HomeMy WebLinkAboutS101 General Structural NotesCOORDINATION WITH
OTHER TRADES
1. The Contractor shall coordinate and check all dimensions
relating to Architectural finishes, mechanical equipment and
openings, elevator shafts and overrides, etc. and notify the
Architect /Engineer of any discrepancies before proceeding with
any work in the area under question.
2. The Structural Drawings shall be used in conjunction with the
Drawings of all other disciplines and the Specifications. The
Contractor shall verify the requirements of other trades as to
sleeves, chases, hangers, inserts, anchors, holes, and other
items to be placed or set in the Structural Work.
3. There shall be no vertical or horizontal sleeves set, or holes
cut or drilled in any beam or column unless it is shown on the
Structural Drawings or approved in writing by the Engineer of Record.
Verify locations and dimensions of mechanical and electrical openings
through supported floors and walls shown on the Structural Drawings
with the Mechanical and Electrical Contractors.
5. Do not install conduit in slabs on grade or concrete walls unless
explicitly shown or noted on the Structural Drawings.
6. Do not suspend any items, such as ductwork, mechanical or electrical
fixtures, ceilings, etc. from wood deck.
7. The Mechanical Contractor shall notify the Engineer of Record of any
Mechanical Unit supported by the structure not shown on the Structural
Drawings, whose weight is greater than 500 lbs.
8. If drawings and specifications are in conflict, the most stringent restrictions
and requirements shall govern.
GENERAL NOTES
The Contractor shall be responsible for complying with all safety
precautions and regulations during the work. The Engineer will not
advise on, nor issue direction as to safety precautions and programs.
2. The Structural Drawings herein represent the finished structure. The
Contractor shall provide all temporary guying and bracing required to
erect and hold the structure in proper alignment until all Structural
Work and connections have been completed. The investigation, design,
safety, adequacy and inspection of erection bracing, shoring, temporary
supports, etc. is the sole responsiblity of the Contractor.
3. The Engineer shall not be responsible for the methods, techniques
and sequences of procedures to perform the Work. The supervision of
the Work is the sole responsibility of the Contractor.
4. Drawings indicate general and typical details of construction. Where
conditions are not specifically shown, similar details of construction
shall be used, subject to approval of the Engineer.
5. All structural systems which are to be composed of components to
be field erected shall be supervised by the Supplier during manu-
facturing, delivery, handling, storage, and erection in accordance
with the Supplier's instructions and requirements.
6. Loading applied to the structure during the process of construction
shall not exceed the safe load- carrying capacity of the structural
members. The live loading used in the design of this structure are
indicated in the "Design Criteria Notes Do not apply any construction
loads until structural framing is properly connected together and until
all temporary bracing is in place.
7. All ASTM and other referenced standards and codes are for the latest
editions of these publications, unless otherwise noted.
8. Shop Drawings and other items shall be submitted to the Engineer for
review prior to fabrication. All Shop Drawings shall be reviewed by
the Contractor before submittal. The Engineer's review is to be for
conformance with the design concept and general compliance with the
relevant Contract Documents. The Engineer's review does not relieve
the Contractor of the sole responsibility to review, check, and
coordinate the Shop Drawings prior to submission. The Contractor
remains solely responsible for errors and omissions associated with
the preparation of Shop Drawings as they pertain to member sizes,
details, dimensions, etc.
9. Submit Shop Drawings in the form of blueline /blackline prints (min. 2 sets/
max. 5 sets) and one reproducible blackline or sepia copy. In no case
shall reproductions of the Contract Documents be used as shop drawings.
As a minimum, submit the following items for review:
A. Concrete Mix Design(s).
B. Reinforcing Steel Shop Drawings.
10. Contractors shall visit the site prior to bid to ascertain conditions which may
adversely affect the work or cost thereof.
11. No structural member may be cut, notched, or otherwise reduced in strength
without written direction from the Engineer of Record.
12. When modifications are proposed to structural elements under the design and
certification of a Specialty Engineer, written authorization by the Specialty
Engineer must be obtained and submitted to the Engineer of Record for review,
prior to performing the proposed modification.
EXISTING CONSTRUCTION
1. The Contractor shall field verify the dimensions, elevations, etc. necessary for the
proper construction and alignment of the new portions of the work to the existing
work. The Contractor shall make all necessary measurements for fabrication and
erection of the structural members. Any discrepancy shall be immediately brought
to the attention of the Engineer of Record.
2. Before proceeding with any work within the existing facility, the Contractor shall
familiarize himself with existing structural and other conditions. Any shoring shown
or noted on the Plans is a partial and schematic representation of that required.
It shall be the Contractor's responsibility to provide all necessary bracing, shoring,
and other safeguards to maintain all parts of the work in a safe condition during
the progress of demolition and construction, and to protect from damage those
portions of the existing work which are to remain. Shoring shall remain in place
until the structural work is complete, has been inspected by the Testing Agency,
and is certified to be in substantial compliance with the Contract Documents.
