HomeMy WebLinkAbout04610066.01 Volume 2 of 2 Specs.pdf
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TABLE OF CONTENTS Page 1 DIVISION 00 -PROCUREMENT AND CONTRACTING REQUIREMENTS 00 11 16 INVITATION TO BID ----------SUBCONTRACTOR BID LIST 00 21 13 INSTRUCTIONS TO BIDDERS 00 41 00 BID
FORM 00 43 25 SUBSTITUTION REQUEST FORM (DURING BIDDING) 00 43 30 SUBCONTRACTORS AND MATERIALS LISTING 00 45 19 NON-COLLUSION AFFIDAVIT 00 50 00 CONTRACTING FORMS AND SUPPLEMENTS 00
52 13 STANDARD FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR WHERE THE BASIS FOR PAYMENT IS A STIPULATED SUM (AIA DOCUMENT A101-2007) 00 61 13 PERFORMANCE AND PAYMENT BOND FORM (AIA
DOCUMENT A312-1984) 00 62 11 SUBMITTAL TRANSMITTAL FORM (SAMPLE) 00 62 76 APPLICATION AND CERTIFICATE FOR PAYMENT (AIA DOCUMENT G702-1992) 00 62 76.13 CONTINUATION SHEET (AIA DOCUMENT
G703-1992) 00 62 76.16 CONSENT OF SURETY TO REDUCTION IN OR PARTIAL RELEASE OF RETAINAGE (AIA DOCUMENT G707A-1994) 00 63 13 REQUEST FOR INTERPRETATION FORM (RFI) 00 63 53 WORK CHANGES
PROPOSAL REQUEST FORM (AIA DOCUMENT G709-2001) 00 63 63 CHANGE ORDER FORM (AIA DOCUMENT G701-2001) 00 65 16 CERTIFICATE OF SUBSTANTIAL COMPLETION FORM (AIA DOCUMENT G704-2000) 00 65
19.13 CONTRACTOR'S AFFIDAVIT OF PAYMENT OF DEBTS AND CLAIMS (AIA DOCUMENT G706-1994) 00 65 19.16 CONTRACTOR'S AFFIDAVIT OF RELEASE OF LIENS (AIA DOCUMENT G706A-1994) 00 65 19.19 CONSENT
OF SURETY COMPANY TO FINAL PAYMENT (AIA DOCUMENT G707-1994) 00 72 00 GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION (AIA DOCUMENT A201-2007)
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TABLE OF CONTENTS Page 2 00 73 00 SUPPLEMENTARY CONDITIONS 00 73 36 EQUAL EMPLOYMENT OPPORTUNITY REQUIREMENTS 00 73 73.23 MEDICARE AND MEDICAID ACCOUNTING REQUIREMENTS ----------ST.
VINCENT HOSPITALS AND HEALTH SERVICES – CONTRACTOR/VENDOR ORIENTATION AND REFERENCE MANUAL DIVISION 01 -GENERAL REQUIREMENTS 01 11 00 SUMMARY OF WORK 01 14 00 WORK RESTRICTIONS 01 21
00 ALLOWANCES 01 29 00 PAYMENT PROCEDURES 01 33 00.13 SUBMITTAL PROCEDURES (WITHOUT DOCUNET) 01 35 33 INFECTION CONTROL PROCEDURES 01 40 00 QUALITY REQUIREMENTS 01 42 00 REFERENCES 01
50 00 TEMPORARY FACILITIES AND CONTROLS 01 60 00 PRODUCT REQUIREMENTS 01 73 00 EXECUTION 01 73 29 CUTTING AND PATCHING 01 77 00 CLOSEOUT PROCEDURES 01 78 23 OPERATION AND MAINTENANCE
DATA 01 78 39 PROJECT RECORD DOCUMENTS 01 79 00 DEMONSTRATION AND TRAINING DIVISION 06 -WOOD, PLASTICS, AND COMPOSITES 06 05 73 WOOD TREATMENT 06 10 00 ROUGH CARPENTRY
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TABLE OF CONTENTS Page 3 06 40 00 ARCHITECTURAL WOODWORK 06 61 16 SOLID SURFACING FABRICATIONS DIVISION 07 -THERMAL AND MOISTURE PROTECTION 07 21 00 THERMAL INSULATION 07 81 16 CEMENTITIOUS
FIREPROOFING 07 84 00 FIRESTOPPING 07 92 00 JOINT SEALANTS 07 95 13 EXPANSION JOINT COVER ASEMBLIES DIVISION 08 -OPENINGS 08 12 13 HOLLOW METAL FRAMES 08 14 16 FLUSH WOOD DOORS 08 31
00 ACCESS DOORS AND PANELS 08 35 13.23 FOLDING FIRE DOORS 08 71 00 DOOR HARDWARE 08 71 13 AUTOMATIC DOOR OPERATORS 08 81 00 GLASS GLAZING DIVISION 09 -FINISHES 09 05 60 COMMON WORK RESULTS
FOR FLOORING PREPARATION 09 21 16 GYPSUM BOARD ASSEMBLIES 09 30 00 TILING 09 51 00 ACOUSTICAL CEILINGS 09 65 00 RESILIENT FLOORING 09 68 00 CARPETING
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TABLE OF CONTENTS Page 4 09 72 00 WALL COVERINGS 09 84 33 SOUND ABSORBING WALL UNITS 09 91 00 PAINTING AND FINISHING 09 96 00 HIGH-PERFORMANCE COATINGS DIVISION 10 -SPECIALTIES 10 11
00 VISUAL DISPLAY SURFACES 10 21 23 CUBICLES 10 26 00 WALL AND DOOR PROTECTION 10 28 13 TOILET ACCESSORIES 10 44 00 FIRE PROTECTION SPECIALTIES 10 51 13 METAL LOCKERS DIVISION 12 -FURNISHINGS
12 22 00 CURTAINS AND DRAPES 12 24 13 ROLLER WINDOW SHADES DIVISION 21 -FIRE SUPPRESSION 21 05 00 COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 13 13 FIRE-SUPPRESSION PIPING DIVISION 22
-PLUMBING 22 05 00 COMMON WORK RESULTS FOR PLUMBING 22 05 19 METERS AND GAGES FOR PLUMBING PIPING 22 05 23 GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 05 29 HANGERS AND SUPPORTS FOR PLUMBING
PIPING AND EQUIPMENT
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TABLE OF CONTENTS Page 5 22 05 53 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT 22 07 00 PLUMBING INSULATION 22 11 16 DOMESTIC WATER PIPING 22 13 16 STORM, SANITARY WASTE AND VENT
PIPING 22 13 19 PLUMBING SPECIALTIES 22 42 00 PLUMBING FIXTURES 22 63 13 MEDICAL GAS PIPING DIVISION 23 -HEATING VENTILATING AND AIR CONDITIONING 23 05 00 COMMON WORK RESULTS FOR HVAC
23 05 13 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT 23 05 23 GENERAL DUTY VALVES FOR HVAC PIPING 23 05 29 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 48 VIBRATION AND
SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 07 00 HVAC INSULATION 23 09
01 ENVIRONMENTAL CONTROL SYSTEM 23 21 13 HYDRONIC PIPING 23 31 13 METAL DUCTS 23 33 00 AIR DUCT ACCESSORIES 23 34 23 HVAC POWER VENTILATORS 23 36 00 AIR TERMINAL UNITS 23 37 13 DIFFUSERS,
REGISTERS, AND GRILLES 23 82 16 AIR COILS
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TABLE OF CONTENTS Page 6 DIVISION 26 -ELECTRICAL 26 05 00 COMMON WORK RESULTS FOR ELECTRICAL 26 05 19 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 26 05 26 GROUNDING AND BONDING
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 05 36 CABLE TRAYS FOR ELECTRICAL SYSTEMS 26 05 53 IDENTIFICATION FOR ELECTRICAL
SYSTEMS 26 24 16 PANELBOARDS 26 27 26 WIRING DEVICES 26 28 13 FUSES 26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS 26 29 13 ENCLOSED CONTROLLERS 26 51 00 INTERIOR LIGHTING DIVISION
27 -COMMUNICATIONS 27 05 00 COMMON WORK RESULTS FOR COMMUNICATIONS 27 41 33 MASTER ANTENNA TELEVISION SYSTEM 27 51 16 PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS 27 52 23 NURSE CALL/CODE
BLUE SYSTEMS 27 60 00 SYSTEM ROUGH-IN REQUIREMENTS DIVISION 28 -ELECTRONIC SAFETY AND SECURITY 28 05 00 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY 28 31 00 FIRE ALARM SYSTEM
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 -1 SECTION 21 05 00 -COMMON WORK RESULTS FOR FIRE SUPPRESSION PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions
of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Piping
materials and installation instructions common to most piping systems. 2. Sleeves. 3. Escutcheons. 4. Fire-suppression piping demolition. 5. Supports and anchorages. 1.3 QUALITY ASSURANCE
A. Steel Support Welding: Qualify processes and operators according to AWS D1.1, "Structural Welding Code--Steel." B. Steel Pipe Welding: Qualify processes and operators according to
ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications." 1. Comply with provisions in ASME B31 Series, "Code for Pressure Piping." 2. Certify that each
welder has passed AWS qualification tests for welding processes involved and that certification is current. C. Electrical Characteristics for Fire-Suppression Equipment: Equipment of
higher electrical characteristics may be furnished provided such proposed equipment is approved in writing and connecting electrical services, circuit breakers, and conduit sizes are
appropriately modified. If minimum energy ratings or efficiencies are specified, equipment shall comply with requirements. 1.4 DELIVERY, STORAGE, AND HANDLING A. Deliver pipes and tubes
with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 -2 1.5 COORDINATION A. Arrange for pipe spaces, chases, slots, and openings in building structure during progress of construction, to
allow for fire-suppression installations. B. Coordinate installation of required supporting devices and set sleeves in poured-in-place concrete and other structural components as they
are constructed. C. Coordinate requirements for access panels and doors for fire-suppression items requiring access that are concealed behind finished surfaces. Access panels and doors
are specified in Division 8 Section "Access Doors and Frames." PART 2 -PRODUCTS 2.1 MANUFACTURERS A. In other Part 2 articles where subparagraph titles below introduce lists, the following
requirements apply for product selection: 1. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified. 2.2 PIPE, TUBE, AND FITTINGS A.
Refer to individual Division 21 piping Sections for pipe, tube, and fitting materials and joining methods. B. Pipe Threads: ASME B1.20.1 for factory-threaded pipe and pipe fittings.
2.3 JOINING MATERIALS A. Refer to individual Division 21 piping Sections for special joining materials not listed below. B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal
conditions of piping system contents. 1. Thermoseal C-4401, 1/16 inch thick. Do not apply gasket compounds, adhesives, or antistick lubricants to gaskets. C. Flange Bolts and Nuts: ASME
B18.2.1, carbon steel, unless otherwise indicated. D. Welding Filler Metals: Comply with AWS D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel
pipe being welded.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 -3 2.4 SLEEVES A. Galvanized-Steel Sheet: 0.0239-inch minimum thickness; round tube closed with welded longitudinal joint. B. Steel
Pipe: ASTM A 53, Schedule 40 for up to 10 inches NPS, standard weight for 12 inches NPS and larger, fabricated with 2 inches integral seal welded water stop, finished assembly painted
with zinc rich paint. C. Cast Iron: Cast or fabricated "wall pipe" equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop, unless otherwise indicated. D. Stack
Sleeve Fittings: Manufactured, cast-iron sleeve with integral clamping flange. Include clamping ring and bolts and nuts for membrane flashing. 1. Underdeck Clamp: Clamping ring with
set screws. E. Stainless Steel Sheet: Fabricated 304L stainless steel, 0.078-inch minimum thickness, round tube closed with welded longitudinal joint, fabricated with 2 inches integral
welded water stop. 2.5 ESCUTCHEONS A. Description: Manufactured wall and ceiling escutcheons and floor plates, with an ID to closely fit around pipe, tube, and insulation of insulated
piping and an OD that completely covers opening. B. One-Piece, Cast-Brass Type: With set screw. 1. Finish: Polished chrome-plated. C. Split-Casting, Cast-Brass Type: With concealed hinge
and set screw. 1. Finish: Polished chrome-plated. D. One-Piece, Stamped-Steel Type: With set screw or spring clips and chrome-plated finish. PART 3 -EXECUTION 3.1 FIRE-SUPPRESSION DEMOLITION
A. Refer to Division 1 Section "Cutting and Patching" and Division 2 Section "Selective Structure Demolition" for general demolition requirements and procedures. B. Disconnect, demolish,
and remove fire-suppression systems, equipment, and components indicated to be removed.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 -4 1. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible
piping material. C. If pipe, insulation, or equipment to remain is damaged in appearance or is unserviceable, remove damaged or unserviceable portions and replace with new products of
equal capacity and quality. 3.2 PIPING SYSTEMS -COMMON REQUIREMENTS A. Install piping according to the following requirements and Division 21 Sections specifying piping systems. B. Drawing
plans, schematics, and diagrams indicate general location and arrangement of piping systems. Indicated locations and arrangements were used to size pipe and calculate friction loss,
expansion, pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved on Coordination Drawings. C. Install piping in concealed
locations, unless otherwise indicated and except in equipment rooms and service areas. D. Install piping indicated to be exposed and piping in equipment rooms and service areas at right
angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise. E. Install piping above accessible ceilings to allow sufficient space for
ceiling panel removal. F. Install piping to permit valve servicing. G. Install piping at indicated slopes. H. Install piping free of sags and bends. I. Install fittings for changes in
direction and branch connections. J. Select system components with pressure rating equal to or greater than system operating pressure. K. Install escutcheons for penetrations of walls,
ceilings, and floors in exposed areas. In dietary, kitchen, cafeteria, sterile processing, sterilizer, sub-sterile and sterile areas do not install escutcheons, but seal pipe penetration
airtight with food grade silicone. L. New concrete floors, walls and roof penetrations are required to have sleeves cast in place (no core drilling unless specifically noted on the Drawings).
For core drilled holes, grout sleeve into concrete, completely filling void between sleeve and hole and maintain fire rating. Coredrilled structures are required to be reinforced as
noted on structural drawings.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 -5 M. Install sleeves for pipes passing through concrete and masonry walls, fire rated gypsum-board partitions, and concrete floor and
roof slabs. 1. Cut sleeves to length for mounting flush with both surfaces. a. Exception: Extend top of sleeves installed in all floors 2 inches above finished floor level. Touch-up
cut ends of galvanized pipe sleeves with zinc-rich coating. Waterstop shall be wholly contained within concrete with approximately 1-1/2 inches of concrete cover. Extend cast-iron sleeve
fittings below floor slab as required to secure clamping ring if ring is specified. 2. Install sleeves in new walls and slabs as new walls and slabs are constructed. 3. Install sleeves
that are large enough to provide 1/4-inch annular clear space between sleeve and pipe or pipe insulation. Use the following sleeve materials. a. Cast Iron or Steel Pipe Sleeves or Stainless
Steel Sheet Sleeves: For pipes penetrating other than gypsum board partitions or walls. b. Galvanized Steel Sheet Sleeves: For pipes penetrating gypsum-board partitions or walls. 4.
Except for underground wall penetrations, seal annular space between sleeve and pipe or pipe insulation, using joint sealants appropriate for size, depth, and location of joint. Refer
to Division 7 Section "Joint Sealants" for materials and installation. N. Fire-Barrier Penetrations: Maintain indicated fire rating of walls, partitions, ceilings, and floors at pipe
penetrations. Seal pipe penetrations with firestop materials. Refer to Division 7 Section "Firestopping" for materials. O. Verify final equipment locations for roughing-in. P. Install
pipe and hangers so that they do not interfere with fully opening access panels on any in structure, or any access panels on any equipment (contract provided or Owner provided). 3.3
PIPING JOINT CONSTRUCTION A. Join pipe and fittings according to the following requirements and Division 21 Sections specifying piping systems. B. Ream ends of pipes and tubes and remove
burrs. Bevel plain ends of steel pipe. C. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly. D. Threaded Joints: Thread pipe with tapered
pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 -6 1. Apply appropriate tape or thread compound to external pipe threads unless dry seal threading is specified. 2. Damaged Threads:
Do not use pipe or pipe fittings with threads that are corroded or damaged. Do not use pipe sections that have cracked or open welds. E. Welded Joints: Construct joints according to
AWS D10.12, using qualified processes and welding operators according to Part 1 "Quality Assurance" Article. F. Flanged Joints: Select appropriate gasket material, size, type, and thickness
for service application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads. 3.4 ERECTION OF METAL SUPPORTS AND ANCHORAGES A. Refer to Division 5 Section
"Metal Fabrications" for structural steel. B. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor fire-suppression
materials and equipment. C. Field Welding: Comply with AWS D1.1. 3.5 ERECTION OF WOOD SUPPORTS AND ANCHORAGES A. Cut, fit, and place wood grounds, nailers, blocking, and anchorages to
support, and anchor firesuppression materials and equipment. B. Select fastener sizes that will not penetrate members if opposite side will be exposed to view or will receive finish
materials. Tighten connections between members. Install fasteners without splitting wood members. C. Attach to substrates as required to support applied loads. END OF SECTION 21 05 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -1 SECTION 21 13 13 -FIRE-SUPPRESSION PIPING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General
and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes fire-suppression piping and equipment for the following
building systems: 1. Wet-pipe, fire-suppression sprinklers, including piping, valves, specialties, and automatic sprinklers. B. Related Sections include the following: 1. Division 10
Section "Fire Extinguisher Cabinets" and "Fire Extinguishers" for cabinets and fire extinguishers. 2. Division 22 Section "Plumbing Specialties" for double check valve assemblies. 3.
Division 28 Section "Fire Detection and Alarm Systems" for alarm devices not in this Section. Section. C. Sprinkler piping shall be seismically restrained in accordance with NFPA 13
and the Building Code. As a minimum, all sprinkler piping in Seismic Design Category C, D, E, and F shall be seismically restrained using a component importance factor = 1.5. 1.3 DEFINITIONS
A. Hose Connection: Valve with threaded outlet matching fire hose coupling thread for attaching fire hose. B. Working Plans: Documents, including drawings, calculations, and material
specifications prepared according to NFPA 13 for obtaining approval from authorities having jurisdiction. 1.4 SYSTEM PERFORMANCE REQUIREMENTS A. Design standpipes and sprinklers to provide
a penalty-free insurance rating as determined by the Owner’s Underwriter and obtain approval from authorities having jurisdiction and Owner’s Insurance Company.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -2 1. Sprinkler Occupancy Hazard Classifications: As follows: a. Building Service Areas: Ordinary Hazard, Group 1. b. Electrical Equipment Rooms: Ordinary
Hazard, Group 1. c. General Storage Areas: Ordinary Hazard, Group 1. d. Office and Public Areas: Light Hazard. e. All Patient Care, Treatment and Customary Access Areas: Light Hazard.
2. Minimum Density for Automatic-Sprinkler Piping Design: As follows: a. Light-Hazard Occupancy: 0.10 gpm over 1500-sq. ft. area. b. Ordinary-Hazard, Group 1 Occupancy: 0.15 gpm over
1500-sq. ft. area. c. Ordinary-Hazard, Group 2 Occupancy: 0.20 gpm over 1500-sq. ft. area. 3. Maximum Protection Area per Sprinkler: As follows: a. Office Space, Patient Care, Treatment,
and Customary Access Areas: 225 sq. ft. b. Storage Areas: 130 sq. ft. c. Mechanical Equipment Rooms: 130 sq. ft. d. Electrical Equipment Rooms: 130 sq. ft. e. Other Areas: According
to NFPA 13 recommendations, unless otherwise indicated. B. Components and Installation: Capable of producing piping systems with 175-minimum working-pressure rating, unless otherwise
indicated. C. Extended Coverage Heads and The Area Density Reduction Calculation Method (NFPA 13, 5-2, 3, 2, 4) shall not be used. 1.5 SUBMITTALS A. Shop drawings shall include the following:
1. Sprinkler piping on ceiling plans to scale. 2. Sprinkler head locations. 3. Accessory locations and details (valves, gages, etc.). 4. Certification and approval of State Fire Marshal,
Owner’s Underwriter and Owner’s Fire Protection Engineer. B. Submit complete shop drawings to the Architect/Engineer for review before submission to Agency having jurisdiction for approval.
Submit approved copies bearing stamp and/or signature of Agency having jurisdiction, Owner’s Insurance Underwriter and Owner’s Fire Protection Engineer for approval to Architect/Engineer
before proceeding with installation.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -3 C. Product Data: For the following: 1. Pipe and fitting materials and methods of joining for sprinkler piping. 2. Pipe hangers and supports. 3. Valves,
including specialty valves, accessories, and devices. 4. Alarm devices. Include electrical data. 5. Sprinklers, escutcheons, and guards. Include sprinkler flow characteristics, mounting,
finish, and other pertinent data. D. Fire-Hydrant Flow Test Report: As specified in "Preparation" Article. E. Approved Sprinkler Piping Drawings: Working plans, prepared according to
NFPA 13, that have been approved by authorities having jurisdiction. Include hydraulic calculations. F. Field Test Reports and Certificates: Indicate and interpret test results for compliance
with performance requirements and as described in NFPA 13 and NFPA 14. Include ""Contractor's Material and Test Certificate for Aboveground Piping" and "Contractor's Material and Test
Certificate for Underground Piping." G. Maintenance Data: For each type of standpipe and sprinkler specialty to include in maintenance manuals specified in Division 1. 1.6 QUALITY ASSURANCE
A. Installer Qualifications: An experienced installer who has designed and installed firesuppression piping similar to that indicated for this Project and obtained design approval and
inspection approval from authorities having jurisdiction. B. Engineering Responsibility: Preparation of working plans, calculations, and field test reports by a qualified Sprinkler Contractor.
Base calculations on results of fire-hydrant flow test. C. Manufacturer Qualifications: Firms whose equipment, specialties, and accessories are listed by product name and manufacturer
in UL's "Fire Protection Equipment Directory" and FM's "Fire Protection Approval Guide" and that comply with other requirements indicated. D. Standpipe and Sprinkler Components: Listing/approval
stamp, label, or other marking by a testing agency acceptable to authorities having jurisdiction. E. Electrical Components, Devices, and Accessories: Listed and labeled as defined in
NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction. F. NFPA Standards: Equipment, specialties, accessories, installation, and testing complying with
the following: 1. NFPA 13, "Installation of Sprinkler Systems."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -4 1.7 EXTRA MATERIALS A. Furnish extra materials described below that match products installed and that are packaged with protective covering for storage
and identified with labels describing contents. 1. Sprinkler Cabinets: Finished, wall-mounting steel cabinet and hinged cover, with space for a minimum of six spare sprinklers plus sprinkler
wrench. Include the number of sprinklers required by NFPA 13 and wrench for sprinklers. Include separate cabinet with sprinklers and wrench for each type of sprinkler on Project. PART
2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the manufacturers as listed in FM approval guide. 2.2 PIPES AND TUBES
A. Standard-Weight Steel Pipe: Black, galvanized ASTM A 53, ASTM A 135 Schedule 40 with roll or cut grooved, threaded or welded joints. B. Schedule 10 Steel Pipe: Black, galvanized ASTM
A 135, Schedule 10 with roll grooved or welded joints 2.3 PIPE AND TUBE FITTINGS A. Cast-Iron Threaded Fittings: ASME B16.4. B. Malleable-Iron Threaded Fittings: ASME B16.3. C. Steel,
Threaded Couplings: ASTM A 865. D. Steel Welding Fittings: ASTM A 234/A 234M, ASME B16.9, or ASME B16.11. E. Steel Flanges and Flanged Fittings: ASME B16.5. F. Steel, Grooved-End Fittings:
UL-listed and FM-approved, ASTM A 47malleable iron or ASTM A 536, ductile iron; with dimensions matching steel pipe and ends factory grooved according to AWWA C606.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -5 2.4 JOINING MATERIALS A. Refer to Division 21 Section "Common Work Results for Fire Suppression" for pipe-flange gasket materials and welding filler
metals. 2.5 GENERAL-DUTY VALVES A. Refer to Division 22 Section "General Duty Valves for Plumbing Piping" for gate, ball, butterfly, globe, and check valves not required to be UL listed
and FM approved. 2.6 FIRE-PROTECTION-SERVICE VALVES A. General: UL listed and FM approved, with minimum 175-psignonshock working-pressure rating. Valves for grooved-end piping may be
furnished with grooved ends instead of type of ends specified. B. Gate Valves, NPS 2 and Smaller: UL 262; cast-bronze, threaded ends; solid wedge; OS&Y; and rising stem. C. Gate Valves,
NPS 2-1/2 and Larger: UL 262, iron body, bronze mounted, taper wedge, OS&Y, and rising stem. Include replaceable, bronze, wedge facing rings and flanged ends. D. Swing Check Valves,
NPS 2 and Smaller: UL 312 or MSS SP-80, Class 150; bronze body with bronze disc and threaded ends. E. Swing Check Valves, NPS 2-1/2 and Larger: UL 312, cast-iron body and bolted cap,
with bronze disc or cast-iron disc with bronze-disc ring and flanged ends. 2.7 SPECIALTY
VALVES A. Alarm Check Valves: UL 193, 175-psig working pressure; designed for horizontal or vertical installation, with cast-iron flanged inlet and outlet, bronze grooved seat with O-ring
seals, and single-hinge pin and latch design. Include trim sets for bypass, drain, electric sprinkler alarm switch, pressure gages, retarding chamber, and fill-line attachment with strainer.
1. Option: Grooved-end connections for use with keyed couplings. 2. Drip Cup Assembly: Pipe drain without valves, and separate from main drain piping. 2.8 SPRINKLERS A. Automatic Sprinklers:
With heat-responsive element complying with the following: 1. UL 199, for applications except residential.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -6 B. Sprinkler Types and Categories: Nominal 1/2-inch orifice for "Ordinary" temperature classification rating, unless otherwise indicated or required
by application. C. Sprinkler types, features, and options include the following: 1. Flat Concealed ceiling quick response sprinklers, including cover plate. 2. Pendent sprinklers. 3.
Upright sprinklers. D. Sprinkler Finishes: Chrome-plated, bronze, and painted. E. Sprinkler Guards: Wire-cage type, including fastening device for attaching to sprinkler. 2.9 SPECIALTY
SPRINKLER FITTINGS A. Specialty Fittings: UL listed and FM approved; made of steel, ductile iron, or other materials compatible with piping. B. Mechanical-T Fittings: UL 213, ductile-iron
housing with pressure-responsive gasket, bolts, and threaded or locking-lug outlet. C. Mechanical-Cross Fittings: UL 213, ductile-iron housing with pressure-responsive gaskets, bolts,
and threaded or locking-lug outlets. D. Sprinkler, Drain and Alarm Test Fittings: UL-listed, cast-or ductile-iron body; with threaded inlet and outlet, test valve, and orifice and sight
glass. E. Sprinkler, Branch-Line Test Fittings: UL-listed, brass body; with threaded inlet and capped drain outlet and threaded outlet for sprinkler. F. Sprinkler, Inspector's Test Fittings:
UL-listed, cast-or ductile-iron housing; with threaded inlet and drain outlet and sight glass. 2.10 ALARM DEVICES A. General: Types matching piping and equipment connections. B. Water-Flow
Indicators: UL 346; electrical-supervision, vane-type water-flow detector; with 250-psig pressure rating; and designed for horizontal or vertical installation. Include two single-pole,
double-throw, circuit switches for isolated alarm and auxiliary contacts, 7 A, 125-V ac and 0.25 A, 24-V dc; complete with factory-set, field-adjustable retard element to prevent false
signals and tamperproof cover that sends signal if removed.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -7 C. Pressure Switches: UL 753; electrical-supervision-type, water-flow switch with retard feature. Include single-pole, double-throw, normally closed
contacts and design that operates on rising pressure and signals water flow. D. Valve Supervisory Switches: UL 753; electrical; single-pole, double throw; with normally closed contacts.
Include design that signals controlled valve is in other than fully open position. 2.11 PRESSURE GAGES A. Pressure Gages: UL 393, 3-1/2-to 4-1/2-inch diameter dial with dial range of
0 to 250 psig. PART 3 -EXECUTION 3.1 PREPARATION A. Perform fire-hydrant flow test according to NFPA 13 and NFPA 291. Use results for system design calculations required in "Quality
Assurance" Article in Part 1 of this Section. B. Report test results promptly and in writing. writing. 3.2 PIPING APPLICATIONS A. Do not use welded joints with galvanized steel pipe.
B. Use black steel pipe in wet pipe sprinkler systems. C. Use Schedule 40 pipe on all 1" vertical drops and sprigs. D. Flanges, unions, and transition and special fittings with pressure
ratings the same as or higher than system's pressure rating may be used in aboveground applications, unless otherwise indicated. 3.3 VALVE APPLICATIONS A. Drawings indicate valve types
to be used. Where specific valve types are not indicated, the following requirements apply: 1. Fire-Protection-Service Valves: UL listed and FM approved for applications where required
by NFPA 13. a. Shutoff Duty: Use gate valves.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -8 2. General-Duty Valves: For applications where UL-listed and FM-approved valves are not required by NFPA 13. a. Shutoff Duty: Use gate, ball, or butterfly
valves. b. Throttling Duty: Use globe, ball, or butterfly valves. 3.4 JOINT CONSTRUCTION A. Refer to Division 21 Section "Common Work Results for Fire Suppression" for basic piping joint
construction. 3.5 PIPING INSTALLATION A. Refer to Division 21 Section "Common Work Results for Fire Suppression" for basic piping installation. B. Locations and Arrangements: Drawing
plans, schematics, and diagrams indicate general location and arrangement of piping. Install piping as indicated, as far as practical. 1. Deviations from approved working plans for piping
require written approval from authorities having jurisdiction. File written approval with Architect/Engineer before deviating from approved working plans. C. Use approved fittings to
make changes in direction, branch takeoffs from mains, and reductions in pipe sizes. D. Install unions adjacent to each valve in pipes NPS 2 and smaller. Unions are not required on flanged
devices or in piping installations using grooved joints. E. Install flanges or flange adapters on valves, apparatus, and equipment having NPS 2-1/2 and larger connections. F. Install
"Inspector's Test Connections" in sprinkler piping, complete with shutoff valve, sized and located according to NFPA 13. G. Install sprinkler piping with drains for complete system drainage.
H. Install sprinkler zone control valves, test assemblies, and drain risers adjacent to standpipes when sprinkler piping is connected to standpipes. I. Install alarm devices in piping
systems. J. Hangers and Supports: Comply with NFPA 13 for hanger materials. Install according to NFPA 13 for sprinkler piping.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -9 K. Earthquake Protection: Install piping according to NFPA 13 and Indiana Building Code to protect from earthquake damage. L. Install piping with
grooved joints according to manufacturer's written instructions. Construct rigid piping joints, unless otherwise indicated. M. Install pressure gages on riser or feed main, at each sprinkler
test connection, and at top of each standpipe. Include pressure gages with connection not less than NPS 1/4 and with soft metal seated globe valve, arranged for draining pipe between
gage and valve. Install gages to permit removal, and install where they will not be subject to freezing. 3.6 SPECIALTY SPRINKLER FITTING INSTALLATION A. Install specialty sprinkler fittings
according to manufacturer's written instructions. 3.7 VALVE INSTALLATION A. Refer to Division 21 Section "Valves" for installing general-duty valves. Install fire-protection specialty
valves, trim, fittings, controls, and specialties according to NFPA 13 and NFPA 14, manufacturer's written instructions, and authorities having jurisdiction. B. Gate Valves: Install
fire-protection-service valves supervised-open, located to control sources of water supply except from fire department connections. Provide permanent identification signs indicating
portion of system controlled by each valve. C. Alarm Check Valves: Install valves in vertical position for proper direction of flow, including bypass check valve and retard chamber drain-line
connection. 3.8 SPRINKLER APPLICATIONS A. General: Use sprinklers according to the following applications: 1. Rooms without Ceilings: Upright sprinklers. 2. Rooms with Suspended Ceilings:
Flat Concealed sprinklers. 3. Sprinkler Finishes: Use sprinklers with the following finishes: a. Upright and Pendent Sprinklers: Chrome-plated in finished spaces exposed to view; view;
rough bronze in unfinished spaces not exposed to view; wax coated where exposed to acids, chemicals, or other corrosive fumes. b. Flat concealed sprinklers: Painted white finish.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -10 3.9 SPRINKLER INSTALLATION A. Sprinkler heads shall be listed quick response type in all rooms throughout all smoke compartments containing sleeping
rooms. B. Center heads in two directions in 2’ X 4’ ceiling tile and provide piping offsets as required. Where 2’ X 4’ ceiling tiles are scored to give the impression of 2’ X 2’ ceiling
tiles, center head in 2’ X 2’ area. If 2’ X 2’ tiles are used, center head in tile. C. Install return bends on the top of all branch lines serving sprinklers that are installed below
the branch lines. 3.10 CONNECTIONS A. Connect water supplies to sprinklers. B. Connect piping to specialty valves, hose valves, specialties, fire department connections, and accessories.
C. Electrical Connections: Power wiring is specified in Division 26. D. Connect alarm devices to fire alarm. 3.11 LABELING AND IDENTIFICATION A. Install labeling and pipe markers on
equipment and piping according to requirements in NFPA 13 and in Division 22 Section "Identification for Plumbing Piping and Equipment." 3.12 FIELD QUALITY CONTROL A. Flush, test, and
inspect sprinkler piping according to NFPA 13, "System Acceptance" Chapter. B. Replace piping system components that do not pass test procedures and retest to demonstrate compliance.
Repeat procedure until satisfactory results are obtained. C. Report test results promptly and in writing to Architect and authorities having jurisdiction. 3.13 CLEANING A. Clean dirt
and debris from sprinklers. B. Remove and replace sprinklers having paint other than factory finish.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE-SUPPRESSION PIPING 21 13 13 -11 3.14 PROTECTION A. Protect sprinklers from damage until Substantial Completion. 3.15 STARTUP AND TESTING A. Verify that specialty valves, trim, fittings,
controls, and accessories are installed and operate correctly. B. Verify that specified tests of piping are complete. C. Verify that damaged sprinklers and sprinklers with paint or coating
not specified are replaced with new, correct type. D. Verify that sprinklers are correct types, have correct finishes and temperature ratings, and have guards as required for each application.
