HomeMy WebLinkAboutC4.1 Erosion Control DetailsEROSION CONTROL SCHEDULE EROSION CONTROL MEASURE MAINTENANCE INSTALLATION SEQUENCE STONE ENTRANCE AS NEEDED PRIOR TO CLEARING AND GRADING SILT FENCE WEEKLY, AFTER STORM EVENTS AND AS NEEDED PRIOR TO CLEARING AND GRADING EXISTING INLET PROTECTION WEEKLY, AFTER STORM EVENTS AND AS NEEDED PRIOR TO CLEARING AND GRADING TREE PROTECTION WEEKLY, AFTER STORM EVENTS AND AS NEEDED PRIOR TO CLEARING AND GRADING TEMPORARY DIVERSIONS WEEKLY, AFTER STORM EVENTS AND AS NEEDED ALONG WITH ROUGH GRADING TEMPORARY SEEDING WATER AS NEEDED AFTER ROUGH GRADING PERMANENT SEEDING WATER AS NEEDED AFTER FINISH GRADING ,0 0111111 1 z D �c N r mw 41 rt% 2 G� 9 m as /A ZVD WEEKLY, AFTER STORM EVENTS AND AS NEEDED AFTER FINISH GRADING STRAW BALES WEEKLY, AFTER STORM EVENTS AND AS NEEDED AFTER FINISH GRADING INLET PROTECTION WEEKLY, AFTER STORM EVENTS AND AS NEEDED AFTER EACH INLET IS PLACED .4 5.8 -7.5 2 REMOVAL OF TREE PROTECTION N/A AFTER PERMANENT SEEDING REMOVAL OF STRAW BALES N/A AFTER ALL AREAS DRAINING TO THESE AREAS ARE STABILIZED REMOVAL OF INLET PROTECTION N/A AFTER ALL AREAS DRAINING TO THESE AREAS ARE STABILIZED REMOVAL OF SILT FENCE N/A AFTER ALL AREAS DRAINING TO THESE AREAS ARE STABILIZED .4 5.8 -7.5 2 1 2 KENTUCKY BLUEGRASS 25 .6 24 -36 5 -14 PROJECT NUMBER 02 -123 T 5. TALL E DESIGN PHASE CONSTRUCTION .8 5.5 -8.3 PLAN NUMBER C4.1 SHEET OF i 1 EROSION CONTROL SCHEDULE EROSION CONTROL MEASURE MAINTENANCE INSTALLATION SEQUENCE STONE ENTRANCE AS NEEDED PRIOR TO CLEARING AND GRADING SILT FENCE WEEKLY, AFTER STORM EVENTS AND AS NEEDED PRIOR TO CLEARING AND GRADING EXISTING INLET PROTECTION WEEKLY, AFTER STORM EVENTS AND AS NEEDED PRIOR TO CLEARING AND GRADING TREE PROTECTION WEEKLY, AFTER STORM EVENTS AND AS NEEDED PRIOR TO CLEARING AND GRADING TEMPORARY DIVERSIONS WEEKLY, AFTER STORM EVENTS AND AS NEEDED ALONG WITH ROUGH GRADING TEMPORARY SEEDING WATER AS NEEDED AFTER ROUGH GRADING PERMANENT SEEDING WATER AS NEEDED AFTER FINISH GRADING EROSION CONTROL MATTING WEEKLY, AFTER STORM EVENTS AND AS NEEDED AFTER FINISH GRADING STRAW BALES WEEKLY, AFTER STORM EVENTS AND AS NEEDED AFTER FINISH GRADING INLET PROTECTION WEEKLY, AFTER STORM EVENTS AND AS NEEDED AFTER EACH INLET IS PLACED .4 5.8 -7.5 2 REMOVAL OF TREE PROTECTION N/A AFTER PERMANENT SEEDING REMOVAL OF STRAW BALES N/A AFTER ALL AREAS DRAINING TO THESE AREAS ARE STABILIZED REMOVAL OF INLET PROTECTION N/A AFTER ALL AREAS DRAINING TO THESE AREAS ARE STABILIZED REMOVAL OF SILT FENCE N/A AFTER ALL AREAS DRAINING TO THESE AREAS ARE STABILIZED SPECIES SEEDING RATE SUITABLE pH SITE SUITABILITY MAY LBS /ACRE LBS /1000 SQ. FT. DROUGHTY WELL DRAINED WET LEVEL AND SLOPING, OPEN AREAS 1. TALL E 35 .8 5.5 -8.3 2 1 2 2. TALL E 25 .6 5.5 -8.3 SPRING OATS 1 3 BU. CLOVER RED 5 .12 SS& 1 LB. 3. KENTUCKY BLUEGRASS 15 .4 5.8 -7.5 2 1 1 CREEPING RED FESCUE 15 .4 12 -18 10 -20 STEEP BANKS AND CUTS 4. TALL E 15 .4 5.8 -7.5 2 1 2 KENTUCKY BLUEGRASS 25 .6 24 -36 5 -14 T 5. TALL E 35 .8 5.5 -8.3 2 1 1 EMERALD ROWNVETCH 10 .25 15 -20 12 -18 5 -10 LAWNS AND 3H MAINTENANCE AREAS 6. KENTUCKY BLUEGRASS 40 .9 5.8 -7.5 2 1 CREEPING RED FESCUE 40 .9 5 -10 24 14 -21 T 7. PERENNIAL RYEGRASS 170 4.0 5.0 -7.5 1 1 2 (TURF TYPE) MED. 1 7 -10 18 5 -10 8. TALL FESCUE 170 4.0 5.5 -8.3 2 1 2 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC NORM DRY COVER SEED 1" TO 1 1/2" DEEP Y Y Y ti' V/ j A Y r X X Y'� y k k SPRING OATS 2.3 LBS. 3 BU. /o /iii; /j SS& 1 LB. 40 LB. COVER SEED 1/4" DEEP \i ///m.,/,,z,/,„ 1 1 1 MED. 1 20 -35 12 -18 10 -20 JAN TEMPORARY SEEDINGS MAR APR MAY JUN TYPE OF SEED 1000 SQ. FT. ACRE REMARKS NOV DEC NORM DRY WHEAT OR RYE 3.5 LBS. 2 BU. COVER SEED 1" TO 1 1/2" DEEP Y Y Y ti' k� k� X X x Y r X X Y'� y k k SPRING OATS 2.3 LBS. 3 BU. COVER SEED 1" DEEP X X r V �k� XX /x X /iii; /j 7 -21 ANNUAL RYEGRASS 1 LB. 40 LB. COVER SEED 1/4" DEEP JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC NORM DRY V X Pav ri k int, ,X kx X Y' j X Y X X k 4 4 4 444$ V la Sr Y Y Y ti' k� k� X X x Y r X X Y'� y k k 1 ,r r X X X k �C Y X X X X X r V �k� XX /x X /iii; /j 7 -21 S KENTUCKY GRASS CIS POA 2 1 2 1 1 1 MED. 1 20 -35 12 -18 10 -20 MT TALL FESTUCA L. FESCUE IDINACEA 1 -.4 `40. 