3. When required by the Specifications or by Plan Note, the Contractor shall submit
for the Engineer of Record's review, a "Proposed Shoring Plan including, but not
limited to: plans, sections, details, notes, description of proposed sequence of
work, and calculations prepared by, or under the supervision of a Professional
Engineer (Specialty Engineer). The Specialty Engineer shall be registered in the
State where the project is located.
4. Welding to and within an existing facility presents potential hazards including:
A. Fire Hazard Due to the existing construction and building contents.
B. Structural Liquefaction Due to welding across the full section of the
structural members.
Recommendations to prevent these hazards include:
A. Fire Hazard Protect existing combustibles prior to welding. Keep a
separate watchman and several fire extinguishers on hand.
B. Structural Liquifaction weld in small increments. Allow welds to harden
before continuing to the next increment.
C. Do not leave the site until satisfied that no fire hazard exists.
D. Preference should be given to the use of beam clamps, mechanical
fasteners, or bolted connections in lieu of welding within existing facilities,
whenever possible. Do not field -drill existing structural members without
the written permission of the Engineer of Record.
FOUNDATIONS
1. Proofroll slab on grade areas with a medium weight roller or
other suitable equipment to check for pockets of soft material
hidden beneath a thin crust of better soil. Any unsuitable
materials thus exposed should be removed and replaced with
compacted, engineered fill as outlined in the specifications.
Proofrolling operations shall be monitored by the Testing Agency.
2. All engineered fill beneath slabs and over footings should
be compacted to a dry density of at least 93% of the Modified
Proctor maximum dry density (ASTM D- 1557). All fill which shall
be stressed by foundation loads shall be approved granular materials
compacted to a dry density of at least 95% (ASTM D- 1557).
Coordinate all fill and compaction operations with the Specifications
and the Subsurface Investigation.
3. Compaction shall be accomplished by placing fill in approx. 8"
lifts and mechanically compacting each lift to at least the
specified minimum dry density. For large areas of fill, field density tests
shall be performed for each 3000 square feet of building area for each lift
as necessary to insure adequate compaction is being achieved.
4. Column footings and wall footings to bear on firm natural soils or well
compacted engineered fill with an assumed allowable bearing pressure of
1,500 psf.
It is essential that the foundations be inspected to ensure that all
loose, soft or otherwise undesirable material (such as organics, existing
fill, etc.) is removed and that the foundation will bear on satisfactory
material. The Testing Agency shall inspect the subgrade and
perform any necessary tests to insure that the actual bearing
capacities meet or exceed the design capacities. The Testing Agency
shall verify the bearing capacity at each spread column footing and
every 10 feet on center for strip footings prior to placement of concrete.
5. Place footings the same day the excavation is performed. If this
is not possible, the footings shall be adequately protected
against any detrimental change in condition, such as from
disturbance, rain and freezing.
6. It is the responsibility of the Contractor and each Sub
Contractor to verify the location of all utilities and services
shown, or not shown; and establish safe working conditions before
commencing work.
7. The Contractor shall layout the entire building and field verify
all dimensions prior to excavation.
REINFORCED MASONRY NOTES
1. All construction of reinforced masonry walls to be in accordance
with the Building Code Requirements For Concrete Masonry
Structures (A.C.I. 530 -05) and commentary.
A) f'm 2000 p.s.i.
B) Maximum height of masonry lift: 5'- 0"
C) Maximum height of grout lift: 5'- 0"
D) See specifications for additional masonry wall information.
2. CONCRETE BLOCK: Minimum compressive test strength on the net
cross sectional area: 2500 p.s.i.
3. MORTAR: Type S required.
4. GROUT: A.S.T.M. C476, 2500 p.s.i. with a slump of 8" min. and
10" max.
5. REINFORCING: fy 60,000 p.s.i. with a min. lap of 48 diameters.
CONCRETE REINFORCING
1. Reinforcement, other than cold drawn wire for spirals and welded
wire fabric, shall have deformed surfaces in accordance with
A.S.T.M. A305.
2. Reinforcing steel shall conform to ASTM A615, Grade 60, unless noted.
3. Welded wire fabric shall conform to ASTM A185, unless noted.
4. Where hooks are indicated, provide standard hooks per A.C.I. and
C.R.S.I. for all bars unless other hook dimensions are shown on
the plans or details.
5. Reinforcement in footings, walls and beams shall be continuous. Lap
bars a minimum of 36 diameters, unless noted otherwise.
6. Reinforcement shall be supported and secured against displacement
in accordance with the Concrete Reinforcing Steel Institute's "Manual of
Standard Practice
7. Details of reinforcing steel fabrication and placement shall conform to
ACI 315 "Details and Detailing of Concrete Reinforcement" and
ACI 315R "Manual of Engineering and Placing Drawings for Reinforced
Concrete Structures unless otherwise indicated.
8. Provide standees for the support of top reinforcement for footings,
pile caps, and mats.
9. Provide individual high chairs with support bars, as required for the
support of top reinforcement for supported slabs. Do not provide
standees.