E. Fill wet-pipe sprinkler piping with water. F. Energize circuits to electrical equipment and devices. G. Adjust operating controls and pressure settings. H. Coordinate with fire alarm
tests. Operate as required. 3.16 DEMONSTRATION A. Demonstrate equipment, specialties, and accessories. Review operating and maintenance information. B. Schedule demonstration with Owner
with at least seven days' advance notice. END OF SECTION 21 13 13
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR PLUMBING 22 05 00 -1 SECTION 22 05 00 -COMMON WORK RESULTS FOR PLUMBING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract,
including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Piping materials and
installation instructions common to most piping systems. 2. Dielectric fittings. 3. Sleeves. 4. Escutcheons. 5. Plumbing demolition. 6. Supports and anchorages. 1.3 SUBMITTALS A. Product
Data: For the following: 1. Transition fittings. 2. Dielectric fittings. 3. Escutcheons. B. Welding certificates. 1.4 QUALITY ASSURANCE A. Steel Support Welding: Qualify processes and
operators according to AWS D1.1, "Structural Welding Code--Steel." B. Steel Pipe Welding: Qualify processes and operators according to ASME Boiler and Pressure Vessel Code: Section IX,
"Welding and Brazing Qualifications." 1. Comply with provisions in ASME B31 Series, "Code for Pressure Piping." 2. Certify that each welder has passed AWS qualification tests for welding
processes involved and that certification is current.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR PLUMBING 22 05 00 -2 C. Electrical Characteristics for Plumbing Equipment: Equipment of higher electrical characteristics may be furnished provided such proposed
equipment is approved in writing and connecting electrical services, circuit breakers, and conduit sizes are appropriately modified. If minimum energy ratings or efficiencies are specified,
equipment shall comply with requirements. 1.5 DELIVERY, STORAGE, AND HANDLING A. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and
handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture. B. Store plastic pipes protected from direct sunlight. Support to prevent sagging and bending.
1.6 COORDINATION A. Arrange for pipe spaces, chases, slots, and openings in building structure during progress of construction, to allow for plumbing installations. B. Coordinate installation
of required supporting devices and set sleeves in poured-in-place concrete and other structural components as they are constructed. C. Coordinate requirements for access panels and doors
for plumbing items requiring access that are concealed behind finished surfaces. Access panels and doors are specified in Division 8 Section "Access Doors and Frames." PART 2 -PRODUCTS
2.1 MANUFACTURERS A. In other Part 2 articles where subparagraph titles below introduce lists, the following requirements apply for product selection: 1. Manufacturers: Subject to compliance
with requirements, provide products by the manufacturers specified. 2.2 PIPE, TUBE, AND FITTINGS A. Refer to individual Division 22 piping Sections for pipe, tube, and fitting materials
and joining methods. B. Pipe Threads: ASME B1.20.1 for factory-threaded pipe and pipe fittings.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR PLUMBING 22 05 00 -3 2.3 JOINING MATERIALS A. Refer to individual Division 22 piping Sections for special joining materials not listed below. B. Pipe-Flange Gasket
Materials: Suitable for chemical and thermal conditions of piping system contents. 1. Thermoseal C-4401, 1/16 inch thick. Do not apply gasket compounds, adhesive, or antistick lubricants
to gaskets. C. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated. D. Solder Filler Metals: ASTM B 32, lead-free alloys. Include water-flushable flux according
to ASTM B 813. E. Brazing Filler Metals: AWS A5.8, BCuP Series, copper-phosphorus alloys for general-duty brazing, unless otherwise indicated; and AWS A5.8, BAg1, silver alloy for refrigerant
piping, unless otherwise indicated. F. Welding Filler Metals: Comply with AWS D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.
G. Solvent Cements for Joining Plastic Piping: 1. PVC Piping: ASTM D 2564. Include primer according to ASTM F 656. H. Fiberglass Pipe Adhesive: As furnished or recommended by pipe manufacturer.
2.4 DIELECTRIC FITTINGS A. Description: Combination fitting of copper alloy and ferrous materials with threaded, solderjoint, plain, or weld-neck end connections that match piping system
materials. B. Insulating Material: Suitable for system fluid, pressure, and temperature. C. Dielectric Unions: Factory-fabricated, union assembly, for 250-psig minimum working pressure
at 180 deg F. 1. Manufacturers: a. Capitol Manufacturing Co. b. Central Plastics Company. c. Eclipse, Inc. d. Epco Sales, Inc. e. Hart Industries, International, Inc. f. Watts Industries,
Inc.; Water Products Div.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR PLUMBING 22 05 00 -4 g. Zurn Industries, Inc.; Wilkins Div. D. Dielectric Flanges: Factory-fabricated, companion-flange assembly, for 150 psig minimum working
pressure as required to suit system pressures. 1. Manufacturers: a. Capitol Manufacturing Co. b. Central Plastics Company. c. Epco Sales, Inc. d. Watts Industries, Inc.; Water Products
Div. E. Dielectric-Flange Kits: Companion-flange assembly for field assembly. Include flanges, fullface-or ring-type neoprene or phenolic gasket, phenolic or polyethylene bolt sleeves,
phenolic washers, and steel backing washers. 1. Manufacturers: a. Advance Products & Systems, Inc. b. Calpico, Inc. c. Central Plastics Company. d. Pipeline Seal and Insulator, Inc.
2. Separate companion flanges and steel bolts and nuts shall have 150-psig minimum working pressure where required to suit system pressures. F. Dielectric Couplings: Galvanized-steel
coupling with inert and non-corrosive, thermoplastic lining; threaded ends; and 300-psig minimum working pressure at 225 deg F. 1. Manufacturers: a. Calpico, Inc. b. Lochinvar Corp.
G. Dielectric Nipples: Electroplated steel nipple with inert and non-corrosive, thermoplastic lining; plain, threaded, or grooved ends; and 300-psig minimum working pressure at 225 deg
F. 1. Manufacturers: a. Perfection Corp. b. Precision Plumbing Products, Inc. c. Sioux Chief Manufacturing Co., Inc. d. Victaulic Co. of America.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR PLUMBING 22 05 00 -5 2.5 SLEEVES A. Galvanized-Steel Sheet: 0.0239-inch (0.6-mm) minimum thickness; round tube closed with welded longitudinal joint. B. Steel
Pipe: Schedule 40 for up to 10" NPS, standard weight for 12" NPS and larger fabricated with 2” integral seal welded water stop, finished assembly painted with zinc rich paint. C. Cast
Iron: Cast or fabricated "wall pipe" equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop, unless otherwise indicated. D. Stack Sleeve Fittings: Manufactured,
cast-iron sleeve with integral clamping flange. Include clamping ring and bolts and nuts for membrane flashing. 1. Underdeck Clamp: Clamping ring with set screws. E. Stainless Steel
Sheet: Fabricated 304L stainless steel, 0.078 inch minimum thickness, round tube closed with welded longitudinal joint, fabricated with 2-inch integral seal welded waterstop. 2.6 ESCUTCHEONS
A. Description: Manufactured wall and ceiling escutcheons and floor plates, with an ID to closely fit around pipe, tube, and insulation of insulated piping and an OD that completely
covers opening. B. One-Piece, Cast-Brass Type: With set screw. 1. Finish: Polished chrome-plated. C. Split-Casting, Cast-Brass Type: With concealed hinge and set screw. 1. Finish: Polished
chrome-plated. D. One-Piece, Stamped-Steel Type: With set screw or spring clips and chrome-plated finish. PART 3 -EXECUTION 3.1 PLUMBING DEMOLITION A. Refer to Division 1 Section "Cutting
and Patching" and Division 2 Section "Selective Structure Demolition" for general demolition requirements and procedures. B. Disconnect, demolish, and remove plumbing systems, equipment,
and components indicated to be removed.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR PLUMBING 22 05 00 -6 1. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping
material. C. If pipe, insulation, or equipment to remain is damaged in appearance or is unserviceable, remove damaged or unserviceable portions and replace with new products of equal
capacity and quality. 3.2 PIPING SYSTEMS -COMMON REQUIREMENTS A. Install piping according to the following requirements and Division 22 Sections specifying piping systems. B. Drawing
plans, schematics, and diagrams indicate general location and arrangement of piping systems. Indicated locations and arrangements were used to size pipe and calculate friction loss,
expansion, pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved on Coordination Drawings. C. Install piping in concealed
locations, unless otherwise indicated and except in equipment rooms and service areas. D. Install piping indicated to be exposed and piping in equipment rooms and service areas at right
angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise. E. Install piping above accessible ceilings to allow sufficient space for
ceiling panel removal. F. Install piping to permit valve servicing. G. Install piping at indicated slopes. H. Install piping free of sags and bends. I. Install fittings for changes in
direction and branch connections. J. Install piping to allow application of insulation. K. Select system components with pressure rating equal to or greater than system operating pressure.
L. Install escutcheons for penetrations of walls, ceilings, and floors in exposed areas. In dietary, kitchen, cafeteria, sterile processing, sterilizer, sub-sterile and sterile areas
do not install install escutcheons, but seal pipe penetration airtight with food grade silicone. M. New concrete floors, walls and roof penetrations are required to have sleeves cast-in-place
(no core drilling unless specifically noted on the Drawings). For core drilled holes, grout sleeve
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR PLUMBING 22 05 00 -7 into concrete, completely filling void between sleeve and hole and maintain fire rating. Coredrilled structures are required to be reinforced
as noted on structural drawings. N. Install sleeves for pipes passing through concrete and masonry walls, fire rated gypsum-board partitions, and concrete floor and roof slabs. 1. Cut
sleeves to length for mounting flush with both surfaces. a. Exception: Extend top of sleeves installed in all floors 2 inches above finished floor level. Touch-up cut ends of galvanized
pipe sleeves with zinc-rich coating. Waterstop shall be wholly contained within concrete with approximately 1-1/2 inches of concrete cover. Extend cast-iron sleeve fittings below floor
slab as required to secure clamping ring if ring is specified. 2. Install sleeves in new walls and slabs as new walls and slabs are constructed. 3. Install sleeves that are large enough
to provide 1/4-inch annular clear space between sleeve and pipe or pipe insulation. Use the following sleeve materials: a. Cast Iron or Steel Pipe Sleeves or Stainless Steel Sheet Sleeves:
For pipes penetrating other than gypsum board partitions or walls. b. Galvanized Steel Sheet Sleeves: For pipes penetrating gypsum-board partitions or walls. 4. Except for underground
wall penetrations, seal annular space between sleeve and pipe or pipe insulation, using joint sealants appropriate for size, depth, and location of joint. Refer to Division 7 Section
"Joint Sealants" for materials and installation. O. Fire-Barrier Penetrations: Maintain indicated fire rating of walls, partitions, ceilings, and floors at pipe penetrations. Seal pipe
penetrations with firestop materials. Refer to Division 7 Section "Firestopping" for materials. P. Install piping and hangers so that they do not interfere with fully opening access
panels on any in structure, nor access panels on any equipment (contract provided or Owner installed). 3.3 PIPING JOINT CONSTRUCTION A. Join pipe and fittings according to the following
requirements and Division 22 Sections specifying piping systems. B. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe. C. Remove scale, slag, dirt, and debris
from inside and outside of pipe and fittings before assembly.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR PLUMBING 22 05 00 -8 D. Soldered Joints: Apply ASTM B 813, water-flushable flux, unless otherwise indicated, to tube end. Construct joints according to ASTM B
828 or CDA's "Copper Tube Handbook," using lead-free solder alloy complying with ASTM B 32. E. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," "Pipe and Tube"
Chapter, using copper-phosphorus brazing filler metal complying with AWS A5.8. F. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and
clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows: 1. Apply appropriate tape or thread compound to external
pipe threads unless dry seal threading is specified. 2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do not use pipe sections that have
cracked or open welds. G. Welded Joints: Construct joints according to AWS D10.12, using qualified processes and welding operators according to Part 1 "Quality Assurance" Article. H.
Flanged Joints: Select appropriate gasket material, size, type, and thickness for service application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.
I. Plastic Piping Solvent-Cement Joints: Clean and dry joining surfaces. Join pipe and fittings according to the following: 1. Comply with ASTM F 402 for safe-handling practice of cleaners,
primers, and solvent cements. 2. PVC Pressure Piping: Join schedule number ASTM D 1785, PVC pipe and PVC socket fittings according to ASTM D 2672. Join other-than-schedule-number PVC
pipe and socket fittings according to ASTM D 2855. 3. PVC Non-pressure Piping: Join according to ASTM D 2855. J. Plastic Pressure Piping Gasketed Joints: Join according to ASTM D 3139.
K. Plastic Non-pressure Piping Gasketed Joints: Join according to ASTM D 3212. 3.4 PIPING CONNECTIONS A. Make connections according to the following, unless otherwise indicated: 1. Install
unions, in piping NPS 2 and smaller, adjacent to each valve and at final connection to each piece of equipment. 2. Install flanges, in piping NPS 2-1/2 and larger, adjacent to flanged
valves and at final connection to each piece of equipment. 3. Dry Piping Systems: Install dielectric unions and flanges to connect piping materials of dissimilar metals.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR PLUMBING 22 05 00 -9 4. Wet Piping Systems: Install dielectric coupling and nipple fittings to connect piping materials of dissimilar metals. 3.5 ERECTION OF
METAL SUPPORTS AND ANCHORAGES A. Refer to Division 5 Section "Metal Fabrications" for structural steel. B. Cut, fit, and place miscellaneous metal supports accurately in location, alignment,
and elevation to support and anchor plumbing materials and equipment. C. Field Welding: Comply with AWS D1.1. 3.6 ERECTION OF WOOD SUPPORTS AND ANCHORAGES A. Cut, fit, and place wood
grounds, nailers, blocking, and anchorages to support, and anchor plumbing materials and equipment. B. Select
fastener sizes that will not penetrate members if opposite side will be exposed to view or will receive finish materials. Tighten connections between members. Install fasteners without
splitting wood members. C. Attach to substrates as required to support applied loads. END OF SECTION 22 05 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METERS AND GAGES FOR PLUMBING PIPING 22 05 19 -1 SECTION 22 05 19 -METERS AND GAGES FOR PLUMBING PIPING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the
Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Thermometers. 2. Gages. 3.
Test plugs. 1.3 SUBMITTALS A. Product Data: For each type of product indicated; include performance curves. B. Shop Drawings: Schedule for thermometers and gages indicating manufacturer's
number, scale range, and location for each. C. Product Certificates: For each type of thermometer and gage, signed by product manufacturer. PART 2 -PRODUCTS 2.1 METAL-CASE, LIQUID-IN-GLASS
THERMOMETERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Ametek, Inc.; U.S. Gage Div. 2. Dresser Inc., Ashcroft. 3. Trerice,
H. O. Co. 4. Weiss Instruments, Inc. 5. Weksler Instruments Operating Unit; Dresser Industries; Instrument Div. B. Case: Die-cast aluminum, 9 inches long.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METERS AND GAGES FOR PLUMBING PIPING 22 05 19 -2 C. Tube: Blue or green reading, organic-liquid filled, with magnifying lens. Do not provide mercury. D. Tube Background: Satin-faced,
non-reflective aluminum with permanently etched scale markings. E. Window: Glass. F. Connector: Adjustable type, 180 degrees in vertical plane, 360 degrees in horizontal plane, with
locking device. G. Stem: Copper-plated steel, aluminum, or brass for thermowell installation and of length to suit installation. H. Accuracy: Plus or minus 1 percent of range or plus
or minus 1 scale division to maximum of 1.5 percent of range. 2.2 BIMETALLIC-ACTUATED DIAL THERMOMETERS A. Manufacturers: Subject to compliance with requirements, provide products by
one of the following: 1. Ashcroft Commercial Instrument Operations; Dresser Industries; Instrument Instrument Div. 2. Miljoco Corp. 3. Trerice, H. O. Co. 4. Weiss Instruments, Inc. 5.
Weksler Instruments Operating Unit; Dresser Industries; Instrument Div. B. Description: Direct-mounting, bimetallic-actuated dial thermometers complying with ASME B40.3. C. Case: Dry
type, stainless steel with 5-inch diameter. D. Element: Bimetal coil. E. Dial: Satin-faced, non-reflective aluminum with permanently etched scale markings. F. Pointer: Red or black metal.
G. Window: Glass. H. Ring: Stainless steel. I. Connector: Adjustable angle type. J. Stem: Metal, for thermowell installation and of length to suit installation.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METERS AND GAGES FOR PLUMBING PIPING 22 05 19 -3 K. Accuracy: Plus or minus 1 percent of range or plus or minus 1 scale division to maximum of 1.5 percent of range. 2.3 THERMOWELLS A.
Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. AMETEK, Inc.; U.S. Gauge Div. 2. Ashcroft Commercial Instrument Operations; Dresser
Industries; Instrument Div. 3. Miljoco Corp. 4. Trerice, H. O. Co. 5. Weiss Instruments, Inc. 6. Weksler Instruments Operating Unit; Dresser Industries; Instrument Div. B. Manufacturers:
Same as manufacturer of thermometer being used. C. Description: Pressure-tight, socket-type metal fitting made for insertion into piping and of type, diameter, and length required to
hold thermometer. 2.4 PRESSURE GAGES A. Basis-of-Design Product: Subject to compliance with requirements, provide products by one of the following: 1. AMETEK, Inc.; U.S. Gauge Div. 2.
Ashcroft Commercial Instrument Operations; Dresser Industries; Instrument Div. 3. Miljoco Corp. 4. Trerice, H. O. Co. 5. Weiss Instruments, Inc. 6. Weksler Instruments Operating Unit;
Dresser Industries; Instrument Div. B. Direct-Mounting, Dial-Type Pressure Gages: Indicating-dial type complying with ASME B40.100. 1. Case: Dry or liquid-filled type, drawn steel or
cast aluminum, 4-1/2-inch diameter. 2. Pressure-Element Assembly: Bourdon tube, unless otherwise indicated. 3. Pressure Connection: Brass, NPS 1/4, bottom-outlet type unless back-outlet
type is indicated. 4. Movement: Mechanical, with link to pressure element and connection to pointer. 5. Dial: Satin-faced, non-reflective aluminum with permanently etched scale markings.
6. Pointer: Red or black metal. 7. Window: Glass. 8. Ring: Stainless steel. 9. Accuracy: Grade A, plus or minus 1 percent of middle half scale.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METERS AND GAGES FOR PLUMBING PIPING 22 05 19 -4 10. Vacuum-Pressure Range: 30-in. Hg of vacuum to 15 psig of pressure. 11. Range for Fluids under Pressure: Two times operating pressure.
C. Pressure-Gage Fittings: 1. Valves: NPS 1/4 brass or stainless-steel needle type. 2. Snubbers: ASME B40.5, NPS 1/4 brass bushing with corrosion-resistant, porous-metal disc of material
suitable for system fluid and working pressure. 2.5 TEST PLUGS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Flow Design, Inc.
2. Peterson Equipment Co., Inc. 3. Trerice, H. O. Co. 4. Watts Industries, Inc.; Water Products Div. B. Description: Corrosion-resistant brass or stainless-steel body with core inserts
and gasketed and threaded cap, with extended stem for units to be installed in insulated piping. C. Minimum Pressure and Temperature Rating: 500 psig at 200 deg F. D. Core Inserts: One
or two self-sealing rubber valves. 1. Insert material for water service at 20 to 200 deg F shall be CR. 2. Insert material for water service at minus 30 to plus 275 deg F shall be EPDM.
E. Test Kit: Furnish one test kit containing one pressure gage and adaptor, one thermometer, and carrying case. Pressure gage, adapter probes, and thermometer sensing elements shall
be of diameter to fit test plugs and of length to project into piping. 1. Pressure Gage: Small bourdon-tube insertion type with 2-to 3-inch diameter dial and probe. Dial range shall
be 0 to 200 psig. 2. Low-Range Thermometer: Small bimetallic insertion type with 1-to 2-inch diameter dial and tapered-end sensing element. Dial ranges shall be 25 to 125 deg F. 3. High-Range
Thermometer: Small bimetallic insertion type with 1-to 2-inch diameter dial and tapered-end sensing element. Dial ranges shall be 0 to 220 deg F. 4. Carrying case shall have formed instrument
padding.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METERS AND GAGES FOR PLUMBING PIPING 22 05 19 -5 PART 3 -EXECUTION 3.1 THERMOMETER APPLICATIONS A. Install liquid-in-glass bimetallic-actuated dial thermometers in the outlet of each
domestic, hotwater storage tank. B. Install liquid-filled-case-type, bimetallic-actuated dial thermometers at suction and discharge of each pump. C. Provide the following temperature
ranges for thermometers: 1. Domestic Hot Water: 30 to 240 deg F, with 2-degree scale divisions. 2. Domestic Cold Water: 0 to 100 deg F, with 2-degree scale divisions. 3.2 GAGE APPLICATIONS
A. Install dry-case-type pressure gages for discharge of each pressure-reducing valve. B. Install liquid-filled-case-type pressure gages at suction and discharge of each pump. 3.3 INSTALLATIONS
A. Install direct-mounting thermometers and adjust vertical and tilted positions. B. Install thermowells with socket extending a minimum of 2 inches into fluid and in vertical position
in piping tees where thermometers are indicated. C. Install direct-mounting pressure gages in piping tees with pressure gage located on pipe at most readable position. D. Install needle-valve
and snubber fitting in piping for each pressure gage. E. Install test plugs in tees in piping. F. Install thermometers and gages adjacent to machines and equipment to allow service and
maintenance for thermometers, gages, machines, and equipment. G. Adjust faces of thermometers and gages to proper angle for best visibility. END OF SECTION 22 05 19
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 05 23 -1 SECTION 22 05 23 -GENERAL-DUTY VALVES FOR PLUMBING PIPING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions
of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Ball valves. 2. Butterfly
valves. 3. Check valves. B. Related Sections: 1. Division 22 plumbing piping Sections for specialty valves applicable to those Sections only. 2. Division 22 Section "Identification for
Plumbing Piping and Equipment" for valve tags and schedules. 1.3 SUBMITTALS A. Product Data: For each type of valve indicated. 1.4 QUALITY ASSURANCE A. Source Limitations for Valves:
Obtain each type of valve from single source from single manufacturer. B. ASME Compliance: Compliance: 1. ASME B16.10 and ASME B16.34 for ferrous valve dimensions and design criteria.
2. ASME B31.1 for power piping valves. 3. ASME B31.9 for building services piping valves. C. NSF Compliance: NSF 61 for valve materials for potable-water service.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 05 23 -2 1.5 DELIVERY, STORAGE, AND HANDLING A. Prepare valves for shipping as follows: 1. Protect internal parts against rust and corrosion.
2. Protect threads, flange faces, grooves, and weld ends. 3. Set ball and plug valves open to minimize exposure of functional surfaces. 4. Set butterfly valves closed or slightly open.
5. Block check valves in either closed or open position. B. Use the following precautions during storage: 1. Maintain valve end protection. 2. Store valves indoors and maintain at higher
than ambient dew point temperature. If outdoor storage is necessary, store valves off the ground in watertight enclosures. C. Use sling to handle large valves; rig sling to avoid damage
to exposed parts. Do not use handwheels or stems as lifting or rigging points. PART 2 --PRODUCTS 2.1 MANUFACTURERS A. In other Part 2 articles where subparagraph titles below introduce
lists, the following requirements apply for product selection: 1. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified. B. Acceptable
Manufacturers: 1. Check valves: Crane, Hammond, Milwaukee, Nibco, Stockham. 2. Ball valves: Apollo, Crane, Hammond, Milwaukee, Nibco, Stockham, Watts 3. Butterfly valves: ABZ, Centerline,
Demco, Hammond, Keystone, Nibco, Stockham, Watts. 2.2 GENERAL REQUIREMENTS FOR VALVES A. Refer to valve schedule articles for applications of valves. B. Valve Pressure and Temperature
Ratings: Not less than indicated and as required for system pressures and temperatures. C. Valve Sizes: Same as upstream piping unless otherwise indicated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 05 23 -3 D. Valve Actuator Types: 1. Gear Actuator: For quarter-turn valves NPS 8 and larger. 2. Handwheel: For valves other than quarter-turn
types. 3. Handlever: For quarter-turn valves NPS 6 and smaller except plug valves. 4. Wrench: For plug valves with square heads. Furnish Owner with 1 wrench for every 10 plug valves,
for each size square plug-valve head. E. Valves in Insulated Piping: With 2-inch stem extensions and the following features: 1. Ball Valves: With extended operating handle of non-thermal-conductive
material, and protective sleeve that allows operation of valve without breaking the vapor seal or disturbing insulation. 2. Butterfly Valves: With extended neck. F. Valve-End Connections:
1. Flanged: With flanges according to ASME B16.1 for iron valves. 2. Threaded: With threads according to ASME B1.20.1. G. Valve Bypass and Drain Connections: MSS SP-45. 2.3 VALVE SCHEDULE
A. Check Valves – 2” and Smaller: 1. Class 125, threaded end, bronze body, horizontal swing, regrinding type, Y-pattern Viton renewable disc. B. Check Valves – 2-1/2” and Larger: 1.
Class 125, flanged end, iron body, bolted bonnet, horizontal swing, renewable cast bronze seat and disc. C. Non-Slam Silent Check Valve – 1” and Larger: 1. Class 125, wafer end, cast
iron body, bronze plug, stainless steel stem, bronze seats, stainless steel spring. D. Ball Valves – 2” and Smaller: 1. 600 psi, blowout proof stems, 2 piece bronze body, standard port,
Teflon seats with bronze trim.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 05 23 -4 E. Butterfly Valve – 12” and Smaller: 1. Class 150, cast iron body, extended neck, stainless steel or aluminum-bronze disc, 416 stainless
steel shaft, Viton seat and Viton o-rings: F. Drain Valves: 1. Class 125, bronze body, screw-in bonnet, rising stem, composition disc, 3/4” hose outlet. PART 3 -EXECUTION 3.1 EXAMINATION
A. Examine valve interior for cleanliness, freedom from foreign matter, and corrosion. Remove special packing materials, such as blocks, used to prevent disc movement during shipping
and handling. B. Operate valves in positions from fully open to fully closed. Examine guides and seats made accessible by such operations. C. Examine threads on valve and mating pipe
for form and cleanliness. D. Examine mating flange faces for conditions that might cause leakage. Check bolting for proper size, length, and material. Verify that gasket is of proper
size, that its material composition is suitable for service, and that it is free from defects and damage. E. Do not attempt to repair defective valves; replace with new valves. 3.2 VALVE
APPLICATIONS A. Ball valves shall be installed in 2” and smaller pipes for shutoff duty in all piping. B. Butterfly valves shall be installed in 2-1/2” and larger pipes for balancing
and shutoff duty in all piping. C. Valves shall be installed on inlet of each fixture or equipment on each branch water line, each side of control valve and elsewhere shown on the Contract
Documents. D. Install wafer type butterfly (6” and smaller) in domestic water system. 3.3 VALVE INSTALLATION A. Install valves with unions or flanges at each piece of equipment arranged
to allow service, maintenance, and equipment removal without system shutdown.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL-DUTY VALVES FOR PLUMBING PIPING 22 05 23 -5 B. Locate valves for easy access and provide separate support where necessary. C. Install valves in horizontal piping with stem at
or above center of pipe. D. Install valves in position to allow full stem movement. E. Install check valves for proper direction of flow and as follows: 1. Swing Check Valves: In horizontal
position with hinge pin level. 2. Center-Guided and Plate-Type Check Valves: In horizontal or vertical position, between flanges. 3. Lift Check Valves: With stem upright and plumb. 3.4
ADJUSTING A. Adjust or replace valve packing after piping systems have been tested and put into service but before final adjusting and balancing. Replace valves if persistent leaking
occurs. END OF SECTION 22 05 23
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -1 SECTION 22 05 29 -HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings
and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes
the following hangers and supports for plumbing system piping and equipment: 1. Steel pipe hangers and supports. 2. Trapeze pipe hangers. 3. Metal framing systems. 4. Thermal-hanger
shield inserts. 5. Fastener systems. 6. Pipe stands. 7. Pipe positioning systems. 8. Equipment supports. B. Related Sections include the following: 1. Division 5 Section "Metal Fabrications"
for structural-steel shapes and plates for trapeze hangers for pipe and equipment supports. 2. Division 21 Section "Fire-Suppression Piping" for pipe hangers for fire-suppression piping.
3. Division 21 Section "Vibration and Seismic Controls for Fire Suppression Piping and Equipment" for vibration isolation devices. 1.3 DEFINITIONS A. MSS: Manufacturers Standardization
Society for The Valve and Fittings Industry Inc. B. Terminology: As defined in MSS SP-90, "Guidelines on Terminology for Pipe Hangers and Supports."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -2 1.4 PERFORMANCE REQUIREMENTS A. Design supports for multiple pipes, including pipe stands, capable of supporting combined
weight of supported systems, system contents, and test water. B. Design equipment supports capable of supporting combined operating weight of supported equipment and connected systems
and components. C. Design seismic-restraint hangers and supports for piping and equipment. 1.5 SUBMITTALS A. Product Data: For the following: 1. Steel pipe hangers and supports. 2. Thermal-hanger
shield inserts. 3. Powder-actuated fastener systems. 4. Pipe positioning systems. B. Shop Drawings: Show fabrication and installation details and include calculations for the following:
1. Trapeze pipe hangers. Include Product Data for components. 2. Metal framing systems. Include Product Data for components. 3. Pipe stands. Include Product Data for components. 4. Equipment
supports. C. Welding certificates. 1.6 QUALITY ASSURANCE A. Welding: Qualify procedures and personnel according to the following: 1. AWS D1.1, "Structural Welding Code--Steel." 2. AWS
D1.2, "Structural Welding Code--Aluminum." 3. AWS D1.4, "Structural Welding Code--Reinforcing Steel." 4. ASME Boiler and Pressure Vessel Code: Section IX.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -3 PART 2 -PRODUCTS 2.1 MANUFACTURERS A. In other Part 2 articles where titles below introduce lists, the following requirements
apply to product selection: 1. Manufacturers: Subject to compliance with requirements, provide products by one of the manufacturers specified. 2.2 STEEL PIPE HANGERS AND SUPPORTS A.
Description: MSS SP-58, Types 1 through 58, factory-fabricated components. Refer to Part 3 "Hanger and Support Applications" Article for where to use specific hanger and support types.
B. Manufacturers: 1. B-Line Systems, Inc.; a division of Cooper Industries. 2. Carpenter & Paterson, Inc. 3. ERICO/Michigan Hanger Co. 4. Grinnell Corp. 5. National Pipe Hanger Corporation.
6. PHD Manufacturing, Inc. 7. PHS Industries, Inc. 8. Tolco Inc. C. Galvanized, Galvanized, Metallic Coatings: Pregalvanized or hot dipped. D. Nonmetallic Coatings: Plastic coating,
jacket, or liner. 2.3 TRAPEZE PIPE HANGERS A. Description: MSS SP-69, Type 59, shop-or field-fabricated pipe-support assembly made from structural-steel shapes with MSS SP-58 hanger
rods, nuts, saddles, and U-bolts. 2.4 METAL FRAMING SYSTEMS A. Description: MFMA-3, shop-or field-fabricated pipe-support assembly made of steel channels and other components. B. Manufacturers:
1. B-Line Systems, Inc.; a division of Cooper Industries. 2. ERICO/Michigan Hanger Co.; ERISTRUT Div.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -4 3. Power-Strut Div.; Tyco International, Ltd. 4. Tolco Inc. 5. Unistrut Corp.; Tyco International, Ltd. C. Coatings:
Manufacturer's standard finish unless bare metal surfaces are indicated. D. Nonmetallic Coatings: Plastic coating, jacket, or liner. 2.5 THERMAL-HANGER SHIELD INSERTS A. Description:
100-psig minimum, compressive-strength insulation insert encased in sheet metal shield. B. Manufacturers: 1. Carpenter & Paterson, Inc. 2. ERICO/Michigan Hanger Co. 3. PHS Industries,
Inc. 4. Pipe Shields, Inc. 5. Rilco Manufacturing Company, Inc. 6. Value Engineered Products, Inc. C. Insulation-Insert Material for Cold Piping: Water-repellent treated, ASTM C 533,
Type I calcium silicate with vapor barrier. D. Insulation-Insert Material for Hot Piping: Water-Water-repellent treated, ASTM C 533, Type I calcium silicate or ASTM C 552 or Type II
cellular glass. E. For Trapeze or Clamped Systems: Insert and shield shall cover entire circumference of pipe. F. For Clevis or Band Hangers: Insert and shield shall cover lower 180
degrees of pipe. G. Insert Length: Extend 2 inches beyond sheet metal shield for piping operating below ambient air temperature. 2.6 FASTENER SYSTEMS A. Mechanical-Expansion Anchors:
Insert-wedge-type zinc-coated steel, for use in hardened portland cement concrete with pull-out, tension, and shear capacities appropriate for supported loads and building materials
where used. 1. Manufacturers: a. B-Line Systems, Inc.; a division of Cooper Industries. b. Hilti, Inc.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -5 c. ITW Ramset/Red Head. 2.7 PIPE STAND FABRICATION A. Pipe Stands, General: Shop or field-fabricated assemblies made
of manufactured corrosionresistant components to support roof-mounted piping. B. Curb-Mounting-Type Pipe Stands: Shop-or field-fabricated pipe support made from structuralsteel shape,
continuous-thread rods, and rollers for mounting on permanent stationary roof curb. 2.8 PIPE POSITIONING SYSTEMS A. Description: IAPMO PS 42, system of metal brackets, clips, and straps
for positioning piping in pipe spaces for plumbing fixtures for commercial applications. B. Manufacturers: 1. C & S Mfg. Corp. 2. HOLDRITE Corp.; Hubbard Enterprises. 3. Samco Stamping,
Inc. 2.9 EQUIPMENT SUPPORTS A. Description: Welded, shop-or field-fabricated equipment support made from structural-steel shapes. 2.10 MISCELLANEOUS MATERIALS A. Structural Steel: ASTM
A 36/A 36M, steel plates, shapes, and bars; black and galvanized. B. Grout: ASTM C 1107, factory-mixed and -packaged, dry, hydraulic-cement, non-shrink and nonmetallic grout; suitable
for interior and exterior applications. 1. Properties: Non-staining, non-corrosive, and nongaseous. 2. Design Mix: 5000-psi, 28-day compressive strength. PART 3 -EXECUTION 3.1 HANGER
AND SUPPORT APPLICATIONS A. Specific hanger and support requirements are specified in Sections specifying piping systems and equipment.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -6 B. Comply with MSS SP-69 for pipe hanger selections and applications that are not specified in piping system Sections.