10■ (M PUBLIC ROAD 12" M INIMUM THICKNESS #2 COARSE AGGREGATE GEOTEXTILE FABRIC TO STABILIZE FOUNDATION (ESPECIALLY IMPORTANT WHERE WETNESS IS ANTICIPATED) S p, TEMPORARY CONSTRUCTION ENTRANCE NOT TO SCALE 1 GOOD 2 MEDIUM IT SEEDBED PREPARATION SEED TOLERANCE SALT TOLERANCE (TO BOTH SOIL SALTS SPRAY) T TOLERANCE MT MEDIUM TOLERANCE S SLIGHT TOLERANCE APPLY LIME J RAISE THE pH TO THE LEVEL NEEDED FOR SPECIES BEING SEEDED. APPLY 3 POUNDS OF 12 -12 -12 ANALYSIS FERTILIZER (OR EQUIVALENT) PER 1000 SQ. FT. PROXIMATELY 1000 POUNDS PER ACRE) OR FERTILIZE ACCORDING TO TEST. APPLICATION OF 150 LBS. OF AMMONIUM NITRATE ON AREAS LOW IN ORGANIC MATTER AND FERTILITY WILL GREATLY ENHANCE VEGETATIVE GROWTH. WORK THE FERTILIZER AND LIME INTO THE SOIL TO A DEPTH OF 2 -3 INCHES WITH A HARROW, DISK OR RAKE OPERATED ACROSS THE SLOPE AS MUCH AS POSSIBLE. SEEDING SELECT A :ED MIXTURE BASED ON PROJECTED USE OF THE AREA (SEE PERMANENT SEED MIXTURE CHART). WHILE CONSIDERING BEST SEEDING DATES. IF PERMANENT SEEDING IS NOT PERMITTED USE TEMPORARY SEEDING UNTIL PERMANENT SEEDING CAN BE APPLIED. IF TOLERANCES ARE A PROBLEM, SUCH AS SALT TOLERANCE OF SEEDINGS ADJACENT TO STREETS AND HIGHWAYS, SEE SEED TOLERANCE CHART. SEED TOLERANCE CHART 1 PREFERRED 2 WILL TOLERATE INOCULATE WITH SPECIFIC INOCULANT. SEEDING DETAIL WHEAT OR RYE OATS ANNUAL RYEGRASS NON- IRRIGATED* IRRIGATED DORMANT SEEDING EXTEND FABRIC TO 4" BELOW SURFACE FILTER FABRIC FLOW NOT NECESSARY WHERE MULCH IS APPLIED. NON WOVEN GEOTEXTI LE FABRIC i ce SPACE POSTS PER MANUFACTURER RECOMMENDATIONS WOOD POST SILT FENCE CONSTRUCTION TEMPORARY SEEDING DATES PERMANENT SEEDING DATES INCREASE SEEDING APPLICATION BY 50 NOT TO SCALE IRRIGATION NEEDED DURING THIS PERIOD. TO CONTROL EROSION AT TIMES OTHER THAN IN THE SHADED AREAS. USE MULCH. LATE SUMMER SEEDING DATES MAY BE EXTENDED 5 DAYS IF MULCH IS APPLIED. NOTE; POSTS SHALL HAVE A MINIMUM LENGTH OF 36 INCHES PLUS BURIAL DEPTH. POST MATERIAL SHALL BE WOOD, STEEL, OR SYNTHETIC, AND SHALL BE OF SUFFICIENT STRENGTH TO RESIST DAMAGE DURING INSTALLATION AND TO SUPPORT APPLIED LOADS. FABRIC SHALL BE A WOVEN GEOTEXTILE FABRIC CONSISTING OF STRONG, ROT RESISTANT, MATERIALS RESISTANT TO DETERIORATION FROM ULTRAVIOLET AND HEAT EXPOSURE. 1. 2 STAKES (TYP) PER BALE COMPACTED SOIL TO PREVENT PIPING STAKED STRAW BALE CHANNEL INSTALLATION NOTE: HORIZONTAL STAPLE SPACING SHOULD BE ALTERED IF NECESSARY TO ALLOW STAPLES TO SECURE THE CRITICAL POINTS ALONG THE CHANNEL SURFACE. REFER TO GENERAL STAPLE PATTERN GUIDE FOR CORRECT STAPLE RECOMMENDATIONS FOR CHANNELS. CRITICAL POINTS A. OVERLAPS AND SEAMS B. PROJECTED WATER LINE C. CHANNEL BOTTOM /SIDE SLOPE VERTICES PLAN SECTION 14649 HIGHWAY 41 NORTH, EVANSVILLE, INDIANA 47711 USA 1- 800 772 -2040 CANADA 1- 800 448 -2040 STORM INLET STRAW BALE PROTECTION NOT TO SCALE BINDINGS FOR STRAW BALES TO BE PLACED PARALLEL TO GROUND STORM INLET STRUCTURE 8. THE TERMINAL END OF THE BLANKETS MUST BE ANCHORED IN A 6" DEEP X 6" WIDE TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING. 7 PREPARE SOIL BEFORE INSTALLING BLANKETS, INCLUDING APPLICATION OF LIME, FERTILIZER, AND SEED. 2. BEGIN AT THE TOP OF THE CHANNEL BY ANCHORING THE BLANKET IN A 6" DEEP X 6" WIDE TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING. 3, ROLL CENTER BLANKET IN DIRECTION OF WATER FLOW ON BOTTOM OF CHANNEL. 4. PLACE BLANKETS END OVER END (SHINGLE STYLE) WITH A 6" OVERLAP. USE A DOUBLE ROW OF' STAGGERED STAPLES 4" APART TO SECURE BLANKETS. 5. FULL LENGTH EDGE OF BLANKETS AT TOP OF SIDE SLOPES MUST BE ANCHORED IN 6" DEEP X 6" WIDE TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING. 6. BLANKETS ON SIDE SLOPES MUST BE OVERLAPPED 4" OVER THE CENTER BLANKET AND STAPLED (2" FOR C350 MATTING). 7. IN HIGH FLOW CHANNEL APPLICATIONS, A STAPLE CHECK SLOT IS RECOMMENDED AT 30 TO 40 FOOT INTERVALS. USE A ROW OF STAPLES 4" APART OVER ENTIRE WIDTH OF THE CHANNEL. PLACE A SECOND ROW 4" BELOW THE FIRST ROW IN A STAGGERED PATTERN. EROSION CONTROL NOTES 1. ALL CONSTRUCTION METHODS AND MATERIALS MUST CONFORM TO CURRENT STANDARDS AND SPECIFICATIONS OF THE FEDERAL, STATE, COUNTY, CITY OR LOCAL REQUIREMENTS, WHICHEVER HAS JURISDICTION. 2. LAND ALTERATION WHICH STRIPS THE LAND OF VEGETATION, INCLUDING REGRADING, SHALL BE DONE IN A WAY THAT WILL MINIMIZE EROSION. 3. THIS PLAN SHALL NOT BE CONSIDERED ALL INCLUSIVE AS THE CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO PREVENT SOIL SEDIMENT FROM LEAVING THE SITE. ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES WILL BE INSTALLED IF DEEMED NECESSARY BY ON -SITE INSPECTION. 4. SEDIMENT LADEN WATER SHALL BE DETAINED BY EROSION CONTROL PRACTICES AS NEEDED TO MINIMIZE SEDIMENTATION IN THE RECEIVING STREAM. NO STORM WATER SHALL BE DISCHARGED FROM THE SITE IN A MANNER THAT CAUSES EROSION AT THE POINT OF DISCHARGE. 