April 3, 2007
City of Carmel
Mr. Michael DeBoy
DeBoy Land Development Services
501 S 9th St, ste 100
Noblesville, IN 46060
RE: Holiday Inn
Dear Mr. DeBoy:
ov44
G
The following letter represents comments for this project specifically addressing the area of alternative
transportation. I have reviewed the drawings submitted for the April 19, 2007 Technical Advisory Committee
meeting and offer the following comments:
ALTERNATIVE TRANSPORTATION REVIEW COMMENTS
1) The Alternative Transportation Plan requires the construction of a 10' asphalt path along Smokey Row Rd
and a 5' sidewalk along Pro Med Dr. Please revise the plans to include and label this path.
We request that all responses to our comments be provided in writing. Failure to provide written responses may
result in delay of the review process.
It is critical that this office be made aware of all modification made on the plans being re- submitted, particularly if
any such changes are considered "new" or fall outside of our previous reviews. Please provide revised plans
indicating all revisions. Please notify us of any changes and specifically state any changes, including changes
resulting from Plan Commission, Special Studies or other committee meetings.
The Department of Community Services reserves the right to provide additional comments based on subsequent
reviews.
If you have questions, please contact me at 571 -2306.
Sincerely,
David Littlejohn
Transportation Systems Coordinator
Department of Community Services
cc: Matt Griffm, Department of Community Services
Engineering Department Review
Project File
ONE CIVIC SQUARE
Page 1
CARMEL, INDIANA 46032 317/571 -2417
CARMEL 0000622
04/12/2007 08:03 3177769628
HAMILTON CO SURVEYOR
PAGE 01/01
fe)
ii
April 12, 2007
:Kenton C. 'Ward, CEM
Surtxyor of ,Hamilton County
'clone ('y7) 77 6-S4 5)5
(Tax (317) .77'6-46'28
DeBoy Land Development Services, Inc.
ATTN: Mike DeBoy
501 South 961 Street, Suite 100
Noblesville, IN 46060
VIA FACSIMILE: 770 -1821
RE: Holiday Ian - Carmel
Dear Mr. DeBoy:
Onc .Hamilton County Square
NoGlcsvi((c, Indiana ¢bO(k' 2230
We have reviewed the construction plans submitted to the Hamilton County Surveyor's
Office on April 2, 2007, for this project and have the following comments:
1. The proposed project falls in the incorporated area and MS4 jurisdiction of the
City of Carmel
2. The proposed project DOES NOT fall in. a Carmel Wellhead Protection Zone.
3. The proposed project does not fall in a Hamilton County Regulated Drain
Watershed.
4. Please direct all storm drainage questions to the City of Carmel Engineering
Department.
5. Please note that further comments may be necessary at a later date.
Should you have any questions, I can be reached at 317 -776 -8495.
Sincerely,
Greg Ho , AC, CFM
Plan Reviewer
CC: Matt Griffin — Carmel DOCD
Amanda Foley — Carmel Engineering
Dick Hill — Carmel Engineering
Greg fiko — Crossroad Engineers
Midwest Hospitality Group — 786 -8886
CARMEL 0000623
Page 1 of 1
Conn, Angelina V
From: Brewer, Scott I
Sent: Tuesday, April 17, 2007 4:52 PM
To: Michael L. DeBoy; 'Ken Remenschneider'
Cc: Conn, Angelina V; Holmes, Christine B; Littlejohn, David W; Duncan, Gary R; Foley, Amanda J; Redden,
Nick
Subject: Holiday Inn - Pro -Med Lane
Dear Mr. DeBoy:
During my initial review of the site plans for this submittal, I noticed a few problems.
1. No where can I find on the existing conditions site plan, the landscape plan, or the site plan any visible indication
of where the right -of -way lines are. They must be shown.
2. Even on the utility plan there is no indication of drainage or utility easements. These easements and the right -of-
way must be included on the plans so that I can be made aware of potential conflicts.