C. Use hangers and supports with galvanized, metallic coatings for piping and equipment that will not have field-applied finish. D. Use nonmetallic coatings on attachments for electrolytic
protection where attachments are in direct contact with copper tubing. E. Horizontal-Piping Hangers and Supports: Unless otherwise indicated and except as specified in piping system
Sections, install the following types: 1. Adjustable, Steel Clevis Hangers (MSS Type 1): For suspension of non-insulated or insulated stationary pipes, NPS 1/2 to NPS 30. Install upper
locknut. 2. Adjustable, Swivel-Ring Band Hangers (MSS Type 10): For suspension of non-insulated stationary pipes, NPS 1/2 to NPS 2. 3. U-Bolts (MSS Type 24): For support of heavy pipes,
NPS 1/2 to NPS 30. 4. Pipe Saddle Supports (MSS Type 36): For support of pipes, NPS 4 to NPS 36, with steel pipe base stanchion support and cast-iron floor flange. 5. Pipe Stanchion
Saddles (MSS Type 37): For support of pipes, NPS 4 to NPS 36, with steel pipe base stanchion support and cast-iron floor flange and with U-bolt to retain pipe. 6. Adjustable, Pipe Saddle
Supports (MSS Type 38): For stanchion-type support for pipes, NPS 2-1/2 to NPS 36, if vertical adjustment is required, with steel pipe base stanchion support and cast-iron floor flange.
7. Single Pipe Rolls (MSS Type 41): For suspension of pipes, NPS 1 to NPS 30, from 2 rods if longitudinal movement caused by expansion and contraction might occur. 8. Adjustable Roller
Hangers (MSS Type 43): For suspension of pipes, NPS 2-1/2 to NPS 20, from single rod if horizontal movement caused by expansion and contraction might occur. 9. Complete Pipe Rolls (MSS
MSS Type 44): For support of pipes, NPS 2 to NPS 42, if longitudinal movement caused by expansion and contraction might occur but vertical adjustment is not necessary. 10. Adjustable
Pipe Roll and Base Units (MSS Type 46): For support of pipes, NPS 2 to NPS 30, if vertical and lateral adjustment during installation might be required in addition to expansion and contraction.
F. Vertical-Piping Clamps: Unless otherwise indicated and except as specified in piping system Sections, install the following types: 1. Extension Pipe or Riser Clamps (MSS Type 8):
For support of pipe risers, NPS 3/4 to NPS 20. 2. Carbon-or Alloy-Steel Riser Clamps (MSS Type 42): For support of pipe risers, NPS 3/4 to NPS 20, if longer ends are required for riser
clamps.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -7 G. Hanger-Rod Attachments: Unless otherwise indicated and except as specified in piping system Sections, install the
following types: 1. Steel Turnbuckles (MSS Type 13): For adjustment up to 6 inches for heavy loads. 2. Steel Weldless Eye Nuts (MSS Type 17): For 120 to 450 deg F piping installations.
H. Building Attachments: Unless otherwise indicated and except as specified in piping system Sections, install the following types: 1. Steel or Malleable Concrete Inserts (MSS Type 18):
For upper attachment to suspend pipe hangers from concrete ceiling. 2. Top-Beam C-Clamps (MSS Type 19): For use under roof installations with bar-joist construction to attach to top
flange of structural shape. 3. Center-Beam Clamps (MSS Type 21): For attaching to center of bottom flange of beams. 4. Welded Beam Attachments (MSS Type 22): For attaching to bottom
of beams if loads are considerable and rod sizes are large. 5. C-Clamps (MSS Type 23): For structural shapes. 6. Top-Beam Clamps (MSS Type 25): For top of beams if hanger rod is required
tangent to flange edge.
7. Side-Beam Clamps (MSS Type 27): For bottom of steel I-beams. 8. Steel-Beam Clamps with Eye Nuts (MSS Type 28): For attaching to bottom of steel Ibeams for heavy loads. 9. Linked-Steel
Clamps with Eye Nuts (MSS Type 29): For attaching to bottom of steel Ibeams for heavy loads, with link extensions. 10. Malleable Beam Clamps with Extension Pieces (MSS Type 30): For
attaching to structural steel. 11. Welded-Steel Brackets: For support of pipes from below, or for suspending from above by using clip and rod. Use one of the following for indicated
loads: a. Light (MSS Type 31): 750 lb. b. Medium (MSS Type 32): 1500 lb. c. Heavy (MSS Type 33): 3000 lb. 12. Horizontal Travelers (MSS Type 58): For supporting piping systems subject
to linear horizontal movement where headroom is limited. I. Saddles and Shields: Unless otherwise indicated and except as specified in piping system Sections, install the following types:
1. Steel Pipe-Covering Protection Saddles (MSS Type 39): To fill interior voids with insulation that matches adjoining insulation. 2. Protection Shields (MSS Type 40): Of length recommended
in writing by manufacturer to prevent crushing insulation. 3. Thermal-Hanger Shield Inserts: For supporting insulated pipe.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -8 J. Spring Hangers and Supports: Unless otherwise indicated and except as specified in piping system Sections, install
the following types: 1. Restraint-Control Devices (MSS Type 47): Where indicated to control piping movement. 2. Spring Cushions (MSS Type 48): For light loads if vertical movement does
not exceed 1-1/4 inches. 3. Spring-Cushion Roll Hangers (MSS Type 49): For equipping Type 41 roll hanger with springs. 4. Spring Sway Braces (MSS Type 50): To retard sway, shock, vibration,
or thermal expansion in piping systems. 5. Variable-Spring Hangers (MSS Type 51): Preset to indicated load and limit variability factor to 25 percent to absorb expansion and contraction
of piping system from hanger. 6. Variable-Spring Base Supports (MSS Type 52): Preset to indicated load and limit variability factor to 25 percent to absorb expansion and contraction
of piping system from base support. 7. Variable-Spring Trapeze Hangers (MSS Type 53): Preset to indicated load and limit variability factor to 25 percent to absorb expansion and contraction
of piping system from trapeze support. 8. Constant Supports: For critical piping stress and if necessary to avoid transfer of stress from one support to another support, critical terminal,
or connected equipment. Include auxiliary stops for erection, hydrostatic test, and load-adjustment capability. These supports include the following types: a. Horizontal (MSS Type 54):
Mounted horizontally. b. Vertical (MSS Type 55): Mounted vertically. c. Trapeze (MSS Type 56): Two vertical-type supports and one trapeze member. K. Comply with MSS SP-69 for trapeze
pipe hanger selections and applications that are not specified in piping system Sections. L. Comply with MFMA-102 for metal framing system selections and applications that are not specified
in piping system Sections. M. Use mechanical-expansion anchors instead of building attachments where required in concrete construction. N. Use pipe positioning systems in pipe spaces
behind plumbing fixtures to support supply and waste piping for plumbing fixtures. 3.2 HANGER AND SUPPORT INSTALLATION A. Steel Pipe Hanger Installation: Comply with MSS SP-69 and MSS
SP-89. Install hangers, supports, clamps, and attachments as required to properly support piping from building structure.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -9 B. Trapeze Pipe Hanger Installation: Comply with MSS SP-69 and MSS SP-89. Arrange for grouping of parallel runs of
horizontal piping and support together on field-fabricated trapeze pipe hangers. 1. Pipes of Various Sizes: Support together and space trapezes for smallest pipe size or install intermediate
supports for smaller diameter pipes as specified above for individual pipe hangers. 2. Field fabricate from ASTM A 36/A 36M, steel shapes selected for loads being supported. Weld steel
according to AWS D1.1. C. Metal Framing System Installation: Arrange for grouping of parallel runs of piping and support together on field-assembled metal framing systems. D. Thermal-Hanger
Shield Installation: Install in pipe hanger or shield for insulated piping. E. Fastener System Installation: 1. Install mechanical-expansion anchors in concrete after concrete is placed
and completely cured. Install fasteners according to manufacturer's written instructions. F. Pipe Stand Installation: 1. Curb-Mounting-Type Pipe Stands: Assemble components or fabricate
pipe stand and mount on permanent, stationary roof curb. Refer to Division 7 Section "Roof Accessories" for curbs. G. Pipe Positioning System Installation: Install support devices to
make rigid supply and waste piping connections to each plumbing fixture. Refer to Division 22 Section "Plumbing Fixtures" for plumbing fixtures. H. Install hangers and supports complete
with necessary inserts, bolts, rods, nuts, washers, and other accessories. I. Equipment Support Installation: Fabricate from welded-structural-steel shapes. J. Install hangers and supports
to allow controlled thermal and seismic movement of piping systems, to permit freedom of movement between pipe anchors, and to facilitate action of expansion joints, expansion loops,
expansion bends, and similar units. K. Install lateral bracing with pipe hangers and supports to prevent swaying. L. Install building attachments within concrete slabs or attach to structural
steel. Install additional attachments at concentrated loads, including valves, flanges, and strainers, NPS 4 and larger and at changes in direction of piping. Install concrete inserts
before concrete is placed; fasten inserts to forms and install reinforcing bars through openings at top of inserts.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -10 M. Load Distribution: Install hangers and supports so piping live and dead loads and stresses from movement will not
be transmitted to connected equipment. N. Pipe Slopes: Install hangers and supports to provide indicated pipe slopes and so maximum pipe deflections allowed by ASME B31.9 (for building
services piping) are not exceeded. O. Insulated Piping: Comply with the following: 1. Attach clamps and spacers to piping. a. Piping Operating above Ambient Air Temperature: Clamp may
project through insulation. b. Piping Operating below Ambient Air Temperature: Use thermal-hanger shield insert with clamp sized to match OD of insert. c. Do not exceed pipe stress limits
according to ASME B31.9 for building services piping. 2. Install MSS SP-58, Type 39, protection saddles if insulation without vapor barrier is indicated. Fill interior voids with insulation
that matches adjoining insulation. a. Option: Thermal-hanger shield inserts may be used. Include steel weightdistribution plate for pipe NPS 4 and larger if pipe is installed on rollers.
3. Install MSS SP-58, Type 40, protective shields on cold piping with vapor barrier. Shields shall span an arc of 180 degrees. a. Option: Thermal-hanger shield inserts may be used. Include
steel weightdistribution plate for pipe NPS 4 and larger if pipe is installed on rollers. 4. Shield Dimensions for Pipe: Not less than the following: a. NPS 1/4 to NPS 3-1/2: 12 inches
long and 0.048 inch thick. b. NPS 4: 12 inches long and 0.06 inch thick. c. NPS 5 and NPS 6: 18 inches long and 0.06 inch thick. d. NPS 8 to NPS 14: 24 inches long and 0.075 inch thick.
e. NPS 16 to NPS 24: 24 inches long and 0.105 inch thick. 5. Pipes NPS 8 and Larger: Include wood inserts. 6. Insert Material: Length at least as long as protective shield. 7. Thermal-Hanger
Shields: Install with insulation same thickness as piping insulation. 3.3 METAL FABRICATIONS A. Cut, drill, and fit miscellaneous metal fabrications for trapeze pipe hangers and equipment
supports.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 22 05 29 -11 B. Fit exposed connections together to form hairline joints. Field weld connections that cannot be shop welded because
of shipping size limitations. C. Field Welding: Comply with AWS D1.1 procedures for shielded metal arc welding, appearance and quality of welds, and methods used in correcting welding
work, and with the following: 1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals. 2. Obtain fusion without undercut or
overlap. 3. Remove welding flux immediately. 4. Finish welds at exposed connections so no roughness shows after finishing and contours of welded surfaces match adjacent contours. 3.4
ADJUSTING A. Hanger Adjustments: Adjust hangers to distribute loads equally on attachments and to achieve indicated slope of pipe. B. Trim excess length of continuous-thread hanger and
support rods to 1-1/2 inches. 3.5 PAINTING A. Touch Up: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same
materials as used for shop painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces. 1. Apply paint by brush or spray to provide minimum dry film thickness
of 2.0 mils. B. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A 780. END OF SECTION 22 05 29
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT 22 05 53 -1 SECTION 22 05 53 -IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and
general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Warning
signs and labels. 2. Pipe labels. 3. Stencils. 4. Valve tags. 5. Warning tags. 1.3 SUBMITTALS A. Product Data: For each type of product indicated. B. Samples: For color, letter style,
and graphic representation required for each identification material and device. C. Valve numbering scheme. D. Valve Schedules: For each piping system to include in maintenance manuals.
1.4 COORDINATION A. Coordinate installation of identifying devices with completion of covering and painting of surfaces where devices are to be applied. B. Coordinate installation of
identifying devices with locations of access panels and doors. C. Install identifying devices before installing acoustical ceilings and similar concealment.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT 22 05 53 -2 PART 2 -PRODUCTS 2.1 WARNING SIGNS AND LABELS A. Material and Thickness: Multilayer, multicolor, plastic labels for mechanical
engraving, 1/16 inch thick, and having predrilled holes for attachment hardware. B. Letter Color: Black. C. Background Color: Yellow. D. Maximum Temperature: Able to withstand temperatures
up to 160 deg F. E. Minimum Label Size: Length and width vary for required label content, but not less than 2-1/2 by 3/4 inch. F. Minimum Letter Size: 1/4 inch for name of units if viewing
distance is less than 24 inches, 1/2 inch for viewing distances up to 72 inches, and proportionately larger lettering for greater viewing distances. Include secondary lettering two-thirds
to three-fourths the size of principal lettering. G. Fasteners: Stainless-steel self-tapping screws. H. Adhesive: Contact-type permanent adhesive, compatible with label and with substrate.
I. Label Content: Include caution and warning information, plus emergency notification instructions. 2.2 PIPE LABELS A. General Requirements for Manufactured Pipe Labels: Preprinted,
color-coded, with lettering indicating service, and showing flow direction. B. Pretensioned Pipe Labels: Precoiled, semi-rigid plastic formed to partially cover circumference of pipe
and to attach to pipe without fasteners or adhesive. C. Self-Adhesive Pipe Labels: Printed plastic with contact-type, permanent-adhesive backing. D. Pipe Label Contents: Include identification
of piping service using same designations or abbreviations as used on Drawings, pipe size, and an arrow indicating flow direction. 1. Flow-Direction Arrows: Integral with piping system
service lettering to accommodate both directions, or as separate unit on each pipe label to indicate flow direction. 2. Lettering Size: At least 1-1/2 inches high.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT 22 05 53 -3 2.3 STENCILS A. Stencils: Prepared with letter sizes according to ASME A13.1 for piping; and minimum letter height of 3/4
inch for access panel and door labels, equipment labels, and similar operational instructions. 1. Stencil Material: Fiberboard or metal. 2. Stencil Paint: Exterior, gloss, alkyd enamel
black unless otherwise indicated. Paint may be in pressurized spray-can form. 3. Identification Paint: Exterior, alkyd enamel in colors according to ASME A13.1 unless otherwise indicated.
2.4 VALVE TAGS A. Valve Tags: Stamped or engraved with 1/4-inch letters for piping system abbreviation and 1/2-inch numbers. 1. Tag Material: Brass, 0.032-inch minimum thickness, and
having predrilled or stamped holes for attachment hardware. 2. Fasteners: Brass wire-link or beaded chain; or S-hook. B. Valve Schedules: For each piping system, on 8-1/2-by-11-inch
bond paper. Tabulate valve number, piping system, system abbreviation (as shown on valve tag), location of valve (room or space), normal-operating position (open, closed, or modulating),
and variations for identification. Mark valves for emergency shutoff and similar special uses. 1. Valve-tag schedule shall be included in operation and maintenance data. 2.5 WARNING
TAGS A. Warning Tags: Preprinted or partially preprinted, accident-prevention tags, of plasticized card stock with matte finish suitable for writing. 1. Size: 3 by 5-1/4 inches minimum.
2. Fasteners: Brass grommet and wire. 3. Nomenclature: Large-size primary caption such as "DANGER," "CAUTION," or "DO NOT OPERATE." 4. Color: Yellow background with black lettering.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT 22 05 53 -4 PART 3 -EXECUTION 3.1 PREPARATION A. Clean piping and equipment surfaces of substances that could impair bond of identification
devices, including dirt, oil, grease, release agents, and incompatible primers, paints, and encapsulants. 3.2 PIPE LABEL INSTALLATION A. Stenciled Pipe Label Option: Stenciled labels
may be provided instead of manufactured pipe labels, at Installer's option. Install stenciled pipe labels with painted, color-coded bands or rectangles, complying with ASME A13.1, on
each piping system. 1. Identification Paint: Use for contrasting background. 2. Stencil Paint: Use for pipe marking. B. Locate pipe labels where piping is exposed or above accessible
ceilings in finished spaces; machine rooms; accessible maintenance spaces such as shafts, tunnels, and plenums; and exterior exposed locations as follows: 1. Near each valve and control
device. 2. Near each branch connection, excluding short takeoffs for fixtures and terminal units. Where flow pattern is not obvious, mark each pipe at branch. 3. Near penetrations through
walls, floors, ceilings, and inaccessible enclosures. 4. At access doors, manholes, and similar access points that permit view of concealed piping. 5. Near major equipment items and
other points of origination and termination. 6. Spaced at maximum intervals of 35 feet along each run. Reduce intervals to 25 feet in areas of congested piping and equipment. 7. On piping
above removable acoustical ceilings. Omit intermediately spaced labels. C. Pipe Label Color Schedule: 1. ASME A131.1. 3.3 VALVE-TAG INSTALLATION A. Install tags on valves and control
devices in piping systems, except check valves; valves within factory-fabricated equipment units; shutoff valves; faucets; convenience and lawn-watering hose connections; and similar
roughing-in connections of end-use fixtures and units. List tagged valves in a valve schedule.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT 22 05 53 -5 3.4 WARNING-TAG INSTALLATION A. Write required message on, and attach warning tags to, equipment and other items where required.
END OF SECTION 22 05 53
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -1 SECTION 22 07 00 -PLUMBING INSULATION PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Insulation materials: a. Flexible elastomeric. b. Mineral fiber.
2. Insulating cements. 3. Adhesives. 4. Factory-applied jackets. 5. Tapes. 6. Corner angles. 1.3 SUBMITTALS A. Product Data: For each type of product indicated. Include thermal conductivity,
thickness, and jackets (both factory and field applied, if any). B. Material Test Reports: From a qualified testing agency acceptable to authorities having jurisdiction indicating, interpreting,
and certifying test results for compliance of insulation materials, sealers, attachments, cements, and jackets, with requirements indicated. Include dates of tests and test methods employed.
1.4 QUALITY ASSURANCE A. Fire-Test-Response Characteristics: Insulation and related materials shall have fire-testresponse characteristics indicated, as determined by testing identical
products per ASTM E 84, by a testing and inspecting agency acceptable to authorities having jurisdiction. Factory label insulation and jacket materials and adhesive, mastic, tapes, and
cement material containers, with appropriate markings of applicable testing and inspecting agency.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -2 1. Insulation Installed Indoors: Flame-spread index of 25 or less, and smoke-developed index of 50 or less. 2. Insulation Installed Outdoors: Flame-spread
index of 75 or less, and smoke-developed index of 150 or less. 1.5 DELIVERY, STORAGE, AND HANDLING A. Packaging: Insulation material containers shall be marked by manufacturer with appropriate
ASTM standard designation, type and grade, and maximum use temperature. 1.6 COORDINATION A. Coordinate size and location of supports, hangers, and insulation shields specified in Division
22 Section "Hangers and Supports for Plumbing Piping and Equipment." B. Coordinate clearance requirements with piping Installer for piping insulation application and equipment Installer
for equipment insulation application. Before preparing piping Shop Drawings, establish and maintain clearance requirements for installation of insulation and fieldapplied jackets and
finishes and for space required for maintenance. C. Coordinate installation and testing of heat tracing. 1.7 SCHEDULING A. Schedule insulation application after pressure testing systems
and, where required, after installing and testing heat tracing. Insulation application may begin on segments that have satisfactory test results. B. Complete installation and concealment
of plastic materials as rapidly as possible in each area of construction. PART 2 -PRODUCTS 2.1 INSULATION MATERIALS A. Comply with requirements in Part 3 schedule articles for where
insulating materials shall be applied. B. Products shall not contain asbestos, lead, mercury, or mercury compounds. C. Products that come in contact with stainless steel shall have a
leachable chloride content of less than 50 ppm when tested according to ASTM C 871.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -3 D. Insulation materials for use on austenitic stainless steel shall be qualified as acceptable according to ASTM C 795. E. Flexible Elastomeric: Closed-cell,
sponge-or expanded-rubber materials. Comply with ASTM C 534, Type I for tubular materials and Type II for sheet materials. 1. Products: Subject to compliance with requirements, provide
one of the following: a. Aeroflex USA Inc.; Aerocel. b. Armacell LLC; AP Armaflex. c. RBX Corporation; Insul-Sheet 1800 and Insul-Tube 180. F. Mineral-Fiber, Preformed Pipe Insulation:
1. Products: Subject to compliance with requirements, provide one of the following: a. Johns Manville; Micro-Lok. b. Knauf Insulation; 1000(Pipe Insulation. c. Owens Corning; Fiberglas
Pipe Insulation. 2. Type I, 850 deg F Materials: Mineral or glass fibers bonded with with a thermosetting resin. Comply with ASTM C 547, Type I, Grade A, with factory-applied ASJ or
with factoryapplied ASJ-SSL. Factory-applied jacket requirements are specified in "Factory-Applied Jackets" Article. 2.2 INSULATING CEMENTS A. Mineral-Fiber Insulating Cement: Comply
with ASTM C 195. 1. Products: Subject to compliance with requirements, provide one of the following: a. Insulco, Division of MFS, Inc.; Triple I. b. P. K. Insulation Mfg. Co., Inc.;
Super-Stik. B. Mineral-Fiber, Hydraulic-Setting Insulating and Finishing Cement: Comply with ASTM C 449/C 449M. 1. Products: Subject to compliance with requirements, provide one of the
following: a. Insulco, Division of MFS, Inc.; SmoothKote. b. P. K. Insulation Mfg. Co., Inc.; PK No. 127, and Quik-Cote. c. Rock Wool Manufacturing Company; Delta One Shot.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -4 2.3 ADHESIVES A. Materials shall be compatible with insulation materials, jackets, and substrates and for bonding insulation to itself and to surfaces
to be insulated, unless otherwise indicated. B. Flexible Elastomeric Adhesive: Comply with MIL-A-24179A, Type II, Class I. 1. Products: Subject to compliance with requirements, provide
one of the following: a. Aeroflex USA Inc.; Aeroseal. b. Armacell LCC; 520 Adhesive. c. Foster Products Corporation, H. B. Fuller Company; 85-75. d. RBX Corporation; Rubatex Contact
Adhesive. C. Mineral-Fiber Adhesive: Comply with MIL-A-3316C, Class 2, Grade A. 1. Products: Subject to compliance with requirements, provide one of the following: a. Childers Products,
Division of ITW; CP-82. b. Foster Products Corporation, H. B. Fuller Company; 85-20. c. ITW TACC, Division of Illinois Tool Works; S-90/80. d. Marathon Industries, Inc.; 225. e. Mon-Eco
Industries, Inc.; 22-25. D. ASJ Adhesive: Comply with MIL-A-3316C, Class 2, Grade A for bonding insulation jacket lap seams and joints. 1. Products: Subject to compliance with requirements,
provide one of the following: a. Childers Products, Division of ITW; CP-82. b. Foster Products Corporation, H. B. Fuller Company; 85-20. c. ITW TACC, Division of Illinois Tool Works;
S-90/80. d. Marathon Industries, Inc.; 225. e. Mon-Eco Industries, Inc.; 22-25. 2.4 FACTORY-APPLIED JACKETS A. Insulation system schedules indicate factory-applied jackets on various
applications. When factory-applied jackets are indicated, comply with the following: 1. ASJ: White, kraft-paper, fiberglass-reinforced scrim with aluminum-foil backing; complying with
ASTM C 1136, Type I. 2. ASJ-SSL: ASJ with self-sealing, pressure-sensitive, acrylic-based adhesive covered by a removable protective strip; complying with ASTM C 1136, Type I.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -5 2.5 TAPES A. ASJ Tape: White vapor-retarder tape matching factory-applied jacket with acrylic adhesive, complying with ASTM C 1136. 1. Products: Subject
to compliance with requirements, provide one of the following: a. Avery Dennison Corporation, Specialty Tapes Division; Fasson 0835. b. Compac Corp.; 104 and 105. c. Ideal Tape Co.,
Inc., an American Biltrite Company; 428 AWF ASJ. d. Venture Tape; 1540 CW Plus, 1542 CW Plus, and 1542 CW Plus/SQ. 2. Width: 3 inches. 3. Thickness: 11.5 mils. 4. Adhesion: 90 ounces
force/inch in width. 5. Elongation: 2 percent. 6. Tensile Strength: 40 lbf/inch in width. 7. ASJ Tape Disks and Squares: Precut disks or squares of ASJ tape. 2.6 CORNER ANGLES A. PVC
Corner Angles: 30 mils thick, minimum 1 by 1 inch, PVC according to ASTM D 1784, Class 16354-C. White or color-coded to match adjacent surface. PART 3 -EXECUTION 3.1 EXAMINATION A. Examine
substrates and conditions for compliance with requirements for installation and other conditions affecting performance of insulation application. 1. Verify that systems and equipment
to be insulated have been tested and are free of defects. 2. Verify that surfaces to be insulated are clean and dry. 3. Proceed with installation only after unsatisfactory conditions
have been corrected. 3.2 PREPARATION A. Surface Preparation: Clean and prepare surfaces to be insulated. Before insulating, apply a corrosion coating to insulated surfaces as follows:
1. Stainless Steel: Coat 300 series stainless steel with an epoxy primer 5 mils thick and an epoxy finish 5 mils thick if operating in a temperature range between 140 and 300 deg F.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -6 Consult coating manufacturer for appropriate coating materials and application methods for operating temperature range. 2. Carbon Steel: Coat carbon steel
operating at a service temperature between 32 and 300 deg F with an epoxy coating. Consult coating manufacturer for appropriate coating materials and application methods for operating
temperature range. B. Coordinate insulation installation with the trade installing heat tracing. Comply with requirements for heat tracing that apply to insulation. C. Mix insulating
cements with clean potable water; if insulating cements are to be in contact with stainless-steel surfaces, use demineralized water. 3.3 GENERAL INSTALLATION REQUIREMENTS A. Install
insulation materials, accessories, and finishes with smooth, straight, and even surfaces; free of voids throughout the length of equipment and piping including fittings, valves, and
specialties. B. Install insulation materials, forms, vapor barriers or retarders, jackets, and thicknesses required for each item of equipment and pipe system as specified in insulation
system schedules. C. Install accessories compatible with insulation materials and suitable for the service. Install accessories that do not corrode, soften, or otherwise attack insulation
or jacket in either wet or dry state. D. Install insulation with longitudinal seams at top and bottom of horizontal runs. E. Install multiple layers of insulation with longitudinal and
end seams staggered. F. Do not weld brackets, clips, or other attachment devices to piping, fittings, and specialties. G. Keep insulation materials dry during application and finishing.
H. Install insulation with tight longitudinal seams and end joints. Bond seams and joints with adhesive recommended by insulation material manufacturer. I. Install insulation with least
number of joints practical. J. Where vapor barrier is indicated, seal joints, seams, and penetrations in insulation at hangers, supports, anchors, and other projections with vapor-barrier
mastic. 1. Install insulation continuously through hangers and around anchor attachments. 2. For insulation application where vapor barriers are indicated, extend insulation on anchor
legs from point of attachment to supported item to point of attachment to structure. Taper and seal ends at attachment to structure with vapor-barrier mastic.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -7 3. Install insert materials and install insulation to tightly join the insert. Seal insulation to insulation inserts with adhesive or sealing compound
recommended by insulation material manufacturer. 4. Cover inserts with jacket material matching adjacent pipe insulation. Install shields over jacket, arranged to protect jacket from
tear or puncture by hanger, support, and shield. K. Apply adhesives, mastics, and sealants at manufacturer's recommended coverage rate and wet and dry film thicknesses. L. Install insulation
with factory-applied jackets as follows: 1. Draw jacket tight and smooth. 2. Cover circumferential joints with 3-inch wide strips, of same material as insulation jacket. Secure strips
with adhesive and outward clinching staples along both edges of strip, spaced 4 inches o.o.c. 3. Overlap jacket longitudinal seams at least 1-1/2 inches. Install insulation with longitudinal
seams at bottom of pipe. Clean and dry surface to receive self-sealing lap. Staple laps with outward clinching staples along edge at 4 inches o.c. a. Do not staple longitudinal laps
on insulation having a vapor barrier. 4. Cover joints and seams with tape as recommended by insulation material manufacturer to maintain vapor seal. 5. Where vapor barriers are indicated,
apply vapor-barrier mastic on seams and joints and at ends adjacent to pipe flanges and fittings. M. Cut insulation in a manner to avoid compressing insulation more than 75 percent of
its nominal thickness. N. Finish installation with systems at operating conditions. Repair joint separations and cracking due to thermal movement. O. Repair damaged insulation facings
by applying same facing material over damaged areas. Extend patches at least 4 inches beyond damaged areas. Adhere, staple, and seal patches similar to butt joints. P. For above ambient
services, do not install insulation to the following: 1. Vibration-control devices. 2. Testing agency labels and stamps. 3. Nameplates and data plates. 4. Manholes. 5. Handholes. 6.
Cleanouts.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -8 3.4 PENETRATIONS A. Insulation Installation at Underground Exterior Wall Penetrations: Terminate insulation flush with sleeve seal. Seal terminations
with flashing sealant. B. Insulation Installation at Aboveground Exterior Wall Penetrations: Install insulation continuously through wall penetrations. 1. Seal penetrations with flashing
sealant. 2. For applications requiring only indoor insulation, terminate insulation inside wall surface and seal with joint sealant. 3. Seal jacket to wall flashing with flashing sealant.
C. Insulation Installation at Interior Wall and Partition Penetrations (That Are Not Fire Rated): Install insulation continuously through walls and partitions. D. Insulation Installation
at Fire-Rated Wall and Partition Penetrations: Install insulation continuously through penetrations of fire-rated walls and partitions. 1. Comply with requirements in Division 7 Section
"Firestopping" and fire-resistive joint sealers. E. Insulation Installation at Floor Penetrations: 1. Pipe: Install insulation continuously through floor penetrations. 2. Seal penetrations
through fire-rated assemblies. Comply with requirements in Division 7 Section "Firestopping." 3.5 GENERAL PIPE INSULATION INSTALLATION A. Requirements in this article generally apply
to all insulation materials except where more specific requirements are specified in various pipe insulation material installation articles. B. Insulation Installation on Fittings, Valves,
Strainers, Flanges, and Unions: 1. Install insulation over fittings, valves, strainers, flanges, unions, and other specialties with continuous thermal and vapor-retarder integrity, unless
otherwise indicated. 2. Insulate pipe elbows using preformed fitting insulation or mitered fittings made from same material and density as adjacent pipe insulation. Each piece shall
be butted tightly against adjoining piece and bonded with adhesive. Fill joints, seams, voids, and irregular surfaces with insulating cement finished to a smooth, hard, and uniform contour
that is uniform with adjoining pipe insulation. 3. Insulate tee fittings with preformed fitting insulation or sectional pipe insulation of same material and thickness as used for adjacent
pipe. Cut sectional pipe insulation to fit. Butt each section closely to the next and hold in place with tie wire. Bond pieces with adhesive.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -9 4. Insulate valves using preformed fitting insulation or sectional pipe insulation of same material, density, and thickness as used for adjacent pipe.
Overlap adjoining pipe insulation by not less than two times the thickness of pipe insulation, or one pipe diameter, whichever is thicker. For valves, insulate up to and including the
bonnets, valve stuffing-box studs, bolts, and nuts. Fill joints, seams, and irregular surfaces with insulating cement. 5. Insulate strainers using preformed fitting insulation or sectional
pipe insulation of same material, density, and thickness as used for adjacent pipe. Overlap adjoining pipe insulation by not less than two times the thickness of pipe insulation, or
one pipe diameter, whichever is thicker. Fill joints, seams, and irregular surfaces with insulating cement. Insulate strainers so strainer basket flange or plug can be easily removed
and replaced without damaging the insulation and jacket. Provide a removable reusable insulation cover. For below ambient services, provide a design that maintains vapor barrier. 6.