10. Field bending of reinforcing steel is prohibited, unless noted on drawings.
11. Minimum concrete cover over main reinforcing steel shall be as
follows: 3" at foundations, 2" at all dirt faces of walls and
beams exposed to the weather, 1 -1/2" at all pier and column ties,
and 3/4" at other wall faces and in structural slabs unless shown
or noted otherwise.
DRILLED -IN DOWELS
ANCHOR BOLTS/RODS
1. All reinforcing steel and threaded rod anchors to be installed
in 2 -part chemical anchoring system shall be treated as follows:
A) Drill holes larger than bar or rod to be embedded. Coordinate
hole diameter with Manufacturer's recommendations.
B) Holes must be cleaned and prepared in accordance with
Manufacturer's recommendations.
C) When reinforcing steel is encountered during drilling for installation of
anchors; stop drilling, use a sensor to locate the reinfocing in the
surrounding area and install anchor(s) as close as possible to the original
location. Contact the Engineer of Record for direction when the revised
location is more than 2" from the original location, or when the original
function of the anchorage is significantly altered. When in doubt,
contact the Engineer of Record for direction.
D) Drill the hole a minimum of 15 bar diameters or as shown on
the plans.
F) Use a two -part adhesive anchoring system, Hilti HY -150, or approved equal.
G) For anchorage into hollow substrate, use Hilti HY -20 system, or approved equal.
H) Reinforcing steel dowels shall be ASTM A615, Grade 60, unless noted.
I) Anchor rods shall be ISO 898 5.8 (Hilti HAS -E), unless noted. Provide
finish as noted on the Drawings. If not noted, provide hot -dip galvanized
finish for interior applications. Provide stainless steel finish for all exterior
applications, unless noted.
DESIGN CRITERIA
1. The building was designed in accordance with the 2008 Indiana Building Code,
for Seismic Design Catagory B. Wind pressures were computed using 90 mph
Basic Wind Speed, Exposure B.
2. The following live loads were used in the design of this structure:
A. Roof: 25 psf drift loads
3. If drawings and specifications are in conflict, the most stringent restrictions
and requirements shall govern.
4. All Contractors are required to coordinate their work with all disciplines to
avoid conflicts. The mechanical, electrical and plumbing aspects are not in the
scope of these drawings. Therefore, all required materials and work may not be
indicated.
CONCRETE NOTES
1. Details of fabrication of reinforcement, handling and placing of
the concrete, construction of forms and placement of reinforcement
not otherwise covered by the Plans and Specifications, shall
comply with the A.C.I. Code Requirements of the latest revised
date.
2. Cold weather concreting shall be in accordance with ACI 306.
3. Hot weather concreting shall be in accordance with ACI 305.
4. Unless otherwise noted in the schedules or details, the minimum 28
day compressive strength of the concrete shall be 4000 p.s.i. for
all parts of the structure except for column and wall footings
which shall be 3000 p.s.i. All concrete shall be regular weight
concrete, unless otherwise noted.
5, A certified Testing Agency shall be retained to perform industry
standard testing including measurement of slump, air temperature,
concrete cylinder testing, etc. to ensure conformance with the
Contract Documents. Submit reports to Architect /Engineer.
6. All concrete exposed to the weather shall be air entrained. All
other concrete may be air entrained or non air entrained at the
contractor's option. For surface finishes and other requirements,
refer to the specifications.
7. Finishing of Slabs: After screeding, bull floating and floating operations
have been completed, apply final finish as indicated below, and as
described in Specification Section 03300 of the Project Manual.
A.
B.
C.
D.
Floor Slabs
Ramps, Stairs Sidewalks
Surfaces to Receive Topping Slab
Surfaces to receive thick set mortar
beds or similar cementitious materials
Hard Trowel Finish
Broom Finish
None -Float Finish
None -Float Finish
Floor Tolerances: See the Specifications for specified Ff and Fl
tolerances. Ff and Fl testing shall be performed by the Testing Agency
in accordance with ASTM E -1155. Results, including acceptance or
rejection of the work will be provided to the Contractor and the
Architect /Engineer within 48 hours after data collection. Remedies
for out -of- tolerance work shall be in accordance with the Specifications.
When approved by the Engineer of Record, measurement of the gaps
beneath a 10 foot straight edge may be used in lieu of Ff and Fl
testing. Approval must be obtained in writing prior to the beginning of
concrete operations.
8. Finishing of Formed Surfaces: Finish formed surfaces as indicated below,
and as described in Specification Section 03300 of the Project Manual.
A. Sides of Footings Pile Caps
B. Sides of Grade Beams
C. Surfaces not exposed to public view
D. Surfaces exposed to public view
LINTEL SCHEDULE
1. Where lintels are not specifically shown or noted on the
Structural or Architectural Drawings, provide the following
lintels over all openings and recesses in both interior and
exterior non -load- bearing walls.
A) Brick: Masonry Opening Angle Size
Upto5' -0" L4x4x5/16
5-1" to 7'-0" L6 x 4 x 5/16
Over 7'-1" L7 x 4 x 3/8
All angles are LLV (long leg vertical) unless noted otherwise.
