HomeMy WebLinkAbout04100001 SP - Cherry Creek Estates, Section 5, Site Plan, pg 07THIS SHEET TO BE USED
FOR EROSION CONTROL ONLY.
PERSON ONSITE RESPONSIBLE FOR EROSION CONTROL:
NAME: TIM WALTER
COMPANY: PLATINUM PROPERTIES
PHONE: (317) -818 -2900
The following is a list in sequence of construction
activities to control soil erosion:
1. The contractor shall schedule a Pre construction
meeting with the Hamilton County Soil and Water
Conservation District prior to any construction on
the site being started.
2. The construction entrance installed.
3. Silt fencing for entire project installed as noted
4. Maintenance and Refueling area constructed
5. Concrete waF :gout area constructed
6. Posting information area shall be constructed. All
items, as outlined in the in the O &M manual for
Post Constuction water quality measures shall be
placed in this area.
7. Grade the site (sides of swales, mounds and
ponds to be seeded and mulched immediately upon
completion). Temporary seeding shall be
recommended for all swales and disturbed areas
that cannot be final seeded within a time period
that will prevent slope erosion. For temporary
seeding, the contractor shall utilize a fast growing
seed of either oats, annual ryegrass, wheat or rye
depending on time of year. Disturbed areas
should be kept to a minimum at all times. All
disturbed areas shall be seeded if left dormant for
more than 15 days
8. Storm inlets are to be protected immediately
after installation.
9. Contractor shall control mud accumulation on all
streets surrounding project by installing stone
surface at all locations where construction traffic
leaves the site. Dust shall be kept to a minimum
by utilizing sprinkling, Calcium Chloride, Vegetative
cover, spray on adhesives or other approved
methods.
10. Maintain all filters and traps during construction
to prevent any blockages from accumulated
sediment. Additional seeding and straw bales may
be required during construction as specified by
Engineer or Soil Conservation Service. Payment
for additional straw bales shall be at the
contractor's expense. Payment for additional
rip —rap (not shown on plans) and seeding shall be
paid for on a unit basis.
11. Contractor shall install all sanitary sewers, storm
sewers, subsurface drains, and water mains.
Straw bale filters shall be installed at all storm
inlets (including street inlets).
NOTE:
EARTHWORK CONTRACTOR SHALL INSTALL
A MINIMUM OF A 20'x300' STONE ACCESS
DRIVE PRIOR TO CONSTRUCTION.
SF SILT FENCE
PECOS
DRIVE
DIVERSION DITCH
Denotes permanent seeding mulch areas
Seeding rate: 130# /acre or 3# /1000 S.F.
Seeding mixture: 25% creeping red fescue
35% perennial rye
40% Kentucky bluegrass
Denotes seeding w /fiber blanket #S150 by North American Green
Seeding rate: 110# /acre or 2.5# /1000 S.F.
Seeding mixture: 38% Kentucky 31 fescue
19% perennial rye
19% annual rye
14% orchard grass
10% Kentucky bluegrass
07
Denotes temporary seeding Sc mulching.
Seeding rate: 50# /acre
Seeding mixture: 100% perennial rye.