Insulate flanges and unions using a section of oversized preformed pipe insulation. Overlap adjoining pipe insulation by not less than two times the thickness of pipe insulation, or
one pipe diameter, whichever is thicker. 7. Cover segmented insulated surfaces with a layer of finishing cement and coat with a mastic. Install vapor-barrier mastic for below ambient
services and a breather mastic for above ambient services. Reinforce the mastic with fabric-reinforcing mesh. Trowel the mastic to a smooth and well-shaped contour. 8. For services not
specified to receive a field-applied jacket except for flexible elastomeric and polyolefin, install fitted PVC cover over elbows, tees, strainers, valves, flanges, and unions. Terminate
ends with PVC PVC end caps. Tape PVC covers to adjoining insulation facing using PVC tape. 9. Stencil or label the outside insulation jacket of each union with the word "UNION." Match
size and color of pipe labels. C. Insulate instrument connections for thermometers, pressure gages, pressure temperature taps, test connections, flow meters, sensors, switches, and transmitters
on insulated pipes, vessels, and equipment. Shape insulation at these connections by tapering it to and around the connection with insulating cement and finish with finishing cement,
mastic, and flashing sealant. 3.6 FLEXIBLE ELASTOMERIC INSULATION INSTALLATION A. Seal longitudinal seams and end joints with manufacturer's recommended adhesive to eliminate openings
in insulation that allow passage of air to surface being insulated. B. Insulation Installation on Pipe Flanges: 1. Install pipe insulation to outer diameter of pipe flange. 2. Make width
of insulation section same as overall width of flange and bolts, plus twice the thickness of pipe insulat
ion. ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -10 3. Fill voids between inner circumference of flange insulation and outer circumference of adjacent straight pipe segments with cut sections of sheet
insulation of same thickness as pipe insulation. 4. Secure insulation to flanges and seal seams with manufacturer's recommended adhesive to eliminate openings in insulation that allow
passage of air to surface being insulated. C. Insulation Installation on Pipe Fittings and Elbows: 1. Install mitered sections of pipe insulation. 2. Secure insulation materials and
seal seams with manufacturer's recommended adhesive to eliminate openings in insulation that allow passage of air to surface being insulated. D. Insulation Installation on Valves and
Pipe Specialties: 1. Install preformed valve covers manufactured of same material as pipe insulation when available. 2. When preformed valve covers are not available, install cut sections
of pipe and sheet insulation to valve body. Arrange insulation to permit access to packing and to allow valve operation without disturbing insulation. 3. Install insulation to flanges
as specified for flange insulation application. 4. Secure insulation to valves and specialties and seal seams with manufacturer's recommended adhesive to eliminate openings in insulation
that allow passage of air to surface being insulated. 3.7 MINERAL-FIBER INSULATION INSTALLATION A. Insulation Installation on Straight Pipes and Tubes: 1. Secure each layer of preformed
pipe insulation to pipe with wire or bands and tighten bands without deforming insulation materials. 2. Where vapor barriers are indicated, seal longitudinal seams, end joints, and protrusions
with vapor-barrier mastic and joint sealant. 3. For insulation with factory-applied jackets on above ambient surfaces, secure laps with outward clinched staples at 6 inches o.c. 4. For
insulation with factory-applied jackets on below ambient surfaces, do not staple longitudinal tabs but secure tabs with additional adhesive as recommended by insulation material manufacturer
and seal with vapor-barrier mastic and flashing sealant. B. Insulation Installation on Pipe Flanges: 1. Install preformed pipe insulation to outer diameter of pipe flange. 2. Make width
of insulation section same as overall width of flange and bolts, plus twice the thickness of pipe insulation. 3. Fill voids between inner circumference of flange insulation and outer
circumference of adjacent straight pipe segments with mineral-fiber blanket insulation.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -11 4. Install jacket material with manufacturer's recommended adhesive, overlap seams at least 1 inch, and seal joints with flashing sealant. C. Insulation
Installation on Pipe Fittings and Elbows: 1. Install preformed sections of same material as straight segments of pipe insulation when available. 2. When preformed insulation elbows and
fittings are not available, install mitered sections of pipe insulation, to a thickness equal to adjoining pipe insulation. Secure insulation materials with wire or bands. D. Insulation
Installation on Valves and Pipe Specialties: 1. Install preformed sections of same material as straight segments of pipe insulation when available. 2. When preformed sections are not
available, install mitered sections of pipe insulation to valve body. 3. Arrange insulation to permit access to packing and to allow valve operation without disturbing insulation. 4.
Install insulation to flanges as specified for flange insulation application. 3.8 PIPING INSULATION SCHEDULE, GENERAL A. Acceptable preformed pipe and tubular insulation materials and
thicknesses are identified for each piping system and pipe size range. If more than one material is listed for a piping system, selection from materials listed is Contractor's option.
B. Items Not Insulated: Unless otherwise indicated, do not install insulation on the following: 1. Drainage piping located in crawl spaces. 2. Underground piping. 3. Chrome-plated pipes
and fittings unless there is a potential for personnel injury. C. Service: Domestic hot and recirculated hot water: 1. Operating Temperature: 60 to 150 deg F. 2. Insulation Material:
Mineral fiber or flexible elastomeric. 3. Insulation Thickness: Apply the following insulation thicknesses: a. Pipe 1” and below: 1/2”. b. Pipe 1-1/4” and above: 1”. 4. Field-Applied
Jacket: None. 5. Vapor Retarder Required: No. 6. Finish: None.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -12 D. Service: Domestic cold water: 1. Operating Temperature: 35 to 60 deg F. 2. Insulation Material: Mineral fiber or flexible elastomeric. 3. Insulation
Thickness: Apply the following insulation thicknesses: a. Pipe 1” and below: 1/2”. b. Pipe 1-1/4” and above: 1”. 4. Field-Applied Jacket: None. 5. Vapor Retarder Required: Yes. 6. Finish:
None. E. Service: Horizontal storm drain piping conductors, including vertical up to RD: 1. Operating Temperature: 32 to 100 deg F. 2. Insulation Material: Mineral fiber or flexible
elastomeric. 3. Insulation Thickness: Apply the following insulation thicknesses: a. Pipe 2” and above: 1/2”. 4. Field-Applied Jacket: None. 5. Vapor Retarder Required: Yes. 6. Finish:
None. F. Service: Roof drain bodies: 1. Operating Temperature: 32 to 100 deg F. 2. Insulation Material: Mineral fiber or flexible elastomeric. 3. Insulation Thickness: 1”. 4. Field-Applied
Jacket: None. 5. Vapor Retarder Required: Yes. 6. Finish: None. G. Service: Horizontal sanitary waste piping: 1. Operating Temperature: 35 to 100 deg F. 2. Insulation Material: Mineral
fiber or flexible elastomeric. 3. Insulation Thickness: Apply the following insulation thicknesses: a. Pipe 1-1/2” and above: 1/2”. 4. Field-Applied Jacket: None. 5. Vapor Retarder Required:
Yes. 6. Finish: None.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING INSULATION 22 07 00 -13 H. Service: Condensate drain piping: 1. Operating Temperature: 35 to 75 deg F. 2. Insulation Material: Flexible elastomeric. 3. Insulation Thickness:
1/2”. 4. Field-Applied Jacket: None. 5. Vapor Retarder Required: Yes. 6. Finish: None. I. Service: Exposed sanitary drains and domestic water supplies and stops for fixtures for the
disabled: 1. Operating Temperature: 35 to 120 deg F. 2. Insulation Material: Truebro Handi Lav-Guard Insulation Kit. 3. Finish: None. END OF SECTION 22 07 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
DOMESTIC WATER PIPING 22 11 16 -1 SECTION 22 11 16 -DOMESTIC WATER PIPING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General
and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes domestic water piping inside the building. B. Related
Sections include the following: 1. Division 22 Section "Meters and Gages" for thermometers, pressure gages, and fittings. 2. Division 22 Section "Plumbing Specialties" for water distribution
piping specialties. 1.3 PERFORMANCE REQUIREMENTS A. Provide components and installation capable of producing domestic water piping systems with 125 psig, unless otherwise indicated.
1.4 SUBMITTALS A. Product Data: For pipe, tube, fittings, and couplings. B. Water Samples: Specified in Part 3 "Cleaning" Article. C. Field quality-control test reports. 1.5 QUALITY
ASSURANCE A. Piping materials shall bear label, stamp, or other markings of specified testing agency. B. Comply with NSF 61, "Drinking Water System Components -Health Effects; Sections
1 through 9," for potable domestic water piping and components.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
DOMESTIC WATER PIPING 22 11 16 -2 PART 2 -PRODUCTS 2.1 MANUFACTURERS A. In other Part 2 articles where titles below introduce lists, the following requirements apply to product selection:
1. Manufacturers: Subject to compliance with requirements, provide products by one of the manufacturers specified. 2.2 PIPING MATERIALS A. Refer to Part 3 "Pipe and Fitting Applications"
Article for applications of pipe, tube, fitting, and joining materials. B. Transition Couplings for Aboveground Pressure Piping: Coupling or other manufactured fitting the same size
as, with pressure rating at least equal to and ends compatible with, piping to be joined. 2.3 COPPER TUBE AND FITTINGS A. Hard Copper Tube: ASTM B 88, Types L, water tube, drawn temper
for piping 4" and smaller. 1. Copper Pressure Fittings: ASME B16.22, wrought-copper, solder-joint fittings. 2. Bronze Flanges: ASME B16.24, Class 150, with solder-joint ends. 3. Copper
Unions: MSS SP-123, cast-copper-alloy, hexagonal-stock body, with ball-andsocket, metal-to-metal seating surfaces, and solder-joint or threaded ends. 2.4 VALVES A. Bronze and cast-iron,
general-duty valves are specified in Division 22 Section "Valves." B. Balancing and drain valves are specified in Division 22 Section "Plumbing Specialties." PART 3 -EXECUTION 3.1 PIPE
AND FITTING APPLICATIONS A. Transition and special fittings with pressure ratings at least equal to piping rating may be used in applications below, unless otherwise indicated. B. Flanges
may be used on aboveground piping, unless otherwise indicated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
DOMESTIC WATER PIPING 22 11 16 -3 C. Fitting Option: Extruded-tee connections and brazed joints may be used on aboveground copper tubing. 3.2 VALVE APPLICATIONS A. Drawings indicate
valve types to be used. Where specific valve types are not indicated, the following requirements apply: 1. Shutoff Duty: Use bronze ball or gate valves for piping NPS 2 and smaller.
Use castiron butterfly or gate valves with flanged ends for piping NPS 2-1/2 and larger. 2. Throttling Duty: Use bronze ball or globe valves for piping NPS 2 and smaller. Use cast-iron
butterfly valves with flanged ends for piping NPS 2-1/2 and larger. 3. Drain Duty: Hose-end drain valves. B. Install shutoff valve close to water main on each branch and riser serving
plumbing fixtures or equipment, on each water supply to equipment, and on each water supply to plumbing fixtures that do not have supply stops. Use ball valves for piping NPS 2 and smaller.
Use butterfly or gate valves for piping NPS 2-1/2 and larger. C. Install drain valves for equipment at base of each water riser, at low points in horizontal piping, and where required
to drain water piping. 1. Install hose-end drain valves at low points in water mains, risers, and branches. 2. Install stop-and-waste drain valves where indicated. 3.3 PIPING INSTALLATION
A. Basic piping installation requirements are specified in Division 22 Section "Basic Mechanical Materials and Methods." B. Install domestic water piping level and plumb. 3.4 JOINT CONSTRUCTION
A. Basic piping joint construction requirements are specified in Division 22 Section "Basic Mechanical Materials and Methods." B. Soldered Joints: Use ASTM B 813, water-flushable, lead-free
flux; ASTM B 32, lead-freealloy solder; and ASTM B 828 procedure, unless otherwise indicated. C. Extruded-Tee Connections: Form tee in copper tube according to ASTM F 2014. Use tool
designed for copper tube; drill pilot hole, form collar for outlet, dimple tube to form seating stop, and braze branch tube into collar.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
DOMESTIC WATER PIPING 22 11 16 -4 3.5 HANGER AND SUPPORT INSTALLATION A. Pipe hanger and support devices are specified in Division 22 Section "Hangers and Supports." Install the following:
1. Vertical Piping: MSS Type 8 or Type 42, clamps. 2. Individual, Straight, Horizontal Piping Runs: According to the following: a. 100 Feet and Less: MSS Type 1, adjustable, steel clevis
hangers. B. Install supports according to Division 22 Section "Hangers and Supports." C. Support vertical piping and tubing at base and at each floor. D. Rod diameter may be reduced
1 size for double-rod hangers, to a minimum of 3/8 inch. E. Install hangers for copper tubing with the following maximum horizontal spacing and minimum rod diameters: 1. NPS 3/4 and
Smaller: 60 inches with 3/8-inch rod. 2. NPS 1 and NPS 1-1/4: 72 inches with 3/8-inch rod. 3. NPS 1-1/2 and NPS 2: 96 inches with 3/8-inch rod. 4. NPS 2-1/2: 108 inches with 1/2-inch
rod. 5. NPS 3 to NPS 4: 10 feet with 1/2-inch rod. F. Install supports for vertical copper tubing every 10 feet. 3.6 CONNECTIONS A. Drawings indicate general arrangement of piping, fittings,
and specialties. B. Install piping adjacent to equipment and machines to allow service and maintenance. 3.7 FIELD QUALITY CONTROL A. Inspect domestic water piping as follows: 1. Do not
enclose, cover, or put piping into operation until it has been inspected and approved by authorities having jurisdiction. 2. During installation, notify authorities having jurisdiction
at least 24 hours before inspection must be made. Perform tests specified below in presence of authorities having jurisdiction: a. Roughing-in Inspection: Arrange for inspection of piping
before concealing or closing-in after roughing-in and before setting fixtures.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
DOMESTIC WATER PIPING 22 11 16 -5 b. Final Inspection: Arrange final inspection for authorities having jurisdiction to observe tests specified below and to ensure compliance with requirements.
3. Reinspection: If authorities having jurisdiction find that piping will not pass test or inspection, make required corrections and arrange for reinspection. 4. Reports: Prepare inspection
reports and have them signed by authorities having jurisdiction. B. Test domestic water piping as follows: 1. Fill domestic water piping. Check components to determine that they are
not air bound and that piping is full of water. 2. Test for leaks and defects in new piping and parts of existing piping that have been altered, extended, or repaired. If testing is
performed in segments, submit separate report for each test, complete with diagram diagram of portion of piping tested. 3. Leave new, altered, extended, or replaced domestic water piping
uncovered and unconcealed until it has been tested and approved. Expose work that was covered or concealed before it was tested. 4. Cap and subject piping to static water pressure of
50 psig above operating pressure, without exceeding pressure rating of piping system materials. Isolate test source and allow to stand for four hours. Leaks and loss in test pressure
constitute defects that must be repaired. 5. Repair leaks and defects with new materials and retest piping or portion thereof until satisfactory results are obtained. 6. Prepare reports
for tests and required corrective action. 3.8 ADJUSTING A. Perform the following adjustments before operation: 1. Close drain valves, hydrants, and hose bibbs. 2. Open shutoff valves
to fully open position. 3. Open throttling valves to proper setting. 4. Adjust balancing valves in hot-water-circulation return piping to provide adequate flow. a. Adjust calibrated
balancing valves to flows indicated. 5. Remove plugs used during testing of piping and plugs used for temporary sealing of piping during installation. 6. Remove and clean strainer screens.
Close drain valves and replace drain plugs. 7. Remove filter cartridges from housings and verify that cartridges are as specified for application where used and are clean and ready for
use. 8. Check plumbing specialties and verify proper settings, adjustments, and operation.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
DOMESTIC WATER PIPING 22 11 16 -6 3.9 CLEANING A. Clean and disinfect potable domestic water piping as follows: 1. Purge new piping and parts of existing domestic water piping that have
been altered, extended, or repaired before using. 2. Use purging and disinfecting procedures prescribed by authorities having jurisdiction or, if methods are not prescribed, procedures
described in either AWWA C651 or AWWA C652 or as described below: a. Flush piping system with clean, potable water until dirty water does not appear at outlets. b. Fill and isolate system
according to either of the following: 1) Fill system or part thereof with water/chlorine solution with at least 50 ppm of chlorine. Isolate with valves and allow to stand for 24 hours.
2) Fill system or part thereof with water/chlorine solution with at least 200 ppm of chlorine. Isolate and allow to stand for three hours. c. Flush system with clean, potable water until
no chlorine is in water coming from system after the standing time. d. Submit water samples in sterile bottles to authorities having jurisdiction. Repeat procedures if biological examination
shows contamination. B. Prepare and submit reports of purging and disinfecting activities. C. Clean interior of domestic water piping system. Remove dirt and debris as work progresses.
END OF SECTION 22 11 16
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
STORM, SANITARY WASTE AND VENT PIPING 22 13 16 -1 SECTION 22 13 16 – STORM, SANITARY WASTE AND VENT PIPING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of
the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. B. This Section includes storm drainage, soil and waste, sanitary
drainage, and vent piping inside the building and to locations indicated. C. Related Sections include the following: 1. Division 22 Section "Plumbing Specialties" for storm drainage,
soil, waste, and vent piping systems specialties. 1.2 PERFORMANCE REQUIREMENTS A. Provide components and installation capable of producing piping systems with the following minimum working-pressure
ratings, unless otherwise indicated: 1. Storm Drainage, Soil, Waste, and Vent Piping: 10-foot head of water. 1.3 SUBMITTALS A. Product Data: For pipe, tube, fittings, and couplings.
B. Field Test Reports: Indicate and interpret test results for compliance with performance requirements. 1.4 QUALITY ASSURANCE A. Piping materials shall bear label, stamp, or other markings
of specified testing agency.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01
____________________________________________________________________________________ STORM, SANITARY WASTE AND VENT PIPING 22 13 16 -2 PART 2 -PRODUCTS 2.1 CAST-IRON SOIL PIPING A. Hubless
Pipe and Fittings for pipe above ground: ASTM A 888 or CISPI 301. 1. CISPI, hubless piping couplings: a. Standards: ASTM C 1277 and CISPI 310 b. Description: Stainless steel corrugated
shield with stainless steel bands and tightening devices and ASTM C564, rubber sleeve with integral, center pipe stop. c. Manufacturers: Subject to compliance with requirements, provide
products of one of the following: 1) ANACO-Husky. 2) Clamp-All. 3) Mission Rubber Co. 4) Tyler Pipe. 2. Heavy duty, hubless pipe couplings: a. Standards: ASTM C 1277 and ASTM C 1540.
b. Description: Stainless steel shield with stainless steel bands and tightening devices and ASTM C 564, rubber sleeve with integral center pipe stop. c. Manufacturers: Subject to compliance
with requirements, provide products of one of the following: 1) ANACO-Husky. 2) Clamp-All d. Application: Install heavy duty pipe couplings on all 6 inch and larger horizontal waste
and storm piping. PART 3 -EXECUTION 3.1 PIPING INSTALLATION A. Refer to Division 22 Section "Common Work Results for Plumbing" for basic piping installation. B. Install cleanouts at
grade and extend to where building sanitary drains connect to building sanitary sewers. C. Install cleanout fitting with closure plug inside the building in sanitary force-main piping.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
STORM, SANITARY WASTE AND VENT PIPING 22 13 16 -3 D. Install cast-iron sleeve with water stop and mechanical sleeve seal at each service pipe penetration through foundation wall. Select
number of interlocking rubber links required to make installation watertight. Refer to Division 22 Section "Basic Mechanical Materials and Methods" for sleeves and mechanical sleeve
seals. E. Install cast-iron soil piping according to CISPI's "Cast Iron Soil Pipe and Fittings Handbook," Chapter IV, "Installation of Cast Iron Soil Pipe and Fittings." F. Make changes
in direction for soil and waste drainage and vent piping using appropriate branches, bends, and long-sweep bends. Sanitary tees and short-sweep 1/4 bends may be used on vertical stacks
if change in direction of flow is from horizontal to vertical. Use long-turn, double Y-branch and 1/8-bend fittings if 2 fixtures are installed back to back or side by side with common
drain pipe. Straight tees, elbows, and crosses may be used on vent lines. Do not change direction of flow more than 90 degrees. Use proper size of standard increasers and reducers if
pipes of different sizes are connected. Reducing size of drainage piping in direction of flow is prohibited. G. Install storm, soil and waste drainage and vent piping at the following
minimum slopes, unless otherwise indicated: 1. Storm Drainage and Building Sanitary Drain: 2 percent downward in direction of flow for piping NPS 2 and smaller; 1 percent downward in
direction of flow for piping NPS 3 and larger. 2. Horizontal Sanitary Drainage Piping: 2 percent downward in direction of flow for piping, NPS 2 and smaller, 1 percent downward in direction
of flow for piping NPS 3 and larger. 3. Vent Piping: 1 percent down toward vertical fixture vent or toward vent stack. H. Do not enclose, cover, or put piping into operation until it
is inspected and approved by authorities having jurisdiction. 3.2 JOINT CONSTRUCTION A. Refer to Division 22 Section "Common Work Results for Plumbing" for basic piping joint construction.
B. Cast-Iron, Soil-Piping Joints: Make joints according to CISPI's "Cast Iron Soil Pipe and Fittings Handbook," Chapter IV, "Installation of Cast Iron Soil Pipe and Fittings." 1. Hubless
Joints: Make with rubber gasket and sleeve or clamp. 3.3 HANGER AND SUPPORT INSTALLATION A. Refer to Division 22 Section "Vibration Controls and Seismic Restraints" for seismic-restraint
devices.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
STORM, SANITARY WASTE AND VENT PIPING 22 13 16 -4 B. Refer to Division 22 Section "Hangers and Supports" for pipe hanger and support devices. Install the following: 1. Vertical Piping:
MSS Type 8 or Type 42, clamps. 2. Individual, Straight, Horizontal Piping Runs: According to the following: a. MSS Type 1, adjustable, steel clevis hangers. C. Install supports according
to Division 22 Section "Hangers and Supports." D. Support vertical piping and tubing at base and at each floor. E. Rod diameter may be reduced 1 size for double-rod hangers, with 3/8-inch
minimum rods. F. Install hangers for cast-iron soil piping with the following maximum horizontal spacing and minimum rod diameters: 1. NPS 1-1/2 and NPS 2: 60 inches with 3/8-inch rod.
2. NPS 3: 60 inches with 1/2-inch rod. 3. NPS 4 and NPS 5: 60 inches with 5/8-inch rod. 4. NPS 6: 60 inches with 3/4-inch rod. 5. NPS 8 to NPS 12: 60 inches with 7/8-inch rod. 6. NPS
15: 60 inches with 1-inch rod. 7. Spacing for 10-foot lengths may be increased to 10 feet. Spacing for fittings is limited to 60 inches. G. Install supports for vertical cast-iron soil
piping every 15 feet. H. Support piping and tubing not listed above according to MSS SP-69 and manufacturer's written instructions. 3.4 CONNECTIONS A. Drawings indicate general arrangement
of piping, fittings, and specialties. B. Connect storm drainage piping to roof drains and storm drainage specialties. C. Connect drainage and vent piping to the following: 1. Plumbing
Fixtures: Connect drainage piping in sizes indicated, but not smaller than required by plumbing code. Refer to Division 22 Section "Plumbing Fixtures." 2. Plumbing Fixtures and Equipment:
Connect atmospheric vent piping in sizes indicated, but not smaller than required by authorities having jurisdiction. 3. Plumbing Specialties: Connect drainage and vent piping in in
sizes indicated, but not smaller than required by plumbing code. Refer to Division 22 Section "Plumbing Specialties."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
STORM, SANITARY WASTE AND VENT PIPING 22 13 16 -5 4. Equipment: Connect drainage piping as indicated. Provide shutoff valve, if indicated, and union for each connection. Use flanges
instead of unions for connections NPS 2-1/2 and larger. 3.5 FIELD QUALITY CONTROL A. During installation, notify authorities having jurisdiction at least 24 hours before inspection must
be made. Perform tests specified below in presence of authorities having jurisdiction. 1. Roughing-in Inspection: Arrange for inspection of piping before concealing or closing-in after
roughing-in and before setting fixtures. 2. Final Inspection: Arrange for final inspection by authorities having jurisdiction to observe tests specified below and to ensure compliance
with requirements. B. Reinspection: If authorities having jurisdiction find that piping will will not pass test or inspection, make required corrections and arrange for reinspection.
C. Reports: Prepare inspection reports and have them signed by authorities having jurisdiction. 1. Test for leaks and defects in new piping and parts of existing piping that have been
altered, extended, or repaired. If testing is performed in segments, submit separate report for each test, complete with diagram of portion of piping tested. 2. Leave uncovered and unconcealed
new, altered, extended, or replaced drainage and vent piping until it has been tested and approved. Expose work that was covered or concealed before it was tested. 3. Roughing-in Plumbing
Test Procedure: Test drainage and vent piping, except outside leaders, on completion of roughing-in. Close openings in piping system and fill with water to point of overflow, but not
less than 10-foot head of water. From 15 minutes before inspection starts to completion of inspection, water level must not drop. Inspect joints for leaks. 4. Finished Plumbing Test
Procedure: After plumbing fixtures have been set and traps filled with water, test connections and prove they are gastight and watertight. Plug ventstack openings on roof and building
drains where they leave building. Introduce air into piping system equal to pressure of 1-inch wg. Use U-tube or manometer inserted in trap of water closet to measure this pressure.
Air pressure must remain constant without introducing additional air throughout period of inspection. Inspect plumbing fixture connections for gas and water leaks. 5. Repair leaks and
defects with new materials and retest piping, or portion thereof, until satisfactory results are obtained. 6. Prepare reports for tests and required corrective action. 3.6 CLEANING A.
Clean interior of piping. Remove dirt and debris as work progresses.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
STORM, SANITARY WASTE AND VENT PIPING 22 13 16 -6 B. Protect drains during remainder of construction period to avoid clogging with dirt and debris and to prevent damage from traffic
and construction work. C. Place plugs in ends of uncompleted piping at end of day and when work stops. END OF SECTION 22 13 16
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING SPECIALTIES 22 13 19 -1 SECTION 22 13 19 -PLUMBING SPECIALTIES PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following plumbing specialties: 1. Backflow preventers.
2. Water filters. 3. Trap seal primer valves. 4. Trap guards. 5. Drain valves. 6. Miscellaneous piping specialties. 7. Cleanouts. 8. Floor drains. B. Related Sections include the following:
1. Division 22 Section "Meters and Gages" for water meters, thermometers, and pressure gages. 1.3 PERFORMANCE REQUIREMENTS A. Provide components and installation capable of producing
piping systems with following minimum working-pressure ratings, unless otherwise indicated: 1. Domestic Water Piping: 125 psig. 2. Sanitary Waste and Vent Piping: 10-foot head of water.
3. Storm Drainage Piping: 10-foot head of water. 1.4 SUBMITTALS A. Product Data: Include rated capacities and shipping, installed, and operating weights. Indicate materials, finishes,
dimensions, required clearances, and methods of assembly of components; and piping and wiring connections for the following:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING SPECIALTIES 22 13 19 -2 1. Backflow preventers. 2. Water filters. 3. Water hammer arresters, air vents, trap seal primer valves and systems, and trap guards. 4. Drain valves.
5. Cleanouts and floor drains. B. Shop Drawings: Diagram power, signal, and control wiring. C. Field test reports. D. Maintenance Data: For plumbing specialties to include in maintenance
manuals. Include the following: 1. Backflow preventers. 2. Water filters. 3. Trap seal primer valves and trap guards. 1.5 QUALITY ASSURANCE A. Product Options: Drawings indicate size,
profiles, and dimensional requirements of plumbing specialties and are based on the specific system indicated. Refer to Division 1 Section "Product Requirements." B. Plumbing specialties
shall bear label, stamp, or other markings of specified testing agency. C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by
a testing agency acceptable to authorities having jurisdiction, and marked for intended use. D. ASME Compliance: Comply with ASME B31.9, "Building Services Piping," for piping materials
and installation. E. NSF Compliance: 1. Comply with NSF 61, "Drinking Water System Components--Health Effects, Sections 1 through 9," for potable domestic water plumbing specialties.
PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING SPECIALTIES 22 13 19 -3 2.2 BACKFLOW PREVENTERS A. Manufacturers: 1. CMB Industries, Inc.; Febco Backflow Preventers. 2. Conbraco Industries, Inc. 3. Watts Industries, Inc.;
Water Products Div. 4. Zurn Industries, Inc.; Wilkins Div. B. General: ASSE standard, backflow preventers. 1. NPS 2 and Smaller: Bronze body with threaded ends. 2. NPS 2-1/2 and Larger:
Bronze, cast-iron, steel, or stainless-steel body with flanged ends. a. Interior Lining: AWWA C550 or FDA-approved, epoxy coating for backflow preventers having cast-iron or steel body.
3. Interior Components: Corrosion-resistant materials. 4. Indiana State Department of Health Approved. C. Pipe-Applied, Atmospheric-Type Vacuum Breakers: ASSE 1001, with floating disc
and atmospheric vent. D. Hose-Connection Vacuum Breakers: ASSE 1011, nickel plated, with non-removable and manual drain features, and ASME B1.20.7, garden-hose threads on outlet. Units
attached to rough-bronze-finish hose connections may be rough bronze. E. Reduced-Pressure-Principle Backflow Preventers: ASSE 1013, suitable for continuous pressure application. Include
outside screw and yoke gate valves on inlet and outlet, and strainer on inlet; test cocks; and pressure-differential relief valve with ASME A112.1.2 air-gap fitting located between two
positive-seating check valves. 1. Pressure Loss: 12 psig maximum, through middle 1/3 of flow range. F. Anti-siphon-Pressure-Type Vacuum Breakers: ASSE 1020, suitable for continuous pressure
application. Include shutoff valves, spring-loaded check valve, spring-loaded floating disc, test cocks, and atmospheric vent. 1. Pressure Loss: 5 psig maximum, through middle 1/3 of
flow range. 2.3 WATER FILTERS A. Manufacturers: 1. CUNO, Incorporated. 2. Filpro Corporation.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING SPECIALTIES 22 13 19 -4 3. Filterspun. 4. Filtrine Manufacturing Company; Drinking Water Division. 5. Harmsco Industrial Filters. 6. Met-Pro Corporation; Keystone Filter Division.
7. U.S. Filter; Filterite Div. 8. Watts Industries, Inc.; Water Products Div. 9. Whatman, Inc.; Balston Div. B. General: Cartridge-type assemblies suitable for potable water. Include
housing, fittings, filter cartridges, and cartridge end caps. C. Wall-Mounting Type: Housing head section with threaded inlet and outlet, mounting bracket, and removable lower section
for 10-inch-long filter cartridge. 1. Housing Material: Plastic, 125-psig minimum operating pressure. 2. Cartridge: Wound-or molded-fiber filter media, 10 inches, 10-micron-particulate
removable rating. 2.4 TRAP SEAL PRIMER VALVES A. Supply-Type Trap Seal Primer Valves: ASSE 1018, water-supply-fed type. 1. Manufacturers: a. Mifab. b. Precision Plumbing Products, Inc.
2. 125 psig minimum working pressure. 3. Bronze body with atmospheric-vented drain chamber. 4. Inlet and Outlet Connections: NPS 1/2 threaded, union, or solder joint. 5. Gravity Drain
Outlet Connection: NPS 1/2 threaded or solder joint. 6. AG-500 trap primer air gap. 7. Finish: Chrome plated, or rough bronze for units used with pipe or tube that is not chrome finished.
2.5 TRAP GUARDS A. Sewer Gas and Sewage Backup Protection Trap Guard: B. Description: 1. Material: Smooth, soft, flexible elastomeric PVC material molded into shape of duck’s bill open
on top with curl closure at bottom. 2. Allows wastewater to open and adequately discharge floor drain through its interior. 3. Closes and returns to original molded shape after waste
water discharge is complete.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING SPECIALTIES 22 13 19 -5 C. Manufacturers: 1. ProSet Systems, Inc. 2.6 DRAIN VALVES A. Hose-End Drain Valves: MSS SP-110, NPS 3/4 ball valve, rated for 400-psig minimum CWP.
Include two-piece, copper-alloy body with standard port, chrome-plated brass ball, replaceable seats and seals, blowout-proof stem, and vinyl-covered steel handle. 1. Inlet: Threaded.
2. Outlet: Short-threaded nipple with ASME B1.20.7, garden-hose threads and cap. 2.7 MISCELLANEOUS PIPING SPECIALTIES A. Water Hammer Arresters: ASSE 1010 or PDI-WH 201, metal-bellows
or copper tube with piston type with pressurized metal cushioning chamber. Sizes indicated are based on ASSE 1010 or PDI-WH 201, Sizes A through F. 1. Manufacturers: a. Josam Co. b.
Mifab. c. Sioux Chief. d. Smith, Jay R. Mfg. Co. e. Tyler Pipe; Wade Div. f. Zurn Industries, Inc.; Specification Drainage Operation. B. Deep-Seal Traps: Cast-iron or bronze casting,
with inlet and outlet matching connected piping and cleanout trap seal primer valve connection. 1. NPS 2: 4-inch-minimum water seal. 2. NPS 2-1/2 and Larger: 5-inch-minimum water seal.
C. Floor-Drain Inlet Fittings: Cast iron, with threaded inlet and threaded or spigot outlet, and trap seal primer valve connection. D. Fixed Air-Gap Fittings: Manufactured cast-iron
or bronze drainage fitting with semi-open top with threads or device to secure drainage inlet piping in top and bottom spigot or threaded outlet larger than top inlet. Include design
complying with ASME A112.1.2 that will provide fixed air gap between installed inlet and outlet piping.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING SPECIALTIES 22 13 19 -6 2.8 CLEANOUTS A. Floor Cleanout Access Covers: 1. Cast iron body with round nickel bronze frame and cover; J. R. Smith 4021. B. Floor Access Covers –
Carpeted Floor: 1. Cast iron body with nickel bronze carpet marker; J. R. Smith 4021-Y. C. Wall Cleanout Access Covers: 1. Stainless steel cover and screw; J. R. Smith 4710. D. Floor
Cleanout Access Cover – Stainless Steel: 1. Stainless steel body with round stainless steel vacuum cover; Blucher-Josem 774.55. E. Products: 1. Blucher Josam. 2. Josam Co. 3. Mifab.
4. Sioux Chief/Finish Line. 5. Smith, Jay R. Mfg. Co. 6. Tyler Pipe, Wade Div. 7. Watts Industries, Inc. 8. Zurn Industries, Inc. 2.9 FLOOR DRAINS A. Floor Drain FD-1: 1. Cast iron body
and flashing collar, nickel bronze adjustable round strainer head with secured square hole grate; J. R. Smith 2005-A. B. Floor Drain FD-2: 1. Cast iron body and flashing collar, nickel
bronze adjustable round strainer head with secured square hole grate; J. R. Smith 2005-A with 3581 funnel. C. Products: 1. Blucher-Josam. 2. Josam Co. 3. Mifab.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING SPECIALTIES 22 13 19 -7 4. Quick-Trench. 5. Sioux Chief/Finish Line. 6. Smith, Jay R. Mfg. Co. 7. Tyler Pipe, Wade Div. 8. Watts Industries, Inc. 9. Zurn Industries, Inc. PART
3 -EXECUTION 3.1 INSTALLATION A. Refer to Division 22 Section "Common Work Results for Plumbing" for piping joining materials, joint construction, and basic installation requirements.
B. Install backflow preventers in each water supply to mechanical equipment and systems and to other equipment and water systems that may be sources of contamination. Comply with authorities
having jurisdiction. 1. Install drain for backflow preventers with atmospheric-vent drain connection with air-gap fitting, fixed air-gap fitting, or equivalent positive pipe separation
of at least two pipe diameters in drain piping and pipe to floor drain. Locate air-gap device attached to or under backflow preventer. Simple air breaks are not acceptable for this application.
