLOSING OR COVERING STORED MATERIAL, UTILIZING SPILL CONTROLS, AND TRAINING EMPLOYEES AND SUBCONTRACTORS IN PROPER FUEUNG PROCEDURES. LIMITATION ONSITE VEHICLE AND EQUIPMENT FUEUNG SHOULD ONLY BE DONE WHEN IT IS NOT FEASIBLE TO SEND VEHICLES AND EQUIPMENT OFFSITE FOR FUELING. VEHICLES AND EQUIPMENT ENTERING AND EXITING THE SITE SHOULD ALWAYS BE DONE AT THE STABIUZED CONSTRUCTION ENTRANCE /EXIT. IMPLEMENTATION. THE USE OF OFFSITE FUELING STATIONS IS ENCOURAGED WHENEVER FEASIBLE. THESE FACILITIES ARE EQUIPPED TO HANDLE FUELING AND SPILLS PROPERLY. PERFORMING THIS WORK OFFSITE MAY BE MORE ECONOMICAL BY EUMiNATiNG THE NEED FOR A SEPARATE DESIGNATED FUELING AREA AND CONTAINMENT MEASURES ONSITE. DISCOURAGE EMPLOYEES FROM "TOPPING -OFF" FUEL TANKS TO PREVENT UNNECESSARY SPILLS. ABSORBENT SPILL CLEANUP MATERIALS AND SPILL KITS SHALL BE AVAILABLE IN ONSITE FUELING AREAS AND ON MOBILE FUELING TRUCKS. PROPERLY DISPOSE OF USED MATERIALS AFTER USE. ABSORBENT PADS OR DRIP PANS SHOULD BE USED DURING VEHICLE AND EQUIPMENT FUELING UNLESS THE FUELING IS PERFORMED OVER AN IMPERVIOUS SURFACE WITHIN A DEDICATED FUELING AREA. ABSORBENT MATERIALS FOR SMALL SPILLS SHALL BE USED. DO NOT WASH OR BURY THE SPILL MATERIAL AS THIS ONLY RESULTS IN ADDITIONAL REMEDIATiON REQUIREMENTS. REMOVE THE CONTAMINATED ABSORBENT MATERIALS PROMPTLY AND DISPOSE OF PROPERLY ACCORDING TO LOCAL AND STATE LAWS. AVOID FUELING OF CONSTRUCTION EQUIPMENT AT VARIOUS LOCATIONS AROUND THE SITE. TRANSPORT THE VEHICLE OR EQUIPMENT TO DESIGNATED ONSITE FUELING AREAS WHERE ADEQUATE PREVENTION AND SPILL CONTAINMENT MATERIALS ARE LOCATED. EMPLOYEES AND SUBCONTRACTORS SHOULD BE TRAINED IN PROPER FUEUNG AND CLEANUP PROCEDURES. DEDICATED FUELING AREAS SHOULD BE PROTECTED FROM STORMWATER INFILTRATION AND RUNOFF, AND SHOULD BE LOCATED AT LEAST 50 FT AWAY FROM DOWNSTREAM DRAINAGE FACILITIES, WATERWAYS, AND FLOOD PLAINS. FUELING MUST BE PERFORMED IN A LEVEL AREA. PROTECT FUELING AREAS WiTH BERMS OR DIKES TO PREVENT INFILTRATION, RUNOFF, AND TO CONTAIN SPILLS. NOZZLES USED IN VEHICLE AND EQUIPMENT FUELING SHOULD BE EQUIPPED WITH AN AUTOMATIC SHUTOFF TO CONTROL SPILLS AND DRIPS. FUELING OPERATIONS SHOULD BE MONITORED BY THE FUELING OPERATOR AT ALL TIMES. FEDERAL SLATE, AND LOCAL REQUIREMENTS SHOULD BE OBSERVED FOR ANY TEMPORARY ABOVE GROUND STORAGE TANKS. INSPECTION AND MAINTENANCE VEHICLES AND EQUIPMENT SHOULD BE