5. WASTES AND UNUSED BUILDING MATERIALS SHALL NOT BE ALLOWED TO BE CARRIED FROM THE SITE BY STORMWATER RUNOFF. PROPER DISPOSAL OF ALL WASTES AND UNUSED BUILDING MATERIALS IS REQUIRED. 6. SEDIMENT BEING TRACED ONTO PUBLIC OR PRIVATE ROADWAYS SHALL BE MINIMIZED. CLEARING OF ACCUMULATED SEDIMENT SHALL NOT INCLUDE FLUSHING WITH WATER. CLEARED SEDIMENT SHALL BE RETURNED TO THE SITE FOR DISPOSAL. 7. SOIL WHICH HAS ACCUMULATED NEXT TO EROSION CONTROL DEVICES SHALL BE COLLECTED AND REDISTRIBUTED ON SITE AFTER EACH RAINFALL EVENT, AND AT LEAST ONCE A WEEK. 8. IF INSTALLATION OF STORM DRAINAGE SYSTEM SHOULD BE INTERRUPTED BY WEATHER OR NIGHTFALL, THE PIPE ENDS SHALL BE COVERED WITH FALTER FABRIC. 9. ALL EXISTING STRUCTURES, FENCING, TREES AND ETC., WITHIN CONSTRUCTION AREA SHALL BE REMOVED AND DISPOSED OF OFF SITE. BURNING IS NOT ALLOWED ON -SITE. 10. SCHEDULE OF EARTHWORK ACTIVITIES: a) THE DURATION OF TIME WHICH AN AREA REMAINS EXPOSED SHALL BE KEPT TO A PRACTICAL MINIMUM. THE AREA SHALL BE STABILIZED SOON AS POSSIBLE. TEMPORARY VEGETATION OR MULCHING SHALL BE USED TO PROTECT EXPOSED AREAS IF PERMANENT VEGETATION CANNOT BE SEEDED WITHIN 14 DAYS OR ACTIVITY CEASES FOR MORE THAN 21 DAYS OR AS DIRECTED BY THE ENGINEER. b) TOPSOIL REPLACEMENT SHALL TAKE PLACE FROM MARCH 1 TO OCTOBER 31. STOCKPILE TOPSOIL AT ALL OTHER TIME OF THE YEAR. PERMANENT AND FINAL VEGETATION AND STRUCTURAL EROSION CONTROL DEVICES SHALL BE INSTALLED WITHIN SEVEN (7) DAYS AFTER FINAL GRADING OR AS SOON AS POSSIBLE. EROSION CONTROL MEASURES MAINTENANCE REQUIREMENTS STRAW BALE DAM MAINTENANCE REQUIREMENTS: 1. INSPECT STRAW BALE DAMS AFTER EACH STORM EVENT AND PROMPTLY REMOVE ANY SEDIMENT DEPOSITS TO ENSURE ADEQUATE STORAGE VOLUME FOR THE NEXT RAIN, TAKING CARE NOT TO UNDERMINE THE ENTRENCHED BALES. 2. INSPECT PERIODICALLY FOR DETERIORATION OR DAMAGE FROM CONSTRUCTION ACTIVITIES AND REPAIR IMMEDIATELY. 3. AFTER THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZED, REMOVE ALL STRAW BALES AND SEDIMENT, BRING THE DISTURBED AREA TO GRADE, AND STABILIZE IT. SILT FENCE MAINTENANCE REQUIREMENTS: 1. INSPECT THE SILT FENCE PERIODICALLY AND AFTER EACH STORM EVENT. 2. IF FENCE FABRIC TEARS, STARTS TO DECOMPOSE, OR IN ANY WAY BECOMES INEFFECTIVE, REPLACE THE AFFECTED PORTION IMMEDIATELY. 3. REMOVE DEPOSITED SEDIMENT WHEN IT REACHES HALF THE HEIGHT OF THE FENCE AT ITS LOWEST POINT OR IS CAUSING THE FABRIC TO BULGE. 4. TAKE CARE TO AVOID UNDERMINING THE FENCE DURING CLEAN OUT. 5. AFTER THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZED, REMOVE THE FENCE AND SEDIMENT DEPOSITS, BRING THE DISTURBED AREA TO GRADE, AND STABILIZE. TEMPORARY SEDIMENT TRAP MAINTENANCE REQUIREMENTS: 1. INSPECT TEMPORARY SEDIMENT TRAPS AFTER EACH STORM EVENT IMMEDIATELY REPAIR ANY EROSION AND PIPING HOLES. 2. REMOVE SEDIMENT WHEN IT HAS ACCUMULATED TO ONE -HALF THE DESIGN DEPTH. 3. REPLACE SPILLWAY GRAVEL FACING IF CLOGGED. 4. INSPECT VEGETATION, AND RE -SEED IF NECESSARY. 5. CHECK THE SPILLWAY DEPTH PERIODICALLY TO ENSURE A MINIMUM OF 1.5 FT. DEPTH FROM THE LOWEST POINT OF THE SETTLED EMBANKMENT TO HIGHEST POINT OF THE SPILLWAY CREST, AND FILL ANY LOW AREAS TO MAINTAIN DESIGN ELEVATION. 6. PROMPTLY REPLACE ANY DISPLACED RIP RAP, BEING CAREFUL THAT NO STONES IN THE SPILLWAY ARE ABOVE DESIGN GRADE. 7. AFTER ALL DISTURBED AREAS HAVE BEEN STABILIZED, REMOVE THE STRUCTURE AND SEDIMENT, SMOOTH THE DISTURBED AREA TO BLEND WITH ADJOINING AREAS, AND STABILIZE. EROSION CONTROL BLANKET (SURFACE APPLIED) MAINTENANCE REQUIREMENTS: 1. DURING VEGETATIVE ESTABLISHMENT, INSPECT AFTER STORM EVENTS FOR ANY EROSION BELOW THE BLANKET. 2. IF ANY AREA SHOWS EROSION, PULL BACK THAT PORTION OF THE BLANKET COVERING IT, ADD SOIL, RE -SEED THE AREA, AND RE -LAY AND STAPLE THE BLANKET. 3. AFTER VEGETATIVE ESTABLISHMENT, CHECK THE TREATED AREA PERIODICALLY. TEMPORARY GRAVEL CONSTRUCTION ENTRANCE MAINTENANCE REQUIREMENTS: 1. INSPECT ENTRANCE PAD AND SEDIMENT DISPOSAL AREA WEEKLY AND AFTER STORM EVENTS OR HEAVY USE. 2. RESHAPE PAD AS NEEDED FOR DRAINAGE AND RUNOFF CONTROL. 3. TOP DRESS WITH CLEAN STONE AS NEEDED. 4. IMMEDIATELY REMOVE MUD AND SEDIMENT TRACKED OR WASHED ONTO PUBLIC ROADS BY BRUSHING OR SWEEPING. FLUSHING SHOULD ONLY BE USED IF THE WATER IS CONVEYED INTO A SEDIMENT TRAP OR BASIN. 