HomeMy WebLinkAboutC4.2a Erosion Control Details pg. 08z
0
a
U
L itt
W
Q
G
DRAWiNG NO. SHEET OF
C4.2a
TITLE:
EROSION CONTROL DETAILS
z
J
a
0
N
0
0
N
S
0
an
M
0
0
0
N
Z
N
0
rp
J
EROSION CONTROL NOTES:
1. CONSTRUCTION ACTIVITY SHALL CONSIST OF
UTILITIES, DRAINAGE SWALES, UNDERGROUND DETENTION
BASIN, BUILDING CONSTRUCTION AND PAVING
2. PRELIMINARY CONSTRUCTION SCHEDULE: :p EARTHWORK WORK
SHALL BEGIN IN THE FALL 2003. INSTALLATION
DRAINAGE STRUCTURES SHALL BE CONCURRENT WITH
EARTHWORK. SANITARY SEWER INSTALLATION SHALL
COMMENCE UPON COMPLETION OF ROUGH GRADING. WATER
MAINS AND REMAINING UTILITY INSTALLATION SHALL
COMMENCE UPON COMPLETION OF SANITARY SEWER
INSTALLATION. FINAL GRADING AND PAVING SHALL OCCUR
AFTER THE BUILDINGS ARE CONSTRUCTED. COMPLETION
OF THE PROJECT IS ANTICIPATED BY SPRING OF 2004. THIS
SCHEDULE IS SUBJECT TO CHANGE.
3. LAND ALTERATION WHICH STRIPS THE LAND OF
VEGETATION, INCLUDING REGRADING, SHALL BE DONE IN
A WAY THAT WILL MINIMIZE EROSION.
4. CONTRACTOR SHALL COMPLY WITH ALL STATE AND LOCAL
ORDINANCES THAT APPLY.
5. THIS PLAN SHALL NOT BE CONSIDERED ALL INCLUSIVE
AS THE CONTRACTOR SHALL TAKE ALL NECESSARY
PRECAUTIONS TO PREVENT SOIL SEDIMENT FROM LEAVING
THE SITE.
6. ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES
SHALL BE INSTALLED IF DEEMED NECESSARY BY ON SITE
INSPECTION.
7. SEDIMENT LADEN WATER SHALL BE DETAINED BY
EROSION CONTROL PRACTICES AS NEEDED TO MINIMIZE
SEDIMENTATION IN THE RECEIVING STREAM. NO STORM
WATER SHALL BE DISCHARGED FROM THE SITE IN A MANNER
THAT CAUSES EROSION AT THE POINT OF DISCHARGE.
8. WASTES AND UNUSED BUILDING MATERIALS SHALL
NOT BE ALLOWED TO BE CARRIED FROM THE SITE BY
STORM WATER RUNOFF. PROPER DISPOSAL OF ALL WASTES
AND UNUSED BUILDING MATERIALS IS REQUIRED.
9. SEDIMENT BEING TRACKED ONTO PUBLIC OR PRIVATE
ROADWAYS SHALL BE MINIMIZED. CLEARED SEDIMENT
SHALL BE RETURNED TO THE SITE FOR DISPOSAL.
10. SOIL WHICH HAS ACCUMULATED NEXT TO EROSION CONTROL
DEVICES SHALL BE COLLECTED AND RE- DISTRIBUTED ON
SITE AFTER EACH RAINFALL EVENT, AND AT LEAST ONCE A WEEK.
11. IF INSTALLATION OF STORM DRAINAGE SYSTEM SHOULD BE
INTERRUPTED BY WEATHER OR NIGHTFALL, THE PIPE ENDS SHALL
BE COVERED WITH FILTER FABRIC.
12. EXISTING VEGETATION SHALL BE PRESERVED IN AREAS
NOT DISTURBED BY CONSTRUCTION ACTIVITY.
13. THERE ARE NO BORROW AREAS.
14. ALL APPLICABLE EROSION CONTROL MEASURES SHALL
BE PLACED BEFORE ANY LAND DISTURBING ACTIVITIES.