INSPECTED DAILY FOR LEAKS. LEAKS SHOULD BE REPAIRED IMMEDIATELY PREFERABLY WiTH THE PROBLEM VEHICLE OR EQUIPMENT REMOVED FROM THE PROJECT SITE FOR REPAIR. MAINTAIN ADEQUATE SUPPLIES OF SPILL CLEANUP MATERIALS ONSITE AND INSURE ALL PERSONEL KNOW THEIR STORAGE LOCATION. IMMEDIATELY CLEAN UP SPILLS AND PROPERLY DISPOSE OF CONTAMINATED SOIL AND CLEANUP MATERIALS ACCORDING TO LOCAL AND STATE LAWS. COLLECTION, STORAGE, AND DISPOSAL OF MATERIALS LITTERING ON THE PROJECT SITE IS PROHIBITED. TO PREVENT CLOGGING OF THE STORM DRAINAGE SYSTEM LITTER AND DEBRIS SHOULD BE REMOVED FROM DRAINAGE GRATES, TRASH RACKS, AND DITCHES DAILY. TRASH RECEPTACLES SHOULD BE PROVIDED IN THE CONSTRUCTION STAGING AREAS, FIELD TRAILER AREAS, AND AREAS UTILIZED FOR LUNCH AND BREAK PERIODS. DOMESTIC TRASH FROM WORK AREAS WiTHIN THE CONSTRUCTION LIMITS OF THE SITE SHOULD BE COLLECTED AND PLACED IN WATERTIGHT DUMPSTERS WEEKLY AT A MINIMUM. DOMESTIC TRASH SHOULD BE COLLECTED FROM THE SiTE REGARDLESS OF THE SOURCE. COLLECTED UTTER AND DEBRIS SHOULD NOT BE PLACED IN OR NEXT TO THE STORMWATER DRAINAGE SYSTEMS OR WATERWAYS. DUMPSTERS OF SUFFICIENT SIZE AND QUANTITY SHOULD BE PROVIDED TO CONTAIN THE SOLID WASTE GENERATED BY THE PROJECT. DUMPSTERS SHOULD BE REMOVED FROM THE PROJECT SITE ONCE THEY BECOME FULL AND THE CONTENTS DISPOSED OF BY THE TRASH HAULING CONTRACTOR. CONSTRUCTION DEBRIS AND WASTE SHOULD BE REMOVED FROM THE SITE WEEKLY OR MORE FREQUENTLY AS REQUIRED. THE CONTRACTOR SHOULD USE THEIR BEST JUDGEMENT IN ANTICIPATING WHEN A DUMPSTER WILL BE FULL AND SCHEDULE A PICKUP iN ADVANCE OF THE DUMPSTER BEiNG FULL TO PREVENT OVER TOPPING OF THE DUMPSTER OR PLACEMENT OF EXCESS MATERIAL ON THE GROUND. CONSTRUCTION MATERIAL VISIBLE TO THE PUBLIC SHOULD BE STORED OR STACKED IN AN ORDERLY MANNER AWAY FROM THE STORM DRAINAGE SYSTEM, WATERWAYS, AND FLOOD PLAIN. STORMWATER RUNOFF SHOULD BE DIVERTED FROM STORED SOLID WASTE THROUGH THE USE OF BERMS, DIKES, OR OTHER TEMPORARY DIVERSION STRUCTURES OR THROUGH THE USE OF MEASURES TO ELEVATE THE WASTE COLLECTION DUMPSTER. SOLiD WASTE STORAGE AREAS SHOULD NOT BE LOCATED IN AREAS PRONE TO FLOODING OR PONDING AND SHOULD BE LOCATED AT LEAST 50 FT FROM STORM DRAINAGE SYSTEMS AND WATERWAYS. INSPECTION AND MAINTENANCE INSPECT AND VERIFY THAT ACTIVITY-BASED PRACTICES ARE IN PLACE PRIOR TO THE START OF CONSTRUCTION IN THAT AREA. INSPECT EACH PRACTICE WEEKLY