HomeMy WebLinkAbout04100002 TAC Carmel Dad's Club, Concession Stand, Site Plan, pg 102'
10' MIN.
WATER MAIN
SANITARY SEWER
/CLASS 22 MECH. JOINT
C.A.. OR CLASS 2 D.I. PIPE
FLEXIBLE COUPLING OR ADAPTER
SANITARY SEWER
PLAN
ELEVATION
10' MIN.
WATER MAIN
CONC. COLLAR COUPLINGS
USf_D WHEN LESS THAN
18 OR IN CASES WHERE
WATER IS BELOW SAN. SEWER
NOTES:
Water and sewer crossings and separations shall be in accordance with
Ten State Standards and local codes.
There shall be no physical connections between a public or private water
supply system and a sanitary sewer or appurtenances thereto which would
permit the passage of any polluted water into the potable supply. Sanitary
sewers shall be laid ten (10) feet horizontally from any existing or proposed
water line. The distance shall be measured edge to edge. In cases where it
is not practical to maintain a ten (10) foot separation, the appropriate
reviewing agency may allow deviation on a case -by -case basis if supported
by data from the design engineer. Such deviation may allow installation of
the sewer closer to a water main provided that the water main is in a
separate trench or on an undisturbed earth shelf located to one side of
the sewer, and at an elevation so the bottom of the water main is at
least 18 inches above the top of the sewer.
Sanitary sewers crossing water mains shall be laid to provide a minimum
vertical separation distance of 18 inches between the outside of water main
and the outside of the sewer. This shall be the case where the water main
is either above or below the sewer. The crossing shall be arranged so that
the sewer joints will be equidistant and as far as possible from the water
main joints. Where a water main crosses under a sewer, adequate structural
support shall be provided for the sewer to prevent damage to the water main.
When it is impossible to obtain proper horizontal and vertical separation as
stipulated above, the sewer shall be designed and construe equal to water
pipe, and shall be pressure tested to assure water tightness prior to backfilling.
MIN. CROSSOVER AND SEPARATION
SA -10 NO SCALE (WATER MAINS SANI, SEWERS)
z
0
5
0
0
v_
NOTE: 1/4 Bend to
be installed at this point
when 90' deflection to
laterals req'd.
3' -0" MAX.
TC= ELEVATION
FINISH GRADE
NO SCALE
18 "x18 "x6" CONC. PAD
BLDG. DRAIN
s
CAST IRON CAP
INSTALLED FLUSH WITH
FINISHED GRADE IN
PAVEMENT AREAS
BACKFILL WITH
COMPACTED GRANULAR
MATERIAL UNDER
PAVEMENT AREAS
NO SCALE
PLAN
45* WYE
SECTION
45' ELBOW
FINISH GRADE
45' WYE
(6 "x6
CLEANOUT PLUG
ADAPTER
4" PVC
1/4 BEND
11111 IND
6" LATERAL
4 "x6" INCREASER
CLEANOUT DETAIL (PVC)
PVC CAP
INSTALLED FLUSH WITH
FINISHED GRADE IN
UNPAVED AREAS
I I I 11.7:1
BACKFILL WITH
SELECT EXCAVATED
MATERIAL FOR
UNPAVED AREAS
SEWER CLEANOUT
EXTENSION SAME
SIZE AS SEWER
UP TO 6" DIAMETER
PLUG SEAL FOR
FUTURE CONNECTION
OR CONTINUATION
OF MAIN.
--41-
III
REPLACE EXCAVATED MATERIAL
BEDDING MATERIAL TO BE
COMPACTED #8 CRUSHED STONE
NOTE: FOR ROCK OR OTHER INCOMPRESSIBLE
MATERIALS, THE TRENCH SHOULD BE OVER
EXCAVATED A MINIMUM OF 6" AND REFILLED
W #8 CRUSHED STONE.
FLEXIBLE PIPE BEDDING DETAIL
NO SCALE
TYPICAL SANITARY SEWER SPECIFICATIONS
TO BE USED FOR PRIVATE SEWER DEVELOPMENT
WITHIN
CLAY TOWNSHIP REGIONAL WASTE DISTRICT
REVISED MAY, 2002
1. Standard specifications of the Clay Township Regional Waste District (District) and Indiana
Department of Transportation shall apply for all work and materials. Pipe shall be installed in
accordance with Section 715 of the latest edition of the Indiana Department of Transportation
Standard Specifications.