2. Do not install bypass piping around backflow preventers. 3. After installation, equipment must be certified by a licensed tester. Copies of certified test results must be submitted
to Owner. C. Install trap seal primer valves with outlet piping pitched down toward drain trap a minimum of 1 percent and connect to floor-drain body, trap, or inlet fitting. Adjust
valve for proper flow. D. Install expansion joints on vertical risers, stacks, and conductors if indicated. E. Install cleanouts in aboveground piping and building drain piping according
to the following, unless otherwise indicated: 1. Size same as drainage piping up to NPS 6. Use NPS 6 for 8” and larger drainage piping unless larger cleanout is indicated. 2. Locate
at each change in direction of piping greater than 45 degrees. 3. Locate at minimum intervals of 50 feet for piping NPS 4 and smaller and 100 feet for larger piping. 4. Locate at at
base of each vertical soil and waste stack. F. Install cleanout deck plates with top flush with finished floor, for floor cleanouts for piping below floors.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING SPECIALTIES 22 13 19 -8 G. Install cleanout wall access covers, of types indicated, with frame and cover flush with finished wall, for cleanouts located in concealed piping.
H. Install flashing flange and clamping device with each stack and cleanout passing through floors with waterproof membrane. I. Install floor drains at low points of surface areas to
be drained. Set grates of drains flush with finished floor, unless otherwise indicated. 1. Position floor drains for easy access and maintenance. 2. Install floor-drain flashing collar
or flange so no leakage occurs between drain and adjoining flooring. Maintain integrity of waterproof membranes where penetrated. 3. Install individual traps for floor drains connected
to sanitary building drain, unless otherwise indicated. J. Fasten wall-hanging plumbing specialties securely to supports attached to building substrate if supports are specified and
to building wall construction if no support is indicated. K. Fasten recessed-type plumbing specialties to reinforcement built into walls. L. Install wood-blocking reinforcement for wall-mounting
and recessed-type plumbing specialties. M. Install individual shutoff valve in each water supply to plumbing specialties. Use ball, gate, or globe valve if specific valve is not indicated.
Install shutoff valves in accessible locations. Refer to Division 22 Section "Valves" for general-duty ball, butterfly, check, gate, and globe valves. N. Install air vents at piping
high points. Include ball, gate, or globe valve in inlet and drain piping from outlet to floor drain. O. Install traps on plumbing specialty drain outlets. Omit traps on indirect wastes
unless trap is indicated. P. Install escutcheons at wall, floor, and ceiling penetrations in exposed finished locations and within cabinets and millwork. Use deep-pattern escutcheons
escutcheons if required to conceal protruding pipe fittings. 3.2 CONNECTIONS A. Piping installation requirements are specified in other Division 22 Sections. Drawings indicate general
arrangement of piping, fittings, and specialties. B. Install piping adjacent to equipment to allow service and maintenance. C. Connect plumbing specialties to piping specified in other
Divisions 21 and 22 Sections.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING SPECIALTIES 22 13 19 -9 D. Connect plumbing specialties and devices that require power according to Division 26 Sections. 3.3 LABELING AND IDENTIFYING A. Equipment Nameplates
and Signs: Install engraved plastic-laminate equipment nameplate or sign on or near each backflow preventer and trap seal primer system. 1. Text: Distinguish among multiple units, inform
operator of operational requirements, indicate safety and emergency precautions, and warn of hazards and improper operations, in addition to identifying unit. 2. Refer to Division 22
Section "Mechanical Identification" for nameplates and signs. 3.4 FIELD QUALITY CONTROL A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect
field-assembled trap seal primer systems and their installation, including piping and electrical connections. Report results in writing. 1. Leak Test: After installation, charge system
and test for leaks. Repair leaks and retest until no leaks exist. 2. Operational Test: After electrical circuitry has been energized, start units to confirm proper motor rotation and
unit operation. Remove malfunctioning units, replace with new units, and retest. 3. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.
3.5 PROTECTION A. Protect drains during remainder of construction period to avoid clogging with dirt and debris and to prevent damage from traffic and construction work. B. Place plugs
in ends of uncompleted piping at end of each day or when work stops. 3.6 DEMONSTRATION A. Engage a factory-authorized service representative to train Owner's maintenance personnel to
adjust, operate, and maintain trap seal primer systems. Refer to Division 1 Section "Demonstration and Training." END OF SECTION 22 13 19
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -1 SECTION 22 42 00 -PLUMBING FIXTURES PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes plumbing fixtures and related components. B. Related Sections include the
following: 1. Division 22 Section "Plumbing Specialties" for backflow preventers and specialty fixtures not in this Section. 1.3 DEFINITIONS A. Accessible Fixture: Plumbing fixture that
can be approached, entered, and used by people with disabilities. B. Fitting: Device that controls flow of water into or out of plumbing fixture. Fittings specified in this Section include
supplies and stops, faucets and spouts, shower heads and tub spouts, drains and tailpieces, and traps and waste pipes. Piping and general-duty valves are included where indicated. 1.4
SUBMITTALS A. Product Data: Include selected fixture and trim, fittings, accessories, appliances, appurtenances, equipment, and supports and indicate materials and finishes, dimensions,
construction details, and flow-control rates for each type of fixture indicated. B. Shop Drawings: Diagram power, signal, and control wiring and differentiate between manufacturer-installed
and field-installed wiring. C. Maintenance Data: For plumbing fixtures to include in maintenance manuals specified in Division 1.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -2 1.5 QUALITY ASSURANCE A. Source Limitations: Obtain plumbing fixtures, faucets, and other components of each category through one source from a single manufacturer.
1. Exception: If fixtures, faucets, or other components are not available from a single manufacturer, obtain similar products from other manufacturers specified for that category. B.
Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked
for intended use. C. Regulatory Requirements: Comply with requirements in ICC A117.1, "Accessible and Usable Buildings and Facilities"; Public Law 90-480, "Architectural
Barriers Act"; and Public Law 101-336, "Americans with Disabilities Act"; about plumbing fixtures for people with disabilities. D. Regulatory Requirements: Comply with requirements in
U.S. Architectural & Transportation Barriers Compliance Board's "Uniform Federal Accessibility Standards (UFAS), 1985-494-187" about plumbing fixtures for people with disabilities. E.
Regulatory Requirements: Comply with requirements in Public Law 102-486, "Energy Policy Act," about water flow and consumption rates for plumbing fixtures. F. NSF Standard: Comply with
NSF 61, "Drinking Water System Components--Health Effects," for fixture materials that will be in contact with potable water. G. Select combinations of fixtures and trim, faucets, fittings,
and other components that are compatible. 1.6 COORDINATION A. Coordinate roughing-in and final plumbing fixture locations, and verify that fixtures can be installed to comply with original
design and referenced standards. B. Coordinate required drain size for strainer, sizes, and quantities of faucet holes; all other sink accessories and hardware with soiled surface manufacturer.
PART 2 -PRODUCTS 2.1 ACCEPTABLE MANUFACTURERS A. Water Closets: American Standard, Crane, Kohler, Zurn.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -3 B. Lavatories: American Standard, Crane, Kohler, Zurn. C. Sinks: Acorn, American Standard, Crane, Eljer, Franke, Just, Kohler, Willoughby, Zurn. D. Shower
Enclosures: Aqua Bath, Acquarius, Fiat, Lasco. E. Bathtubs: American Standard, Kohler. F. Mop Basins: Creative Industries, Fiat, Mustee, Stern Williams, Zurn. G. Hose Boxes: Acorn, Guy
Gray, Metcraft, Willoughby Industries. H. Toilet Seats: Bemis, Beneke, Centoco, Church, Olsonite. I. Flush Valves: Sloan, Zurn. J. Carriers: Josam, Mifab, Smith, Wade, Watts, Zurn. K.
Faucets: American Standard, Chicago Faucet, Symmons, T&S Brass, Zurn. L. Electronic Faucets: Chicago Faucet, Sloan. M. Shower Valves: Symmons. N. Supply and Waste Fittings: Brass Craft,
Bridgeport Brass, Chicago Faucet, McGuire. O. All water faucets shall meet N.F.S. Standard 61, Section 9 for drinking water faucets and shall be certified by Underwriters Laboratory.
Product cartons shall feature the UL logo signifying certification to NSF 61, Section 9. The project shall be manufactured from brass construction brass components, which contact water
within the faucet, shall be from brass which contains no more than 3 percent lead by dry weight. 2.2 PLUMBING FIXTURES A. Water Closets: 1. WC-1: a. Fixture: American Standard Madera
3461.160 white vitreous china floor outlet siphon jet elongated bowl with top spud. b. Trim: Sloan 111 DFB flush valve with vacuum breaker, screwdriver stop, quiet equipment. c. Seat:
Centoco AMFR1500STSCCSS, white polypropylene open front integral check seat.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -4 2. WC-2: a. Fixture: American Standard Madera 3462.160 white vitreous china floor outlet siphon jet elongated bowl with bedpan lugs and top spud. b. Trim:
Sloan BPW 1150 – DFB flush valve with vacuum breaker, screwdriver stop, quiet equipment and diverter valve assembly with spray arm. c. Seat: Centoco AMFR1500STSCCSS, white polypropylene
open front integral check seat. B. Lavatories: 1. LAV-1: (No Alternate fixture and Faucet) a. Fixture: Kohler Escape K-19029-8 biscuit vitreous china self-rim counter insert basin. b.
Faucet: Hansgrohe 31073831 Metris C widespread faucet with 1.5 gpm aerator, less pop-up drain; polished nickel finish. c. Trim: McGuire 155 WC, open grid strainer with horizontal offset,
McGuire 8902 adjustable chrome plated semi-cast brass p-trap with cleanout and escutcheon. Brass Craft KTR17C, 1/2" X 3/8" angle ball stop with 3/8" flexible chrome plated copper riser.
2. LAV-2: (No Alternate Fixture and Faucet) a. Fixture: Kohler Maratea K-2831-1 self-rim counter basin. b. Faucet: Hansgrohe 31102001 electronic sensor supply fitting with 1.5 gpm aerator
and manual temperature control; chrome finish. c. Trim: McGuire 155WC, open grid strainer with horizontal offset, McGuire 8902 adjustable chrome plated semi-cast brass p-trap with cleanout
and escutcheon, Brass Craft KTR17C, 1/2" X 3/8" angle ball stop with 3/8" flexible chrome plated copper riser. d. Insulate trap, waste, and water supplies with white Truebro Handi Lav-Guard
Insulation. 3. LAV-3: a. Fixture: American Standard Lucerne 0356.015, 20" X 18" white vitreous china high back basin for concealed arm bracket, mount fixture at handicapped height. b.
Faucet: Chicago Faucet 786-GN2FCXKCP rigid/swing gooseneck supply fitting with 1.6 gpm integral flow control and laminar flow stream regulator and wrist blade handles. c. Trim: McGuire
155WC open grid strainer with horizontal offset, McGuire 8902 adjustable chrome plated cast brass p-trap with cleanout and escutcheon, Brass Craft KTR17C, 1/2" X 3/8" flexible chrome
plated copper risers. d. Carrier: J.R. Smith 700 KW-Z Series suitable for fixture. e. Insulate trap, waste, and HW supply with white Truebro Handi Lav-Guard Insulation Kit.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -5 4. LAV-4: a. Fixture: Provided by others. b. Faucet: Symmons S-20-0-BH-G, single lever supply fitting with 0.5 gpm aerator. c. Trim: McGuire 155WC, open
grid strainer with horizontal offset. McGuire 8902 adjustable chrome plated cast brass p-trap with cleanout and escutcheon, Brass Craft KTR17C, 1/2" X 3/8" angle ball stop with 3/8"
flexible chrome plated copper riser. d. Insulate trap, waste, and HW supply with white Truebro Handi Lav-Guard Insulation Kit. C. Sinks: 1. SK-1: a. Fixture: American Standard Surgeons
Scrub Sink 9047.044, 28" X 22" white vitreous china wall hung scrub sink. b. Faucet: Chicago Faucet 786-GN2FCXKCP rigid/swing gooseneck supply fitting with 1.6 gpm integral flow control
and laminar flow stream regulator, and wrist blade handles. c. Trim: American Standard 7716.020 grid drain, McGuire 8902 adjustable chrome plated cast brass p-trap with cleanout and
escutcheon, Brass Craft KTR17C, 1/2" X 3/8" angle ball stop with 3/8" flexible chrome plated copper risers. d. Carrier: J. R. Smith 870-KW-M31 exposed bracket support. 2. SK-2: a. Fixture:
Provided by others. b. Faucet: Chicago Faucet 786-GN2FCXKCP rigid/swing gooseneck supply fitting with 1.6 gpm integral flow control and laminar flow stream regulator, and wrist blade
handles. c. Trim: McGuire 155WC, open grid strainer with horizontal offset, McGuire 8902 adjustable chrome plated cast brass p-trap with cleanout and escutcheon, Brass Craft KTR17C,
1/2" X 3/8" angle ball stop with flexible chrome plated copper risers. 3. SK-3: (No Alternate Fixture or Faucet) a. Fixture: Linea Amano, ZEVIO LI-1800,18 gage stainless steel counter
insert with 10" deep bowl. b. Faucet: Hansgrohe 31078831 single level supply fitting with 1.5 gpm aerator; less pop-up drain; polished nickel finish. c. Trim: McGuire 8902 adjustable
chrome plated plated cast brass p-trap with cleanout and escutcheon, Brass Craft KTR17C, 1/2" X 3/8" angle ball stop with flexible chrome plated copper risers.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -6 4. SK-4: a. Fixture: Elkay LR-1918, 19” X 18” single compartment, 18 gage stainless steel self-rim counter insert three hole ledge sink with 7-1/2” deep
bowl. b. Faucet: Chicago Faucet 786-GN2FCXKCP rigid/swing gooseneck supply fitting with 1.6 gpm integral flow control and laminar flow stream regulator and wrist blade handles. c. Trim:
Elkay LK-99 stainless steel strainer with tailpiece, McGuire 8902 adjustable chrome plated cast brass p-trap with cleanout and escutcheon, Brass Craft KTR17C, 1/2” X 3/8” angle ball
stop with flexible chrome plated copper risers. 5. SK-5: a. Fixture: American Standard 7501.000, 22-7/8" X 20-3/4" single compartment, 18 gage stainless steel under-counter mount with
8-5/8" deep bowl. b. Faucet: American Standard 4205.100 single lever supply fitting with pull-out spray in polished chrome finish less escutcheon. c. Trim: Elkay LK-99 stainless steel
strainer with tailpiece, McGuire 8902 adjustable chrome plated cast brass p-trap with cleanout and escutcheon, Brass Craft KTR17C, 1/2" X 3/8" angle ball stop with flexible chrome plated
copper risers. D. Shower Units: 1. SU-1: (No Alternate Shower Valve) a. Fixture: Provided by others. b. Shower valve: Hansgrohe 04231830 thermostatic temperature control, volume control,
and diverter for two outlets, Hansgrohe 27874000, RainDance 36" wall bar with external vacuum breaker, and 25 gpm spray, Hansgrohe 28428831,12" diameter rain shower head. c. Drain: 2"
FD-1. 2. SU-2: a. Fixture: Aqua Bath C4136BF, 36" X 36" X 84" high one piece acrylic shower enclosure with vertical and horizontal stainless steel grab bars, shower curtain rod with
white shower curtain, 5/8" drywall flange less molded in seat and with phenolic fold down seat, 3/4" threshold, color as selected by Architect. b. Shower valve: Symmons 1-117-FS pressure
balanced mixing valve with integral stops, 4-458 lever diverter, 4-141 shower head with 2.5 gpm flow restrictor, 300 shower arm head fitting, H321 hand spray with elevated vacuum breaker
and adjustable bar. c. Drain: 2" chrome plated cast brass shower drain. d. Dome light: Cut hole in top for light fixture furnished and installed by Division 26.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -7 E. Bathtubs: 1. BT-1: a. Fixture: Bain Ultra AMMA 6036, white drop-in bath with color matching grab bars. b. Shower valve: Symmons 1-217-FS pressure balanced
mixing valve with integral stops,460 lever diverter, 060 tub spout, 4-141 shower head with 2.5 gpm flow restrictor, 300 shower arm heat fitting, H321 hand spray with elevated vacuum
breaker and adjusting bar. c. Drain: American Standard 1560.135 chrome plated brass drain fitting and tailpiece. F. Mop Basins: 1. MB-1: a. Fixture: Fiat MSB 2424, 24" X 24" molded stone
receptor with brass drain body, stainless steel dome strainer, lint basket, and vinyl bumper guard. b. Faucet: Chicago Faucet 897-CP supply fitting with integral stops, vacuum breaker,
bucket hook, wall brace, and hose end spout. c. Accessories: Fiat 832-AA, 30" long heavy-duty cloth reinforced rubber hose with stainless steel hose bracket, 889-CC stainless steel mop
hanger with three rubber tool grips, 833-AA silicone sealant, MSG 2424 wall guard. G. Hose Box: 1. RB-1: a. Fixture: Guy Gray SS1B2 stainless steel refrigerator connection box. PART
3 -EXECUTION 3.1 EXAMINATION A. Examine roughing-in for water soil and for waste piping systems and supports to verify actual locations and sizes of piping connections and that locations
and types of supports match those indicated, before plumbing fixture installation. Use manufacturer's roughing-in data if roughing-in data are not indicated. B. Examine walls, floors,
and cabinets for suitable conditions where fixtures are to be installed. C. Proceed with installation only after unsatisfactory conditions have been corrected.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -8 3.2 FIXTURE INSTALLATION A. Assemble fixtures, trim, fittings, and other components according to manufacturers' written instructions. B. For wall-hanging
fixtures, install off-floor supports affixed to building substrate. 1. Use carrier supports with waste fitting and seal for back-outlet fixtures. 2. Use carrier supports without waste
fitting for fixtures with tubular waste piping. 3. Use chair-type carrier supports with rectangular steel uprights for accessible fixtures. C. Install back-outlet, wall-hanging fixtures
onto waste fitting seals and attach to supports. D. Install floor-mounting fixtures on closet flanges or other attachments to piping or building substrate. E. Install wall-hanging fixtures
with tubular waste piping attached to supports. F. Install counter-mounting fixtures in and attached to casework. G. Install fixtures level and plumb according to manufacturers' written
instructions and roughing-in drawings. H. Install water-supply piping with stop on each supply to each fixture to be connected to water distribution piping. Attach supplies to supports
or substrate within pipe spaces behind fixtures. Install stops in locations where they can be easily reached for operation. 1. Exception: Use ball, gate, or globe valve if stops are
not specified with fixture. Refer to Division 22 Section "Valves" for general-duty valves. I. Install trap and tubular waste piping on drain outlet of each fixture to be directly connected
to sanitary drainage system. J. Install tubular waste piping on drain outlet of each fixture to be indirectly connected to drainage system. K. Install flushometer valves for accessible
water closets and urinals with handle mounted on wide side of compartment. Install other actuators in locations that are easy for people with disabilities to reach. L. Install toilet
toilet seats on water closets. M. Install faucet-spout fittings with specified flow rates and patterns in faucet spouts if faucets are not available with required rates and patterns.
Include adapters if required. N. Install water-supply, flow-control fittings with specified flow rates in fixture supplies at stop valves.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -9 O. Install faucet, flow-control fittings with specified flow rates and patterns in faucet spouts if faucets are not available with required rates and patterns.
Include adapters if required. P. Install shower, flow-control fittings with specified maximum flow rates in shower arms. Q. Install traps on fixture outlets. 1. Exception: Omit trap
on fixtures with integral traps. 2. Exception: Omit trap on indirect wastes, unless otherwise indicated. R. Install disposer in outlet of sinks indicated to have disposer. Install switch
where indicated or in wall adjacent to sink if location is not indicated. S. Install escutcheons at piping wall ceiling penetrations in exposed, finished locations and within cabinets
and millwork. Use deep-pattern escutcheons if required to conceal protruding fittings. fittings. Refer to Division 22 Section "Basic Mechanical Materials and Methods" for escutcheons.
T. Set bathtubs, shower receptors, and service basins in leveling bed of cement grout. Refer to Division 22 Section "Common Work Results for Plumbing" for grout. U. Seal joints between
fixtures and walls, floors, and counters using sanitary-type, one-part, mildew-resistant, silicone sealant. Match sealant color to fixture color. Refer to Division 7 Section "Joint Sealants"
for sealant and installation requirements. 3.3 ROUGH-IN A. Final connections to fixtures unless otherwise shown on the Drawings. HOT WATER COLD WATER WASTE VENT 1. Lavatory or sink 1/2"
1/2" 1-1/2" 1-1/2" 2. Water closet 1-1/2" 4" 2" 3. Shower unit 3/4" 3/4" 2" 1-1/2" 4. Mop basin 3/4" 3/4" 3" 1-1/2" 5. Clinic sink 3/4" 1-1/2" 4" 2" 3.4 MOUNTING A. Mount Heights: 1.
Water closet: 15" floor to rim. 2. Water closet (handicapped): 17" floor to trim, install flush valve handle on wide side of toilet per ADA requirements. 3. Lavatory: 31" floor to r
im. ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -10 4. Lavatory (handicapped): 34" floor to rim. 5. Surgeons sink: 36" floor to rim. 6. Clinic sink: 30" floor to rim. 7. Shower mixing valve: 40" floor to
centerline. 8. Shower head: 75" floor to centerline. 9. Mop basin: 36" floor to faucet; 18" floor to hose bracket; 54" floor to mop hanger. 3.5 CONNECTIONS A. Piping installation requirements
are specified in other Division 22 Sections. Drawings indicate general arrangement of piping, fittings, and specialties. B. Connect water supplies from water distribution piping to fixtures.
C. Connect drain piping from fixtures to drainage piping. D. Supply and Waste Connections to Plumbing Fixtures: Connect fixtures with water supplies, stops, risers, traps, and waste
piping. Use size fittings required to match fixtures. Connect to plumbing piping. E. Supply and Waste Connections to Fixtures and Equipment Specified in Other Sections: Connect fixtures
and equipment with water supplies, stops, risers, traps, and waste piping specified. Use size fittings required to match fixtures and equipment. Connect to plumbing piping. F. Ground
Equipment: 1. Tighten electrical connectors and terminals according to manufacturer's published torquetightening values. If manufacturer's torque values are not indicated, use those
specified in UL 486A and UL 486B. 3.6 FIELD QUALITY CONTROL A. Verify that installed fixtures are categories and types specified for locations where installed. B. Check that fixtures
are complete with trim, faucets, fittings, and other specified components. C. Inspect installed fixtures for damage. Replace damaged fixtures and components. D. Test installed fixtures
after water systems are pressurized for proper operation. Replace malfunctioning fixtures and components, then retest. Repeat procedure until units operate properly. E. Install fresh
batteries in sensor-operated mechanisms.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PLUMBING FIXTURES 22 42 00 -11 3.7 ADJUSTING A. Operate and adjust faucets and controls. Replace damaged and malfunctioning fixtures, fittings, and controls. B. Operate and adjust disposers
and controls. Replace damaged and malfunctioning units and controls. C. Adjust water pressure at faucets, shower valves, and flushometer valves to produce proper flow and stream. D.
Replace washers and seals of leaking and dripping faucets and stops. 3.8 CLEANING A. Clean fixtures, faucets, and other fittings with manufacturers' recommended cleaning methods and
materials. Do the following: 1. Remove faucet spouts and strainers, remove sediment and debris, and reinstall strainers and spouts. 2. Remove sediment and debris from drains. 3.9 PROTECTION
A. Provide protective covering for installed fixtures and fittings. B. Do not allow use of fixtures for temporary facilities unless approved in writing by Owner. END OF SECTION 22 42
00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -1 SECTION 22 63 13 -MEDICAL GAS PIPING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes medical gas piping and related specialties for the following medical gas
systems: 1. Medical gas pressure systems: a. Oxygen piping, designated "oxygen." b. Medical compressed-air piping, designated "medical air." 2. Medical gas suction systems: a. Medical-surgical
vacuum piping, designated "medical vacuum." 1.3 PERFORMANCE REQUIREMENTS A. General: Provide medical gas and vacuum piping systems that comply with the following NFPA 99 level categories:
1. Level 1: For entire facility with systems where failure of medical gas supply would be immediate and direct life-safety threat to patients. 1.4 SUBMITTALS A. Product Data: For the
following: 1. Medical gas tubes and fittings. 2. Medical gas valves and valve boxes. 3. Medical gas service connections. 4. Alarm system components. B. Shop Drawings: Diagram power,
signal, control, and alarm wiring.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -2 C. Coordination Drawings: For medical gas systems. Include relationship to other services that serve same work area. D. Brazing Certificates: As required
by ASME Boiler and Pressure Vessel Code, Section IX, or AWS B2.2. E. Piping Material Certification: Signed by Installer certifying that medical gas piping materials comply with NFPA
99 – 2005 requirements. F. Certificates of Shop Inspection and Data Report for Bulk Medical Gas Storage Tanks: As required by ASME Boiler and Pressure Vessel Code. G. Qualification Data:
For testing agency. H. Field quality-control test reports. I. Operation and Maintenance Data: For medical gas piping and specialties to include in emergency, operation, and maintenance
manuals. Include data for the following: 1. Medical gas service connections. 2. Alarm system. 1.5 QUALITY ASSURANCE A. Testing Agency Qualifications: An independent testing agency, with
the experience and capability to conduct the testing indicated, that is NITC 60/30 certified and that is listed below: 1. ARTEC. (317) 965-2165 2. DEW, LLC. (812) 933-9076 3. MGM, Inc.
(865) 414-0123 4. Gas Medix. (812) 477-2150 5. Northeast Medical Consultants. (888) 534-4295 B. Brazing: Qualify processes and operators according to ASME Boiler and Pressure Vessel
Code: Section IX, "Welding and Brazing Qualifications," or AWS B2.2, "Standard for Brazing Procedure and Performance Qualification." C. Electrical Components, Devices, and Accessories:
Listed and labeled as defined in NFPA 70, Article 100, by testing agency acceptable to authorities having jurisdiction, and marked for intended use. D. ASME Compliance: Fabricate and
label bulk medical gas storage tanks to comply with ASME Boiler and Pressure Vessel Code: Section VIII, "Pressure Vessels." E. Comply with NFPA 70, "National Electrical Code."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -3 F. Comply with NFPA 99 -2005, "Health Care Facilities," for materials and installation. G. Comply with ASSE 6010, "Professional Qualification Standard
for Medical Gas System Installers." PART 2 -PRODUCTS 2.1 MANUFACTURERS A. In other Part 2 articles where titles below introduce lists, the following requirements apply for product selection:
1. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified. 2.2 PIPES, TUBES, AND FITTINGS A. Hard Copper Tube: ASTM B 819, Type L, seamless,
drawn-temper, medical gas tube that has been factory cleaned, purged, and sealed for oxygen service. Include standard color marking "OXY," "MED," "OXY/MED," "OXY/ACR," or "ACR/MED" in
blue for Type L tube. 1. Fittings: Factory cleaned, purged, and bagged for oxygen service according to ASTM B 819. a. Copper Pressure Fittings: ASME B16.22, wrought-copper solder-joint
pressure type with socket depth cut down to ASME B16.50 standard or ASME B16.50, wrought copper with dimensions for brazed joints. b. Cast-Copper-Alloy Flanges: ASME B16.24, Class 300.
c. Copper Unions: ASME B16.22 or MSS SP-123. B. Hard Copper Tube: ASTM B88, Type L, seamless, drawn temper medical gas tube for medical vacuum piping. 1. Copper pressure fittings: ASME
B16.22, wrought copper solder joint pressure type with socket depth cut down to ASME B16.50 or ASME B16.50, wrought copper with dimensions for brazed joints. 2. Cast copper alloy flanges:
ASME B16.24, Class 300. 3. Copper unions: ASME B16.22 or MSS SP-123. 2.3 JOINING MATERIALS A. Refer to Division 22 Section "Common Work Results for Plumbing" for joining materials not
in this Section.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -4 B. Brazing Filler Metals: AWS A5.8, BCuP series alloys. Flux is prohibited unless used with bronze fittings. C. Threaded-Joint Tape: PTFE. D. Gasket Material:
ASME B16.21, nonmetallic, flat, asbestos free, and suitable for oxygen service. 2.4 MEDICAL GAS VALVES A. Valves, General: Factory cleaned for oxygen service and bagged. B. Copper-Alloy
Ball Valves: MSS SP-110, 3-piece-body, full-port ball valve rated for 300-psig minimum working pressure; with chrome-plated brass ball, PTFE or TFE seats, blowout-proof stem, threaded
or solder-joint ends, and locking-type handle designed for quarter turn between opened and closed positions. 1. Manufacturers: a. Allied Healthcare Products, Inc.; Chemetron Div. b.
Amico Corporation. c. Beacon Medaes. d. Ohio Medical. C. Bronze Check Valves: Straight-through-pattern, spring-loaded ball check valve; designed for 300-psig minimum working pressure.
D. Zone Valve Boxes: Formed or extruded aluminum for recessed mounting, with holes for medical gas piping and anchors. Include boxes for single-or multiple-valve installation with pressure
gage and in sizes to permit manual operation of valves. 1. Interior Finish: Factory-applied white enamel. 2. Cover Plate: Stainless steel with NAAMM AMP 503, No. 4 finish with frangible
or removable windows. 3. Valve-Box Windows: Clear or tinted transparent plastic with labeling that includes rooms served, according to NFPA 99 -2005. E. Pressure Regulators: Bronze body
and trim; spring-loaded, diaphragm-operated, relieving type; manual pressure-setting adjustment; rated for 250-psig minimum inlet pressure; and capable of controlling delivered air pressure
within 0.5 psig for each 10-psig inlet pressure. 2.5 MEDICAL GAS SERVICE CONNECTIONS A. Connection Devices: For specific medical gas pressure and vacuum services listed. Include roughing-in
assemblies, finishing assemblies, and cover plates. Individual cover plates are not
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -5 required if service connection is in multiple unit or assembly with cover plate. Furnish recessed-type units made for concealed piping, unless otherwise
indicated. 1. Outlet Configuration: Pin Index (Beacon Medaes). 2. Manufacturers: a. Allied Healthcare Products, Inc.; Chemetron Div. b. Amico Corporation. c. Beacon Medaes Diamond Care
d. Ohio Medical. 3. Roughing-in Assembly: a. Steel outlet box for recessed mounting and concealed piping. b. Brass-body outlet block with secondary check valve that will prevent gas
flow when primary valve is removed. c. Double seals that will prevent gas leakage. d. ASTM B 819, Type K, copper inlet or outlet tube brazed to valve with gas-service marking and tube-end
dust cap. 4. Finishing Assembly: a. Brass housing with primary check valve. b. Double seals that will prevent gas leakage. c. Cover plate with gas-service label. 5. Quick-Connect Service
Connections: With keyed indexing to prevent interchange between services, constructed to permit one-handed connection and removal of equipment, and with positive-locking ring that retains
equipment stem in valve during use. Include the following: a. Oxygen Service Connections: Keyed oxygen outlet. b. Medical Air Service Connections: Keyed medical air outlet. c. Medical
Vacuum Service Connections: Keyed medical vacuum suction inlet. d. Medical Vacuum Slide Brackets: With pattern matching medical vacuum service connection. 6. Wall Outlet Service Connection
Cover Plates: One piece, stainless steel, with NAAMM AMP 503, No. 4 finish and permanent, color-coded, medical gas identifying label matching corresponding outlets. 7. Vacuum Bottle-Slide
Brackets: Bottle-slide and
mounting assembly matching pattern of vacuum inlet. Include one slide bracket for each wall-mounting vacuum inlet unless no slide bracket requirement is indicated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -6 2.6 MEDICAL GAS ALARM SYSTEM A. Manufacturers: 1. Allied Healthcare Products, Inc.; Chemetron Div. 2. Amico Corporation. 3. Beacon Medaes. 4. Ohio Medical.
B. Medical Gas Alarm System, General: Compatible alarm panels, remote sensing devices, and other related components as required by NFPA 99 -2005 for Level 1 medical gas alarm systems.
Refer to Division 22 Section "Medical Air and Vacuum Equipment" for air compressors and vacuum pumps. Power wiring is specified in Division 26 Sections. C. Components: Designed for continuous
service and to operate on power supplied from 120-V ac power source to alarm panels and with connections for 24-or 12-V ac low-voltage wiring to remote sensing devices. Include step-down
transformers if required. D. Pressure and Vacuum Switches or Pressure Transducer Sensors: Continuous line monitoring with electrical connections for alarm system. 1. Low-Pressure Switches:
0-to 100-psig operating range. 2. High-Pressure Switches: Up to 250-psig operating range. 3. Vacuum Switches: 0-to 30-in. Hg range. E. Medical Gas Alarm Panels: Factory wired with audible
and color-coded visible signals to indicate specified functions. 1. Mounting: Recessed installation. 2. Enclosures: Fabricated from minimum 0.047-inch-thick steel or minimum 0.05-inchthick
aluminum, with knockouts for electrical and piping connections. 3. Area Alarm Panels: Separate trouble alarm signals; pressure and vacuum gages; and indicators for oxygen, medical air,
and medical vacuum. Alarms signal when the following conditions exist: a. Oxygen: Pressure drops below 40 psig or rises above 60 psig. b. Medical Air: Pressure drops below 40 psig or
rises above 60 psig. c. Medical Vacuum: Vacuum drops below 12 in. Hg. 2.7 MEDICAL GAS CYLINDER STORAGE RACKS A. Wall Storage Racks for Medical Gas Cylinders: Fabricate racks with chain
restraints for upright gas cylinders as indicated or provide equivalent manufactured wall racks. B. Freestanding Storage Racks for Medical Gas Cylinders: Fabricate racks for gas cylinders
as indicated or provide equivalent manufactured storage racks.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -7 2.8 TEST GAS A. Description: Oil-free dry nitrogen complying with CGA P-9, for purging and testing of piping. 2.9 IDENTIFICATION A. Refer to Division 22
Section "Identification for Plumbing Piping and Equipment" for identification of piping, valves, gages, alarms, and specialties. PART 3 -EXECUTION 3.1 PREPARATION A. Interruption of
Existing Medical Gas Service: Do not interrupt medical gas service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging
to provide temporary medical gas service according to requirements indicated: 1. Notify Architect and Owner not less than two days in advance of proposed interruption of medical gas
service. 2. Do not proceed with interruption of medical gas service without Architect's and Owner's written permission. 3.2 PIPING APPLICATIONS A. Specialty and Equipment Flanged Connections:
Use cast-copper-alloy companion flange with gasket and brazed joint for connection to copper tube. 3.3 MEDICAL GAS VALVE APPLICATIONS A. Drawings indicate medical gas valve types to
be used. If specific valve types are not indicated, the following requirements apply: 1. Medical Gas Pressure Piping: a. Shutoff Valves NPS 4 and Smaller: Copper-alloy ball valve. b.