TO VERIFY IMPLEMENTATION. INSPECT CONSTRUCTION WASTE COLLECTION AREA REGULARLY TO INSURE ALL WASTE MATERIALS ARE BEING DISPOSED OF PROPERLY. ARRANGE FOR REGULAR WASTE COLLECTION WITH A TRASH HAUUNG CONTRACTOR. CONCRETE AND MASONRY WASHOUT AREAS THE FOLLOWING STEPS WILL HELP REDUCE STORMWATER POLLUTION FROM CONCRETE AND MASONRY WASTES: DISCUSS THE CONCRETE MANAGEMENT TECHNIQUES DESCRIBED, SUCH AS HANDLING OF CONCRETE WASTE AND WASHOUT AREAS WITH THE READY -MIX CONCRETE SUPPLIER BEFORE ANY DELIVERIES ARE MADE. DISCUSS MASONRY WASTE MANAGEMENT TECHNIQUES WITH THE MASONRY CONTRACTORS FOR THE CONTROL OF CEMENT MIXER WASHOUT AREAS. INCORPORATE REQUIREMENTS FOR CONCRETE AND MASONRY WASTE MANAGEMENT INTO MATERIAL SUPPLIER AND SUBCONTRACTOR AGREEMENTS. STORE DRY AND LIQUID MATERIALS IN A COVERED AREA AWAY FROM DRAINAGE AREAS. PREVENT MASONRY SAND STOCKPILE FROM WASHING INTO STREETS, STORM DRAINAGE SYSTEMS, AND WATERWAYS. AVOID MIXING EXCESS AMOUNTS OF FRESH CONCRETE OR MORTAR. PERFORM WASHOUT OF CONCRETE TRUCKS OFFSITE OR iN DESIGNATED AREAS ONLY. PERFORM MORTAR MIXER WASHOUT IN ONE DESIGNATED AREA FOR THE DURATION OF THE PROJECT. DO NOT WASH OUT CONCRETE TRUCKS OR MORTAR MIXERS INTO STORM DRAINS, OPEN DiTCHES, STREETS, OR WATERWAYS. DO NOT ALLOW EXCESS CONCRETE OR MORTAR TO BE DUMPED ONSITE, EXCEPT IN DESIGNATED AREAS. FOR ONSITE WASHOUT AREAS: LOCATE WASHOUT AREA AT LEAST 50 FEET FROM STORM DRAINS, OPEN DITCHES, OR WATERWAYS. DO NOT ALLOW RUNOFF TO LEAVE THE DESIGNATED AREA BY CONSTRUCTING A TEMPORARY PIT OR BERMED AREA LARGE ENOUGH FOR LIQUID AND SOLID WASTE. -WASH OUT WASTES INTO THE TEMPORARY PIT WHERE THE CONCRETE CAN SET, BE BROKEN UP, AND BE DISPOSED OF PROPERLY. -AVOID CREATING UNNECESSARY RUNOFF BY NI WATER f 0 D CR DRAINING WA E FROM THE WASHOUT AREA INTO A BERMED, LEVEL AREA WHEN WASHING CONCRETE TO REMOVE FINE PARTICLES AND EXPOSE THE AGGREGATE. DO NOT WASH SWEEPINGS FROM EXPOSED AGGREGATE CONCRETE INTO THE STREET OR STORM DRAIN SYSTEM. COLLECT AND RETURN SWEEPINGS TO AGGREGATE BASE STOCKPILE OR DISPOSE OF PROPERLY. B4 SEDIMENT CONTROL MEASURES FOR SHEET FLOW AREAS: SEE SHEET C401 B5 SEDIMENT CONTROL MEASURES FOR CONCENTRATED FLOW AREAS: CONCENTRATED FLOW AREAS ARE INCORPORATED INTO THE STORM SEWER SYSTEM. INLETS ARE PROTECTED FROM SEDIMENT VIA SILT FENCING, AND INLET CONTROL MEASURES AS LISTED ON SHEET C401. B6 STORM SEWER INLET PROTECTION