15. SCHEDULE OF EROSION CONTROL ACTIVITIES:
a) INSTALL SAND BAGS AROUND INLETS IMMEDIATELY UPON
COMPLETION OF THE STRUCTURE. REMOVE SAND BAGS FOR
PAVING OPERATION. REPLACE SAND BAGS AFTER PAVING
IS COMPLETE. SAND BAGS SHALL REMAIN IN PLACE
UNTIL VEGETATION IS ESTABLISHED ON SEEDED
AREAS BEHIND THE CURB.
b) THE DURATION OF TIME WHICH AN AREA REMAINS
EXPOSED SHALL BE KEPT TO A PRACTICAL MINIMUM. THE
AREA SHALL BE STABILIZED AS SOON AS POSSIBLE.
CHING SHALL BE USED
TEMPORARY VEGETATION OA M FLPERMANENT VEGETATION ON
TO PROTECT EXPOSED ARES
CANNOT BE SEEDED WITHIN 14 DAYS OR ACTIVITY
CEASES FOR MORE THAN 21 DAYS OR AS DIRECTED BY
THE ENGINEER.
c) TOPSOIL REPLACEMENT SHALL TAKE PLACE FROM
MARCH 1 TO OCTOBER 31. STOCKPILE TOPSOIL AT ALL
OTHER TIMES OF THE YEAR. PERMANENT AND FINAL
VEGETATION AND STRUCTURAL EROSION CONTROL DEVICES
SHALL BE INSTALLED WITHIN SEVEN (7) DAYS AFTER FINAL
GRADING OR AS SOON AS POSSIBLE.
16. CONTRACTOR SHALL BE RESPONSIBLE OF ENVIRONMENTAL
OF INTENT WITH THE INDIANA DEPARTMENT
MANAGEMENT
17. APPLY FERTILIZER AT A RATE ADEQUATE TO PROVIDE 1 LB. OF
ACTUAL NITROGEN PER 1,000 SQUARE f EUTRA CHARACTER CONSISTING
GRADE COMPLETE FERTILIZER
OF FAST AND SLOW RELEASE NITROGEN, 50 PERCENT DERIVED FROM
NATURAL ORGANIC SOURCES OF UREA -FORM, PHOSPHOROUS, AND
IN FOLLOWING COMPOSITION:
a) FERTILIZER FOR LAWNS: PROVIDE A FAST RELEASE
FERTILIZER WiTH A COMPOSITION OF 1 LB PER 1,000 SQ. FT. OF
ACTUAL NITROGEN, 4 PERCENT PHOSPHOROUS, AND 2 PERCENT
POTASSIUM BY WEIGHT
b) SLOW- RELEASE FERTILIZER FOR TREES AND SHRUBS:
GRANULAR FERTILIZER CONSISTING OF 50 PERCENT WATER INSOLUBLE
NITROGEN, PHOSPHOROUS AND POTASSIUM MADE UP OF A
COMPOSITION BY WEIGHT OF 5 PERCENT
18. ADD LIME TO TOPSOIL TO OBTAIN A pH RANGE OF
6.0 TO 7.0. LIME SHALL BE ASTM C 602, CLASS T, AGRICULTURAL
LIMESTONE CONTAINING A MINIMUM OF 80 PERCENT CALCIUM CARBONATE
EQUIVALENT, WITH A MINIMUM 99 PERCENT PASSING A NO. 8 (2.36 mm)
SIEVE AND A MINIMUM 75 PERCENT PASSING A NO. 50 (250 MICROMETER)
SIEVE.
19. CONSTRUCTION TRAFFIC SHALL ENTER THE SITE AT DRIVES WHICH ARE
CURRENTLY PAVED.
MATERIAL HANDLING AND SPILL PREVENTION PLAN
This Material Handling and Spill Prevention plan is designed to reduce or prevent the pollution
of soil and stormwater by the proposed construction activities. The contractor and
subcontractors shall make a conscious effort to eliminate opportunity for contaminating spills
and reduce the amount of construction waste generated.
Hazardous Construction Chemicals and Solvents
Potential Pollutants
Chemicals, paints, solvents, fertilizers and other toxic or hazardous materials
Implementation Measures
Whenever possible the use of hazardous materials and the generation of
hazardous wastes shall be minimized
All Hazardous waste materials shall be disposed of in the manner
specified by federal, state, or local regulations.
