From: Eric Carter [cartere @weihe.net]
Sent: Thursday, July 08, 2010 9:25 AM
To: Redden, Nick
Cc: Jamie Shinneman; Conn, Angelina V; Jon C. Dobosiewicz (E -mail)
Subject: RE: Carmel Turkey Hill resubmit
Attachments: C105 Utility Plan.PDF; C106 Traffic Plan.PDF; C201 det DETAILS 202.P IF; C001 title Title
Carmel.pdf; 2010 -07 -08 response.pdf
Good Morning Nick,
Attached are the revised sheets. Do I need to send you hard copies or can you look at the pdf's? (tryini, to stay green!).
as these were minor changes. On Sheet C202,1 revision clouded the changes.
Isn't the Carmel requirement for entrances in R/W to be Concrete? We did have a Concrete detail for t e R/W of Carmel
drive shown on our plans. The detail you are asking to be placed on the plans is Asphalt?
Thank you
Thank you,
Eric
Eric A. Carter, R.L.A., ASLA
Project Manager, Commercial Development
Weihe Engineers. Inc.
317846 -6611.
weihe.net
Original Message
From: Redden, Nick [mailto:nredden @carmel.in.gov]
Sent: Wednesday, July 07, 2010 11:30 AM
To: Eric Carter
Subject: RE: Carmel Turkey Hill resubmit
From: Eric Carter [mailto:cartere@weihe.net]
Sent: Wednesday, July 07, 2010 9:41 AM
To: Redden, Nick
Cc: Barnes, David R; Duncan, Gary R; Jamie Shinneman
Subject: RE: Carmel Turkey Hill resubmit
Hi Nick,
I just dropped off an updated set of plans for you. If you don't receive them...let me know!
Thank you
Thank you.
Eric
1
..ter W A J I F t
ENGINEERS
July 8, 2010
Mr. Nicholas Redden
Plan Review Coordinator
Department of Engineering
One Civic Square
Cannel, IN 46032
317- 571 -2441
RE: Turkey Hill Minit Markets Store #602
Project Review 1
Dear Mr. Redden:
This letter is in response to your comment email letter dated July 7, 2010 for the above
referenced project. We have prepared the following responses to the plan review comments
listed below.
Construction Drawing Review Comments
36. Comment: General Comments
b. Please add the following note to the drawings. "IF IT WILL BE NECESSARY
TO RELOCATE EXISTING UTILITIES; THE EXPENSE OI SUCH
RELOCATION SHALL BE THE RESPONSIBILITY OF THE DEVELOPER.
ALL UTILITY POLES SHA BE LOCATED WITHIN ONE FOOT OF THE
PROPOSED RIGHT—OF—WAY
Response: b. Please see Sheet C105, General Note 13 for this note.
42. Comment: Please omit Sheet L101, Landscape Plan and Sheet L201, Landscape Details
from construction sets (and their Index) to be submitted for review by the
department. The Department of Engineering does not have approval authority
over landscape plans.
Response: See omitted landscape plan from set.
44. Comment: Sheet CO01 Title Sheet
a. Please remove the titles for the Landscape Plan and Landscape
Details from the Sheet Index.
Response: a. See omitted from sheet index.
i(I1 N ol?c_!c /,:unu:• isr.r�roli._ IN 45 r n. nit ;t '7 th -hi,! t NMI 7 .7 -44!,, _;r7 F.3i f7 +,6
Allan }I. 4111 1'L i ti Yro7,3cur
121 WRIHE
ENGINEERS
Turkey Hill Minit Markets
Carmel Drive E. Rangeline Rd
July 8, 2010
Page 2 of 2
46. Comment: Please revise the text on the signs (Road Work Ahead, One Lane Road, and
flogger symbol) such that it can be read from the bottom of the plan sheet.
Please revise "100' BUFFER" such that it can he read from the right side of the
sheet.
Response: See updated sheet for text adjustments.
47. Comment: Sheet C202 SITE LAYOUT DETAILS".
a. In the CURB JOINT DETAILS, please revise the maximum spacing
between transverse expansion joints from 100 feet to 50 Indicate
a maximum spacing between transverse contraction joints of 10 feet on
tangent sections and 5 feet on radius sections. Please indicate that
the 50 feet is a maximum spacing.
b. Please acid a pavement section for areas within the City right -of -way.
This pavement section shall he 1.5 inches H1't14 #I1 surface on 2
inches HAM #8 binder on 3 inches HMA #5D base on 7 inches #53
stone on 4 inches #2 stone. Didn't find this pavement section on
Sheet C202.
Response: a. Please see sheet C202 for revised detail.
b. See sheet C202 for added detail.
Should you have any further questions or requests for additional information pertaining to this
project review, please contact me at 317- 846 -6611.
Sincerely,
Eric Carter, R.L.A.
Project Manager, Commercial Development
H:\20091w090429\docs\Subminals12010-07-08 TAC ENGINEERING 42\2010 -07 -08 Comment Ietter.doc