Provide 1" bearing per foot of span each end, min. 8
Rough Form Finish
Rough Form Finish
Rough Form Finish
Smooth Form Finish
9. The Contractor shall consult with the Engineer before starting
concrete work to establish a satisfactory placing schedule and to
determine the location of construction joints so as to minimize
the effects of shrinkage in the floor system.
10. Sawn or tooled control /contraction joints shall be provided in
all slabs on grade. For a framed structure, joints shall be
located on all column lines. If the column spacing exceeds
20' -0 provide intermediate joints. Exterior slabs, and interior
slabs without columns shall have joints spaced a maximum of
15' -0" apart. Layout joints so that maximum aspect ratio
(ratio of long side to short side) does not exceed 1.5.
11. Where vinyl composition tile, thin -set epoxy terrazzo, or other similar
material is the specified finish floor material, the Contractor shall
coordinate the location of control /contraction and construction joints
with the finished floor contractor. Submit a dimensioned plan
showing joint locations and proposed sequence of floor pours.
12. See Architectural Drawings for exact locations and dimensions of
recessed slabs, ramps, stairs, thickened slabs, etc. Slope slabs
to drains where shown on the Architectural and Plumbing Drawings.
13. Joints in slabs to receive a finished floor may remain unfilled, unless
required by the finish flooring contractor. All exposed slabs shall
be filled with sealant specified in Divison 7, or as follows: All slabs
in industrial, manufacturing, or warehouse applications subject to
wheeled traffic shall be filled with specified epoxy resin sealant,
all other joints shall be filled with specified elastomeric sealant.
Defer filling of joints as long as possible, preferably a minimum of
4 to 6 weeks after the slab has been cured. Prior to filling, remove
All debris from the slab joints, then fill in accordance with the
manufacturer's recommendations.
14. Sidewalks, drives, exterior retaining walls, and other site concrete
are not indicated on the Structural Drawings. Refer to the Site /Civil
and Architectural Drawings for locations, dimensions, elevations,
jointing and finish details.
WOOD STRUCTURAL DATA
1. All interior exterior wall studs
shall be #2 Spruce Pine Fir Northern per N.L.G.A. or better:
Fb 875 psi
Ft 450 psi
Fv 70 psi
Fc (PER) 425 psi
Fc (PAR) 1,150 psi
E 1,400,000 psi
2. All rafters, ceiling joists, ridge and valley boards, headers and
misc. blocking shall be #2 Hem -Fir, or better:
(alternate: Southern Yellow Pine).
Fb
Ft
Fv
Fc I
Fc I
E
PER
PAR
1,000 psi
575 psi
75 psi
370 psi
1,450 psi
1,600,000 psi
3. All laminated veneer lumber (L.V.L.) shall be manufactured by
Trus -Joist McMillan, Alpine Structures, Inc., Or Mitek Wood Products:
Fb 2,900 psi
Fv 285 psi
E 2,000,000 psi
NOTES:
1. Refer to specifications for additional information.
2. Alternate grades and species may be proposed. Any substitution
must be approved in writing by the architect engineer.
3. Allowable stresses for dimensional lumber listed above are for 2' -4" thick x 2"
wider. Size adjustment factors (Cf), repetitive member
factor (Cr), duration of load factor (Cd), etc. have been applied
in the design of structural elements.
PLYWOOD SHEATHING NOTES
1. All plywood construction shall be in accordance with the
American Plywood Association (APA) specifications.
2. All roof panel sheathing shall be 19/32" Exposure 1
APA -rated sheathing. Suitable edge support shall be provided
by use of panel clips or blocking between framing unless otherwise
noted. Connect roof sheathing with 8d common nails spaced 6" o..c.
at supported edges and 12" o.c. at intermediate supports.
3. All wall panel sheathing shall be 7/16" Exposure 1
APA -rated sheathing, unless otherwise indicated. Connect wall
sheathing with 8d common nails spaced 6" o.c. at supported panel
edges and 12" o.c. at intermediate supports, unless otherwise noted.
4. Unless otherwise noted or shown, install plywood sheathing with the
long dimension of the panel across supports and with panel
continuous over two or more spans. Stagger panel end joints. Allow
1/8" spacing at panel ends and edges unless otherwise recommended
by the sheathing manufacturer.
5. All nailing shall be carefully driven and not overdriven. The use of
staples and pnuematic nail guns are prohibited from use.
6. Provide 2X blocking at unsupported panel edges as follows:
Roofs and floors only where indicated on plans /sections.
Walls only where indicated on plans /sections.
CSO Arc]
ARCHITECTURE IN7
on
m. (a 11 g
00
io' G
Carmel
Redevelopment Commission
111 West Main Street
Cannel, Indiana 46032
317.571 -2787 (ARTS)
IJE(
El
Scope Drawings:
These drawings indicate the general scope of the project
in terms of architectural design concept, the dimensions of
the building, the major architectural elements and the type
of structural, mechanical and electrical systems.