5. REPAIR ANY BROKEN ROAD PAVEMENT IMMEDIATELY. EROSION AND SEDIMENT CONTROL PLAN SUMMARY AND "RULE 5" DATA PROJECT: GODDARD SCHOOL NATURE AND PURPOSE: DAYCARE ESTIMATED START: SPRING 2003 ESTIMATED COMPLETION OF SITE DEVELOPMENT: FALL 2003 FLOODPLAINS, FLOODWAY FRINGES, FLOODWAYS: NOT APPLICABLE EXISTING SOIL TYPES DESCRIPTION CROSBY SILT LOAM: DEEP, SOMEWHAT POORLY DRAINED SOIL MIAMI SILT LOAM: DEEP, WELL DRAINED SOIL RECEIVING WATERS: WHITE RIVER POTENTIAL AREAS WHERE STORMWATER MAY ENTER GROUNDWATER: NONE KNOWN EXISTING VEGETATION: THE SITE IS CURRENTLY COVERED WITH SHORT GRASSES. CONTACT PERSON: JIM PECK CIVIL DESIGNS, LLP 2415 DIRECTORS ROW, SUITE E INDIANAPOLIS, INDIANA 46241 (317) 244 -1968 ADJACENT LAND USE: NORTH COMMERCIAL SOUTH COMMERCIAL EAST RESIDENTIAL WEST COMMERCIAL SITE SPECIFIC SEQUENCE AND ADDITIONAL NOTES: THE PERIMETER SILT FENCES SHOULD BE CONSTRUCTED AND STABILIZED AS EARLY AS PRACTICAL TO PREVENT RUN -OFF FROM LEAVING THE SITE OR CLEAN OFF -SITE WATER FROM WASHING THROUGH THE SITE. EROSION CONTROL AND INLET PROTECTION SHALL BE INSTALLED IMMEDIATELY AFTER INSTALLATION OF STORM SEWERS. J SOIL CONDITION SHADE TOLERANCE CLOSE MOWING TO 2 -3 1/2 INCHES TRAMPING TOLERANCE FERTILITY NEEDS WINTER HARDINESS FLOODING TOLERANCE (DAYS) MATURE HEIGHT (INCHES) EMERGENCE TIME (DAYS) SOIL TOLERANCE WET NORM DRY V X Pav ri k int, ,X kx X Y' j X Y X X k 4 4 4 444$ V la Sr Y Y Y ti' k� k� X X x Y r X X Y'� y k k 1 ,r r X X X k �C Y X X X X X r V �k� XX /x X PIOTOOPTO 0 •6•4* "WM 4 1 -.4 `40. 10■ (M PUBLIC ROAD 12" M INIMUM THICKNESS #2 COARSE AGGREGATE GEOTEXTILE FABRIC TO STABILIZE FOUNDATION (ESPECIALLY IMPORTANT WHERE WETNESS IS ANTICIPATED) S p, TEMPORARY CONSTRUCTION ENTRANCE NOT TO SCALE 1 GOOD 2 MEDIUM IT SEEDBED PREPARATION SEED TOLERANCE SALT TOLERANCE (TO BOTH SOIL SALTS SPRAY) T TOLERANCE MT MEDIUM TOLERANCE S SLIGHT TOLERANCE APPLY LIME J RAISE THE pH TO THE LEVEL NEEDED FOR SPECIES BEING SEEDED. APPLY 3 POUNDS OF 12 -12 -12 ANALYSIS FERTILIZER (OR EQUIVALENT) PER 1000 SQ. FT. PROXIMATELY 1000 POUNDS PER ACRE) OR FERTILIZE ACCORDING TO TEST. APPLICATION OF 150 LBS. OF AMMONIUM NITRATE ON AREAS LOW IN ORGANIC MATTER AND FERTILITY WILL GREATLY ENHANCE VEGETATIVE GROWTH. WORK THE FERTILIZER AND LIME INTO THE SOIL TO A DEPTH OF 2 -3 INCHES WITH A HARROW, DISK OR RAKE OPERATED ACROSS THE SLOPE AS MUCH AS POSSIBLE. SEEDING SELECT A :ED MIXTURE BASED ON PROJECTED USE OF THE AREA (SEE PERMANENT SEED MIXTURE CHART). WHILE CONSIDERING BEST SEEDING DATES. IF PERMANENT SEEDING IS NOT PERMITTED USE TEMPORARY SEEDING UNTIL PERMANENT SEEDING CAN BE APPLIED. IF TOLERANCES ARE A PROBLEM, SUCH AS SALT TOLERANCE OF SEEDINGS ADJACENT TO STREETS AND HIGHWAYS, SEE SEED TOLERANCE CHART. SEED TOLERANCE CHART 1 PREFERRED 2 WILL TOLERATE INOCULATE WITH SPECIFIC INOCULANT. SEEDING DETAIL WHEAT OR RYE OATS ANNUAL RYEGRASS NON- IRRIGATED* IRRIGATED DORMANT SEEDING EXTEND FABRIC TO 4" BELOW SURFACE FILTER FABRIC FLOW NOT NECESSARY WHERE MULCH IS APPLIED. NON WOVEN GEOTEXTI LE FABRIC i ce SPACE POSTS PER MANUFACTURER RECOMMENDATIONS WOOD POST SILT FENCE CONSTRUCTION TEMPORARY SEEDING DATES PERMANENT SEEDING DATES INCREASE SEEDING APPLICATION BY 50 NOT TO SCALE IRRIGATION NEEDED DURING THIS PERIOD. TO CONTROL EROSION AT TIMES OTHER THAN IN THE SHADED AREAS. USE MULCH. LATE SUMMER SEEDING DATES MAY BE EXTENDED 5 DAYS IF MULCH IS APPLIED. NOTE; POSTS SHALL HAVE A MINIMUM LENGTH OF 36 INCHES PLUS BURIAL DEPTH. POST MATERIAL SHALL BE WOOD, STEEL, OR SYNTHETIC, AND SHALL BE OF SUFFICIENT STRENGTH TO RESIST DAMAGE DURING INSTALLATION AND TO SUPPORT APPLIED LOADS. FABRIC SHALL BE A WOVEN GEOTEXTILE FABRIC CONSISTING OF STRONG, ROT RESISTANT, MATERIALS RESISTANT TO DETERIORATION FROM ULTRAVIOLET AND HEAT EXPOSURE. 1. 2 STAKES (TYP) PER BALE COMPACTED SOIL TO PREVENT PIPING STAKED STRAW BALE CHANNEL INSTALLATION NOTE: HORIZONTAL STAPLE SPACING SHOULD BE ALTERED IF NECESSARY TO ALLOW STAPLES TO SECURE THE CRITICAL POINTS ALONG THE CHANNEL SURFACE. REFER TO GENERAL STAPLE PATTERN GUIDE FOR CORRECT STAPLE RECOMMENDATIONS FOR CHANNELS. CRITICAL POINTS A. OVERLAPS AND SEAMS B. PROJECTED WATER LINE C. CHANNEL BOTTOM /SIDE SLOPE VERTICES PLAN SECTION 14649 HIGHWAY 41 NORTH, EVANSVILLE, INDIANA 47711 USA 1- 800 772 -2040 CANADA 1- 800 448 -2040 STORM INLET STRAW BALE PROTECTION NOT TO SCALE BINDINGS FOR STRAW BALES TO BE PLACED PARALLEL TO GROUND STORM INLET STRUCTURE 8. THE TERMINAL END OF THE BLANKETS MUST BE ANCHORED IN A 6" DEEP X 6" WIDE TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING. 7 PREPARE SOIL BEFORE INSTALLING BLANKETS, INCLUDING APPLICATION OF LIME, FERTILIZER, AND SEED. 2. BEGIN AT THE TOP OF THE CHANNEL BY ANCHORING THE BLANKET IN A 6" DEEP X 6" WIDE TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING. 3, ROLL CENTER BLANKET IN DIRECTION OF WATER FLOW ON BOTTOM OF CHANNEL. 