MEASURE LOCATIONS AND SPECIFICATIONS: SEE SHEETS C401 -C402 B7 RUNOFF CONTROL MEASURES: RUNOFF CONTROL MEASURES INCLUDE RIPRAP, SiLT FENCING, AND INLET CONTROL MEASURES AS SHOWN ON SHEETS C401 -C402. CONSTRUCTION DETAILS AND SPECIFICATIONS FOR THESE MEASURES ARE INCLUDED ON THIS SHEET. B8 STORMWATER OUTLET PROTECTION SPECIFICATIONS: SEE SHEETS C401 -C402 AND DETAIL EC-16 ON THIS SHEET. B9 GRADE STABILIZATION STRUCTURE LOCATIONS AND SPECIFICATIONS: PLEASE SEE SHEETS C401 -C4O2 B10 LOCATION. DIMENSIONS, SPECIFICATIONS AND CONSTRUCTION DETAILS FOR EACH STORMWATER QUALITY MEASURE: SEE SHEET C401 AND ASSOCIATED EROSION CONTROL DETAILS ON THIS SHEET. B11 TEMPORARY SURFACE STABILIZATION METHODS APPROPRIATE FOR EACH SEASON: SEE SHEET C401 AND IMPLEMENTATION AND MAINTENANCE PROCEDURE ON THIS SHEET B12 PERMANENT SURFACE STABILIZATION SPECIFICATIONS: SEE SHEET C401 IMPLEMENTATION AND MAINTENANCE PROCEDURE ON THIS SHEET e B13 MATERIAL HANDLING AND SPILL PREVENTION PLAN: EXPECTED CONSTRUCTION MATERIALS ON SITE MAY INCLUDE VEHICLE LUBRICANTS, OILS, VEHICULAR FUELS, CONCRETE WASH -OUT, MULCH, PAINTS AND SOLVENTS, PESTICIDES, HERBICIDES, FERTILIZER, AND TRASH. FUELS, OILS, AND GASOLINE CAN LEAK OR BE SPILLED FROM TRUCKS AND CONSTRUCTION EQUIPMENT WHICH COULD FIND THEIR WAY TO MUD CREEK. SMALL SPILLS AND LEAKS OF THESE MATERIALS ONTO NON -PAVED AREAS WILL BE SHOVELED INTO CONTAINERS OR DUMPSTERS FOR PROPER DISPOSAL. SPILLS OF PAINTS, SOLVENTS, FERTILIZER, AND OR PESTICIDES SHALL BE ADDRESSED PER MANUFACTURERS INSTRUCTIONS AND PER PRODUCTS MATERIAL SAFETY DATA SHEET (MSDS). CONCRETE WASH -OUT TO BE OPERATED IN DESIGNATED CONSTRUCTION STAGING AREA ONLY. FUELING TRUCKS WILL BE EQUIPPED WiTH SPILL PREVENTION KITS FOR SMALLER FUEL SPILLS. ALL VEHICULAR MAINTENANCE SHALL BE PERFORMED IN THE SAME DESIGNATED AREA THROUGHOUT THE CONSTRUCTION TIME FRAME. IF POSSIBLE, VEHICULAR MAINTENANCE SHALL BE DONE OFF -SITE AT FACILITIES THAT ARE DESIGNED TO HANDLE ANY MATERIAL SPILLAGE. THIS SHALL INCLUDE FUELING OF VEHICLES WHENEVER POSSIBLE. THE CARMEL CLAY FIRE DEPARTMENT (317) 571 -2600 OR 911, INDIANA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT, OFFICE OF EMERGENCY RESPONSE (800)- 233 -7745, SHALL BE NOTIFIED IMMEDIATELY FOR LARGER SPILLS OR LEAKS. THE NATIONAL RESPONSE CENTER (800)- 424 -8802 SHALL BE NOTIFIED AND PROVIDED WITH THE FOLLOWING INFORMATION: TIME OF SPILL