The drawings do not necessarily indicate or describe all
work required for full performance and completion of the
requirements of the Contract.
On the basis of the general scope indicated or described,
the trade contractors shall furnish all items required for the
proper execution and completion of the work.
Revisions:
Issue Date
01/16/09
Drawn By
M.D.L.
Checked By
M.D.L.
Drawing Title:
General
Structural
Notes
Certified By:
Drawing Number:
S 1 0 1
Project Number:
28133
COORDINATION WITH
OTHER TRADES
1. The Contractor shall coordinate and check all dimensions
relating to Architectural finishes, mechanical equipment and
openings, elevator shafts and overrides, etc. and notify the
Architect /Engineer of any discrepancies before proceeding with
any work in the area under question.
2. The Structural Drawings shall be used in conjunction with the
Drawings of all other disciplines and the Specifications. The
Contractor shall verify the requirements of other trades as to
sleeves, chases, hangers, inserts, anchors, holes, and other
items to be placed or set in the Structural Work.
3. There shall be no vertical or horizontal sleeves set, or holes
cut or drilled in any beam or column unless it is shown on the
Structural Drawings or approved in writing by the Engineer of Record.
Verify locations and dimensions of mechanical and electrical openings
through supported floors and walls shown on the Structural Drawings
with the Mechanical and Electrical Contractors.
5. Do not install conduit in slabs on grade or concrete walls unless
explicitly shown or noted on the Structural Drawings.
6. Do not suspend any items, such as ductwork, mechanical or electrical
fixtures, ceilings, etc. from wood deck.
7. The Mechanical Contractor shall notify the Engineer of Record of any
Mechanical Unit supported by the structure not shown on the Structural
Drawings, whose weight is greater than 500 lbs.
8. If drawings and specifications are in conflict, the most stringent restrictions
and requirements shall govern.
GENERAL NOTES
The Contractor shall be responsible for complying with all safety
precautions and regulations during the work. The Engineer will not
advise on, nor issue direction as to safety precautions and programs.
2. The Structural Drawings herein represent the finished structure. The
Contractor shall provide all temporary guying and bracing required to
erect and hold the structure in proper alignment until all Structural
Work and connections have been completed. The investigation, design,
safety, adequacy and inspection of erection bracing, shoring, temporary
supports, etc. is the sole responsiblity of the Contractor.
3. The Engineer shall not be responsible for the methods, techniques
and sequences of procedures to perform the Work. The supervision of
the Work is the sole responsibility of the Contractor.
4. Drawings indicate general and typical details of construction. Where
conditions are not specifically shown, similar details of construction
shall be used, subject to approval of the Engineer.
5. All structural systems which are to be composed of components to
be field erected shall be supervised by the Supplier during manu-
facturing, delivery, handling, storage, and erection in accordance
with the Supplier's instructions and requirements.
6. Loading applied to the structure during the process of construction
shall not exceed the safe load- carrying capacity of the structural
members. The live loading used in the design of this structure are
indicated in the "Design Criteria Notes Do not apply any construction
loads until structural framing is properly connected together and until
all temporary bracing is in place.
7. All ASTM and other referenced standards and codes are for the latest
editions of these publications, unless otherwise noted.
8. Shop Drawings and other items shall be submitted to the Engineer for
review prior to fabrication. All Shop Drawings shall be reviewed by
the Contractor before submittal. The Engineer's review is to be for
conformance with the design concept and general compliance with the
relevant Contract Documents. The Engineer's review does not relieve
the Contractor of the sole responsibility to review, check, and
coordinate the Shop Drawings prior to submission. The Contractor
remains solely responsible for errors and omissions associated with
the preparation of Shop Drawings as they pertain to member sizes,
details, dimensions, etc.
9. Submit Shop Drawings in the form of blueline /blackline prints (min. 2 sets/
max. 5 sets) and one reproducible blackline or sepia copy. In no case
shall reproductions of the Contract Documents be used as shop drawings.
As a minimum, submit the following items for review:
A. Concrete Mix Design(s).
B. Reinforcing Steel Shop Drawings.
10. Contractors shall visit the site prior to bid to ascertain conditions which may
adversely affect the work or cost thereof.
11. No structural member may be cut, notched, or otherwise reduced in strength
without written direction from the Engineer of Record.
12. When modifications are proposed to structural elements under the design and
certification of a Specialty Engineer, written authorization by the Specialty
Engineer must be obtained and submitted to the Engineer of Record for review,
prior to performing the proposed modification.
EXISTING CONSTRUCTION
1. The Contractor shall field verify the dimensions, elevations, etc. necessary for the
proper construction and alignment of the new portions of the work to the existing
work. The Contractor shall make all necessary measurements for fabrication and
erection of the structural members. Any discrepancy shall be immediately brought
to the attention of the Engineer of Record.
2. Before proceeding with any work within the existing facility, the Contractor shall
familiarize himself with existing structural and other conditions. Any shoring shown
or noted on the Plans is a partial and schematic representation of that required.