Check Valves NPS 3 and Smaller: Bronze. 2. Medical Vacuum Piping: a. Shutoff Valves NPS 4 and Smaller: Copper-alloy ball valve. b. Check Valves NPS 3 and Smaller: Bronze. 3. Zone Valves:
With copper-tube extensions and gage.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -8 3.4 PIPING INSTALLATION A. Refer to Division 22 Section "Common Work Results for Plumbing" for basic piping installation. B. Install supports and anchors
according to Division 22 Section "Hangers and Supports for Plumbing Piping and Equipment" with spacing according to NFPA 99 -2005. C. Install thermometers and pressure gages according
to Division 22 Section "Meters and Gages for Plumbing Piping." D. Purge medical gas piping, using oil-free dry nitrogen, after installing piping but before connecting to service connections,
alarms, and gages. E. All piping installations shall conform to NFPA Bulletin 99 -2005, CGA, and/or any other Federal, State or Local Codes and Ordinances covering these installations.
F. All piping, fittings, valves, and other devices shall be received on the job cleaned, sealed, and marked for oxygen service. On-site cleaning is prohibited. G. Tools used in cutting
or reaming shall be kept free from oil or grease. H. After installation of piping, but before installation of the outlet valves, the line shall be blown clean by means of nitrogen. I.
Apply pipe labeling during installation process and not after installation is complete. J. Joints shall be made using a brazing compound containing silver alloys having a melting point
of 1000F or higher. Piping shall be purged with nitrogen during brazing to prevent the formation of copper oxide particles. The outside of the pipe and fittings shall be cleaned by
washing with hot water after assembly. K. Screw joints used in shutoff valves shall be installed by tinning the male thread with soft solder. Litharge and glycerin, or an approved oxygen
luting or sealing compound, are acceptable. L. Medical gas piping shall not be installed in kitchens, electrical switchgear rooms, elevator shafts, and areas with open flames. 3.5 MEDICAL
GAS VALVE INSTALLATION A. Refer to Division 22 Section "Common Work Results for Plumbing" for basic piping and valve installation. B. Install valves in locations required by and according
to NFPA 99 -2005. C. Install shutoff valve at each connection to and from medical gas specialties.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -9 D. Install check valves to maintain correct direction of fluid flow to and from medical gas specialties and equipment. E. Install valve boxes recessed
in wall and anchored to substrate. Single boxes may be used for multiple valves that serve same area or function. F. Install zone valves and gages in valve boxes. Rotate valves to angle
that prevents closure of cover when valve is in closed position. 1. Pressure System Valves: Install pressure gage downstream from valve. 2. Suction System Valves: Install vacuum gage
upstream from valve. G. Install pressure safety and vacuum relief valves where recommended by specialty manufacturers. H. Install pressure regulators in piping to reduce pressure. 3.6
JOINT CONSTRUCTION A. Refer to Division 22 Section "Common Work Results for Plumbing" for basic piping joint construction. B. Brazed Joints: Use silver-or copper-phosphorus-composition
filler metal and comply with CDA's "Copper Tube Handbook," Section VII, "Brazed Joints"; or AWS D10.13, "Recommended Practices for the Brazing of Copper Pipe and Tubing for Medical Gas
Systems." 3.7 MEDICAL GAS SERVICE CONNECTION INSTALLATION A. Install medical gas service connections, of types indicated, in walls. Attach roughing-in assembly to substrate; attach finishing
assembly to roughing-in assembly. B. Install medical gas service connections, of types indicated, in medical gas service units. 3.8 MEDICAL GAS ALARM SYSTEM INSTALLATION A. Install medical
gas alarm system components in locations required by and according to NFPA 99 -2005 and manufacturer's written instructions. B. Install medical gas alarm panels where indicated. C. All
wiring and metal conduit required to interconnect and operate the complete medical gas alarm system specified herein shall be included in the mechanical contract.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -10 D. Control wiring shall be installed in accordance with an electrical wiring diagram prepared and furnished by the supplier of the medical gas outlets
who shall be solely responsible for its accuracy and completeness. Submit wiring diagrams to Engineer for approval before proceeding with installation. E. Primary 110 volt power to the
respective alarm panels shall be the responsibility of the Electrical Contractor. F. All medical gas alarm wiring shall be installed in EMT conduit. 3.9 CONNECTIONS A. Drawings indicate
general arrangement of piping, fittings, and specialties. B. Install piping adjacent to specialties and equipment to allow service and maintenance. C. Connect medical gas piping to specialties,
equipment, and accessories. 1. Connection NPS 2 and Smaller: With shutoff valve and copper union. 2. Connection NPS 2-1/2 and Larger: With shutoff valve and cast-copper-alloy flange.
D. Ground specialties according to Division 26 Section "Grounding and Bonding." E. Connect wiring according to Division 26 Section "Conductors and Cables." F. Tighten electrical connectors
and terminals according to manufacturer's published torquetightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A and UL 486B. 3.10 LABELING
AND IDENTIFICATION A. Install identifying labels and devices for medical gas piping systems according to NFPA 99-2005. Refer to Division 22 Section "Mechanical Identification" for labeling
and identification materials. B. Captions and Color-Coding: Use the following or similar medical gas captions and colorcoding for medical gas piping products where required by NFPA 99-2005:
1. Oxygen: White letters on green background or green letters on white background. 2. Medical Air: Black letters on yellow background. 3. Medical Vacuum: Black letters letters on white
background. C. Label medical gas systems operating at other-than-standard pressure with system operating pressure.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -11 D. Apply pipe labeling during installation process and not after installation is complete. E. Mounting Heights: 1. Zone valves shall be mounted at 60”
above finish floor to the center of the valve. 2. Service fittings shall be mounted at 54” above finish floor to the center of fitting unless otherwise shown on the Drawings. 3. Alarm
panels shall be mounted at 54” above finish floor to the center of the panel. 3.11 FIELD QUALITY CONTROL A. Testing Agency: Engage a qualified independent testing and inspecting agency
to perform the following field tests and inspections and prepare test reports: B. Perform the following field tests and inspections and prepare test reports: 1. Provide oil-free dry
nitrogen, medical gases, materials, and equipment required for testing. 2. Level 1 Pressure Medical Gas Testing: Use oil-free dry nitrogen, unless otherwise indicated, and perform procedures
and tests as indicated in NFPA 99-2005 performance and testing paragraphs for piped gas systems. Include the following: a. Performance Testing: 1) Blow Down: Clear piping before connecting
service connections or outlets. 2) Initial Pressure Tests: Subject each piping section to test pressure of 1.5 times system working pressure, but not less than 150 psig, before attaching
system components, after installing station outlets with test caps (if supplied) in place, and before concealing piping system. Maintain test until joints are examined for leaks by means
of soapy water. Repair leaks with new materials and retest systems. 3) Cross-Connection Tests: Determine that no cross connections of piping systems exist. Disconnect all systems except
system to be checked. Pressurize system to 50 psig. Verify that gas flow from service connections and outlets is only from system being checked. Repeat for each system. Verify correct
labeling. 4) Purge Tests: Perform heavy intermittent purging of piping and full-flow purging of service connections. 5) Standing-Pressure Tests: Install assembled system components after
testing individual systems as specified above. Subject systems to 24-hour standingpressure test at 20 percent above normal line pressure. Verify that pressure differences comply with
required calibration. Repair leaks with new materials and retest systems.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -12 b. System Verification: 1) Cross-Connection Tests: Repeat cross-connection test above or perform alternate tests with each gas at different pressure.
2) Flow Tests: Perform flow test at each outlet. 3) Valve Tests: Verify proper valve operation. 4) Alarm Tests: Operate systems and verify proper warning indication of each medical gas
piping system function. 5) Piping Purity Tests: Test for dew point and hydrocarbons as compared to source gas. 6) Final Tie-End Tests: Verify that above tests have been successfully
performed. 7) Operational Pressure Tests: Use designated system gases and test for pressure and flow. 8) Medical Gas Concentration Tests: Test each gas for required concentration. 9)
Labeling: Verify correct labeling. 3. Level 1 Vacuum System Testing: Use oil-free dry nitrogen, unless otherwise indicated, and perform procedures and tests as indicated in NFPA 99-2002
performance and testing paragraphs for piped vacuum systems. Include the following: a. Blow Down: Clear piping before connecting service connections or inlets. b. Initial Pressure Tests:
Subject each piping section to test pressure not less than 150 psig before attaching system components, after installing station outlets with test caps (if supplied) in place, and before
concealing piping system. Maintain test until joints are examined for leaks by means of soapy water. Repair leaks with new materials and retest systems. c. Initial Cross-Connection Tests:
Determine that no cross connections of piping systems exist. Disconnect all systems except system to be checked. Pressurize system to 50 psig. Verify that gas flow from service connections
and outlets is only from system being checked. Repeat for each system. Verify correct labeling. d. Standing-Pressure Tests: Install assembled system components after testing individual
systems as specified above. Subject systems to 24-hour standingpressure test at not less than 60 psig. e. Final Cross-Connection Tests: Repeat cross-connection test above or perform
alternate tests with each system at different pressure. f. Vacuum Tests: Verify functional operation of components. g. Valve Tests: Verify proper valve operation. h. Alarm Tests: Operate
systems and verify proper warning indication of each medical gas piping system function. i. Labeling: Verify correct labeling. 4. Test and adjust controls and safeties.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MEDICAL GAS PIPING 22 63 13 -13 C. Testing Certification: Certify that specified tests, inspections, and procedures have been performed and certify report results. Include the following:
1. Inspections performed. 2. Procedures, materials, and gases used. 3. Test methods used. 4. Results of tests. 3.12 DEMONSTRATION A. Engage a factory-authorized service representative
to train Owner's maintenance personnel to adjust, operate, and maintain medical gas alarm system. Refer to Division 1 Section "Demonstration and Training." END OF SECTION 22 63 13
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -1 SECTION 23 05 00 -COMMON WORK RESULTS FOR HVAC PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including
General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Piping materials and installation
instructions common to most piping systems. 2. Dielectric fittings. 3. Mechanical sleeve seals. 4. Sleeves. 5. Escutcheons. 6. Grout. 7. HVAC demolition. 8. Equipment installation requirements
common to equipment sections. 9. Painting and finishing. 10. Concrete bases. 11. Supports and anchorages. 12. Roof curbs. 13. Equipment supports. 1.3 DEFINITIONS A. Finished Spaces:
Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and duct chases, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawlspaces,
and tunnels. B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms. C. Exposed, Exterior Installations:
Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations. D. Concealed, Interior Installations: Concealed from view
and protected from physical contact by building occupants. Examples include above solid ceilings and within chases.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -2 E. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants but
subject to outdoor ambient temperatures. Examples include installations within unheated shelters. F. The following are industry abbreviations for plastic materials: 1. CPVC: Chlorinated
polyvinyl chloride plastic. 2. PE: Polyethylene plastic. 3. PVC: Polyvinyl chloride plastic. G. The following are industry abbreviations for rubber materials: 1. EPDM: Ethylene-propylene-diene
terpolymer rubber. 2. NBR: Acrylonitrile-butadiene rubber. 1.4 SUBMITTALS A. Product Data: For the following: 1. Dielectric fittings. 2. Mechanical sleeve seals. 3. Escutcheons. 4. Roof
curbs. 1.5 QUALITY ASSURANCE A. Steel Support Welding: Qualify processes and operators according to AWS D1.1, "Structural Welding Code--Steel." B. Steel Pipe Welding: Qualify processes
and operators according to ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications." 1. Comply with provisions in ASME B31 Series, "Code for Pressure Piping."
2. Certify that each welder has passed AWS qualification tests for welding processes involved and that certification is current. C. Electrical Characteristics for HVAC Equipment: Equipment
of higher electrical characteristics may be furnished provided such proposed equipment is approved in writing and connecting electrical services, circuit breakers, and conduit sizes
are appropriately modified. If minimum energy ratings or efficiencies are specified, equipment shall comply with requirements. D. Roofing Standards: Comply with the following: 1. SMACNA’s
“Architectural Sheet Metal Manual” details for fabrication including flanges and cap flashing to coordinate with type of roofing indicated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -3 2. NRCA’s “Roofing and Waterproof Manual” details for installing units. 1.6 DELIVERY, STORAGE, AND HANDLING A. Deliver pipes and tubes with factory-applied
end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture. B. Store plastic pipes protected
from direct sunlight. Support to prevent sagging and bending. C. Deliver, store and install materials and equipment (including supports and hangers) such that they are maintaining “as-new”
condition (e.g., no rust) upon installation and up through the date of Substantial Completion. Account for environmental conditions of the construction site and schedule work accordingly.
1.7 COORDINATION A. Arrange for pipe spaces, chases, slots, and openings openings in building structure during progress of construction, to allow for HVAC installations. B. Coordinate
installation of required supporting devices and set sleeves in poured-in-place concrete and other structural components as they are constructed. C. Coordinate requirements for access
panels and doors for HVAC items requiring access that are concealed behind finished surfaces. Access panels and doors are specified in Division 8. D. Existing Utilities: Do not interrupt
utilities serving facilities occupied or partially occupied by the Owner or others unless specifically allowed under the following conditions and then only after arranging to provide
temporary utility services according to requirements indicated. 1. Notify Owner at least seven days in advance of proposed utility interruptions. Identify extent and duration of utility
interruptions. 2. Indicate method of proposed utility interruptions in detail. 3. Do not proceed with proposed utility interruptions without Owner’s permission. E. Coordinate installation
of above ceiling components and devices such that maintenance access is achieved at the completion of the project when all ceiling mounted components are installed. Coordinate with all
trades. Ultimate responsibility for any rework required to achieve maintenance access is the responsibility of the Contractor responsible for coordination as noted in Division 1 Sections.
The required maintenance access is defined here for this contract: 1. A person with a 24” arm length can stand on a folding ladder which rests on the finished floor and which does not
extend through the ceiling grid. All lights and diffusers remain in the grid when defining maintenance access. Ceiling tiles with sprinkler heads, smoke
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -4 detectors, fire alarm devices and other system devices remain in the grid when defining maintenance access. 2. While standing on a step of this
ladder which is rated for standing upon and while not leaning against the ceiling grid, this person can touch the following items with both hands at the same time: a. Terminal unit/terminal
box damper actuators. b. Terminal unit/terminal box reheat valve actuators. c. Terminal unit/terminal box airflow controller. d. Terminal unit/terminal box transformers, EP switches,
temperature sensor, and all other control components. e. Terminal box discharge low pressure volume dampers on diffuser runouts. f. Terminal unit/terminal box piped accessories – strainer,
PT ports, air vents, drains, shutoff valves, unions and calibrated balance valves. valves. g. Piped hydronic system shutoff valves, calibrated balance valves, control valves, vents,
and drains. h. Steam system traps, control valves, humidifier components and humidifier control components. i. Fire damper and fire/smoke damper duct access doors. j. Fire damper and
fire/smoke damper fusible links. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. In other Part 2 articles where subparagraph titles below introduce lists, the following requirements apply for
product selection: 1. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified. 2.2 PIPE, TUBE, AND FITTINGS A. Refer to individual Division
23 piping Sections for pipe, tube, and fitting materials and joining methods. B. Pipe Threads: ASME B1.20.1 for factory-threaded pipe and pipe fittings. C. Hex bushings, face bushings,
and plugs are not acceptable in any Division 23 piping system. 2.3 JOINING MATERIALS A. Refer to individual Division 23 piping Sections for special joining materials not listed below.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -5 B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system contents. 1. Steam service: ASME B16.20, spiral
wound gasket with stainless steel metal winding strip, flat, asbestos-free graphite filler, 1/8-inch (3.2-mm) maximum thickness unless thickness or specific material is indicated. Suitable
for pressure class of service and a minimum operating temperature of 600 deg F. Similar to Flexitallic Style CG. 2. All other services: Thermoseal C-4401, 1/16” thick. 3. Do not apply
compounds, adhesives, or anti-stick lubricants to gasket surface. C. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated. D. Plastic, Pipe-Flange Gasket, Bolts,
and Nuts: Type and material recommended by piping system manufacturer, unless otherwise indicated. E. Solder Filler Metals: ASTM B 32, lead-free alloys. Include water-flushable flux
according to ASTM B 813. F. Brazing Filler Metals: AWS A5.8, BCuP Series, copper-phosphorus alloys for general-duty brazing, unless otherwise indicated; and AWS A5.8, BAg1, silver alloy
for refrigerant piping, unless otherwise indicated. G. Welding Filler Metals: Comply with AWS D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel
pipe being welded. H. Solvent Cements for Joining Plastic Piping: 1. CPVC Piping: ASTM F 493. 2. PVC Piping: ASTM D 2564. Include primer according to ASTM F 656. I. Fiberglass Pipe Adhesive:
As furnished or recommended by pipe manufacturer. 2.4 DIELECTRIC FITTINGS A. Description: Combination fitting of copper alloy and ferrous materials with threaded, solderjoint, plain,
or weld-neck end connections that match piping system materials. B. Insulating Material: Suitable for system fluid, pressure, and temperature. C. Dielectric Unions: Factory-fabricated,
union assembly, for 250-psig (1725-kPa) minimum working pressure at 225 deg F. Minimum 400 volts dielectric resistance, insulated against galvanic corrosion, threaded ends, O-ring. 1.
Manufacturers: a. Capitol Manufacturing Co.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -6 b. Central Plastics Company. c. Eclipse, Inc. d. Epco Sales, Inc. e. Hart Industries, International, Inc. f. Watts Industries, Inc.; Water Products
Div. g. Zurn Industries, Inc.; Wilkins Div. D. Dielectric Flanges: Factory-fabricated, companion-flange assembly, for 150-or 300-psig (1035-or 2070-kPa) minimum working pressure as required
to suit system pressures. 1. Manufacturers: a. Capitol Manufacturing Co. b. Central Plastics Company. c. Epco Sales, Inc. d. Watts Industries, Inc.; Water Products Div. E. Dielectric-Flange
Kits: Companion-flange assembly for field assembly. Include flanges, fullface-or ring-type neoprene or phenolic gasket, phenolic or polyethylene bolt sleeves, phenolic washers, and steel
backing washers. 1. Manufacturers: a. Advance Products & Systems, Inc. b. b. Calpico, Inc. c. Central Plastics Company. d. Pipeline Seal and Insulator, Inc. 2. Separate companion flanges
and steel bolts and nuts shall have 150-or 300-psig (1035-or 2070-kPa) minimum working pressure where required to suit system pressures. F. Dielectric Couplings: Galvanized-steel coupling
with inert and non-corrosive, thermoplastic lining; threaded ends; and 300-psig (2070-kPa) minimum working pressure at 225
deg F (107 deg C). 1. Manufacturers: a. Calpico, Inc. b. Lochinvar Corp. G. Dielectric Nipples: Electroplated steel nipple with inert and non-corrosive, thermoplastic lining; plain,
threaded, or grooved ends; and 300-psig (2070-kPa) minimum working pressure at 225 deg F (107 deg C). 1. Manufacturers: a. Perfection Corp., Clearflow Dielectric Fittings.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -7 b. Precision Plumbing Products, Inc. c. Sioux Chief Manufacturing Co., Inc. d. Victaulic Co. of America. 2.5 MECHANICAL SLEEVE SEALS A. Description:
Modular sealing element unit, designed for field assembly, to fill annular space between pipe and sleeve. 1. Manufacturers: a. Advance Products & Systems, Inc. b. Calpico, Inc. c. Metraflex
Co. d. Pipeline Seal and Insulator, Inc. 2. Sealing Elements: EPDM interlocking links shaped to fit surface of pipe. Include type and number required for pipe material and size of pipe.
3. Pressure Plates: Stainless steel. Include two for each sealing element. 4. Connecting Bolts and Nuts: Stainless steel of length required to secure pressure plates to sealing elements.
Include one for each sealing element. 2.6 SLEEVES A. Galvanized-Steel Sheet: Sheet: 0.0239-inch (0.6-mm) minimum thickness; round tube closed with welded longitudinal joint. B. Steel
Pipe: ASTM A 53, Type E, Grade B, Schedule 40 up to 10” NPS, standard weight for 12” NPS and larger, galvanized, plain ends, fabricated with 2” integral seal welded waterstop. Touch
up cut ends of galvanized pipe sleeves with zinc-rich coating prior to installation. C. Cast Iron: Cast or fabricated "wall pipe" equivalent to ductile-iron pressure pipe, with plain
ends and integral waterstop, unless otherwise indicated. 1. Manufacturers: a. Calpico, Inc. D. Stack Sleeve Fittings: Manufactured, cast-iron sleeve with integral clamping flange. Include
clamping ring and bolts and nuts for membrane flashing. 1. Underdeck Clamp: Clamping ring with set screws. E. Stainless Steel Sheet: Fabricated 304L stainless steel, 0.078” minimum thickness,
round tube closed with welded longitudinal joint, fabricated with 2” integral seal welded waterstop.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -8 2.7 ESCUTCHEONS A. Description: Manufactured wall and ceiling escutcheons and floor plates, with an ID to closely fit around pipe, tube, and
insulation of insulated piping and an OD that completely covers opening. B. One-Piece, Cast-Brass Type: With set screw. 1. Finish: Polished chrome-plated. C. Split-Casting, Cast-Brass
Type: With concealed hinge and set screw. 1. Finish: Polished chrome-plated. D. One-Piece, Stamped-Steel Type: With set screw or spring clips and chrome-plated finish. 2.8 GROUT A. Description:
ASTM C 1107, Grade B, non-shrink and nonmetallic, dry hydraulic-cement grout. 1. Characteristics: Post-hardening, volume-adjusting, non-staining, non-corrosive, nongaseous, and recommended
for interior and exterior applications. 2. Design Mix: 5000-psi (34.5-MPa), 28-day compressive strength. 3. Packaging: Premixed and factory packaged. 2.9 ROOF CURBS A. General: If not
specified in individual Division 23 specification sections, provide roof curbs capable of supporting superimposed live and dead loads, including equipment loads and other construction
to be supported on roof curbs. Coordinate dimensions with rough-in information or shop drawings of equipment to be supported. B. Manufacturers: Subject to compliance with requirements,
provide products by the manufacturers specified: 1. Custom Curb, Inc. 2. Pate Co. (The). 3. ThyCurb, Inc.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -9 C. Fabrication: Unless otherwise indicated or required for strength, fabricate units from minimum 0.0747 inch (1.9 mm) thick, structural quality,
hot dip galvanized or aluminum zinc alloy coated steel sheet, factory primed and prepared for painting with welded or sealed mechanical corner joints. 1. Provide fire retardant treated
wood nailers at tops of curbs and formed flanges at perimeter bottom for mounting to roof. 2. On ribbed or fluted metal roofs, form flange at perimeter bottom to conform to roof profile.
3. Provide manufacturer’s standard rigid or semi-rigid insulation and metal liners. 4. Provide formed cants and base profile coordinated with roof insulation thickness. 5. Fabricate
units to minimum height of 16 inches (400 mm) unless otherwise indicated. 6. Sloping roofs: Where slop of roof deck exceeds 1/4 inch per foot (1:48) fabricate curb units with water diverter
or cricket and with height tapered to match slope to level tops of units. 7. Provide curbs suitable for equipment dead weight, wind loads, seismic lifting, and anchoring forces as required.
8. Provide anchoring instructions. 2.10 EQUIPMENT SUPPORTS A. General: If not specified in individual Division 23 specification sections, provide equipment supports capable of supporting
superimposed live and dead loads, including equipment loads and other construction to be supported. Coordinate dimensions with rough-in information or shop drawings of equipment to be
supported. B. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified. 1. Custom Curb, Inc. 2. Pate Co. (The). 3. ThyCurb, Inc. C. Fabrication:
Unless otherwise indicated or required for strength, fabricate units from minimum 0.0747 inch (1.9 mm) thick, structural quality, hot dip galvanized or aluminum zinc alloy coated steel
sheet; factory primed and prepared for painting with welded or sealed mechanical corner joints. 1. Provide fire retardant treated wood nailers at tops of curbs and formed flanged at
perimeter bottom for mounting to roof. 2. On ribbed or fluted metal roofs, form flange at perimeter bottom to conform to roof profile. 3. Fabricate units to minimum height of 12 inches
(300 mm), unless otherwise indicated. 4. Sloping roofs: Where slope of roof deck exceeds 1/4 inch per foot (1:48), fabricate support units with water diverters and height tapered to
match slope to level tops of units.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -10 5. Provide supports suitable for equipment dead weight, wind loads, seismic lifting, and anchoring forces as required. 6. Provide anchoring
instructions. PART 3 -EXECUTION 3.1 HVAC DEMOLITION A. Refer to Division 1 Section "Cutting and Patching" and Division 2 Section "Selective Structure Demolition" for general demolition
requirements and procedures. B. Disconnect, demolish, and remove HVAC systems, equipment, and components indicated to be removed. No equipment or components shall be abandoned in place
unless specifically noted on the drawings. 1. Piping to be Removed: Remove portion of piping indicated to be removed and cap remaining piping with same or compatible piping material.
2. Piping to be Abandoned in Place: Drain piping and cap piping with same or compatible piping piping material. 3. Ducts to be Removed: Remove portion of ducts indicated to be removed
and cap remaining ducts with same or compatible ductwork material. Seal remaining ductwork to seal Class C. Duct tape is not permitted. 4. Ducts to be Abandoned in Place: Cap ducts with
same or compatible ductwork material. 5. Equipment to Be Removed: Disconnect and remove services and remove equipment. Cap piping and ductwork as required. 6. Equipment to be Removed
and Reinstalled: Disconnect and cap services and remove, clean, store equipment and protect in a safe location during construction to prevent damage; when appropriate, reinstall, reconnect,
and make equipment operational. 7. Equipment Piping and Ductwork to be Removed and Salvaged: Disconnect and cap services and remove equipment. Owner shall be given first right of refusal
to all items removed from the Owner’s facility or property. Deliver salvaged items to Owner at location requested by Owner. C. If pipe, insulation, or equipment is damaged in appearance
or is unserviceable due to demolition work, remove damaged or unserviceable portions and replace with new products of equal capacity and quality. 3.2 PIPING SYSTEMS -COMMON REQUIREMENTS
A. Install piping according to the following requirements and Division 23 Sections specifying piping systems. B. Drawing plans, schematics, and diagrams indicate general location and
arrangement of piping systems. Indicated locations and arrangements were used to size pipe and calculate friction
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -11 loss, expansion, pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved on Coordination
Drawings. C. Install piping in concealed locations, unless otherwise indicated and except in equipment rooms and service areas. D. Install piping indicated to be exposed and piping in
equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise. E. Install piping above accessible
ceilings to allow sufficient space for ceiling panel removal. F. Install piping to permit valve servicing. G. Install piping at indicated slopes. H. Install piping free of sags and bends.
I. Install fittings for changes in direction and branch connections. Utilize tee fittings for branch connections that have all three connection sizes of NPS 1-1/2” and larger. It is
acceptable to utilize threadolet fittings with dielectric nipples on carbon steel piping of NPS 2-1/2” and larger when the branch connection size is NPS 1” or less and a bronze body
ball valve is installed on the other end of the dielectric nipple. J. Install piping and ductwork to allow application of insulation. K. Select system components with pressure rating
equal to or greater than system operating pressure. L. Install escutcheons for penetrations of walls, barriers, ceilings, and floors in exposed areas. In Dietary, Kitchen, Cafeteria,
Sterile Processing, Sterilizer, Sub-Sterile, Animal Holding, Operating Rooms, Procedure Rooms and other sterile areas do not install escutcheons, but seal pipe penetrations airtight
with clear food grade silicone. M. New concrete floors, walls, and roof penetrations are required to have sleeves cast-in-place (no core drilling is allowed unless specifically noted
on the drawings). 1. Core drilling in buildings that are occupied up to two floors above the construction area or two floors below the construction area or are occupied on the same floor
within 100 linear feet shall be accomplished with wet core drilling machines with slurry extraction to reduce noise. N. Install sleeves for pipes passing through concrete and masonry
walls, gypsum-board partitions, and concrete floor and roof slabs. 1. Cut sleeves to length for mounting flush with both surfaces.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -12 a. Exception: Extend top of sleeves installed in all floors (including mechanical equipment areas) and penthouses 2 inches (50 mm) above finished
floor level. Waterstop shall be entirely contained within concrete with approximately 1-1/2” of concrete cover. Extend cast-iron sleeve fittings below floor slab as required to secure
clamping ring if ring is specified. 2. Install sleeves in new walls and slabs as new walls and slabs are constructed. 3. Install sleeves that are large enough to provide 1/4-inch (6.4-mm)
annular clear space between sleeve and pipe or pipe insulation. Use the following sleeve materials: a. Steel pipe sleeves, cast iron pipe sleeves or stainless steel sheet sleeves for
all pipes penetrating other than gypsum board partitions or walls. b. Galvanized Steel Steel Sheet Sleeves: For pipes and larger, penetrating gypsum-board partitions or walls. 4. Except
for underground wall penetrations, seal annular space between sleeve and pipe or pipe insulation, using joint sealants appropriate for size, depth, and location of joint. Refer to Division
7 Section "Joint Sealants" for materials and installation. O. Aboveground, Exterior-Wall Pipe Penetrations: Seal penetrations using sleeves and mechanical sleeve seals. Select sleeve
size to allow for 1-inch (25-mm) annular clear space between pipe and sleeve for installing mechanical sleeve seals. 1. Install steel pipe for sleeves smaller than 6 inches (150 mm)
in diameter. 2. Install cast-iron "wall pipes" for sleeves 6 inches (150 mm) and larger in diameter. 3. Mechanical Sleeve Seal Installation: Select type and number of sealing elements
required for pipe material and size. Position pipe in center of sleeve. Assemble mechanical sleeve seals and install in annular space between pipe and sleeve. Tighten bolts against pressure
plates that cause sealing elements to expand and make watertight seal. P. Underground, Exterior-Wall Pipe Penetrations: Install cast-iron "wall pipes" for sleeves. Seal pipe penetrations
using mechanical sleeve seals. Select sleeve size to allow for 1-inch (25-mm) annular clear space between pipe and sleeve for installing mechanical sleeve seals. 1. Mechanical Sleeve
Seal Installation: Select type and number of sealing elements required for pipe material and size. Position pipe in center of sleeve. Assemble mechanical sleeve seals and install in
annular space between pipe and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make watertight seal. Q. Fire-Barrier Penetrations: Maintain indicated
fire rating of walls, partitions, barriers, ceilings, and floors at pipe penetrations. Seal pipe penetrations with firestop materials. Refer to Division 7 Section "Firestopping" for
materials. R. Verify final equipment locations for roughing-in.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -13 S. Refer to equipment specifications in other Sections of these Specifications for roughing-in requirements. T. Install piping, hangers and
equipment so that they do not interfere with fully opening the access panels on any part of the structure, any contractor installed access panels, nor access panels on any equipment
(either contract provided or Owner provided or Owner installed equipment). 3.3 PIPING JOINT CONSTRUCTION A. Join pipe and fittings according to the following requirements and Division
23 Sections specifying piping systems. B. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe. C. Remove scale, slag, dirt, and debris from inside and outside
of pipe and fittings before assembly. D. Soldered Joints: Apply ASTM B 813, water-flushable flux, unless otherwise indicated, to tube end. Construct joints according to ASTM B 828 or
CDA's "Copper Tube Handbook," using lead-free solder alloy complying with ASTM B 32. E. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," "Pipe and Tube" Chapter,
using brazing filler metal complying with AWS A5.8. F. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies.
Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows: 1. Apply appropriate tape or thread compound to external pipe threads unless dry
seal threading is specified. 2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do not use pipe sections that have cracked or open welds.
G. Welded Joints: Construct joints according to AWS D10.12, using qualified processes and welding operators according to Part 1 "Quality Assurance" Article. H. Flanged Joints: Select
appropriate gasket material, size, type, and thickness for service application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads. I. Plastic Piping Solvent-Cement
Joints: Clean and dry joining surfaces. Join pipe and fittings according to the following: 1. Comply with ASTM F 402 for safe-handling practice of cleaners, primers, and solvent cements.
2. CPVC Piping: Join according to ASTM D 2846/D 2846M Appendix.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -14 3. PVC Pressure Piping: Join schedule number ASTM D 1785, PVC pipe and PVC socket fittings according to ASTM D 2672. Join other-than-schedule-number
PVC pipe and socket fittings according to ASTM D 2855. 4. PVC Non-pressure Piping: Join according to ASTM D 2855. J. Plastic Pressure Piping Gasketed Joints: Join according to ASTM D
3139. K. Plastic Non-pressure Piping Gasketed Joints: Join according to ASTM D 3212. L. PE Piping Heat-Fusion Joints: Clean and dry joining surfaces by wiping with clean cloth or paper
towels. Join according to ASTM D 2657. 1. Plain-End Pipe and Fittings: Use butt fusion. 2. Plain-End Pipe and Socket Fittings: Use socket fusion. M. Fiberglass Bonded Joints: Prepare
pipe ends and fittings, apply adhesive, and join according to pipe manufacturer's written instructions. 3.4 PIPING CONNECTIONS A. Make connections according to the following, unless
otherwise indicated: 1. Install unions, in piping NPS 2 (DN 50) and smaller, adjacent to each valve and at final connection to each piece of equipment. 2. Install flanges, in piping
NPS 2-1/2 (DN 65) and larger, adjacent to flanged valves and at final connection to each piece of equipment. 3. Dry Piping Systems: Install dielectric unions and flanges to connect piping
materials of dissimilar metals. 4. Wet Piping Systems: Install dielectric coupling and nipple fittings to connect piping materials of dissimilar metals. Do not utilize dielectric unions
with O-rings on wet piping systems. 3.5 EQUIPMENT INSTALLATION -COMMON REQUIREMENTS A. Install equipment to allow maximum possible headroom unless specific mounting heights are not indicated.