LOCATION OF SPILL, MATERIAL, SOURCE OF SPILL, APPROXIMATE VOLUME AND LENGTH OF SPILLAGE, WEATHER CONDITIONS AT TIME OF SPILL, PERSONAL PRESENT AT TIME OF SPILL, AND ALL ACTION TAKEN FOR POST SPILL CLEANUP. CONTRACTOR SHALL CONTACT A WASTE RECOVERY AGENCY IMMEDIATELY FOR REMOVAL OF CONTAMINATES AND COORDINATION OF MONITORING THE SITE DURING CLEANUP UNTIL ALL OF THE HAZARDOUS MATERIAL HAS BEEN REMOVED. CONTRACTOR SHALL COOPERATE WiTH IDEM DURING AND AFTER THE SPILL TO INSURE ALL REQUIRED CLEANUP AND FILING REPORTS ARE PROPERLY SUBMITTED. THE DEVELOPER SHALL BE CONTINUALLY INFORMED OF ANY CONTAMINATION CONCERNS OCCURRING ON THE SITE. THE CONSTRUCTION MANAGER SHALL KEEP ON SITE A LIST OF QUALIFIED CONTRACTORS FOR SPILL REMEDIATION. ALL SITE PERSONNEL, INCLUDING MAINTENANCE EMPLOYEES, SHALL BE MADE AWARE OF PROPER SPILL PREVENTION AND REMEDIATION TECHNIQUES. ALL MATERIALS USED TO ABSORB SPILLS SHALL BE PROPERLY DISPOSED OF IN AN APPROVED MANOR WILL LOCAL AND STATE LAWS. DO NOT FLUSH SPILL MATERIALS WITH WATER UNLESS DIRECTED TO DO SO BY A GOVERNING AGENCY. IT IS IMPORTANT THAT ALL MANUFACTURER'S INSTRUCTIONS BE FOLLOWED WHEN USING OR APPLYING ALL FERTILIZERS, HERBICIDES, AND PESTICIDES. B14 MONITORING AND MAINTENANCE GUIDELINES FOR EACH PROPOSED POLLUTION PREVENTION MEASURE: REFER TO MAINTENANCE GUIDELINES SHOWN FOR EACH EROSION CONTROL MEASURE THIS SHEET. B15 EROSION AND SEDIMENT CONTROL SPECIFICATIONS FOR INDIVIDUAL BUILDING LOTS: NOT APPLICABLE ASSESSMENT OF STORMWATER POLLUTION PREVENTION POST CONSTRUCTION COMPONENT (SECTION C) e Cl DESCRIPTION OF POTENTIAL POLLUTANT SOURCES ASSOCIATED WITH THE PROPOSED LAND USE: POTENTIAL POLLUTANT SOURCES POST CONSTRUCTION INCLUDE DISTURBED SOILS FROM SUBSEQUENT DEVELOPMENT, FERTILIZERS, HERBICIDES, PESTICIDES AND OTHER LAWN TREATMENT APPLICATIONS, SPILLS OR OVERFILLS AT THE FUELING STATION, AND ASSORTED FUELS, OiLS AND LIQUIDS ASSOCIATED WiTH VEHICULAR TRAFFIC THROUGHOUT THE DEVELOPMENT. C2 SEQUENCE DESCRIBING STORMWATER QUALITY MEASURE IMPLEMENTATION: THE STORMWATER QUALITY MEASURE IMPLEMENTATION SHALL BE SUBSTANTIALLY COMPLETE UPON COMPLETION OF THE CONSTRUCTION ACTiTIES FOR THE PROPOSED PROJECT. ADDITIONAL STORMWATER QUALITY MEASURES WiLL BE IMPLEMENTED AT THE DEVELOPMENT OF SUBSEQUENT CONSTRUCTION PHASES. PRE CONSTRUCTION ACTIONS, CONSTRUCTION ACCESS, DEMOLITION, AND CLEARING AND GRUBBING WILL BEGIN THE