It shall be the Contractor's responsibility to provide all necessary bracing, shoring,
and other safeguards to maintain all parts of the work in a safe condition during
the progress of demolition and construction, and to protect from damage those
portions of the existing work which are to remain. Shoring shall remain in place
until the structural work is complete, has been inspected by the Testing Agency,
and is certified to be in substantial compliance with the Contract Documents.
3. When required by the Specifications or by Plan Note, the Contractor shall submit
for the Engineer of Record's review, a "Proposed Shoring Plan including, but not
limited to: plans, sections, details, notes, description of proposed sequence of
work, and calculations prepared by, or under the supervision of a Professional
Engineer (Specialty Engineer). The Specialty Engineer shall be registered in the
State where the project is located.
4. Welding to and within an existing facility presents potential hazards including:
A. Fire Hazard Due to the existing construction and building contents.
B. Structural Liquefaction Due to welding across the full section of the
structural members.
Recommendations to prevent these hazards include:
A. Fire Hazard Protect existing combustibles prior to welding. Keep a
separate watchman and several fire extinguishers on hand.
B. Structural Liquifaction weld in small increments. Allow welds to harden
before continuing to the next increment.
C. Do not leave the site until satisfied that no fire hazard exists.
D. Preference should be given to the use of beam clamps, mechanical
fasteners, or bolted connections in lieu of welding within existing facilities,
whenever possible. Do not field -drill existing structural members without
the written permission of the Engineer of Record.
FOUNDATIONS
1. Proofroll slab on grade areas with a medium weight roller or
other suitable equipment to check for pockets of soft material
hidden beneath a thin crust of better soil. Any unsuitable
materials thus exposed should be removed and replaced with
compacted, engineered fill as outlined in the specifications.
Proofrolling operations shall be monitored by the Testing Agency.
2. All engineered fill beneath slabs and over footings should
be compacted to a dry density of at least 93% of the Modified
Proctor maximum dry density (ASTM D- 1557). All fill which shall
be stressed by foundation loads shall be approved granular materials
compacted to a dry density of at least 95% (ASTM D- 1557).
Coordinate all fill and compaction operations with the Specifications
and the Subsurface Investigation.
3. Compaction shall be accomplished by placing fill in approx. 8"
lifts and mechanically compacting each lift to at least the
specified minimum dry density. For large areas of fill, field density tests
shall be performed for each 3000 square feet of building area for each lift
as necessary to insure adequate compaction is being achieved.
4. Column footings and wall footings to bear on firm natural soils or well
compacted engineered fill with an assumed allowable bearing pressure of
1,500 psf.
It is essential that the foundations be inspected to ensure that all
loose, soft or otherwise undesirable material (such as organics, existing
fill, etc.) is removed and that the foundation will bear on satisfactory
material. The Testing Agency shall inspect the subgrade and
perform any necessary tests to insure that the actual bearing
capacities meet or exceed the design capacities. The Testing Agency
shall verify the bearing capacity at each spread column footing and
every 10 feet on center for strip footings prior to placement of concrete.
5. Place footings the same day the excavation is performed. If this
is not possible, the footings shall be adequately protected
against any detrimental change in condition, such as from
disturbance, rain and freezing.
6. It is the responsibility of the Contractor and each Sub
Contractor to verify the location of all utilities and services
shown, or not shown; and establish safe working conditions before
commencing work.
7. The Contractor shall layout the entire building and field verify
all dimensions prior to excavation.
REINFORCED MASONRY NOTES
1. All construction of reinforced masonry walls to be in accordance
with the Building Code Requirements For Concrete Masonry
Structures (A.C.I. 530 -05) and commentary.
A) f'm 2000 p.s.i.
B) Maximum height of masonry lift: 5'- 0"
C) Maximum height of grout lift: 5'- 0"
D) See specifications for additional masonry wall information.
2. CONCRETE BLOCK: Minimum compressive test strength on the net
cross sectional area: 2500 p.s.i.
3. MORTAR: Type S required.
4. GROUT: A.S.T.M. C476, 2500 p.s.i. with a slump of 8" min. and
10" max.
5. REINFORCING: fy 60,000 p.s.i. with a min. lap of 48 diameters.
CONCRETE REINFORCING
1. Reinforcement, other than cold drawn wire for spirals and welded
wire fabric, shall have deformed surfaces in accordance with
A.S.T.M. A305.
2. Reinforcing steel shall conform to ASTM A615, Grade 60, unless noted.
3. Welded wire fabric shall conform to ASTM A185, unless noted.
4. Where hooks are indicated, provide standard hooks per A.C.I. and
C.R.S.I. for all bars unless other hook dimensions are shown on
the plans or details.
5. Reinforcement in footings, walls and beams shall be continuous. Lap
bars a minimum of 36 diameters, unless noted otherwise.
6. Reinforcement shall be supported and secured against displacement
in accordance with the Concrete Reinforcing Steel Institute's "Manual of
Standard Practice
7. Details of reinforcing steel fabrication and placement shall conform to
ACI 315 "Details and Detailing of Concrete Reinforcement" and
ACI 315R "Manual of Engineering and Placing Drawings for Reinforced
Concrete Structures unless otherwise indicated.