1.
2. Sanitary sewer pipe shall be PVC and accordance he pipe s shall be of PVC plastic having 2 a cell
PVC pipe shall have a grooved be gasket.
classification of 12454B.
3. PVC sewer fittings shall conform to the requirements of ASTM D- 3034 -89 specification. Fittings in
sizes through 8" shall be molded in one piece with elastomeric joints and minimum socket depths as
specified in sections 6.2 and 7.3.2. Fittings 10" and larger shall be molded or fabricated in
accordance with section 7.11 with manufacturers standard pipe bells and gaskets. Wall thickness of
fittings shall be SDR 26 as defined in section 7.4.1 of specifications. Gaskets for elastomeric joints
shall be molded with a minimum cross sectional area of 0.20 square inches and conform to ASTM
F -477 specification.
4. All sanitary manholes shall be Aprecast concrete® manholes in accordance with ASTM C -478 and
Section 720. 0 -rings shall conform to C -443. Kent Seal or equivalent shall also be applied to all
joints and between riser rings and castings. Manhole step spacing shall be no more than 16- inches.
Manholes shall be air tested for leakage in accordance with ASTM C1244 -93, Standard Test Method
for Concrete Sewer Manholes by the Negative Air Pressure (Vacuum) Test.
A Installation and operation of vacuum equipment and indicating devices must be in accordance with
manufacturer =s recommendations and performance specifications which have been provided by the
manufacturer and accepted by the Engineer. The vacuum equipment must be capable of testing the
entire manhole, including the casting and riser rings.
B. With the vacuum tester set in place:
1. Connect the vacuum pump to the outlet port with the valve open.
2. Draw a vacuum of ten (10) inches of Hg. and dose the valve.
C. Accepted standards for leakage will be established from the elapsed time for a negative pressure
change from ten (10) inches to nine (9) inches of mercury. The maximum allowable leakage rate
for a four (4) foot diameter manhole must be in accordance with the following:
Minimum Elapsed Time for a
Manhole Depth Pressure Change of 1 Inch Hg
10 feet or less 60 seconds
>10 feet but <15 feet 75 seconds
>15 feet but <25 feet 90 seconds
For manholes five (5) feet in diameter, add an additional fifteen (15) seconds and for manholes six
(6) feet in diameter, add an additional thirty (30) seconds to the time requirements for four (4) foot
diameter manholes. For all manholes deeper than twenty -five (25) feet. Engineer will determine the
applicable minimum elapsed time.
D. If the manhole fails the test, necessary ssry repairs a test must be made and the vacuum test and
repairs must be repeated until the manhole passes
E. If manhole joint sealants are pulled out during the vacuum test, the manhole must be
disassembled and the joint sealants replaced.
F. Manholes will be subject to visual inspection with all visual Teaks being repaired.
5. Butyl rubber coating shall be applied around each manhole joint from 6- inches above to 6- inches
below each joint. The appropriate primer shall be applied prior to applying the rubber coating.
Inside joints to be filled with precoat plug material.
6. The manhole chimney =s including all riser rings shall be sealed using Infi Shield AUniband® or
approved equal. Prior to placement, the top 4- inches of the manhole cone and casting frame shall
be cleaned and primed. The Uniband shall extend from 3- inches below the top of the cone section
to 2- inches over the flange of the manhole casting frame.
7. The casting elevations are set by plan. However, the castings are to be adjusted in the field by
the Engineer =s representative, should a discrepancy occur between plan grade and existing grade.
New manhole ring and cover shall be installed to establish grade. Maximum height of adjusting rings
shall be 12- inches.
8. Backfill around all structures and all cuts under paved areas with granular material. Trenches
opening within 5 -feet of paved roadways shall be backfilled with granular material in accordance with
Section 211. Backfill under sidewalks shall be granular, unless the walks are constructed a minimum
of 6 months after backfill has been in place.
9. The Contractor shall be responsible for to verifying that ha all state highways, city, and county permits
have been obtained by the developer prior
The Contractor shall be required to furnish the developer =s Engineer with a set of prints, marked
in red pencil, showing actual sewer location and invert, to include lateral location, depth and length.