3. In the US 31 overlay zone there are requirements for tree preservation. There are no indications of any tree
preservation at all. There are also many trees in the right -of -way, they must also be preserved. These need to be
shown on the existing conditions plan. Grade changes need to be taken into consideration as well.
4. This site is covered by the US 31 overlay and Section 26.04 bufferyard requirements. A chart should be
prepared and submitted on the landscape plans, which shows the amount of plant material that is required, and
the amount that is proposed.
5. There is no landscape buffer on the east side of the building. Unless a buffer is proposed to be provided and
committed to remain on the adjacent property, that does not meet the ordinance.
I will have further comments once receive this information. You may contact me by email if you have any questions or
wish to set a meeting to discuss these issues.
Scott Brewer, City Forester
Environmental Planner, DOCS
City of Carmel,
One Civic Square
Carmel, IN 46032
PH: 317- 571 -2478
FAX: 317- 571 -2426
3/5/2009
CARMEL 0000624
CARMEL TEANICAIL ADVISORY COMlVYI4E MINUTES
Date: April 18, 2007
Place: Department of Community Services Conference Room
3rd Floor - Carmel City Hall
Time: 9:00 ANI
9:00 a.m.
9:15 a.m.
Docket No. 07030034 SP: Carlson Corners Secondary Plat
The applicant seeks approval to plat 4 lots on 10.6 acres:
The site is located at 2345 West 141st Street and is zoned S1/Residential.
Filed by Reed Carlson.
Reed Carlson gave a brief overview of the project. This project has come before the TAC
Committee previously. It had presented by Chris Badger and Mr. Carlson's brother. There
are 3 lots that left to develop. Mr. Carlson indicated he has made some changes to the
plans and is nowvhoping to move this project along to completion.
David Littlejohn ROCS: has not received any plans to date. He indicated that from
previous correspondence there was a need tot a 10 ft. pathway clearly shown on the plans.
Greg Hoyes - Hamilton County Surveyor's Office. Did you receive any plans either.
However, going back a letter was sent February 2005, Greg will send previous
correspondence to Mr. Carlson'this afternoon.
Shirley Hunter - Duke Energy, gave her.eard to Mr. Carlson. She has not received any
plans. Requested a copy of the plans belemailed to her
Chuck Shupperd - Vectren Energy has not received any plans. Chuck gave a new
contact name to Mr. Carlson. This will mos;h
t:kely be a service request. Just send a site
plan.
Gary Hoyt - Carmel FirerDepartment, no comment at this time
Nick Redden- Engineering , a comment letter was sent, previously. Mr. Carlson has
given plans to Fred Glaser in Engineering — Nick will check with Fred.
Ryan Hartmanw CTRWD, has not received plans. Please resubmit. He distributed an
application to Mr. Carlson.
k?}
Scott Brewer — DOCS, does not have a new set of plans. Please submit.
J4.
Christine Barton - Holmes -DOCS — Christine did review plans and there are several
outstanding issues. A comment letter will be sent.
This project will be forwarded to a future TAC meeting for final resolution.
Docket:,, o .07030035 DP Pro Med Lane Holiday Inn . .
The applicant seeks site plan approval for a proposed full service hotel. Elevations and an
ADLS/DP Amend application will be submitted at a later date.
The site is located at 136th Street and Pro -Med Lane, and is zoned B6, within the US
31/Meridian Street Overlay.
Filed by Stacey of DeBoy Land Development Services, Inc. for Justus Home Builders, Inc.
CARMEL 0000625
• •
Colin Patterson of DeBoy Land Development Services spoke for the petitioner. He was
accompanied by: Sharon Oldham, Jon Herron and Dave Sanders of Kensington Hall
Homeowners Association and Stacy Fouts of DeBoy Land Development Services. This
property will be 103 room, 6 floor hotel. Not proposing any retention for this site. It has
been incorporated into the Marriot development.
David Littlejohn -DOCS indicated that the alternative transportation ordinance requires a
10 ft. path. This will need to be included in the plans along Smokey Row. When plans are
resubmitted this will be included.