Except during application, hazardous chemical containers shall be kept in
trucks or in bermed areas within covered storage facilities.
Runoff containing such materials shall be collected, removed from the site
and disposed of in accordance with the federal, state, and local regulations.
The operator following on -site location of the facility shall indicate the
location of any hazardous waste storage and disposal areas on the
tormwater pollution prevention plan.
The location of any hazardous waste storage areas shall not be located
within 50 ft of a drainage feature or watercourse.
Inspection and Maintenance
A foreman or supervisor should be designated in writing to oversee,
enforce and instruct construction workers on proper hazardous waste
procedures.
The designated individual shall inspect the hazardous chemical storage
and disposal areas on a daily bases to ensure they are appropriately
constructed and functioning properly.
Arrange for regular collection and proper disposal of the hazardous
materials.
Solid Construction Waste Disposal
Potential Pollutants
Solid waste generated from the demolition of existing structures, trees,
shrubs and any site clearing activities
Packaging materials including wood, paper, plastic, styrofoam and other
materials used for packaging.
Surplus building materials including but not limited to scrap metals,
rubber, plastic and masonry products.
Wastes from workers including but not limited to food and beverage
containers, paper and plastic bags, wrappers, and cigarettes.
Construction wastes including brick, mortar, timber, steel and metal
scraps, pipe and electrical scraps, and any other solid material used during
construction.
Implementation Measures
Appropriate waste collection areas shall be located on site, and indicated
in the Pollution Prevention Plan.
There shall be an adequate amount of watertight collection containers in
each of the waste collection areas.
Inform all contractors and sub contractors of the location of the waste
collection areas and of their responsibility to appropriately dispose of solid
wastes in these containers.
MONITORING AND REPORTING
THE CONTRACTOR SHALL IMPLEMENT A SELF MONITORING PROGRAM.
THE FOLLOWING ITEMS ARE REQUIRED:
1. A TRAINED PERSON SHALL PERFORM A WRITTEN EVALUATION OF THE
PROJECT SITE BY THE END OF THE NEXT BUSINESS DAY FOLLOWING
EACH MEASURABLE STORM EVENT AND AT A MINIMUM OF ONE TIME
PER WEEK.
2. THE EVALUATION MUST ADDRESS THE MAINTENANCE OF EXISTING STORM
WATER QUALITY MEASURES TO ENSURE THEY ARE FUNCTIONING PROPERLY
AND IDENTIFY ADDITIONAL MEASURES NECESSARY TO REMAIN IN COMPLIANCE
WITH ALL APPLICABLE STATUTES AND RULES.
3. THE WRITTEN EVALUATION REPORT MUST INCLUDE:
a) THE NAME OF THE INDIVIDUAL PERFORMING THE EVALUATION
b) THE DATE OF THE EVALUATION
c) PROBLEMS IDENTIFIED AT THE PROJECT SITE
d) DETAILS OF CORRECTIVE ACTIONS RECOMMENDED AND COMPLETED
e) ALL EVALUATION REPORTS FOR THE PROJECT SITE MUST BE MADE
AVAILABLE TO THE INSPECTING AUTHORITY WITHIN FORTY -EIGHT
HOURS OF A REQUEST
SEQUENCE DESCRIBING STORM WATER QUALITY MEASURE
IMPLEMENTATION RELATIVE TO LAND DISTURBING ACTIVITIES
1. BEFORE CONSTRUCTION, EVALUATE, MARK, AND PROTECT IMPORTANT TREES.
2. INSTALL CONSTRUCTION ENTRANCE AND STAGING AREA.
3. INSTALL PERIMETER SILT FENCES.
4. INSTALL OFFSITE STORM SEWER.
5. INSTALL TEMPORARY OR FINAL SEEDING ON DISTURBED AREAS FOR THE
OFFSITE STORM SEWER.
6. INSTALL SEDIMENT BASIN AND THE DIVERSION SWALE ALONG THE WEST
PROPERTY LINE TO SEDIMENT BASIN AS SHOWN.
