9:00 a.m. Docket No. 09070003 TAC: ACES Power Marketing
The applicant seeks TAC approval to construct a 2 -story building addition with relocated
parking. The site is located at 4140 W 99 St. and is zoned I- 1/Industrial. Filed by Greg
Snelling, LLC for Alliance for Cooperative Energy Service Power Marketing, LLC.
Greg Snelling with Snelling Engineering and Jim Fram with BDMD presented for the
Petitioner. Greg stated that the overall project has been scaled back since the original
plans were submitted -still working out final details. The building addition size will
remain the same, the elevations will have little change, interior components of design will
change. Office space will be on the second floor and the "uses" inside are being
decreased which will allow for traffic demands to decrease. Therefore there is no longer a
need to expand the parking area. They have heard from most of the City agencies. They
are working with 3 outstanding items from Clay Twp. Regional Waste and one item from
Dept. of Community Services regarding landscape plans and feel as though they can
work through.
Shirley Hunter -Duke Energy
-Not in Duke Energy's service territory, No comments
Greg Hoyes Hamilton County Surveyor's Office
Sent comment letter, No additional comments
Scale back will not change drainage items
Mr. Thompson with Surveyor's Office is not ok with the Phase 2 Erosion
Control Plan and issues are being worked out at this time
Nick Redden- Engineering
Outside of jurisdiction area, No comments
Ryan Hartman -Clay Township Regional Waste
Sent comment letter, No additional comments
Will review revised plans and send any additional comments at that time
Trudy Weddington DOCS Building and Code Services
Once Infrastructure items are settled, can start building permit process
Scott Brewer -Urban Forestry
Spoke with Catherine Clark and Greg Snelling prior
Will review revised plans and send any additional comments at that time
Asked if some of small islands are being eliminated or expanded
Greg stated some trees that were noted as being removed or relocated
will now remain. Feel will be some new trees and islands will be
similar to what is already shown. Some of the islands will be located by
a lot more green area rather than in the asphalt as previous plans
showed
Scott sent comments regarding structure soil and where it should or
should not go, will depend on revised plans and can work together on
looking at different options that could be less expensive
David Littlejohn -DOCS
Sent comment letter, No additional comments
Angie Conn -DOCS
Need to submit revised plans to committee
END
9:10 a.m. Docket No. 09070011 SP: Lakeland Subdivision
The applicant seeks secondary plat approval for 2 lots on 10 acres. The site is located at
12650 Clay Center Rd. and is zoned S -1 /Residence. Filed by Mike DeBoy of DeBoy
Land Development Services for Christian Browning.
Colin Paterson with DeBoy Land Development presented for the Petitioner seeking
approval for 2 lots one lot will be 2.5 acres on East side of property. Infrastructure on
both lots. Access to the 2.5 acre lot will be from Chyverton Circle. Access for east lot
will be off of Clay Center with emergency access to Chyverton Circle.
Shirley Hunter -Duke Energy
-Does not have copy of plans for this project
Referring to Stephen Vollmer Engineer at Duke (passed out contact info.)
-Both houses being built simultaneously?
-2.5 acre lot (smaller lot) being closed on soon, but not sure which
home being stated
Requested egress and degress easement with dedicated utility easement during
Primary Plat approval
Closest electrical facility is located on Clay Center Road
May have an issue with getting power to site. Suggestion was made to
tap into service that feeds from subdivision south of this area.
Need to submit Auto CAD site plan and service request to Steve so they can
start process on how to determine how to get power to that location
Greg Hoyes Hamilton County Surveyor's Office
-Will check with City of Carmel regarding drainage concerns
Petitioner to regulate the section of Elliott Creek
Easement adjustments to be made on final plat
Nick Redden- Engineering
Provided comment letter at Primary Plot Phase -most concerns stays in effect
-No further comments at this time
-Will address any issues during construction plan phase
Scott Brewer -Urban Forestry
Waiting on Construction and Landscape Plans
Last plan revision regarding the tree preservation on Landscape Plans dated
March 16, 2009 needs to also be listed on Secondary Plot Landscape Plans
(Landscape Buffer on west side is missing/not marked)
Ryan Hartman -Clay Township Regional Waste
Sent email with comments on August 10, 2009
Extension of 10 Ft. sanitary sewer easement to Lot 1 property line
David Littlejohn -DOCS- Building and Code Services
Sent comment letter, No further comments at this time
Multi -Use Path Construction agreed upon at Plan Commission
Colin asked if the "value" of the remaining 50 feet of the path that was
to be constructed within Right of Way up to the flood way can be
compensated back to the City of Carmel rather than finishing the path.
Petitioner is still finalizing
Referred to Engineering to approve and determine value amount
Angie Conn -DOCS
Waiting on full set of Construction and Landscaping Plans