4. PLACE BLANKETS END OVER END (SHINGLE STYLE) WITH A 6" OVERLAP. USE A DOUBLE ROW OF' STAGGERED STAPLES 4" APART TO SECURE BLANKETS. 5. FULL LENGTH EDGE OF BLANKETS AT TOP OF SIDE SLOPES MUST BE ANCHORED IN 6" DEEP X 6" WIDE TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING. 6. BLANKETS ON SIDE SLOPES MUST BE OVERLAPPED 4" OVER THE CENTER BLANKET AND STAPLED (2" FOR C350 MATTING). 7. IN HIGH FLOW CHANNEL APPLICATIONS, A STAPLE CHECK SLOT IS RECOMMENDED AT 30 TO 40 FOOT INTERVALS. USE A ROW OF STAPLES 4" APART OVER ENTIRE WIDTH OF THE CHANNEL. PLACE A SECOND ROW 4" BELOW THE FIRST ROW IN A STAGGERED PATTERN. EROSION CONTROL NOTES 1. ALL CONSTRUCTION METHODS AND MATERIALS MUST CONFORM TO CURRENT STANDARDS AND SPECIFICATIONS OF THE FEDERAL, STATE, COUNTY, CITY OR LOCAL REQUIREMENTS, WHICHEVER HAS JURISDICTION. 2. LAND ALTERATION WHICH STRIPS THE LAND OF VEGETATION, INCLUDING REGRADING, SHALL BE DONE IN A WAY THAT WILL MINIMIZE EROSION. 3. THIS PLAN SHALL NOT BE CONSIDERED ALL INCLUSIVE AS THE CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO PREVENT SOIL SEDIMENT FROM LEAVING THE SITE. ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES WILL BE INSTALLED IF DEEMED NECESSARY BY ON -SITE INSPECTION. 4. SEDIMENT LADEN WATER SHALL BE DETAINED BY EROSION CONTROL PRACTICES AS NEEDED TO MINIMIZE SEDIMENTATION IN THE RECEIVING STREAM. NO STORM WATER SHALL BE DISCHARGED FROM THE SITE IN A MANNER THAT CAUSES EROSION AT THE POINT OF DISCHARGE. 5. WASTES AND UNUSED BUILDING MATERIALS SHALL NOT BE ALLOWED TO BE CARRIED FROM THE SITE BY STORMWATER RUNOFF. PROPER DISPOSAL OF ALL WASTES AND UNUSED BUILDING MATERIALS IS REQUIRED. 6. SEDIMENT BEING TRACED ONTO PUBLIC OR PRIVATE ROADWAYS SHALL BE MINIMIZED. CLEARING OF ACCUMULATED SEDIMENT SHALL NOT INCLUDE FLUSHING WITH WATER. CLEARED SEDIMENT SHALL BE RETURNED TO THE SITE FOR DISPOSAL. 7. SOIL WHICH HAS ACCUMULATED NEXT TO EROSION CONTROL DEVICES SHALL BE COLLECTED AND REDISTRIBUTED ON SITE AFTER EACH RAINFALL EVENT, AND AT LEAST ONCE A WEEK. 8. IF INSTALLATION OF STORM DRAINAGE SYSTEM SHOULD BE INTERRUPTED BY WEATHER OR NIGHTFALL, THE PIPE ENDS SHALL BE COVERED WITH FALTER FABRIC. 9. ALL EXISTING STRUCTURES, FENCING, TREES AND ETC., WITHIN CONSTRUCTION AREA SHALL BE REMOVED AND DISPOSED OF OFF SITE. BURNING IS NOT ALLOWED ON -SITE. 10. SCHEDULE OF EARTHWORK ACTIVITIES: a) THE DURATION OF TIME WHICH AN AREA REMAINS EXPOSED SHALL BE KEPT TO A PRACTICAL MINIMUM. THE AREA SHALL BE STABILIZED SOON AS POSSIBLE. TEMPORARY VEGETATION OR MULCHING SHALL BE USED TO PROTECT EXPOSED AREAS IF PERMANENT VEGETATION CANNOT BE SEEDED WITHIN 14 DAYS OR ACTIVITY CEASES FOR MORE THAN 21 DAYS OR AS DIRECTED BY THE ENGINEER. b) TOPSOIL REPLACEMENT SHALL TAKE PLACE FROM MARCH 1 TO OCTOBER 31. STOCKPILE TOPSOIL AT ALL OTHER TIME OF THE YEAR. PERMANENT AND FINAL VEGETATION AND STRUCTURAL EROSION CONTROL DEVICES SHALL BE INSTALLED WITHIN SEVEN (7) DAYS AFTER FINAL GRADING OR AS SOON AS POSSIBLE. EROSION CONTROL MEASURES MAINTENANCE REQUIREMENTS STRAW BALE DAM MAINTENANCE REQUIREMENTS: 1. INSPECT STRAW BALE DAMS AFTER EACH STORM EVENT AND PROMPTLY REMOVE ANY SEDIMENT DEPOSITS TO ENSURE ADEQUATE STORAGE VOLUME FOR THE NEXT RAIN, TAKING CARE NOT TO UNDERMINE THE ENTRENCHED BALES. 2. INSPECT PERIODICALLY FOR DETERIORATION OR DAMAGE FROM CONSTRUCTION ACTIVITIES AND REPAIR IMMEDIATELY. 3. AFTER THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZED, REMOVE ALL STRAW BALES AND SEDIMENT, BRING THE DISTURBED AREA TO GRADE, AND STABILIZE IT. SILT FENCE MAINTENANCE REQUIREMENTS: 1. INSPECT THE SILT FENCE PERIODICALLY AND AFTER EACH STORM EVENT. 2. IF FENCE FABRIC TEARS, STARTS TO DECOMPOSE, OR IN ANY WAY BECOMES INEFFECTIVE, REPLACE THE AFFECTED PORTION IMMEDIATELY. 3. REMOVE DEPOSITED SEDIMENT WHEN IT REACHES HALF THE HEIGHT OF THE FENCE AT ITS LOWEST POINT OR IS CAUSING THE FABRIC TO BULGE. 4. TAKE CARE TO AVOID UNDERMINING THE FENCE DURING CLEAN OUT. 5. AFTER THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZED, REMOVE THE FENCE AND SEDIMENT DEPOSITS, BRING THE DISTURBED AREA TO GRADE, AND STABILIZE. TEMPORARY SEDIMENT TRAP MAINTENANCE REQUIREMENTS: 1. INSPECT TEMPORARY SEDIMENT TRAPS AFTER EACH STORM EVENT IMMEDIATELY REPAIR ANY EROSION AND PIPING HOLES. 