Such Aas built@ prints must be aterals d by the stubs termination shall shall the
be final
indicated sated contract
on payment
authorized. The sanitary sewer I the surface with a
metal fence post set immediately above the said termination point.
11. All sanitary sewer lines upon completion will be required to pass a low pressure air test. Said
test shall be conducted according to ASTM 1417 -92, and shall be witnessed by an Engineer and a
representative of the District. The testing shall be in accordance with Table 1. Add 0.5 psig for
each foot of water above the sewer line being tested.
12. Deflection tests shall be performed on all flexible* pipe after the final backfill has been in place
at least 30 days. No pipe shall exceed a vertical deflection of 57. deflection test results. *The
following are considered non flexible pipes: concrete pipe, ductile iron pipe, and cast iron pipe). The
deflection test shall be performed with a nine -point mandrel. Proving rings shall be available.
13. All mandrel testing shall be observed by a professional engineer representative for certification and
a representative of the District.
14. The ends of laterals are to be plugged tight with a braced plastic disc or cap capable of
withstanding a low pressure air test without leakage.
15. Bedding for flexible pipe shall be No. 8 crushed stone from 6- inches below the pipe to
12- inches above the pipe. Bedding for rigid pipe shall be No. 8 crushed stone from 6- inches below
the pipe to the spring line of the placed pipe n from
less than point nche 12-inches 8 cbushed bedding or
equivalent. Manholes shall be plac on no
16. Water and sewer line crossings and separations shall be in accordance with 327IAC 3 -6 -9.
17. Trench shall be opened sufficiently ahead of pipe laying to reveal obstruction, and shall be
properly protected and /or barricaded when left unattended.
18. No water shall be permitted to flow into the sanitary sewer system during construction.
Contractor shall utilize a pump to keep the water
state
and below
federal laws and Pump
regulations discharge
(327 shall
IAC be
directed to a storm outlet in accordance with
3- 6 -20). Any pipe entering existing sewers shall be plugged with screw type mechanical, braced plug
until such time as all tests on the sewers have been completed and the lines have passed all punch
lists.
19. All sewer laterals installed by the mainline Contractor shall be bedded the same as the main line
sewer.
20. trucy -ntion.ght Also, 48 hours 8 hour s n notice shall
shallbbegiven to the
given prior to District
doing prior
any testing done on the sewer.
construc. o, 4ur
21. Manhole castings shall be stamped SANITARY SEWER, Neenah Casting R 1642A or equal and be
self sealing type. The casting flange s1916eF�4and stamped the
SANITARY SEWER. shall be 24 inches.
Waterproof castings shall be Neenah R
22. The minimum slope for sewer acceptance by the Clay Township Regional Waste District are:
Size of Pipe Minimum Constructed Slope
8 -inch 0.40%
10 -inch 0.28%
12 -inch 0.22%
15 -inch 0.15%
18 -inch 0.12%
23. The Contractor shall provide measurements of the slope of the sewer for each manhole section
as construction progresses. Such measurements shall be certified by a Registered Land Surveyor or
Engineer and be available on -site for observation by the District=s Insp
n s ector. No more than three
manhole sections can be constructed in advance
24. In the event the Contractor does not meet t the h m ra pes, the o sewer section and any other
affected sewer sections shall be reconstructed
25. Laterals are to be traced with a minimum size of 14 gauge wire from the wye to the terminus.
The contractor for the building or home will extend the wire from this terminus to the building
cleanout adjacent to the building.
i
1
v)
w re
F
ce W
z
0 a
W
N
c� o
W Q Z O Q
Z W Z w t
Z� gNa
W N
S J C3 C O Z
ZZZ<
oo
0)
o
u7
N
o N
cc z a
Q
Ct v
rn
?d
w Il
fY 0
t` Q tV Lv
5 CO
r-
M
If It#
PE 10000126
t 1
STATE OF
dt
;'L c,„
111)111u o‘
Drawn By:
Checked By:
Quality Memo=
Scale:
O Scale: t' NA' NM
NMI
Sheet
C503
oat.
10/04/04
Project Number
040368 -10000
1