FIRST WEEK OF CONSTRUCTION. STRIPPING TOPSOIL WILL BEGIN THE SECOND WEEK OF CONSTRUCTION. ROUGH GRADING WILL BEGIN THE THIRD WEEK. SURFACE DRAINAGE EXCAVATION WILL BEGIN THE FIFTH WEEK. UTILITY INSTALLATION WILL BEGIN SOON AFTER. TEMPORARY SEEDING WILL BE PLACED IMMEDIATELY AFTER COMPLETION OF A DISTURBED AREA, OR IMMEDIATELY PRIOR TO ANY PROLONGED BREAK (GREATER THAN SEVEN DAYS) FOR A GIVEN DISTURBED AREA. C3 DESCRIPTION OF PROPOSED POST CONSTRUCTION STORMWATER QUALITY MEASURES: POST CONSTRUCTION STORMWATER QUALITY MEASURES WILL CONSIST OF VEGETATIVE COVER ON THE DISTURBED AREAS, AN OIL WATER SEPERATOR CONNECTED TO THE INLET AT THE FUEL ISLAND, CATCH BASINS TO REDUCE SEDIMENT FROM PARKING AREAS, AND THE EXISTING RETENTION POND. C4 LOCATION, DIMENSIONS. SPECIFICATIONS, AND CONSTRUCTION DETAILS OF EACH STORMWATER QUALITY MEASURE: THE STORMWATER QUALITY MEASURES FOR POST CONSTRUCTION ACTMTES ARE INDICATED WITHIN THESE CONSTRUCTION DOCUMENTS. REFER TO SHEET C401 FOR EROSION CONTROL MEASURES TO BE IMPLEMENTED WITHIN THE PROJECT SITE, AND SHEET C501 FOR STORM SEWER IMPROVEMENTS INTENDED TO SERVE THE POST CONSTRUCTED AREA. DIMENSIONS, SPECIFICATIONS AND CONSTRUCTION DETAILS FOR THESE STORMWATER QUALITY MEASURES ARE INCLUDED WITHIN THE AFOREMENTIONED SERIES OF CONSTRUCTION DOCUMENTS. C5 DESCRIPTION OF MAINTENANCE GUIDELINES FOR POST CONSTRUCTION STORMWATER QUALITY MEASURES: BUILDING AND GROUNDS PERSONNEL WILL PROVIDE MAINTENANCE ACTIVITIES FOR THE POST CONSTRUCTION WATER QUALITY MEASURES. MAINTENANCE ACTMTIES WILL BE COMPLETED AS DESCRIBED BELOW. ALL INLET CASTINGS WILL BE INSPECTED MONTHLY. DEBRIS AND TRASH AROUND OR OBSTRUCTING INLETS WILL BE REMOVED. CATCH BASINS WILL BE INSPECTED QUARTERLY. TRASH, STICKS, DEBRIS, AND SEDIMENT WILL BE REMOVED TO ENSURE PROPER PERFORMANCE OF THE CATCH BASIN. GRASS AREAS SURROUNDING INLETS WILL BE MAINTAINED ON A REGULAR MOWING CYCLE. TRASH AND DEBRIS WILL BE REMOVED FROM SEEDED AND PAVED AREAS. DAMAGE TO INLET CASTINGS, INLET STRUCTURES, STORM STRUCTURES, OR CATCH BASINS SHOULD BE REPAIRED AS SOON AS POSSIBLE. 0: 11994t945011100401Cad1EVCDs1C402- C403.dwg, 10/2812004 3:34:24 PM, mwag z 0 0 L.LJ Drown Checked Approved Scale Sheet Dote to W 0: Z 0 C9 I- L 0 ce S 0 MAW DJO DAL 1 =30' CONSULTANTS w o: 0 z 0 z wz U) N Lx Lx D U) 0 a J z J U) 0 0 1 z W 2 z 0 fY w C402 08/30/04 Project number PIC 0940501 -101 CONTROL DETAILS