2. REMOVE SEDIMENT WHEN IT HAS ACCUMULATED TO ONE -HALF THE DESIGN DEPTH. 3. REPLACE SPILLWAY GRAVEL FACING IF CLOGGED. 4. INSPECT VEGETATION, AND RE -SEED IF NECESSARY. 5. CHECK THE SPILLWAY DEPTH PERIODICALLY TO ENSURE A MINIMUM OF 1.5 FT. DEPTH FROM THE LOWEST POINT OF THE SETTLED EMBANKMENT TO HIGHEST POINT OF THE SPILLWAY CREST, AND FILL ANY LOW AREAS TO MAINTAIN DESIGN ELEVATION. 6. PROMPTLY REPLACE ANY DISPLACED RIP RAP, BEING CAREFUL THAT NO STONES IN THE SPILLWAY ARE ABOVE DESIGN GRADE. 7. AFTER ALL DISTURBED AREAS HAVE BEEN STABILIZED, REMOVE THE STRUCTURE AND SEDIMENT, SMOOTH THE DISTURBED AREA TO BLEND WITH ADJOINING AREAS, AND STABILIZE. EROSION CONTROL BLANKET (SURFACE APPLIED) MAINTENANCE REQUIREMENTS: 1. DURING VEGETATIVE ESTABLISHMENT, INSPECT AFTER STORM EVENTS FOR ANY EROSION BELOW THE BLANKET. 2. IF ANY AREA SHOWS EROSION, PULL BACK THAT PORTION OF THE BLANKET COVERING IT, ADD SOIL, RE -SEED THE AREA, AND RE -LAY AND STAPLE THE BLANKET. 3. AFTER VEGETATIVE ESTABLISHMENT, CHECK THE TREATED AREA PERIODICALLY. TEMPORARY GRAVEL CONSTRUCTION ENTRANCE MAINTENANCE REQUIREMENTS: 1. INSPECT ENTRANCE PAD AND SEDIMENT DISPOSAL AREA WEEKLY AND AFTER STORM EVENTS OR HEAVY USE. 2. RESHAPE PAD AS NEEDED FOR DRAINAGE AND RUNOFF CONTROL. 3. TOP DRESS WITH CLEAN STONE AS NEEDED. 4. IMMEDIATELY REMOVE MUD AND SEDIMENT TRACKED OR WASHED ONTO PUBLIC ROADS BY BRUSHING OR SWEEPING. FLUSHING SHOULD ONLY BE USED IF THE WATER IS CONVEYED INTO A SEDIMENT TRAP OR BASIN. 5. REPAIR ANY BROKEN ROAD PAVEMENT IMMEDIATELY. EROSION AND SEDIMENT CONTROL PLAN SUMMARY AND "RULE 5" DATA PROJECT: GODDARD SCHOOL NATURE AND PURPOSE: DAYCARE ESTIMATED START: SPRING 2003 ESTIMATED COMPLETION OF SITE DEVELOPMENT: FALL 2003 FLOODPLAINS, FLOODWAY FRINGES, FLOODWAYS: NOT APPLICABLE EXISTING SOIL TYPES DESCRIPTION CROSBY SILT LOAM: DEEP, SOMEWHAT POORLY DRAINED SOIL MIAMI SILT LOAM: DEEP, WELL DRAINED SOIL RECEIVING WATERS: WHITE RIVER POTENTIAL AREAS WHERE STORMWATER MAY ENTER GROUNDWATER: NONE KNOWN EXISTING VEGETATION: THE SITE IS CURRENTLY COVERED WITH SHORT GRASSES. CONTACT PERSON: JIM PECK CIVIL DESIGNS, LLP 2415 DIRECTORS ROW, SUITE E INDIANAPOLIS, INDIANA 46241 (317) 244 -1968 ADJACENT LAND USE: NORTH COMMERCIAL SOUTH COMMERCIAL EAST RESIDENTIAL WEST COMMERCIAL SITE SPECIFIC SEQUENCE AND ADDITIONAL NOTES: THE PERIMETER SILT FENCES SHOULD BE CONSTRUCTED AND STABILIZED AS EARLY AS PRACTICAL TO PREVENT RUN -OFF FROM LEAVING THE SITE OR CLEAN OFF -SITE WATER FROM WASHING THROUGH THE SITE. EROSION CONTROL AND INLET PROTECTION SHALL BE INSTALLED IMMEDIATELY AFTER INSTALLATION OF STORM SEWERS. J SOIL CONDITION SHADE TOLERANCE CLOSE MOWING TO 2 -3 1/2 INCHES TRAMPING TOLERANCE FERTILITY NEEDS WINTER HARDINESS FLOODING TOLERANCE (DAYS) MATURE HEIGHT (INCHES) EMERGENCE TIME (DAYS) SOIL TOLERANCE WET NORM DRY GEN. SOIL SPRAY CREEPING RED FESTUCA FESCUE 3RA 2 1 2 1 1 1 MED. 1 20 -25 12 -18 7 -21 S KENTUCKY GRASS CIS POA 2 1 2 1 1 1 MED. 1 20 -35 12 -18 10 -20 MT TALL FESTUCA L. FESCUE IDINACEA 2 1 1 1 1 1 LOW 1 24 -35 24 -36 5 -14 T PERENNIAL LOLLUM (NESS 2 1 2 1 2 HIGH 2 15 -20 12 -18 5 -10 MT CROWWETCH CORONILLA RLA 1 1 2 LOW 1 5 -10 24 14 -21 T RED CLOVER "ENSE 1 2 MED. 1 7 -10 18 5 -10 S S 1 -.4 `40. 10■ (M PUBLIC ROAD 12" M INIMUM THICKNESS #2 COARSE AGGREGATE GEOTEXTILE FABRIC TO STABILIZE FOUNDATION (ESPECIALLY IMPORTANT WHERE WETNESS IS ANTICIPATED) S p, TEMPORARY CONSTRUCTION ENTRANCE NOT TO SCALE 1 GOOD 2 MEDIUM IT SEEDBED PREPARATION SEED TOLERANCE SALT TOLERANCE (TO BOTH SOIL SALTS SPRAY) T TOLERANCE MT MEDIUM TOLERANCE S SLIGHT TOLERANCE APPLY LIME J RAISE THE pH TO THE LEVEL NEEDED FOR SPECIES BEING SEEDED. APPLY 3 POUNDS OF 12 -12 -12 ANALYSIS FERTILIZER (OR EQUIVALENT) PER 1000 SQ. FT. PROXIMATELY 1000 POUNDS PER ACRE) OR FERTILIZE ACCORDING TO TEST. APPLICATION OF 150 LBS. OF AMMONIUM NITRATE ON AREAS LOW IN ORGANIC MATTER AND FERTILITY WILL GREATLY ENHANCE VEGETATIVE GROWTH. WORK THE FERTILIZER AND LIME INTO THE SOIL TO A DEPTH OF 2 -3 INCHES WITH A HARROW, DISK OR RAKE OPERATED ACROSS THE SLOPE AS MUCH AS POSSIBLE. SEEDING SELECT A :ED MIXTURE BASED ON PROJECTED USE OF THE AREA (SEE PERMANENT SEED MIXTURE CHART). WHILE CONSIDERING BEST SEEDING DATES. IF PERMANENT SEEDING IS NOT PERMITTED USE TEMPORARY SEEDING UNTIL PERMANENT SEEDING CAN BE APPLIED. IF TOLERANCES ARE A PROBLEM, SUCH AS SALT TOLERANCE OF SEEDINGS ADJACENT TO STREETS AND HIGHWAYS, SEE SEED TOLERANCE CHART. SEED TOLERANCE CHART 1 