Provide a minimum of 7’-2” headroom under all exposed equipment. B. Install equipment level and plumb, parallel and perpendicular to other building systems and components in exposed
interior spaces, unless otherwise indicated. C. Install HVAC equipment to facilitate service, maintenance, and repair or replacement of components. Connect equipment for ease of disconnecting,
with minimum interference to other installations. Extend grease fittings to accessible locations. D. Install equipment to allow right of way for piping installed at required slope.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -15 E. Comply with the equipment manufacturer’s written installation instructions. 3.6 PAINTING A. Painting of HVAC systems, equipment, and components
is specified in Division 9 Sections. B. Damage and Touchup: Repair marred and damaged factory-painted finishes with materials and procedures to match original factory finish. 3.7 CONCRETE
BASES A. Concrete Bases: Anchor equipment to concrete base according to equipment manufacturer's written instructions and according to seismic codes at Project. 1. Construct concrete
bases of dimensions indicated, not less than 3.5 inches thick and not less than 4 inches (100 mm) larger in both directions than supported unit. 2. Install dowel rods to connect concrete
base to concrete floor. Unless otherwise indicated, install dowel rods on 18-inch ((450-mm) centers around the full perimeter of the base. 3. Install epoxy-coated anchor bolts for supported
equipment that extend through concrete base, and anchor into structural concrete floor. 4. Place and secure anchorage devices. Use supported equipment manufacturer's setting drawings,
templates, diagrams, instructions, and directions furnished with items to be embedded. 5. Install anchor bolts to elevations required for proper attachment to supported equipment. 6.
Install anchor bolts according to anchor-bolt manufacturer's written instructions. 7. Use 3000-psi (20.7-MPa), 28-day compressive-strength concrete and reinforcement as specified in
Division 3 Section. 3.8 ERECTION OF METAL SUPPORTS AND ANCHORAGES A. Refer to Division 5 Section "Metal Fabrications" for structural steel. B. Cut, fit, and place miscellaneous metal
supports accurately in location, alignment, and elevation to support and anchor HVAC materials and equipment. C. Field Welding: Comply with AWS D1.1. 3.9 ERECTION OF WOOD SUPPORTS AND
AND ANCHORAGES A. Cut, fit, and place wood grounds, nailers, blocking, and anchorages to support, and anchor HVAC materials and equipment.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -16 B. Select fastener sizes that will not penetrate members if opposite side will be exposed to view or will receive finish materials. Tighten
connections between members. Install fasteners without splitting wood members. C. Attach to substrates as required to support applied loads. 3.10 GROUTING A. Mix and install grout for
HVAC equipment base bearing surfaces, pump and other equipment base plates, and anchors. B. Clean surfaces that will come into contact with grout. C. Provide forms as required for placement
of grout. D. Avoid air entrapment during placement of grout. E. Place grout, completely filling equipment bases. Obtain pump manufacturer’s written installation instructions. F. Place
grout on concrete bases and provide smooth bearing surface for equipment. G. Place grout around anchors. H. Cure placed grout. 3.11 ROOF CURBS AND EQUIPMENT AND PIPE SUPPORTS A. General:
Comply with manufacturer’s written instructions. Coordinate installation of roof accessories with installation of roof deck, roof insulation, flashing, roofing membranes, penetrations,
equipment, and other construction involving roof accessories to ensure that each element of the work performs properly and that combined elements are waterproof and weathertight. Anchor
roof accessories securely to support structural substrates so they are capable of withstanding lateral and thermal stresses, and inward and outward loading pressures. B. Install roof
accessory items according to construction details of NRCA’s "Roofing and Waterproofing Manual" unless otherwise indicated. C. Separation: Separate metal from incompatible metal or corrosive
substrates, including wood, by coating concealed surfaces or at locations of contact, with bituminous coating or providing other permanent separation. D. Flange Seals: Unless otherwise
indicated, set flanges of accessory units with a thick bed of roofing cement to form a seal.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR HVAC 23 05 00 -17 E. Cap Flashing: Where required as component of accessory, install cap flashing to provide waterproof overlap with roofing or roof flashing
(as counterflashing). Seal overlap with thick bead of mastic sealant. END OF SECTION 23 05 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT 23 05 13 -1 SECTION 23 05 13 – COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general
provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes basic requirements
for factory-installed motors. 1.3 DEFINITIONS A. Factory-Installed Motor: A motor installed by motorized-equipment manufacturer as a component of equipment. 1.4 SUBMITTALS A. Product
Data for Installed Motors: For each type and size of motor, provide: 1. Nameplate data and ratings (hp; full load amps; rpm; voltage; power factor; temperature rise class; insulation
class; service factor; enclosure type, frame material of construction). 2. Shipping weights. 3. Four pole, nominal 1,800 rpm, full load, nominal efficiency. 1.5 QUALITY ASSURANCE A.
Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked
for intended use. B. Comply with NFPA 70.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT 23 05 13 -2 1.6 COORDINATION A. Coordinate features of motors, installed units, and accessory devices. Provide motors that are: 1. Compatible
with the following: a. Magnetic controllers. b. Multi-speed controllers. c. Reduced-voltage controllers. d. Variable frequency controllers: 1) Cable distance. 2. Matched to torque, speed,
and horsepower requirements of the load. 3. Matched to ratings and characteristics of supply circuit and required control sequence. 4. Matched to ambient and environmental conditions
at installation location. B. Motors shall not operate in service factor range. C. Coordinate motor support with requirements for driven load; access for maintenance and motor replacement;
installation of accessories, belts, belt guards; and adjustment of sliding rails for belt tensioning. D. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into
bases. Concrete, reinforcement, and formwork requirements are specified in Division 3 Section. PART 2 -PRODUCTS 2.1 MOTOR REQUIREMENTS A. Motor requirements apply to all motors except
when starter requirements, performance, or characteristics for a motor are specified in another section or on the drawings. 2.2 MOTOR CHARACTERISTICS A. Motors 1 HP and Larger: Three
phase. B. Motors Smaller Than 1 HP: Single phase. C. Frequency Rating: 60 Hz. D. Voltage Rating: Matched to voltage of supply circuit. E. Service Factor: 1.35 for 1/3 HP and below; 1.25
above 1/3 HP to 3/4 HP; 1.15 above 3/4 HP.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT 23 05 13 -3 F. Duty: Continuous duty at ambient temperature of 105 deg F (40 deg C) and at altitude of 3300 feet (1005 m) above sea level.
G. Capacity and Torque Characteristics: NEMA Standards MG1; Sufficient to start, accelerate, and operate connected loads at designated speeds, at installed altitude and environment,
with indicated operating sequence, and without exceeding nameplate ratings or considering service factor. H. Enclosure: Open drip-proof unless noted otherwise in specific equipment specification
or on the drawings. Motor enclosures in hazardous areas shall be of the proper UL Class and group for the atmosphere in which they are located. 2.3 POLYPHASE MOTORS A. Description: NEMA
MG 1, Design B, medium induction motor. B. Efficiency: Four-pole, full load, minimum nominal efficiency and minimum power factor at nominal 1,800 rpm and nominal 460 VAC: HP MINIMUM
EFFICIENCY PERCENT MINIMUM POWER FACTOR 7.5 91.0 75 10 91.5 80 15 92.5 80 20 92.5 80 C. Service Factor: Minimum 1.15. D. Stator: Copper windings, unless otherwise indicated. 1. Multi-speed
motors shall have separate winding for each speed. E. Rotor: Squirrel cage, unless otherwise indicated. F. Bearings: Double-shielded, prelubricated ball bearings less than 40 HP, regreasable
40 HP and larger, suitable for radial and thrust loading. G. Temperature Rise: Class B at 1.0 service factor, unless noted otherwise. H. Insulation: Class F, unless otherwise indicated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT 23 05 13 -4 I. Code Letter Designation: NEMA code letters for AC motors normally started on full voltage. NEMA starting code for Code G for
motors 15 Hp and larger. J. Enclosure Material: Cast iron for motors 10 HP and larger; rolled steel for motors smaller than 10 HP. 2.4 POLYPHASE MOTORS WITH ADDITIONAL REQUIREMENTS A.
Motors Used with Reduced-Inrush Controllers: Match wiring connection requirements for controller with required motor leads. Provide terminals and/or leads in motor terminal box, suited
to control method. B. Motors Used with Variable Frequency Controllers: Ratings, characteristics, and features coordinated with and approved by controller manufacturer. Designed and labeled
for inverter duty per NEMA MG-1, Part 31 in its entirety and suitable for use throughout 20% to 100% motor base speed range in a variable torque application without overheating. 1. Designed
with critical vibration frequencies outside operating range of controller output. 2. Temperature Rise: Matched to rating for Class B insulation. 3. Insulation: IEEE Standard 117. Designed
to resist transient spikes, high frequencies, and short time pulses. 4. Thermal Protection: Comply with NEMA MG 1 requirements for thermally protected motors. C. Severe-Duty Motors:
Totally enclosed, with 1.15 minimum service factor, greased bearings, integral condensate drains, and capped relief vents. Windings insulated with non-hygroscopic material. Comply with
IEEE 841. 1. Finish: Chemical-resistant paint over corrosion-resistant primer. 2.5 SINGLE-PHASE MOTORS A. Type: One of the following, to suit starting torque and requirements of specific
motor application: 1. Permanent-split capacitor. 2. Split-phase start, capacitor run. 3. Capacitor start, capacitor run. B. Shaded-Pole or Permanent Split Capacitor Motors: For motors
1/20 hp and smaller only. C. Thermal Protection: Internal protection to automatically open power supply circuit to motor when winding temperature exceeds a safe value calibrated to temperature
rating of motor insulation. Thermal-protection device shall automatically reset when motor temperature returns to normal range.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT 23 05 13 -5 D. Bearings: Ball type for belt-connected motors and other motors with high radial forces on motor shaft; sealed, prelubricated-sleeve
type for other single-phase motors. E. Source Quality Control: Perform the following tests on each motor according to NEMA Standards MG 1: 1. Measure winding resistance. 2. Read no-load
current and speed at rated voltage and frequency. 3. Measure locked rotor current at rated frequency. PART 3 -EXECUTION 3.1 EXAMINATION A. Examine areas to receive motors for compliance
with requirements, installation tolerances, and other conditions affecting performance. B. Examine roughing-in of conduit systems to verify actual locations of conduit connections before
motor installation. C. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 MOTOR INSTALLATION A. Anchor each motor assembly to base, adjustable rails,
or other support, arranged and sized according to manufacturer's written instructions. Attach by bolting. Level and align with load transfer link. B. Comply with mounting and anchoring
requirements specified in Division 23 Section "HVAC Vibration and Seismic Controls." 3.3 FIELD QUALITY CONTROL A. Prepare for acceptance tests as follows: 1. Run each motor with its
controller. Demonstrate correct rotation, alignment, and speed at motor design load. 2. Test interlocks and control features for proper operation. 3. Verify that current in each phase
is within nameplate rating. B. Testing: Perform the following field quality-control testing: 1. Perform each electrical test and visual and mechanical inspection stated in NETA ATS,
Section 7.15.1. Certify compliance with test parameters.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT 23 05 13 -6 2. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units
and retest. C. Manufacturer's Field Service: Engage a factory-authorized service representative to perform the following: 1. Inspect field-assembled components, equipment installation,
and piping and electrical connections for compliance with requirements. 2. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. 3. Verify
bearing lubrication. 4. Verify proper motor rotation. 5. Test Reports: Prepare a written report to record the following: a. Test procedures used. b. Test results that comply with requirements.
c. Test results that do not comply with requirements and corrective action taken to achieve compliance. 3.4 ADJUSTING A. Align motors, bases, shafts, pulleys and belts. Tension belts
according to manufacturer's written instructions. 3.5 CLEANING A. After completing equipment installation, inspect unit components. Remove paint splatters and other spots, dirt, and
debris. Repair damaged finish to match original finish. B. Clean motors and nameplates, on completion of installation, according to manufacturer's written instructions. END OF SECTION
23 05 13
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL DUTY VALVES FOR HVAC PIPING 23 05 23 -1 SECTION 23 05 23 – GENERAL DUTY VALVES FOR HVAC PIPING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the
Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes: 1. Ball valves. 2. Butterfly valves.
3. Check valves. 4. Gate valves. 5. Globe valves. B. Related Sections include the following: 1. Division 23 Section "Identification for HVAC Piping and Equipment" for valve tags and
charts. 2. Division 23 Section "Environmental Control System" for control valves and actuators. 3. Division 23 piping sections for specialty valves applicable to those sections only.
1.3 SUBMITTALS A. Product Data: For each type of valve indicated. Include body, seating and trim materials; valve design; pressure and temperature classifications; end connections; arrangement;
dimensions; and required clearances. Include list indicating valve type and its piping system application. Include rated capacities; shipping, installed and operating weights; furnished
specialties; and accessories. 1.4 QUALITY ASSURANCE A. ASME Compliant: 1. ASME B31.9 for building services piping valves. 2. ASME B31.3 for power piping valves.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL DUTY VALVES FOR HVAC PIPING 23 05 23 -2 B. ASME Compliance for Ferrous Valves: ASME B16.10 and ASME B16.34 for dimension and design criteria. C. Source Limitations: Obtain each
type of valve from a single source from a single manufacturer. 1.5 DELIVERY, STORAGE AND HANDLING A. Prepare valves for shipping as follows: 1. Protect internal parts against rust and
corrosion. 2. Protect threads, flange faces, grooves and weld ends. 3. Set gate and globe valves closed to prevent rattling. 4. Set ball and plug valves open to minimize exposure of
functional surfaces. 5. Set butterfly valves closed or slightly open. 6. Block check valves in either closed or open position. B. Use the following precautions during storage: 1. Maintain
valve end protection. 2. Store valves indoors and maintain at higher than ambient dew-point temperature. If outdoor storage is necessary, store valves at least 4” off the ground in watertight
enclosures. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. In other Part 2 articles where subparagraph titles below introduce lists, the following requirements apply for product selection: 1.
Manufactures: Subject to compliance with requirements, provide products by the manufacturers specified. B. Acceptable Manufacturers: 1. Gate valves: Crane, Hammond, Milwaukee, Nibco,
Stockham, Vogt. 2. Globe valves: Crane, Hammond, Milwaukee, Nibco, Stockham. 3. Check valves: Crane, Hammond, Metraflex, Milwaukee, Nibco, Stockham. 4. Ball valves: Apollo, Hammond,
Metraflex, Nibco Stockham, Watts. 5. Butterfly valves: Apollo, Centerline, Demco, Hammond, Keystone, Nibco, Watts. 6. Strainers: Armstrong, Yarway, Flexonics, Keckley, Metraflex, Mueller,
Watts, Hayward. 7. Drain valves: Apollo, Nibco, Watts. 8. Non-slam silent check valves: Metraflex, Mueller.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL DUTY VALVES FOR HVAC PIPING 23 05 23 -3 2.2 GENERAL REQUIREMENTS FOR VALVES A. Refer to Valve Schedule Articles for application of valves. B. Bronze Valves: NPS 2 and smaller
with threaded ends, unless otherwise indicated. C. Ferrous Valves: NPS 2-1/2 and larger with flanged ends, unless otherwise indicated. D. Valve Pressure and Temperature Ratings: Not
less than indicated and as required for system pressures and temperatures. E. Valve Sizes: Same as upstream pipe, unless otherwise indicated. F. Extended Valve Stems: 2-inch extensions
on all valves. G. Valve Flanges: ASME B16.1 for cast-iron valves, ASME B16.5 for steel valves and ASME B16.24 for bronze valves. H. Valve Threads: According to ASME B1.20.1. I. Valve
Bypass and Drain Connections: MSS SP-45. 2.3 VALVE SCHEDULE A. Gate Valves – 2" and Smaller: 1. 125 psig steam, 200 psig CWP rating, MSS SP-80, threaded end, bronze body, union bonnet,
rising stem, solid wedge. B. Gate Valves – 2-1/2" and Larger: 1. Class 125, 125 psig steam rating, flanged end, outside screw and yoke, cast iron body, bolted bonnet, solid wedge, bronze
mounted. C. Globe Valve – 2" and Smaller: 1. 125 psig steam, 200 psig CWP rating, MSS SP-80, threaded end, bronze body, union bonnet, integral seat, renewable TFE disc. D. Globe Valve
– 2-1/2" and Larger: 1. Class 125, 200 psig CWP rating, 125 psig steam rating, MSS SP-85, flanged end, cast iron body, bolted bonnet, renewable cast bronze seat and disc, bronze mounted.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL DUTY VALVES FOR HVAC PIPING 23 05 23 -4 E. Check Valves – 2” and Smaller: 1. Class 125, 200 psig CWP rating, MSS SP-80, threaded end, bronze body, horizontal swing, bronze regrinding
type disc, bronze renewable disc seat. F. Check Valves – 2-1/2" and Larger: 1. Class 125, 200 psig CWP rating, MSS SP-71, flanged end, cast iron body, bolted bonnet, horizontal swing,
renewable cast bronze seat and disc. G. Non-Slam Silent Check Valve – 1" and Larger: 1. Class 125, 200 psig CWP rating, wafer end, cast iron body, bronze plug, stainless steel stem,
bronze seats, stainless steel spring. H. Ball Valves – 2" and Smaller: 1. 600 psig CWP rating, MSS SP-110, blowout proof stem, 2 piece bronze body, standard port, chrome plated brass
ball, Teflon seats with bronze trim, threaded end, zinc plated steel handle with plastic coating. Provide extended handle that allows operation of valve without breaking the vapor barrier
or otherwise disturbing insulation. I. Butterfly Valve – 12" and Smaller: 1. Class 125, 200 psig CWP rating, MSS SP-67, ductile iron body, lug style with MSS SP-69 face-to-face dimensions,
extended neck, stainless steel or aluminum bronze disc, 416 stainless steel shaft, reinforced resilient EPDM seat and EPDM o-rings, shaft seal, worm gear operator with handwheel size
6” and larger, locking handle size 5” and smaller: J. Drain Valves: 1. Class 125, bronze body, screw-in bonnet, rising stem, composition disc, 3/4" hose outlet. PART 3 -EXECUTION 3.1
EXAMINATION A. Examine piping system for compliance with requirements for installation tolerances and other conditions affecting performance. 1. Proceed with installation only after
unsatisfactory conditions have been corrected. B. Examine valve interior for cleanliness, freedom from foreign matter and corrosion. Remove special packing materials, such as blocks,
used used to prevent disc movement during shipping and handling.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL DUTY VALVES FOR HVAC PIPING 23 05 23 -5 C. Operate valves in positions from fully open to fully closed. Examine guides and seats made accessible by such operations. D. Examine
threads on valve and mating pipe for form and cleanliness. E. Examine mating flange faces for conditions that might cause leakage. Check bolting for proper size, length, and material.
Verify that gasket is of proper size, that its material composition is suitable for service and that it is free from defects and damage. F. Do not attempt to repair defective valves,
replace with new valves. 3.2 VALVE APPLICATIONS A. Gate valves shall be installed for shutoff duty in steam supply and condensate return piping systems. B. Globe valves shall be installed
for throttling service. C. Ball valves shall be installed in 2" and smaller pipes for shutoff duty in all piping except steam supply and condensate return. D. Butterfly valves shall
be installed in 2-1/2" and larger pipes for shutoff duty in all piping systems except steam supply and condensate return. E. Valves shall be installed on the inlet and outlet of each
coil, at each piece of equipment, on each piping line coming out of a shaft to serve a floor, on each side of control valves and elsewhere as shown on the Contract Documents. F. Safety
valves shall have a relieving capacity of not less than the MBH output of the equipment. Relief shall be piped full size, without shutoff devices in line, to the nearest floor drain
unless shown piped to the exterior on the Contract Documents. 3.3 VALVE INSTALLATION A. Piping installation requirements are specified in other Division 23 sections. Drawings indicate
general arrangement of piping, fittings and specialties. B. Install valves with unions or flanges at each piece of equipment arranged to allow service, maintenance and equipment removal
without system shutdown. C. Locate valves for easy access and provide separate support where necessary. D. Install valves in horizontal piping with stem at or above 45 degrees from vertical.
E. Install valves in position to allow full stem movement.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GENERAL DUTY VALVES FOR HVAC PIPING 23 05 23 -6 F. Install check valves for proper direction of flow and as follows: 1. Swing Check Valves: In horizontal position with hinge pin level.
2. Dual-Plate Check Valves: In horizontal or vertical position, between flanges. 3. Lift Check Valves: With stem upright and plumb. 3.4 ADJUSTING A. Adjust or replace valve packing after
piping systems have been tested and put into service, but before insulating or final adjusting and balancing. Replace valves if any leaking occurs. END OF SECTION 23 05 23
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -1 SECTION 23 05 29 -HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings
and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes
the following hangers and supports for HVAC system piping and equipment: 1. Steel pipe hangers and supports. 2. Trapeze pipe hangers. 3. Metal framing systems. 4. Thermal-hanger shield
inserts. 5. Fastener systems. 6. Pipe stands. 7. Equipment supports. B. Related Sections include the following: 1. Division 5 Section "Metal Fabrications" for structural-steel shapes
and plates for trapeze hangers for pipe and equipment supports. 2. Division 21 Section "Water-Water-Based Fire-Suppression Systems" for pipe hangers for fireprotection piping. 3. Division
23 Section "Vibration and Seismic Controls for HVAC Piping and Equipment" for vibration isolation devices. 4. Division 23 Section "Metal Ducts" for duct hangers and supports. 1.3 DEFINITIONS
A. MSS: Manufacturers Standardization Society for The Valve and Fittings Industry Inc. B. Terminology: As defined in MSS SP-90, "Guidelines on Terminology for Pipe Hangers and Supports."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -2 1.4 PERFORMANCE REQUIREMENTS A. Design supports for multiple pipes, including pipe stands, capable of supporting combined
weight of supported systems, system contents, and test water. B. Design equipment supports capable of supporting combined operating weight of supported equipment and connected systems
and components. C. Design seismic-restraint hangers and supports for piping and equipment. 1.5 SUBMITTALS A. Product Data: For the following: 1. Steel pipe hangers and supports. 2. Thermal-hanger
shield inserts. 3. Powder-actuated fastener systems. B. Shop Drawings: Show fabrication and installation details and include calculations for the following: 1. Trapeze pipe hangers.
Include Product Data for components. 2. Metal framing systems. Include Product Data for components. 3. Pipe stands. Include Product Data for components. 4. Equipment supports. 1.6 QUALITY
ASSURANCE A. Welding: Qualify procedures and personnel according to the following as applicable: 1. AWS D1.1, "Structural Welding Code--Steel." 2. AWS D1.2, "Structural Welding Code--Aluminum."
3. AWS D1.3, "Structural Welding Code--Sheet Steel." 4. AWS D1.4, "Structural Welding Code--Reinforcing Steel." 5. ASME Boiler and Pressure Vessel Code: Section IX. PART 2 -PRODUCTS
2.1 MANUFACTURERS A. In other Part 2 articles where titles below introduce lists, the following requirements apply to product selection:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -3 1. Manufacturers: Subject to compliance with requirements, provide products by one of the manufacturers specified. 2.2
STEEL PIPE HANGERS AND SUPPORTS A. Description: MSS SP-58, Types 1 through 58, factory-fabricated components. Refer to Part 3 "Hanger and Support Applications" Article for where to use
specific hanger and support types. B. Manufacturers: 1. B-Line Systems, Inc.; a division of Cooper Industries. 2. Carpenter & Paterson, Inc. 3. ERICO/Michigan Hanger Co. 4. Anvil International,
Inc. 5. National Pipe Hanger Corporation. 6. PHD Manufacturing, Inc. 7. PHS Industries, Inc. 8. Piping Technology & Products, Inc. 9. Tolco Inc. C. Galvanized, Metallic Coatings: Pregalvanized
or hot dipped. D. Nonmetallic Coatings: Plastic coating, jacket, or liner. 2.3 TRAPEZE PIPE HANGERS A. Description: MSS SP-69, Type 59, shop-or field-fabricated pipe-support assembly
made from structural-steel shapes with MSS SP-58 hanger rods, nuts, saddles, and U-bolts. 2.4 METAL FRAMING SYSTEMS A. Description: MFMA-3, shop-or field-fabricated pipe-support assembly
made of steel channels and other components. B. Manufacturers: 1. B-Line Systems, Inc.; a division of Cooper Industries. 2. ERICO/Michigan Hanger Co.; ERISTRUT Div. 3. Power-Strut Div.;
Tyco International, Ltd. 4. Thomas & Betts Corporation. 5. Tolco Inc. 6. Unistrut Corp.; Tyco International, Ltd. C. Coatings: Manufacturer's standard finish, unless bare metal surfaces
are indicated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -4 D. Nonmetallic Coatings: Plastic coating, jacket, or liner. 2.5 THERMAL-HANGER SHIELD INSERTS A. Description: 100-psig-(690-kPa-)
minimum, compressive-strength insulation insert encased in sheet metal shield. B. Manufacturers: 1. Carpenter & Paterson, Inc. 2. ERICO/Michigan Hanger Co. 3. PHS Industries, Inc. 4.
Pipe Shields, Inc. 5. Rilco Manufacturing Company, Inc. 6. Value Engineered Products, Inc. C. Insulation-Insert Material for Cold Piping: Water-repellent treated, ASTM C 552, Type II
cellular glass with vapor barrier. D. Insulation-Insert Material for Hot Piping: Water-repellent treated, ASTM C 533, Type I calcium silicate or ASTM C 552, Type II cellular glass. E.
For Trapeze and Clamped Systems: Insert and shield shall cover entire circumference of of pipe. F. For Clevis or Band Hangers: Insert and shield shall cover lower 180 degrees of pipe.
G. Insert Length: Extend 2 inches (50 mm) beyond sheet metal shield for piping operating below ambient air temperature. 2.6 FASTENER SYSTEMS A. Mechanical-Expansion Anchors: Insert-wedge-type
zinc-coated or stainless steel, for use in hardened portland cement concrete with pull-out, tension, and shear capacities appropriate for supported loads and building materials where
used. 1. Manufacturers: a. B-Line Systems, Inc.; a division of Cooper Industries. b. Empire Industries, Inc. c. Hilti, Inc. d. ITW Ramset/Red Head. e. MKT Fastening, LLC. f. Powers Fasteners.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -5 2.7 PIPE STAND FABRICATION A. Pipe Stands, General: Shop or field-fabricated assemblies made of manufactured corrosionresistant
components to support piping. B. Compact Pipe Stand: One-piece UV-inhibited plastic unit with integral-rod-roller, pipe clamps, or V-shaped cradle to support pipe, for roof installation
without membrane penetration, complete with seismic restraints. All metal components shall be hot dipped galvanized in accordance with ASTM A123 after fabrication. 1. Manufacturers:
a. ERICO/Michigan Hanger Co. b. MIRO Industries. c. Portable Pipe Hangers. C. Curb-Mounting-Type Pipe Stands: Shop-or field-fabricated pipe support made from structuralsteel shape, continuous-thread
rods, and rollers for mounting on permanent stationary roof curb. 2.8 EQUIPMENT SUPPORTS A. Description: Welded, shop-or field-fabricated equipment support made from structural-steel
shapes. 2.9 MISCELLANEOUS MATERIALS A. Structural Steel: ASTM A 36/A 36M, steel plates, shapes, and bars; black and galvanized. B. Grout: ASTM C 1107, factory-mixed and -packaged, dry,
hydraulic-cement, non-shrink and nonmetallic grout; suitable for interior and exterior applications. 1. Properties: Non-staining, non-corrosive, and nongaseous. 2. Design Mix: 5000-psi
(34.5-MPa), 28-day compressive strength. PART 3 -EXECUTION 3.1 HANGER AND SUPPORT APPLICATIONS A. Specific hanger and support requirements are specified in Sections specifying piping
systems and equipment. B. Comply with MSS SP-69 for pipe hanger selections and applications that are not specified in piping system Sections.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -6 C. Use hangers and supports with galvanized, metallic coatings for piping and equipment that will come into direct contact
with galvanized piping. D. Use nonmetallic coatings on attachments for electrolytic protection where attachments are in direct contact with copper tubing. E. Use plain finish for indoor
steel pipe hangers unless otherwise indicated. F. Horizontal-Piping Hangers and Supports: Unless otherwise indicated and except as specified in piping system Sections, install the following
types: 1. Adjustable, Steel Clevis Hangers (MSS Type 1): For suspension of non-insulated or insulated stationary pipes, NPS 1/2 to NPS 30 (DN 15 to DN 750). Install second upper lockout.
2. Adjustable, Swivel-Ring Band Hangers (MSS Type 10): For suspension of non-insulated stationary pipes, NPS 1/2 to NPS 2 (DN 15 to DN 50). 3. U-Bolts (MSS Type 24): For support of heavy
pipes, NPS 1/2 to NPS 30 (DN 15 to DN 750). 4. Pipe Stanchion Saddles (MSS Type 37): For support of pipes, NPS 4 to NPS 36 (DN 100 to DN 900), with steel pipe base stanchion support
and cast-iron floor flange and with Ubolt to retain pipe. 5. Adjustable, Pipe Saddle Supports (MSS Type 38): For stanchion-type support for pipes, NPS 2-1/2 to NPS 36 (DN 65 to DN 900),
if vertical adjustment is required, with steel pipe base stanchion support and cast-iron floor flange. 6. Single Pipe Rolls (MSS Type 41): For suspension of pipes, NPS 1 to NPS 30 (DN
25 to DN 750), from 2 rods if longitudinal movement caused by expansion and contraction might occur. 7. Adjustable Roller Hangers (MSS Type 43): For suspension of pipes, NPS 2-1/2 to
NPS 20 (DN 65 to DN 500), from single rod if horizontal movement caused by expansion and contraction might occur. 8. Complete Pipe Rolls (MSS Type 44): For support of pipes, NPS 2 to
NPS 42 (DN 50 to DN 1050), if longitudinal movement caused by expansion and contraction might occur but vertical adjustment is not necessary. 9. Adjustable Pipe Roll and Base Units (MSS
Type 46): For support of pipes, NPS 2 to NPS 30 (DN 50 to DN 750), if vertical and lateral adjustment during installation might be required in addition to expansion and contraction.
G. Vertical-Piping Clamps: Unless otherwise indicated and except as specified in piping system Sections, install the following types: 1. Extension Pipe or Riser Clamps (MSS Type 8):
For support of pipe risers, NPS 3/4 to NPS 12. 2. Carbon-or Alloy-Steel Riser Clamps (MSS Type 42): For support of pipe risers, NPS 14 to NPS 20, if longer ends are required for riser
clamps. H. Hanger-Rod Attachments: Unless otherwise indicated and except as specified in piping system Sections, install the following types:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -7 1. Steel Turnbuckles (MSS Type 13): For adjustment up to 6 inches (150 mm) for heavy loads. 2. Steel Weldless Eye Nuts
(MSS Type 17): For 120 to 450 deg F (49 to 232 deg C) piping installations. I. Building Attachments: Unless otherwise indicated and except as specified in piping system Sections, install
the following types: 1. Steel or Malleable Concrete Inserts (MSS Type 18): For upper attachment to suspend pipe hangers from concrete ceiling. 2. Top-Beam C-Clamps (MSS Type 19): For
use under roof installations with bar-joist construction to attach to top flange of structural shape. 3. Center-Beam Clamps (MSS Type 21): For attaching to center of bottom flange of
beams. 4. C-Clamps (MSS Type 23): For structural shapes. 5. Top-Beam Clamps (MSS Type 25): For For top of beams
if hanger rod is required tangent to flange edge. 6. Side-Beam Clamps (MSS Type 27): For bottom of steel I-beams. 7. Steel-Beam Clamps with Eye Nuts (MSS Type 28): For attaching to bottom
of steel Ibeams for heavy loads. 8. Linked-Steel Clamps with Eye Nuts (MSS Type 29): For attaching to bottom of steel Ibeams for heavy loads, with link extensions. 9. Malleable Beam
Clamps with Extension Pieces (MSS Type 30): For attaching to structural steel. 10. Welded-Steel Brackets: For support of pipes from below, or for suspending from above by using clip
and rod. Use one of the following for indicated loads: a. Light (MSS Type 31): 750 lb (340 kg). b. Medium (MSS Type 32): 1500 lb (680 kg). c. Heavy (MSS Type 33): 3000 lb (1360 kg).
11. Horizontal Travelers (MSS Type 58): For supporting piping systems subject to linear horizontal movement where headroom is limited. 12. For building attachments other than those indicated
(such as Z purlins), install appropriate attachments directly to building or install unistrut to structure and hang from the unistrut. Clarify with the Structural Engineer as required
J. Saddles and Shields: Unless otherwise indicated and except as specified in piping system Sections, install the following types: 1. Steel Pipe-Covering Protection Saddles (MSS Type
39): To fill interior voids with insulation that matches adjoining insulation. 2. Protection Shields (MSS Type 40): Of length recommended in writing by manufacturer to prevent crushing
insulation. 3. Thermal-Hanger Shield Inserts: For supporting insulated pipe. K. Spring Hangers and Supports: Unless otherwise indicated and except as specified in piping system Sections,
install the following types:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -8 1. Restraint-Control Devices (MSS Type 47): Where indicated to control piping movement. 2. Spring Cushions (MSS Type 48):
For light loads if vertical movement does not exceed 1-1/4 inches (32 mm). 3. Spring-Cushion Roll Hangers (MSS Type 49): For equipping Type 41 roll hanger with springs. 4. Spring Sway
Braces (MSS Type 50): To retard sway, shock, vibration, or thermal expansion in piping systems. 5. Variable-Spring Hangers (MSS Type 51): Preset to indicated load and limit variability
factor to 25 percent to absorb expansion and contraction of piping system from hanger. 6. Variable-Spring Base Supports (MSS Type 52): Preset to indicated load and limit variability
factor to 25 percent to absorb expansion and contraction of piping system from base support. 7. Variable-Spring Trapeze Hangers (MSS Type 53): Preset to indicated load and limit variability
factor to 25 percent to absorb expansion and contraction of piping system from trapeze support. 8. Constant Supports: For critical piping stress and if necessary to avoid transfer of
stress from one support to another support, critical terminal, or connected equipment. Include auxiliary stops for erection, hydrostatic test, and load-adjustment capability. These supports
include the following types: a. Horizontal (MSS Type 54): Mounted horizontally. b. Vertical (MSS Type 55): Mounted vertically. c. Trapeze (MSS Type 56): Two vertical-type supports and
one trapeze member. L. Comply with MSS SP-69 for trapeze pipe hanger selections and applications that are not specified in piping system Sections. M. Comply with MFMA-102 for metal framing
system selections and applications that are not specified in piping system Sections. N. Use mechanical-expansion anchors instead of building attachments where required in concrete construction.