8. Provide standees for the support of top reinforcement for footings,
pile caps, and mats.
9. Provide individual high chairs with support bars, as required for the
support of top reinforcement for supported slabs. Do not provide
standees.
10. Field bending of reinforcing steel is prohibited, unless noted on drawings.
11. Minimum concrete cover over main reinforcing steel shall be as
follows: 3" at foundations, 2" at all dirt faces of walls and
beams exposed to the weather, 1 -1/2" at all pier and column ties,
and 3/4" at other wall faces and in structural slabs unless shown
or noted otherwise.
DRILLED -IN DOWELS
ANCHOR BOLTS/RODS
1. All reinforcing steel and threaded rod anchors to be installed
in 2 -part chemical anchoring system shall be treated as follows:
A) Drill holes larger than bar or rod to be embedded. Coordinate
hole diameter with Manufacturer's recommendations.
B) Holes must be cleaned and prepared in accordance with
Manufacturer's recommendations.
C) When reinforcing steel is encountered during drilling for installation of
anchors; stop drilling, use a sensor to locate the reinfocing in the
surrounding area and install anchor(s) as close as possible to the original
location. Contact the Engineer of Record for direction when the revised
location is more than 2" from the original location, or when the original
function of the anchorage is significantly altered. When in doubt,
contact the Engineer of Record for direction.
D) Drill the hole a minimum of 15 bar diameters or as shown on
the plans.
F) Use a two -part adhesive anchoring system, Hilti HY -150, or approved equal.
G) For anchorage into hollow substrate, use Hilti HY -20 system, or approved equal.
H) Reinforcing steel dowels shall be ASTM A615, Grade 60, unless noted.
I) Anchor rods shall be ISO 898 5.8 (Hilti HAS -E), unless noted. Provide
finish as noted on the Drawings. If not noted, provide hot -dip galvanized
finish for interior applications. Provide stainless steel finish for all exterior
applications, unless noted.
DESIGN CRITERIA
1. The building was designed in accordance with the 2008 Indiana Building Code,
for Seismic Design Catagory B. Wind pressures were computed using 90 mph
Basic Wind Speed, Exposure B.
2. The following live loads were used in the design of this structure:
A. Roof: 25 psf drift loads
3. If drawings and specifications are in conflict, the most stringent restrictions
and requirements shall govern.
4. All Contractors are required to coordinate their work with all disciplines to
avoid conflicts. The mechanical, electrical and plumbing aspects are not in the
scope of these drawings. Therefore, all required materials and work may not be
indicated.
CONCRETE NOTES
1. Details of fabrication of reinforcement, handling and placing of
the concrete, construction of forms and placement of reinforcement
not otherwise covered by the Plans and Specifications, shall
comply with the A.C.I. Code Requirements of the latest revised
date.
2. Cold weather concreting shall be in accordance with ACI 306.
3. Hot weather concreting shall be in accordance with ACI 305.
4. Unless otherwise noted in the schedules or details, the minimum 28
day compressive strength of the concrete shall be 4000 p.s.i. for
all parts of the structure except for column and wall footings
which shall be 3000 p.s.i. All concrete shall be regular weight
concrete, unless otherwise noted.
5, A certified Testing Agency shall be retained to perform industry
standard testing including measurement of slump, air temperature,
concrete cylinder testing, etc. to ensure conformance with the
Contract Documents. Submit reports to Architect /Engineer.
6. All concrete exposed to the weather shall be air entrained. All
other concrete may be air entrained or non air entrained at the
contractor's option. For surface finishes and other requirements,
refer to the specifications.
7. Finishing of Slabs: After screeding, bull floating and floating operations
have been completed, apply final finish as indicated below, and as
described in Specification Section 03300 of the Project Manual.
A.
B.
C.
D.
Floor Slabs
Ramps, Stairs Sidewalks
Surfaces to Receive Topping Slab
Surfaces to receive thick set mortar
beds or similar cementitious materials
Hard Trowel Finish
Broom Finish
None -Float Finish
None -Float Finish
Floor Tolerances: See the Specifications for specified Ff and Fl
tolerances. Ff and Fl testing shall be performed by the Testing Agency
in accordance with ASTM E -1155. Results, including acceptance or
rejection of the work will be provided to the Contractor and the
Architect /Engineer within 48 hours after data collection. Remedies
for out -of- tolerance work shall be in accordance with the Specifications.
When approved by the Engineer of Record, measurement of the gaps
beneath a 10 foot straight edge may be used in lieu of Ff and Fl
testing. Approval must be obtained in writing prior to the beginning of
concrete operations.
8. Finishing of Formed Surfaces: Finish formed surfaces as indicated below,
and as described in Specification Section 03300 of the Project Manual.