PREFERRED 2 WILL TOLERATE INOCULATE WITH SPECIFIC INOCULANT. SEEDING DETAIL WHEAT OR RYE OATS ANNUAL RYEGRASS NON- IRRIGATED* IRRIGATED DORMANT SEEDING EXTEND FABRIC TO 4" BELOW SURFACE FILTER FABRIC FLOW NOT NECESSARY WHERE MULCH IS APPLIED. NON WOVEN GEOTEXTI LE FABRIC i ce SPACE POSTS PER MANUFACTURER RECOMMENDATIONS WOOD POST SILT FENCE CONSTRUCTION TEMPORARY SEEDING DATES PERMANENT SEEDING DATES INCREASE SEEDING APPLICATION BY 50 NOT TO SCALE IRRIGATION NEEDED DURING THIS PERIOD. TO CONTROL EROSION AT TIMES OTHER THAN IN THE SHADED AREAS. USE MULCH. LATE SUMMER SEEDING DATES MAY BE EXTENDED 5 DAYS IF MULCH IS APPLIED. NOTE; POSTS SHALL HAVE A MINIMUM LENGTH OF 36 INCHES PLUS BURIAL DEPTH. POST MATERIAL SHALL BE WOOD, STEEL, OR SYNTHETIC, AND SHALL BE OF SUFFICIENT STRENGTH TO RESIST DAMAGE DURING INSTALLATION AND TO SUPPORT APPLIED LOADS. FABRIC SHALL BE A WOVEN GEOTEXTILE FABRIC CONSISTING OF STRONG, ROT RESISTANT, MATERIALS RESISTANT TO DETERIORATION FROM ULTRAVIOLET AND HEAT EXPOSURE. 1. 2 STAKES (TYP) PER BALE COMPACTED SOIL TO PREVENT PIPING STAKED STRAW BALE CHANNEL INSTALLATION NOTE: HORIZONTAL STAPLE SPACING SHOULD BE ALTERED IF NECESSARY TO ALLOW STAPLES TO SECURE THE CRITICAL POINTS ALONG THE CHANNEL SURFACE. REFER TO GENERAL STAPLE PATTERN GUIDE FOR CORRECT STAPLE RECOMMENDATIONS FOR CHANNELS. CRITICAL POINTS A. OVERLAPS AND SEAMS B. PROJECTED WATER LINE C. CHANNEL BOTTOM /SIDE SLOPE VERTICES PLAN SECTION 14649 HIGHWAY 41 NORTH, EVANSVILLE, INDIANA 47711 USA 1- 800 772 -2040 CANADA 1- 800 448 -2040 STORM INLET STRAW BALE PROTECTION NOT TO SCALE BINDINGS FOR STRAW BALES TO BE PLACED PARALLEL TO GROUND STORM INLET STRUCTURE 8. THE TERMINAL END OF THE BLANKETS MUST BE ANCHORED IN A 6" DEEP X 6" WIDE TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING. 7 PREPARE SOIL BEFORE INSTALLING BLANKETS, INCLUDING APPLICATION OF LIME, FERTILIZER, AND SEED. 2. BEGIN AT THE TOP OF THE CHANNEL BY ANCHORING THE BLANKET IN A 6" DEEP X 6" WIDE TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING. 3, ROLL CENTER BLANKET IN DIRECTION OF WATER FLOW ON BOTTOM OF CHANNEL. 4. PLACE BLANKETS END OVER END (SHINGLE STYLE) WITH A 6" OVERLAP. USE A DOUBLE ROW OF' STAGGERED STAPLES 4" APART TO SECURE BLANKETS. 5. FULL LENGTH EDGE OF BLANKETS AT TOP OF SIDE SLOPES MUST BE ANCHORED IN 6" DEEP X 6" WIDE TRENCH. BACKFILL AND COMPACT THE TRENCH AFTER STAPLING. 6. BLANKETS ON SIDE SLOPES MUST BE OVERLAPPED 4" OVER THE CENTER BLANKET AND STAPLED (2" FOR C350 MATTING). 7. IN HIGH FLOW CHANNEL APPLICATIONS, A STAPLE CHECK SLOT IS RECOMMENDED AT 30 TO 40 FOOT INTERVALS. USE A ROW OF STAPLES 4" APART OVER ENTIRE WIDTH OF THE CHANNEL. PLACE A SECOND ROW 4" BELOW THE FIRST ROW IN A STAGGERED PATTERN. EROSION CONTROL NOTES 1. ALL CONSTRUCTION METHODS AND MATERIALS MUST CONFORM TO CURRENT STANDARDS AND SPECIFICATIONS OF THE FEDERAL, STATE, COUNTY, CITY OR LOCAL REQUIREMENTS, WHICHEVER HAS JURISDICTION. 2. LAND ALTERATION WHICH STRIPS THE LAND OF VEGETATION, INCLUDING REGRADING, SHALL BE DONE IN A WAY THAT WILL MINIMIZE EROSION. 3. THIS PLAN SHALL NOT BE CONSIDERED ALL INCLUSIVE AS THE CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO PREVENT SOIL SEDIMENT FROM LEAVING THE SITE. ADDITIONAL EROSION AND SEDIMENT CONTROL MEASURES WILL BE INSTALLED IF DEEMED NECESSARY BY ON -SITE INSPECTION. 4. SEDIMENT LADEN WATER SHALL BE DETAINED BY EROSION CONTROL PRACTICES AS NEEDED TO MINIMIZE SEDIMENTATION IN THE RECEIVING STREAM. NO STORM WATER SHALL BE DISCHARGED FROM THE SITE IN A MANNER THAT CAUSES EROSION AT THE POINT OF DISCHARGE. 5. WASTES AND UNUSED BUILDING MATERIALS SHALL NOT BE ALLOWED TO BE CARRIED FROM THE SITE BY STORMWATER RUNOFF. PROPER DISPOSAL OF ALL WASTES AND UNUSED BUILDING MATERIALS IS REQUIRED. 6. SEDIMENT BEING TRACED ONTO PUBLIC OR PRIVATE ROADWAYS SHALL BE MINIMIZED. CLEARING OF ACCUMULATED SEDIMENT SHALL NOT INCLUDE FLUSHING WITH WATER. CLEARED SEDIMENT SHALL BE RETURNED TO THE SITE FOR DISPOSAL. 7. SOIL WHICH HAS ACCUMULATED NEXT TO EROSION CONTROL DEVICES SHALL BE COLLECTED AND REDISTRIBUTED ON SITE AFTER EACH RAINFALL EVENT, AND AT LEAST ONCE A WEEK. 8. IF INSTALLATION OF STORM DRAINAGE SYSTEM SHOULD BE INTERRUPTED BY WEATHER OR NIGHTFALL, THE PIPE ENDS SHALL BE COVERED WITH FALTER FABRIC. 