7. PLACE THE REMAINDER OF THE FILL ON -SITE AND ESTABLISH ROUGH GRADE.
8. INSTALL TEMPORARY SEEDING ON THE FUTURE BUILDING PADS AND DETENTION POND.
9. BEGIN CONSTRUCTION ON THE PROPOSED BUILDING. INSTALL STONE STAGING
AREA PRIOR TO BUILDING CONSTRUCTION.
10. INSTALL PROPOSED STORM SEWER AND PROVIDE SEDIMENT PROTECTION AT EACH
INLET AT TIME OF CONSTRUCTION.
11. INSTALL REMAINDER OF UTILITIES.
12. ESTABLISH FINISH GRADE FOR THE PARKING LOT.
13. INSTALL CURBS, SIDEWALKS AND ASPHALT PARKING LOT.
14. INSTALL TEMPORARY OR PERMANENT SEEDING ON ALL DISTURBED AREAS
NOT CURRENTLY BEING WORKED FOR THE BUILDING CONSTRUCTION.
15. ESTABLISH FINISH GRADE AROUND BUILDINGS.
16. INSTALL PERMANENT SEEDING OVER ENTIRE SITE.
17. MAINTAIN ALL EROSION AND SEDIMENT CONTROL PRACTICES UNTIL ALL
DISTURBED AREAS ARE STABILIZED.
Provide an adequate number of lids or covers that can be placed over the
containers to keep rain out and to prevent loss of wastes due to wind.
Collect site trash daily and place in the appropriate containers.
Promptly remove solid wastes in erosion and sediment control devices.
No toxic liquid wastes such as sued oils, solvents, and paints or chemicals
such as acids, pesticides, additives, or curing compounds shall be disposed
of in dumpsters designed for construction debris.
Dumpsters shall be emptied by an approved waste hauler and shall not be
hosed down, or cleaned out on site.
Arrange for regular collection of the waste from the containers and ensure
that no solid wastes are placed outside of the containers.
Immediately clean up any wastes spilled from the containers.
Ensure that construction waste is collected, removed, and disposed of only
at the disposal areas provided. Solid waste storage areas shall be located
no closer than 50 ft from drainage facilities and watercourses and should
not be located in areas prone to flooding or ponding.
inspection and Maintenance
A foreman or supervisor should be designated in writing to oversee,
enforce and instruct construction workers on proper solid waste
procedures.
The designated individual shall inspect and verify that the collection
facilities are appropriately established prior to the start of construction
activities. The waste collection facilities shall be inspected on a daily
basis to verify compliance with this pollution prevention plan.
Arrange for regular waste collection.
Equipment Fueling and StoraaeAreas
Potential Pollutants
Spilled fuel, hydraulic oils and lubrication during equipment refueling, leaking
equipment
implementation Measures
The use of offsite fueling stations shall be encouraged whenever possible.
Construction equipment shall be properly inspected and maintained to
ensure it is not leaking. Any leaking equipment shall be repaired before
its use on site.
If refueling activities will occur onsite, and bermed refueling area shall be
established no closer than 50 ft from a drainage facility or watercourse.
All fuel storage containers shall be located with in the bermed refueling
area.
All individuals working on the site shall be notified of the location of the
refueling area and that refueling is permitted only in this area.
The "topping -off" of fuel tanks shall be discouraged.
Absorbent spill cleanup materials and spill kits shall be supplied in the
refueling areas and on refueling trucks. All spent absorbent or materials
used in cleaning spilled fuels shall be appropriately disposed of according
to IDEM Regulations.
Drip pans and absorbent pads shall be used during refueling activities that
are not performed over impermeable surfaces.
Employees and subcontractors shall be properly trained in fueling and
cleanup procedures.
Nozzles used in vehicle and equipment fueling should be equipped with an
automatic shutoff to control drips. Fueling operations hall not be left
unattended.
ACTION PLAN FOR CONTAMINATING SPILL
In the event of a contaminating spill. the following actions shall be taken
Any contaminating spill shall be immediately cleaned up according to
IDEM and USEPA regulations and the contaminated materials and soil
shall be properly disposed of at an approved facility.
Contact the Carmel fire department at (317) 571 -2600.
if the contaminated material or runoff containing the contaminating
material enters the legal drain the Hamilton County Surveyor shall
be contacted at (317) 776 -8495.