A. Sides of Footings Pile Caps
B. Sides of Grade Beams
C. Surfaces not exposed to public view
D. Surfaces exposed to public view
LINTEL SCHEDULE
1. Where lintels are not specifically shown or noted on the
Structural or Architectural Drawings, provide the following
lintels over all openings and recesses in both interior and
exterior non -load- bearing walls.
A) Brick: Masonry Opening Angle Size
Upto5' -0" L4x4x5/16
5-1" to 7'-0" L6 x 4 x 5/16
Over 7'-1" L7 x 4 x 3/8
All angles are LLV (long leg vertical) unless noted otherwise.
Provide 1" bearing per foot of span each end, min. 8
Rough Form Finish
Rough Form Finish
Rough Form Finish
Smooth Form Finish
9. The Contractor shall consult with the Engineer before starting
concrete work to establish a satisfactory placing schedule and to
determine the location of construction joints so as to minimize
the effects of shrinkage in the floor system.
10. Sawn or tooled control /contraction joints shall be provided in
all slabs on grade. For a framed structure, joints shall be
located on all column lines. If the column spacing exceeds
20' -0 provide intermediate joints. Exterior slabs, and interior
slabs without columns shall have joints spaced a maximum of
15' -0" apart. Layout joints so that maximum aspect ratio
(ratio of long side to short side) does not exceed 1.5.
11. Where vinyl composition tile, thin -set epoxy terrazzo, or other similar
material is the specified finish floor material, the Contractor shall
coordinate the location of control /contraction and construction joints
with the finished floor contractor. Submit a dimensioned plan
showing joint locations and proposed sequence of floor pours.
12. See Architectural Drawings for exact locations and dimensions of
recessed slabs, ramps, stairs, thickened slabs, etc. Slope slabs
to drains where shown on the Architectural and Plumbing Drawings.
13. Joints in slabs to receive a finished floor may remain unfilled, unless
required by the finish flooring contractor. All exposed slabs shall
be filled with sealant specified in Divison 7, or as follows: All slabs
in industrial, manufacturing, or warehouse applications subject to
wheeled traffic shall be filled with specified epoxy resin sealant,
all other joints shall be filled with specified elastomeric sealant.
Defer filling of joints as long as possible, preferably a minimum of
4 to 6 weeks after the slab has been cured. Prior to filling, remove
All debris from the slab joints, then fill in accordance with the
manufacturer's recommendations.
14. Sidewalks, drives, exterior retaining walls, and other site concrete
are not indicated on the Structural Drawings. Refer to the Site /Civil
and Architectural Drawings for locations, dimensions, elevations,
jointing and finish details.
WOOD STRUCTURAL DATA
1. All interior exterior wall studs
shall be #2 Spruce Pine Fir Northern per N.L.G.A. or better:
Fb 875 psi
Ft 450 psi
Fv 70 psi
Fc (PER) 425 psi
Fc (PAR) 1,150 psi
E 1,400,000 psi
2. All rafters, ceiling joists, ridge and valley boards, headers and
misc. blocking shall be #2 Hem -Fir, or better:
(alternate: Southern Yellow Pine).
Fb
Ft
Fv
Fc I
Fc I
E
PER
PAR
1,000 psi
575 psi
75 psi
370 psi
1,450 psi
1,600,000 psi
3. All laminated veneer lumber (L.V.L.) shall be manufactured by
Trus -Joist McMillan, Alpine Structures, Inc., Or Mitek Wood Products:
Fb 2,900 psi
Fv 285 psi
E 2,000,000 psi
NOTES:
1. Refer to specifications for additional information.
2. Alternate grades and species may be proposed. Any substitution
must be approved in writing by the architect engineer.
3. Allowable stresses for dimensional lumber listed above are for 2' -4" thick x 2"
wider. Size adjustment factors (Cf), repetitive member
factor (Cr), duration of load factor (Cd), etc. have been applied
in the design of structural elements.
PLYWOOD SHEATHING NOTES
1. All plywood construction shall be in accordance with the
American Plywood Association (APA) specifications.
2. All roof panel sheathing shall be 19/32" Exposure 1
APA -rated sheathing. Suitable edge support shall be provided
by use of panel clips or blocking between framing unless otherwise
noted. Connect roof sheathing with 8d common nails spaced 6" o..c.
at supported edges and 12" o.c. at intermediate supports.
3. All wall panel sheathing shall be 7/16" Exposure 1
APA -rated sheathing, unless otherwise indicated. Connect wall
sheathing with 8d common nails spaced 6" o.c. at supported panel
edges and 12" o.c. at intermediate supports, unless otherwise noted.
4. Unless otherwise noted or shown, install plywood sheathing with the
long dimension of the panel across supports and with panel
continuous over two or more spans. Stagger panel end joints. Allow
1/8" spacing at panel ends and edges unless otherwise recommended
by the sheathing manufacturer.
5. All nailing shall be carefully driven and not overdriven. The use of
staples and pnuematic nail guns are prohibited from use.
6. Provide 2X blocking at unsupported panel edges as follows:
Roofs and floors only where indicated on plans /sections.
Walls only where indicated on plans /sections.