Greg Hoyes - Hamilton County Surveyor's Office, Out of his service area.
Shirley Hunter - Duke Energy, reviewed the transformer location and indicated it may
be a difficult transformer set up. She has not visited the site yet. She indicated that a
service request will need to be made quickly, there is a 90 -120 day turn- around time for
transformers. She also requested a CAD drawing of site plan.
Chuck Shupperd - Vectren Energy, we have a gas facility there on 136th street and also
on Pro Med Lane. So all that is needed is a Customer Data sheet .
Gary Hoyt - Carmel Fire Department, distributed a letter with comments. He would
like to set up a meeting to discuss some of the following: the location of the fire
department connection, it is a high -rise building it will be sprinkled, we all request an
exterior entrance to the sprinkler riser room, discuss private fire hydrants on site
strategically located. Would like to discuss the possibility of some type of fire department
access lane either brick pavers or grass pavers that would wrap around the building , so
that aerial rescues could be conducted on the east side of the building. Also requesting a
Knox Box for emergency access and also Knox Caps it is a lockable cap that fits on
Siamese connection so that the connection is kept pristine.Would also like to see a remote
enunciator panel located at the front entrance. We need at least one elevator that is
capable of an ambulance cot. Call the office to set up a meeting to discuss.
Nick Redden- Engineering We are still reviewing the plans and we will get our
comments to you as soon as we are able.
Ryan Hartman – CTRWD, Outside of our jurisdiction.
Scott Brewer – DOCS, sent email to Mike,
Christine Barton - Holmes -DOCS, requested the elevations as soon as possible. She will
have further comments at that time.
Angie Conn – DOCS – no comments at this time.
9:30 a.m. Docket No. 07030037 DP /ADLS: Midland`Atlantic— Market Place at West Carmel
The applicant seeks site ,plan and design approval for a proposed one - story, 21,600- square
foot retail building on 2.73 acres.
The site is located at the no`rtheast'corner of 98th Street and Michigan Road, and is zoned
S1/Residential, pending reclassification to B3 /Office- Retail, and is within the US 421
Overlay.
Filed by Paul Reis of 'Bose McKinney & Evans, LLP for Midland Atlantic Properties.
CARMEL 0000626
9:15 a.m.
Docket No. 07030035 DP: Pro -Med Lane Holiday Inn
The applicant seeks site plan approval for a proposed full- service hotel. Elevations and
an ADLS /DP Amend application will be submitted at a later date.
The site is located at 136th Street and Pro -Med Lane, and is zoned B6, within the US
31 /Meridian Street Overlay.
Filed by Stacey of DeBoy Land Development Services, Inc. for Justus Home Builders,
Inc.
Colin Patterson of DeBoy Land Development Services spoke for the petitioner. He
was accompanied by: Sharon Oldham, Jon Herron and Dave Sanders of Kensington Hall
Homeowners Association and Stacy Fouts of DeBoy Land Development Services. This
property will be 103 room, 6 floor hotel. Not proposing any retention for this site. It has
been incorporated into the Marriot development.
David Littlejohn -DOCS indicated that the alternative transportation ordinance requires
a 10 ft. path. This will need to be included in the plans along Smokey Row. When plans
are resubmitted this will be included.
Greg Hoyes - Hamilton County Surveyor's Office, Out of his service area.
Shirley Hunter - Duke Energy, reviewed the transformer location and indicated it may
be a difficult transformer set up. She has not visited the site yet. She indicated that a
service request will need to be made quickly, there is a 90 -120 day turn - around time for
transformers. She also requested a CAD drawing of site plan.
Chuck Shupperd - Vectren Energy, we have a gas facility there on 136`h street and
also on Pro Med Lane. So all that is needed is a Customer Data sheet .