IDEM shall be contacted at (888) 233 -7745 in the event of a
contaminating spill in accordance to IDEM title 327IAC 2 -61.
The project manager for Lauth Property Group shall be notified of
any and all spills involved with the construction of this project.
WETLAND SEED MIXTURE
Seed Mixture D. This seed mixture is intended for ditch
situations which experience seasonal to chronic saturated
soils. This seed mixture shall be used on maintenance
contracts or where otherwise specified. This mixture shall be
applied at the rate of 16.5 kg /ha (14 lb 12 oz per acre). The
mix shall be composed of 28 g (1 oz) Fowl Mana Grass, 85 g
(3 oz) wetland Carex species, 56 g (2 oz) Rice Cut Grass, 56 g
(2 oz) Bullrush, 56 g (2 oz) Leptochloa fasicularis, 56 g (2 oz)
Barnyard Grass, 56 g (2 oz) Prairie Wild Rye, 4.5 kg (10 lb)
perennial ryegrass, 1 kg (2 Ib) Jasper Red Fescue, 56 g (2 oz)
"Fults" Puccinella Distans, and 0.5 kg (1 Ib) Redtop. If certain
species in this mix are unavailable, substitutions may be
submitted for approval. The mix shall be applied as specified
per hectare (acre). The method of planting shall be by means
of hydroseeding or by means of a hand method with a minimal
amount of mulch applied in a separate operation. Fertilizer
shall not be added to this seed mixture.
Federal, state, and local requirements should be observed for any
stationary above ground storage tanks.
In the event of a spill, contact the local fire department at (317) 776 -6336.
inspection and Maintenance
Vehicles and equipment should be inspected each day for leaks. Leaks
shall be repaired immediately or the equipment shall be removed from the
site.
Appropriate and ample spill cleanup materials and supplies shall be kept
in the designated refueling areas.
Any spill shall be immediately cleanup up and the contaminated materials
and soil shall be properly disposed of.
Concrete Washout
Potential Pollutants
Excess concrete material, portland cement, chemical additives, etc.
implementation Measures
All concrete contractors and suppliers shall be informed of the standard
concrete washing procedures and the location of the concrete washout
area.
A bermed concrete washout area shall be established not less than 50 feet
from a drainage facility or watercourse.
The location of the concrete washout area shall be indicated on the
pollution prevention plan.
A temporary pit shall be established with in the concrete washout area
where concrete can set, be broken up, and disposed of properly.
The washing of concrete trucks and equipment shall only occur in this
designated concrete washout area.
No excess concrete shall be disposed of on site unless inside the concrete
washout area.
Inspection and Maintenance
The project superintendent or foreman shall be made responsible to ensure
that concrete washout areas are properly constructed and that concrete
washing activities only occur in these areas.
The temporary pit shall be cleaned and the material properly disposed of
before the pit is allowed to over flow.
Sanitary /Septic
Contractors and subcontractors must comply with all state and local sanitary sewer, portable
toilet or septic system regulations. Sanitary facilities shall be provided at the site by each
contractor or subcontractor throughout construction activities. The sanitary facilities should be
utilized by all construction personnel and be serviced regularly. All expenses associated with
providing sanitary facilities are the responsibility of the contractors and subcontractors. The
location of any sanitary facilities should be indicated on the stormwater pollution prevention plan
by the operator following on -site location of said facilities.
Dust Control /Off -Site Vehicle Tracking
During construction, water trucks should be used, as needed, by each contractor or subcontractor
to reduce dust. After construction, the site should be stabilized to reduce dust.
Construction traffic should enter and exit the site at a Construction Entrance with a rock pad or
equivalent device. The purpose of the rock pad is to minimize the amount of soil and mud that is
tracked onto existing streets. If sediment escapes the construction site, offsite accumulations of
sediment must be removed at a frequency sufficient to minimize offsite impacts.
Water Source
Water used to establish and maintain grass, to control dust, and for other construction purposes
must originate from a public water supply or private well approved by the State or local health
department.
La
a
I-
a
La
z
v
U
z
J h-
cn
c z
O G.)
z
0
S
0
W
I--
7
W
8
m
z
I N 2004.0387.071.PLAN.DWG