9. ALL EXISTING STRUCTURES, FENCING, TREES AND ETC., WITHIN CONSTRUCTION AREA SHALL BE REMOVED AND DISPOSED OF OFF SITE. BURNING IS NOT ALLOWED ON -SITE. 10. SCHEDULE OF EARTHWORK ACTIVITIES: a) THE DURATION OF TIME WHICH AN AREA REMAINS EXPOSED SHALL BE KEPT TO A PRACTICAL MINIMUM. THE AREA SHALL BE STABILIZED SOON AS POSSIBLE. TEMPORARY VEGETATION OR MULCHING SHALL BE USED TO PROTECT EXPOSED AREAS IF PERMANENT VEGETATION CANNOT BE SEEDED WITHIN 14 DAYS OR ACTIVITY CEASES FOR MORE THAN 21 DAYS OR AS DIRECTED BY THE ENGINEER. b) TOPSOIL REPLACEMENT SHALL TAKE PLACE FROM MARCH 1 TO OCTOBER 31. STOCKPILE TOPSOIL AT ALL OTHER TIME OF THE YEAR. PERMANENT AND FINAL VEGETATION AND STRUCTURAL EROSION CONTROL DEVICES SHALL BE INSTALLED WITHIN SEVEN (7) DAYS AFTER FINAL GRADING OR AS SOON AS POSSIBLE. EROSION CONTROL MEASURES MAINTENANCE REQUIREMENTS STRAW BALE DAM MAINTENANCE REQUIREMENTS: 1. INSPECT STRAW BALE DAMS AFTER EACH STORM EVENT AND PROMPTLY REMOVE ANY SEDIMENT DEPOSITS TO ENSURE ADEQUATE STORAGE VOLUME FOR THE NEXT RAIN, TAKING CARE NOT TO UNDERMINE THE ENTRENCHED BALES. 2. INSPECT PERIODICALLY FOR DETERIORATION OR DAMAGE FROM CONSTRUCTION ACTIVITIES AND REPAIR IMMEDIATELY. 3. AFTER THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZED, REMOVE ALL STRAW BALES AND SEDIMENT, BRING THE DISTURBED AREA TO GRADE, AND STABILIZE IT. SILT FENCE MAINTENANCE REQUIREMENTS: 1. INSPECT THE SILT FENCE PERIODICALLY AND AFTER EACH STORM EVENT. 2. IF FENCE FABRIC TEARS, STARTS TO DECOMPOSE, OR IN ANY WAY BECOMES INEFFECTIVE, REPLACE THE AFFECTED PORTION IMMEDIATELY. 3. REMOVE DEPOSITED SEDIMENT WHEN IT REACHES HALF THE HEIGHT OF THE FENCE AT ITS LOWEST POINT OR IS CAUSING THE FABRIC TO BULGE. 4. TAKE CARE TO AVOID UNDERMINING THE FENCE DURING CLEAN OUT. 5. AFTER THE CONTRIBUTING DRAINAGE AREA HAS BEEN STABILIZED, REMOVE THE FENCE AND SEDIMENT DEPOSITS, BRING THE DISTURBED AREA TO GRADE, AND STABILIZE. TEMPORARY SEDIMENT TRAP MAINTENANCE REQUIREMENTS: 1. INSPECT TEMPORARY SEDIMENT TRAPS AFTER EACH STORM EVENT IMMEDIATELY REPAIR ANY EROSION AND PIPING HOLES. 2. REMOVE SEDIMENT WHEN IT HAS ACCUMULATED TO ONE -HALF THE DESIGN DEPTH. 3. REPLACE SPILLWAY GRAVEL FACING IF CLOGGED. 4. INSPECT VEGETATION, AND RE -SEED IF NECESSARY. 5. CHECK THE SPILLWAY DEPTH PERIODICALLY TO ENSURE A MINIMUM OF 1.5 FT. DEPTH FROM THE LOWEST POINT OF THE SETTLED EMBANKMENT TO HIGHEST POINT OF THE SPILLWAY CREST, AND FILL ANY LOW AREAS TO MAINTAIN DESIGN ELEVATION. 6. PROMPTLY REPLACE ANY DISPLACED RIP RAP, BEING CAREFUL THAT NO STONES IN THE SPILLWAY ARE ABOVE DESIGN GRADE. 7. AFTER ALL DISTURBED AREAS HAVE BEEN STABILIZED, REMOVE THE STRUCTURE AND SEDIMENT, SMOOTH THE DISTURBED AREA TO BLEND WITH ADJOINING AREAS, AND STABILIZE. EROSION CONTROL BLANKET (SURFACE APPLIED) MAINTENANCE REQUIREMENTS: 1. DURING VEGETATIVE ESTABLISHMENT, INSPECT AFTER STORM EVENTS FOR ANY EROSION BELOW THE BLANKET. 2. IF ANY AREA SHOWS EROSION, PULL BACK THAT PORTION OF THE BLANKET COVERING IT, ADD SOIL, RE -SEED THE AREA, AND RE -LAY AND STAPLE THE BLANKET. 3. AFTER VEGETATIVE ESTABLISHMENT, CHECK THE TREATED AREA PERIODICALLY. TEMPORARY GRAVEL CONSTRUCTION ENTRANCE MAINTENANCE REQUIREMENTS: 1. INSPECT ENTRANCE PAD AND SEDIMENT DISPOSAL AREA WEEKLY AND AFTER STORM EVENTS OR HEAVY USE. 2. RESHAPE PAD AS NEEDED FOR DRAINAGE AND RUNOFF CONTROL. 3. TOP DRESS WITH CLEAN STONE AS NEEDED. 4. IMMEDIATELY REMOVE MUD AND SEDIMENT TRACKED OR WASHED ONTO PUBLIC ROADS BY BRUSHING OR SWEEPING. FLUSHING SHOULD ONLY BE USED IF THE WATER IS CONVEYED INTO A SEDIMENT TRAP OR BASIN. 5. REPAIR ANY BROKEN ROAD PAVEMENT IMMEDIATELY. EROSION AND SEDIMENT CONTROL PLAN SUMMARY AND "RULE 5" DATA PROJECT: GODDARD SCHOOL NATURE AND PURPOSE: DAYCARE ESTIMATED START: SPRING 2003 ESTIMATED COMPLETION OF SITE DEVELOPMENT: FALL 2003 FLOODPLAINS, FLOODWAY FRINGES, FLOODWAYS: NOT APPLICABLE EXISTING SOIL TYPES DESCRIPTION CROSBY SILT LOAM: DEEP, SOMEWHAT POORLY DRAINED SOIL MIAMI SILT LOAM: DEEP, WELL DRAINED SOIL RECEIVING WATERS: WHITE RIVER POTENTIAL AREAS WHERE STORMWATER MAY ENTER GROUNDWATER: NONE KNOWN EXISTING VEGETATION: THE SITE IS CURRENTLY COVERED WITH SHORT GRASSES. CONTACT PERSON: JIM PECK CIVIL DESIGNS, LLP 2415 DIRECTORS ROW, SUITE E INDIANAPOLIS, INDIANA 46241 (317) 244 -1968 ADJACENT LAND USE: NORTH COMMERCIAL SOUTH COMMERCIAL EAST RESIDENTIAL WEST COMMERCIAL SITE SPECIFIC SEQUENCE AND ADDITIONAL NOTES: THE PERIMETER SILT FENCES SHOULD BE CONSTRUCTED AND STABILIZED AS EARLY AS PRACTICAL TO PREVENT RUN -OFF FROM LEAVING THE SITE OR CLEAN OFF -SITE WATER FROM WASHING THROUGH THE SITE. EROSION CONTROL AND INLET PROTECTION SHALL BE INSTALLED IMMEDIATELY AFTER INSTALLATION OF STORM SEWERS. J