Gary Hoyt - Carmel Fire Department, distributed a letter with comments. He would
like to set up a meeting to discuss some of the following: the location of the fire
department connection, it is a high -rise building it will be sprinkled, we all request an
exterior entrance to the sprinkler riser room, discuss private fire hydrants on site
strategically located. Would like to discuss the possibility of some type of fire
department access lane either brick pavers or grass pavers that would wrap around the
building , so that aerial rescues could be conducted on the east side of the building. Also
requesting a Knox Box for emergency access and also Knox Caps it is a lockable cap
that fits on Siamese connection so that the connection is kept pristine.Would also like to
see a remote enunciator panel located at the front entrance. We need at least one
elevator that is capable of an ambulance cot. Call the office to set up a meeting to
discuss.
Nick Redden- Engineering We are still reviewing the plans and we will get our
comments to you as soon as we are able.
Ryan Hartman — CTRWD, Outside of our jurisdiction.
Scott Brewer — DOCS, sent email to Mike,
Christine Barton - Holmes -DOCS, requested the elevations as soon as possible. She
will have further comments at that time.
Angie Conn — DOCS — no comments at this time.
CARMEL 0000627
Page 1 of 2
Conn, Angelina V
From: Foley, Amanda J
Sent: Friday, April 20, 2007 8:15 AM
To: Brewer, Scott I; Brent A. White (baw @deboyland.com)
Cc: Conn, Angelina V; Holmes, Christine B; Duncan, Gary R; Redden, Nick
Subject: RE: Holiday Inn - Pro -Med Lane
Brent,
In an attempt to conduct a review of the stormwater pollution prevention plan for this project, it was quickly evident that
plans for this project will need to be resubmitted before I can conduct a thorough review. Some initial problems found .
were:
o The vicinity map and location map are incorrect.
• The contours cannot be depicted on C1.0
o The soils map does not identify any roads nor does it identify the project site location.
o Parts of the SWPPP are not for this project or have not been adequately addressed. Part C is referencing a linear
project for a legal drain relocation; and therefore, no post construction stormwater quality plan has been identified.
In consideration of these preliminary findings, please resubmit a complete set of plans for this project.
If you have any questions, please contact me.
Thanks,
Amanda Foley
Storm Water Administrator
City of Carmel
Department of Engineering
One Civic Square
Carmel, IN 46032
(317) 571 -2314
(317) 571 -2439 (fax)
afoley @carmel.in.gov
From: Brewer, Scott I
Sent: Tuesday, April 17, 2007 4:52 PM
To: Michael L. DeBoy; 'Ken Remenschneider'
Cc: Conn, Angelina V; Holmes, Christine B; Littlejohn, David W; Duncan, Gary R; Foley, Amanda J; Redden, Nick
Subject: Holiday Inn - Pro -Med Lane
Dear Mr. DeBoy:
During my initial review of the site plans for this submittal, I noticed a few problems.
1. No where can I find on the existing conditions site plan, the landscape plan, or the site plan any visible
indication of where the right -of -way lines are. They must be shown.
2. Even on the utility plan there is no indication of drainage or utility easements. These easements and the
right -of -way must be included on the plans so that I can be made aware of potential conflicts.
3. In the US 31 overlay zone there are requirements for tree preservation. There are no indications of any
3/5/2009
CARMEL 0000628
Page 2 of 2
tree preservation at all. There are also many trees in the right -of -way, they must also be preserved. These
need to be shown on the existing conditions plan. Grade changes need to be taken into consideration as
well.
4. This site is covered by the US 31 overlay and Section 26.04 bufferyard requirements. A chart should be
prepared and submitted on the landscape plans, which shows the amount of plant material that is required,
and the amount that is proposed.
5. There is no landscape buffer on the east side of the building. Unless a buffer is proposed to be provided
and committed to remain on the adjacent property, that does not meet the ordinance.
will have further comments once receive this information. You may contact me by email if you have any questions or
wish to set a meeting -to discuss these issues.
Scott Brewer, City Forester
Environmental Planner, DOCS
City of Carmel,
One Civic Square
Carmel, IN 46032
PH: 317- 571 -2478
FAX: 317- 571 -2426
3/5/2009
CARMEL 0000629