3.2 HANGER AND SUPPORT INSTALLATION A. Steel Pipe Hanger Installation: Comply with MSS SP-69 and MSS SP-89. Install hangers, supports, clamps, and attachments as required to properly
support piping from building structure. B. Trapeze Pipe Hanger Installation: Comply with MSS SP-69 and MSS SP-89. Arrange for grouping of parallel runs of horizontal piping and support
together on field-fabricated trapeze pipe hangers. 1. Pipes of Various Sizes: Support together and space trapezes for smallest pipe size or install intermediate supports for smaller
diameter pipes as specified above for individual pipe hangers.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -9 2. Field fabricated from ASTM A 36/A 36M, steel shapes selected for loads being supported. Weld steel according to AWS
D1.1. C. Metal Framing System Installation: Arrange for grouping of parallel runs of piping and support together on field-assembled metal framing systems. D. Thermal-Hanger Shield Installation:
Install in pipe hanger or shield for insulated piping. E. Fastener System Installation: 1. Install mechanical-expansion anchors in concrete after concrete is placed and completely cured.
Install fasteners according to manufacturer's written instructions. F. Pipe Stand Installation: 1. Curb-Mounting-Type Pipe Stands: Assemble components or fabricate pipe stand and mount
on permanent, stationary roof curb. Refer to Division 7 Section "Roof Accessories" for curbs. 2. Insulate pipe stands which come in direct contact with piping or piping system components
which operate below 50 deg F. G. Install hangers and supports complete with necessary inserts, bolts, rods, nuts, washers, and other accessories. H. Equipment Support Installation: Fabricate
from welded-structural-steel shapes. I. Install hangers and supports to allow controlled thermal and seismic movement of piping systems, to permit freedom of movement between pipe anchors,
and to facilitate action of expansion joints, expansion loops, expansion bends, and similar units. J. Install lateral bracing with pipe hangers and supports to prevent swaying. K. Install
building attachments within concrete slabs or attach to structural steel. Install additional attachments at concentrated loads, including valves, flanges, and strainers, NPS 4 and larger
and at changes in direction of piping. Install concrete inserts before concrete is placed; fasten inserts to forms and install reinforcing bars through openings at top of inserts. L.
Load Distribution: Install hangers and supports so piping live and dead loads and stresses from movement will not be transmitted to connected equipment. M. Pipe Slopes: Install hangers
and supports to provide indicated pipe slopes and so maximum pipe deflections allowed by ASME B31.1 (for power piping) and ASME B31.9 (for building services piping) are not exceeded.
N. Insulated Piping: Comply with the following: 1. Attach clamps and spacers to piping.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -10 a. Piping Operating above Ambient Air Temperature: Clamp may project through insulation. b. Piping Operating below Ambient
Air Temperature: Use thermal-hanger shield insert with clamp sized to match OD of insert. c. Do not exceed pipe stress limits according to ASME B31.1 for power piping and ASME B31.9
for building services piping. 2. Install MSS SP-58, Type 39, protection saddles if insulation without vapor barrier is indicated. Fill interior voids with insulation that matches adjoining
insulation. a. Option: Thermal-hanger shield inserts may be used. Include steel weightdistribution plate for pipe NPS 4 (DN 100) and larger if pipe is installed on rollers. 3. Install
MSS SP-58, Type 40, protective shields on cold piping with vapor barrier. Shields shall shall span an arc of 180 degrees. a. Option: Thermal-hanger shield inserts may be used. Include
steel weightdistribution plate for pipe NPS 4 (DN 100) and larger if pipe is installed on rollers. 4. Shield Dimensions for Pipe: Not less than the following: a. NPS 1/4 to NPS 3-1/2
(DN 8 to DN 90): 12 inches (305 mm) long and 0.048 inch (1.22 mm) thick. b. NPS 4 (DN 100): 12 inches (305 mm) long and 0.06 inch (1.52 mm) thick. c. NPS 5 and NPS 6 (DN 125 and DN 150):
18 inches (457 mm) long and 0.06 inch (1.52 mm) thick. d. NPS 8 to NPS 14 (DN 200 to DN 350): 24 inches (610 mm) long and 0.075 inch (1.91 mm) thick. e. NPS 16 to NPS 24 (DN 400 to DN
600): 24 inches (610 mm) long and 0.105 inch (2.67 mm) thick. 5. Pipes NPS 8 (DN 200) and Larger: Include wood inserts. 6. Insert Material: Length at least as long as protective shield.
7. Thermal-Hanger Shields: Install with insulation same thickness as piping insulation. 8. Pipe Spacing: Arrange piping so that a minimum of 2-1/2” of clear space exists between the
outer surface of the pipe insulation on parallel piping. 9. Spaces with no ceiling: Attach protective insulation shield to hanger utilizing tack weld such that shield cannot be dislodged
from the hanger. 3.3 EQUIPMENT SUPPORTS A. Fabricate structural-steel stands to suspend equipment from structure overhead or to support equipment above floor. B. Grouting: Place grout
under supports for equipment and make smooth bearing surface.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT 23 05 29 -11 C. Provide lateral bracing, to prevent swaying, for equipment supports. D. Paint supports with corrosion resistant paint.
E. Insulate supports which come in direct contact with equipment or piping which operates below 50 deg F. 3.4 METAL FABRICATIONS A. Cut, drill, and fit miscellaneous metal fabrications
for trapeze pipe hangers and equipment supports. B. Fit exposed connections together to form hairline joints. Field weld connections that cannot be shop welded because of shipping size
limitations. C. Field Welding: Comply with AWS D1.1 procedures for shielded metal arc welding, appearance and quality of welds, and methods used in correcting welding work, and with
the following: 1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals. 2. Obtain fusion without undercut or overlap. 3. Remove
welding flux immediately. 4. Finish welds at exposed connections so no roughness shows after finishing and contours of welded surfaces match adjacent contours. 3.5 ADJUSTING A. Hanger
Adjustments: Adjust hangers to distribute loads equally on attachments and to achieve indicated slope of pipe. B. Trim excess length of continuous-thread hanger and support rods to 1-1/2
inches (40 mm). 3.6 PAINTING A. Touch Up: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same materials as
used for shop painting. Comply with SSPC-PA 1 requirements for touching up field-painted surfaces. 1. Apply paint by brush or spray to provide minimum dry film thickness of 2.0 mils
(0.05 mm). B. Galvanized Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A 780. END OF SECTION 23 05 29
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -1 SECTION 23 05 48 – VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT PART 1 -GENERAL 1.1 RELATED DOCUMENTS
A. Drawing and general provisions of the contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section
includes vibration isolation and seismic controls for HVAC components. This section includes seismic restraints for equipment, piping, and ductwork. B. This Section includes the following:
1. Elastomeric isolation pads. 2. Restrained elastomeric isolation mounts. 3. Freestanding and restrained spring isolators. 4. Housed spring mounts. 5. Elastomeric hangers. 6. Spring
hangers with vertical-limit stops. 7. Pipe riser resilient supports. 8. Resilient pipe guides. 9. Restrained vibration isolation roof-curb rails. 10. Seismic snubbers. 11. Restraining
cables. 12. Steel and inertia, vibration isolation equipment bases. 13. Anchor bolts. 1.3 DEFINITIONS A. OSHPD: Office of Statewide Health Planning & Development for the State of California.
B. SMACNA: Sheet Metal and Air Conditioning Contractors National Association, Inc. C. NFPA: National Fire Protection Association. D. IBC: International Building Code.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -2 1.4 PERFORMANCE REQUIREMENTS A. Seismic Restraint: 1. Design Spectral Acceleration, Short Period: 0.19 IBC 2000
Equation 16-18. 2. Seismic Design Category D. 3. Component Importance Factor: 1.5. B. Seismic Hazard Level Designations, Piping and Ductwork Seismic Restraints and Equipment Pad Construction:
1. SMACNA Seismic Hazard Level C for attachments made to slab on grade through the roof structure. C. Seismic restraint shall be provided in accordance with requirements of the applicable
Building Code and Mechanical Code and other locally enforced codes. D. Wind Restraint Loading: 1. Basic Wind Speed and Building Classification: See structural drawings. 2. Minimum 10
lb/sq. ft. multiplied by the maximum area of the HVAC component projected on a vertical plane that is normal to the wind direction and 45 degrees either side of normal. 1.5 SUBMITTALS
A. Product Data: Include load deflection curves rated load and overload capacity for each vibration isolation device. B. Equipment Shop Drawings: Signed and sealed by a qualified professional
engineer. Include the following: 1. Vibration Isolation Base Details: Detail fabrication, including anchorages and attachments to structure and to supported equipment. Include auxiliary
motor slides and rails, base weights, equipment static loads, power transmission, component misalignment, and cantilever loads. 2. Seismic-Restraint Details: Detail fabrication and attachment
of seismic restraints and snubbers. Show anchorage details and indicate material, strength, finish, quantity, diameter, depth of penetration of anchors, and required anchor edge distances.
C. Manufacturer Seismic Qualification Certification: Submit certification that all specified equipment will withstand seismic and wind restraint forces identified in "Performance Requirements"
Article above. Include the following: 1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculations.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -3 a. The term "withstand" means "the unit will remain in place without separation of any parts from the device
when subjected to the seismic forces specified" for all components with a performance criteria factor of 1.0. b. The term "withstand" means "the unit will remain in place without separation
of any parts from the device when subjected to the seismic forces specified and the unit will be fully operational after the seismic event" for all components with a performance criteria
factor of 1.5. 2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions. 3. Detailed description of equipment
anchorage devices on which the certification is based and their installation requirements. D. Piping and Ductwork Seismic Restraint Shop Drawings signed and sealed by a qualified professional
engineer. Include the following: 1. Location of all piping and ductwork seismic restraints shown in plan view. Utilize contractor’s in-progress as-built drawings for the plans. Identify
which type of restraint is used in which location (provide schedule as necessary). 2. Submit seismic restraint shop drawing of piping and ductwork seismic restraints prior to the area
undergoing its above ceiling inspection. 3. Submit written verification that seismic restraint installation is complete and meets project requirements. E. Wind Restraint Details: Detail
fabrication and attachment of restraints. Show anchorage details and indicate quantity, diameter, and depth of penetration of anchors. Submit calculations showing wind forces and compliance
with all state and local codes. 1.6 QUALITY ASSURANCE A. Seismic-restraint devices shall have horizontal and vertical load testing and analysis performed according to to OSHPD and shall
bear anchorage preapproval "OPA" number, from OSHPD or another agency acceptable to authorities having jurisdiction, showing maximum seismicrestraint ratings. Ratings based on independent
testing are preferred to ratings based on calculations. If preapproved ratings are not available, submittals based on independent testing are preferred. Calculations (including combining
shear and tensile loads) to support seismicrestraint designs must be signed and sealed by a qualified professional engineer. B. Welding: Qualify procedures and personnel according to
AWS D1.1/D1.1M, "Structural Welding Code--Steel." C. HVAC equipment mounted outside the building shall be anchored to building structure in compliance with lateral load requirements
of the locally enforced building code.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -4 1.7 COORDINATION A. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into base. Concrete,
reinforcement, and formwork requirements are specified in Division 3. B. Coordinate installation of roof curbs, equipment supports, and roof penetrations. These items are specified in
Division 7 Section "Roof Accessories." C. Coordinate with all trades the locations of seismic restraints for HVAC piping and equipment with all other systems and equipment in the vicinity.
PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the manufacturers specified. 1. Amber/Booth Company, Inc., A
VMC Group Company. 2. Kinetics Noise Control, Inc. 3. Mason Industries, Inc. 4. Vibration Eliminator Company, Inc. 5. Vibro-Acoustics. 6. Vibration Mountings and Controls, Inc. 2.2 VIBRATION
ISOLATORS A. Elastomeric Isolator Pads: Oil and water resistant neoprene arranged in single or multiple layers, molded with non-slip pattern and galvanized steel baseplates of sufficient
stiffness for uniform loading over pad area and factory cut to sizes that match requirements of supported equipment. 1. Material: Standard neoprene. B. Spring Isolators: Freestanding,
laterally stable, open spring isolators. 1. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated load. 2. Minimum Additional Travel: 50 percent
of the required deflection at rated load. 3. Lateral Stiffness: More than 80 percent of the rated vertical stiffness. 4. Overload Capacity: Support 200 percent of rated load, fully compressed,
without deformation or failure.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -5 5. Baseplates: Factory drilled for bolting to structure and bonded to 1/4-inch-(6-mm-) thick, rubber isolator
pad attached to baseplate underside. Baseplates shall limit floor load to 100 psig (690 kPa). 6. Top Plate and Adjustment Bolt: Threaded top plate with adjustment bolt and cap screw
to fasten and level equipment. C. Restrained Spring Isolators: Freestanding, steel, open spring isolators with seismic restraint. 1. Housing: Steel with resilient vertical-limit stops
to prevent spring extension due to wind loads or if weight is removed; factory-drilled baseplate bonded to 1/4-inch-(6-mm-) thick, elastomeric isolator pad attached to baseplate underside;
and adjustable equipment mounting and leveling bolt that acts as blocking during installation. 2. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring
at rated load. 3. Minimum Additional Travel: 50 percent of the required deflection at rated load. 4. Lateral Stiffness: More than 80 percent of the rated vertical stiffness. 5. Overload
Capacity: Support 200 percent of rated load, fully compressed, without deformation or failure. 6. Restraint: Seismic stop as required for equipment and authorities having jurisdiction.
D. Elastomeric Hangers: Double deflection type, with molded, oil resistant rubber or neoprene isolator elements, steel housings with threaded connections for hanger rods. Color coded
or otherwise identified to indicate capacity range. E. Spring Hangers: Combination coil-spring and elastomeric-insert hanger with spring and insert in compression. 1. Frame: Steel, fabricated
for connection to threaded hanger rods and to allow for a maximum of 30 degrees of angular hanger-rod misalignment without binding or reducing isolation efficiency. 2. Outside Spring
Diameter: Not less than 80 percent of the compressed height of the spring at rated load. 3. Minimum Additional Travel: 50 percent of the required deflection at rated load. 4. Lateral
Stiffness: More than 80 percent of the rated vertical stiffness. 5. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or failure. 6. Elastomeric
Element: Molded, oil-resistant rubber or neoprene. Steel-washer-reinforced cup to support spring and bushing projecting through bottom of frame or other method which puts the neoprene
in series with the spring. 7. Self-centering hanger rod cap to ensure concentricity between hanger rod and support spring coil. F. Spring Hangers with Vertical-Limit Stop: Combination
coil-spring and elastomeric-insert hanger with spring and insert in compression and with a vertical-limit stop.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -6 1. Frame: Steel, fabricated for connection to threaded hanger rods and to allow for a maximum of 30 degrees of
angular hanger-rod misalignment without binding or reducing isolation efficiency. 2. Outside Spring Diameter: Not less than 80 percent of the compressed height of the spring at rated
load. 3. Minimum Additional Travel: 50 percent of the required deflection at rated load. 4. Lateral Stiffness: More than 80 percent of the rated vertical stiffness. 5. Overload Capacity:
Support 200 percent of rated load, fully compressed, without deformation or failure. 6. Elastomeric Element: Molded, oil-resistant rubber or neoprene. 7. Adjustable Vertical Stop: Steel
washer with neoprene washer "up-stop" on lower threaded rod. 8. Self-centering hanger rod rod cap to ensure concentricity between hanger rod and support spring coil. G. Pipe Riser Resilient
Support: All-directional, acoustical pipe anchor consisting of 2 steel tubes separated by a minimum of 1/2-inch-(13-mm-) thick neoprene. Include steel and neoprene vertical-limit stops
arranged to prevent vertical travel in both directions. Design support for a maximum load on the isolation material of 500 psig (3.45 MPa) and for equal resistance in all directions.
H. Resilient Pipe Guides: Telescopic arrangement of 2 steel tubes separated by a minimum of 1/2-inch-(13-mm-) thick, neoprene. Factory set guide height with a shear pin to allow vertical
motion due to pipe expansion and contraction. Shear pin shall be removable and reinsertable to allow for selection of pipe movement. Guides shall be capable of motion to meet location
requirements. 2.3 RESTRAINED VIBRATION ISOLATION ROOF-CURB RAILS A. Description: Factory-assembled, fully enclosed, insulated, airtight and watertight curb rail designed to resiliently
support equipment and to withstand seismic and wind forces. Wind forces shall be a minimum of 125-mph (56-m/s) wind impinging laterally against side of equipment. B. Lower Support Assembly:
Sheet-metal "Z" section containing adjustable and removable steel springs that support upper floating frame. Upper frame shall provide continuous support for equipment and shall be captive
to resiliently resist wind and seismic forces. Lower support assembly shall have a means for attaching to building structure and a wood nailer for attaching roof materials, and shall
be insulated with a minimum of 2 inches (50 mm) of rigid, glass-fiber insulation on inside of assembly. C. Spring Isolators: Adjustable, restrained spring isolators shall be mounted
on 1/4-inch-(6-mm-) thick, elastomeric vibration isolation pads and shall have access ports, for level adjustment, with removable waterproof covers at all isolator locations. Isolators
shall be located so they are accessible for adjustment at any time during the life of the installation without interfering with the integrity of the roof.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -7 1. Restrained Spring Isolators: Freestanding, steel, open-spring isolators with seismic and/or wind restraint.
a. Housing: Steel with resilient vertical-limit stops and adjustable equipment mounting and leveling bolt. b. Outside Spring Diameter: Not less than 80 percent of the compressed height
of the spring at rated load. c. Minimum Additional Travel: 50 percent of the required deflection at rated load. d. Lateral Stiffness: More than 80 percent of the rated vertical stiffness.
e. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or failure. 2. Elastomeric Isolator Pads: Oil-and water-resistant elastomer or natural
rubber, arranged in single or multiple layers, molded with a non-slip pattern and galvanized steel baseplates of sufficient stiffness for uniform loading over pad area, and factory cut
to sizes that match requirements of supported equipment. a. Material: Standard neoprene. D. Snubber Bushings: All-directional, elastomeric snubber bushings at least 1/4 inch (6 mm) thick.
E. Water Seal: Galvanized sheet metal with EPDM seals at corners, attached to upper support frame, extending down past wood nailer of lower support assembly, and counterflashed over
roof materials. 2.4 SEISMIC-RESTRAINT DEVICES A. Structural Safety Factor: Allowable strength in tension, shear, and pullout force of components shall be at least three times the maximum
seismic forces to which they will be subjected. B. Resilient Isolation Washers and Bushings: 1-piece, molded, neoprene having a durometer of 40 -60, plus or minus 5, with a flat washer
face. C. Seismic Snubbers: Factory fabricated using welded structural-steel shapes and plates, anchor bolts, and replaceable resilient isolation washers and bushings. 1. Anchor bolts
for for attaching to concrete shall be seismic-rated, drill-in, and stud-wedge or female-wedge type. 2. Resilient Isolation Washers and Bushings: 1-piece, molded, bridge-bearing neoprene
complying with AASHTO M 251 and having a durometer of 40 -60, plus or minus 5. 3. Maximum 1/4-inch air gap and minimum 1/4-inch thick resilient cushion. D. Restraining Cables: ASTM A603
galvanized steel aircraft cables with end connections made of steel assemblies that adjust to final installation angle and utilize clamping bolts or other method for cable engagement.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS
FOR HVAC PIPING AND EQUIPMENT 23 05 48 -8 E. Anchor Bolts: Seismic-rated, drill-in, and stud-wedge or female-wedge type suitable for seismic use in accordance with ACI 355. Select anchor
bolts with strength required for anchor and as tested according to ASTM E 488/E 488M. 2.5 VIBRATION ISOLATION EQUIPMENT BASES A. Steel Base: Factory-fabricated, welded, structural-steel
bases and rails. 1. Design Requirements: Lowest possible mounting height with not less than 1-inch (25-mm) clearance above the floor and not more than 1-1/2 inch clearance. Include equipment
anchor bolts and auxiliary motor slide bases or rails. Include supports for suction and discharge elbows for pumps. 2. Structural Steel: Steel shapes, plates, and bars complying with
ASTM A 36/A 36M. Bases shall have shape to accommodate supported equipment. 3. Support Brackets: Factory-welded steel angles on frame for outrigger isolation mountings and to provide
for anchor bolts and equipment support. B. Inertia Base Factory-fabricated, welded, structural-steel bases and rails ready for field-applied, cast-in-place concrete. 1. Design Requirements:
Lowest possible mounting height with not less than 1-inch (25-mm) clearance above the floor. Include equipment anchor bolts and auxiliary motor slide bases or rails. Include supports
for suction and discharge elbows for pumps. 2. Structural Steel: Steel shapes, plates, and bars complying with ASTM A 36/A 36M. Bases shall have shape to accommodate supported equipment.
3. Support Brackets: Factory-welded steel angles on frame for outrigger isolation mountings and to provide for anchor bolts and equipment support. 4. Fabrication: Fabricate steel templates
to hold equipment anchor-bolt sleeves and anchors in place during placement of concrete. Obtain anchor-bolt templates from supported equipment equipment manufacturer. 2.6 FACTORY FINISHES
A. Finish: Manufacturer's standard paint applied to factory-assembled and -tested equipment before shipping. 1. Powder coating on springs and housings. 2. All hardware shall be electro-galvanized.
Hot-dip galvanized metal components for exterior use. 3. Baked enamel for metal components on isolators for interior use. 4. Color-code or otherwise mark vibration isolation and seismic-control
devices to indicate capacity range.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -9 PART 3 -EXECUTION 3.1 EXAMINATION A. Examine areas and equipment to receive vibration isolation and seismic-control
and wind control devices for compliance with requirements, installation tolerances, and other conditions affecting performance. B. Examine roughing-in of reinforcement and cast-in-place
anchors to verify actual locations before installation. C. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 INSTALLATION A. Install roof curbs,
equipment supports, and roof penetrations as specified in Division 7 Section "Roof Accessories" and in accordance with applicable codes as required by the authorities having jurisdiction.
B. Install thrust limits at centerline of thrust, symmetrical on either side of equipment. C. Install seismic snubbers or restrained springs on isolated equipment. Locate snubbers as
close as possible to vibration isolators and bolt to equipment base and supporting structure. D. Install restraining cables steel angles or channel at each trapeze and individual pipe
hanger as specified herein. Install cables so they do not bend across sharp edges of adjacent equipment or building structure. Requirements apply equally to hanging equipment. Do not
weld angles to threaded rods. E. Install resilient bolt isolation washers on equipment anchor bolts. F. Install hanger rod stiffeners where required to prevent buckling of hanger rods
due to seismic forces. G. Multiple Pipe Supports: Secure pipes to trapeze member with clamps approved for application by ICC-ES, OSHPD, or another agency acceptable to authorities having
jurisdiction. H. Attachment to Structure: Anchor bracing to structure at flange of beams, at upper chord of truss or at concrete members. I. Drilled in Anchors: 1. Identify position
of reinforcing steel and other embedded items prior to drilling holes for anchors. Do not damage reinforced steel and embedded items. Locate and avoid all items.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -10 2. Do not drill holes until concrete has achieved full design strength. 3. Set anchors to manufacturer’s recommended
torque, using a torque wrench. 4. Install zinc coated anchors for interior and stainless steel anchors for exterior applications. J. Field installed identification means on each actual
seismic restraint which is cross-referenced to the submittal drawing. K. Fill concrete inertia bases, after installing base frame, with 3000-psi (20.7-MPa) concrete; trowel to a smooth
finish. 1. Cast-in-place concrete materials and placement requirements as specified in Division 3. 3.3 EQUIPMENT BASES A. Concrete Equipment Bases: Anchor equipment to concrete base
according to supported equipment manufacturer's written instructions for seismic codes codes at Project site. B. Positively anchor concrete base to concrete floor. Unless otherwise indicated,
install #3 with 6" hook dowel rods, 6" from edge of base, minimum four per base, on 18-inch (457-mm) centers around the full perimeter of the base. 1. Place and secure anchorage devices
a minimum of 6" from edge of base. Use Setting Drawings, templates, diagrams, instructions, and directions furnished with items to be embedded. 2. Install anchor bolts to elevations
required for proper attachment to supported equipment. 3. Install anchor bolts according to anchor-bolt manufacturer's written instructions. 4. Cast-in-place concrete materials and placement
requirements are specified in Division 3. 3.4 ACCOMMODATION OF DIFFERENTIAL SEISMIC MOTION A. Install flexible connections in piping where they cross seismic joints, where adjacent sections
or branches are supported by different structural elements, and where the connections terminate with connection to equipment that is anchored to a different structural element from the
one supporting the connections as they approach equipment. Comply with requirements in Division 23 Section "Hydronic Piping" for piping flexible connections. 3.5 ADJUSTING A. Adjust
isolators after piping systems have been filled and equipment is at operating weight. B. Adjust limit stops on restrained spring isolators to mount equipment at normal operating height.
After equipment installation is complete, adjust limit stops so they are out of contact during normal operation.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -11 C. Attach thrust limits at centerline of thrust and adjust to a maximum of 1/4-inch (6-mm) movement during start
and stop. D. Adjust active height of spring isolators. E. Adjust snubbers according to manufacturer's written recommendations. F. Adjust seismic restraints to permit free movement of
equipment within normal mode of operation. G. Torque anchor bolts according to equipment manufacturer's written recommendations to resist seismic forces. 3.6 CLEANING A. After completing
equipment installation, inspect vibration isolation and seismic-control devices. Remove paint splatters and other spots, dirt, and debris, leaving equipment free to move on isolation
supports. 3.7 PIPING AND DUCTWORK RESTRAINTS A. All ductwork and piping shall be provided provided with seismic restraints in accordance with SMACNA Seismic Restraint Manual: Guidelines
for Mechanical Systems, Second Edition with September 2000 Amendment No. 1 as published by the Sheet Metal and Air Conditioning Contractors National Association, Inc. (ANSI/SMACNA 001-2000).
Seismic Hazard Levels required are noted in Part 1 "Performance Requirements." 1. "12 inch" exceptions for duct and piping are not applicable. Utilize the methods of the Seismic Restraint
Manual without utilizing these exceptions. B. Piping restraints shall comply with requirements at MSS SP-127. 1. Brace a change in direction longer than 12 feet. C. Seismically restrain
(brace) all piping as follows: 1. Brace all HVAC piping 2-1/2” nominal diameter and larger. D. Seismically restrain all ductwork as follows: 1. Seismically restrain all ductwork six
square feet and larger in cross sectional area. 2. Seismically restrain all ductwork four square foot and larger in cross sectional area associated with air handling systems serving
operating rooms. 3. Seismically restrain all ductwork four square foot and larger in cross-sectional area associated with air handling systems serving emergency departments.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT 23 05 48 -12 4. Seismically restrain all ductwork four square foot and larger in cross-sectional area associated with exhaust
systems serving airborne infectious isolation rooms. E. Generate a coordination drawing showing pipe and ductwork restraint locations in a timely manner to facilitate coordination with
other trades. 3.8 EQUIPMENT VIBRATION ISOLATION AND SEISMIC RESTRAINT A. Manufacturer shall design and provide vibration isolation and seismic restraints to meet the requirements of
this specification and as indicated on the Drawings. B. Seismic restraints shall be designed and provided for all equipment. C. All floor mounted equipment whether vibration isolated
or not shall be anchored, bolted or welded to the structure to comply with the required design forces. D. Suspended equipment shall be two rigid restraint or four point cables independently
braced. END OF SECTION 23 05 48
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 -1 SECTION 23 05 53 – IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general
provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following
mechanical identification materials and their installation: 1. Equipment labels. 2. Access panel and door labels. 3. Pipe labels. 4. Duct labels. 5. Stencils. 6. Valve tags. 7. Valve
schedules. 8. Ceiling and thermostat labels. 1.3 SUBMITTALS A. Product Data: For each type of product indicated. B. Valve Tag Schedules: For each piping system. Include a listing of
all valves to be labeled with proposed content for each label. Include valve numbering scheme. Furnish extra copies (in addition to mounted copies) to include in maintenance manuals.
C. Equipment Label Schedule: Include a listing of all equipment to be labeled with proposed content for each label. 1.4 QUALITY ASSURANCE A. ASME Compliance: Comply with ASME A13.1,
"Scheme for the Identification of Piping Systems," for letter size, length of color field, colors, and viewing angles of identification devices for piping.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 -2 1.5 COORDINATION A. Coordinate installation of identifying devices with completion of covering and painting of surfaces where
devices are to be applied. B. Coordinate installation of identifying devices with location of access panels and doors. C. Install identifying devices before installing acoustical ceilings
and similar concealment. D. Coordinate identifying devices to be consistent in appearance in all exposed locations. PART 2 -PRODUCTS 2.1 EQUIPMENT IDENTIFICATION DEVICES A. Equipment
Labels: Engraved, color-coded, multi-layer, multi-color laminated plastic for mechanical engraving. Include contact-type, permanent adhesive suitable for surface temperature of equipment.
1. Terminology: Match Owner's numbering scheme or drawing schedules with unique equipment number. 2. Size: Length and width vary for required label content, but not less than 4-1/2 by
6 inches (115 by 150 mm) for equipment, 1/8" thick. 3. Letters: 1/2" minimum. B. Access Panel and Door Labels: 1/16-inch-(1.6-mm-) thick, engraved laminated plastic, with abbreviated
terms and numbers corresponding to identification. Provide 1/8-inch (3.2-mm) center hole for attachment. 1. Terminology: Match Owner’s labeling scheme. 2. Fasteners: Self-tapping, stainless-steel
screws or contact-type, permanent adhesive. 2.2 PIPING IDENTIFICATION DEVICES A. Manufactured Pipe Labels, General: Preprinted, color-coded, with lettering indicating service, and an
arrow showing direction of flow. 1. Colors: ASME A13.1 or Owner's current color scheme. 2. Lettering: a. Heating Water Supply HWS b. Heating Water Return HWR
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 -3 3. Pipes with OD, Including Insulation, Less Than 6 Inches (150 mm): Full-band pipe markers extending 360 degrees around pipe
at each location. 4. Pipes with OD, Including Insulation, 6 Inches (150 mm) and Larger: Either full-band or strip-type pipe markers at least three times letter height and of length required
for label. 5. Arrows: Integral with piping system service lettering to accommodate both directions; or as separate unit on each pipe marker to indicate direction of material flow in
piping. B. Pretensioned Pipe Labels: Precoiled semi-rigid plastic formed to cover full circumference of pipe and to attach to pipe without adhesive. C. Plastic Tape Pipe Labels: Continuously
printed, vinyl tape at least 3 mils (0.08 mm) thick with pressure-sensitive, permanent-type, self-adhesive back. 1. Width for Markers on Pipes with OD, Including Insulation, Less Than
6 Inches (150 mm): 3/4 inch (19 mm) minimum. 2. Width for Markers on Pipes with OD, Including Insulation, 6 Inches (150 mm) or Larger: 1-1/2 inches (38 mm) minimum. 2.3 DUCT IDENTIFICATION
DEVICES A. Duct Labels: Preprinted, color-coded with lettering indicating service. Include direction of airflow and duct service (such as supply, return, and exhaust). Include contact-type,
permanent adhesive. 2.4 DUCT AND ACCESS DOOR STENCILS A. Stencils: Prepared with letter sizes according to ASME A13.1; minimum letter height of 1-1/4 inches (32 mm) for ducts; and minimum
letter height of 3/4 inch (19 mm) for access panel and door markers and similar operational instructions. 1. Stencil Paint: Exterior, gloss, acrylic enamel black, unless otherwise indicated.
Paint may be in pressurized spray-can form. 2. Identification Paint: Exterior, acrylic enamel in colors according to ASME A13.1, unless otherwise indicated. 2.5 VALVE TAGS A. Valve Tags:
Stamped with 1/4-inch (6.4-mm) letters for piping system abbreviation and 1/2-inch (13-mm) numbers, with numbering scheme approved by Owner. Provide 5/32-inch (4-mm) hole for fastener.
1. Material: 0.032-inch-(0.8-mm-) thick brass. 2. Valve-Tag Fasteners: Brass S-hook. 3. Lettering: Black filled.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 -4 4. Size: Minimum 1-1/2”, larger as required for labeling scheme. 2.6 VALVE SCHEDULES A. Valve Schedules: For each piping system,
on standard-size bond paper. Tabulate valve number, piping system, system abbreviation (as shown on valve tag), location of valve (room or space), normal-operating position (open, closed,
or modulating), and variations for identification. Mark valves for emergency shutoff and similar special uses. 1. Valve-Schedule Frames: Glazed display frame for removable mounting on
masonry walls for each page of valve schedule. Include mounting screws. 2. Frame: Extruded aluminum. 3. Glazing: ASTM C 1036, Type I, Class 1, Glazing Quality B, 2.5-mm, single-thickness
glass. 2.7 CEILING LABELS A. Description: 1/2-inch wide clear extra strength tape with 1/4-inch high black letters. Extra strength adhesive suitable for use on rough, textured, or uneven
surfaces, as well as painted and powder coated surfaces. 2.8 TEMPERATURE SENSOR LABELS A. Description: 1/4-inch wide clear extra strength tape with 1/8-inch high black letters. Extra
strength adhesive for use on rough textured or uneven surfaces, as well as painted or powder coated surfaces. PART 3 -EXECUTION 3.1 APPLICATIONS, GENERAL A. Products specified are for
applications referenced in other Division 23 Sections. If more than single-type material, device, or label is specified for listed applications, selection is Installer's option. 3.2
EQUIPMENT IDENTIFICATION A. Install equipment labels with permanent adhesive on or near each item of mechanical equipment.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 -5 1. Letter Size: Minimum 3/4-inch (19 mm) for name of units and proportionately larger lettering for greater viewing distances.
Include secondary lettering two-thirds to threefourths the size of principal lettering. 2. Data: Distinguish among multiple units, indicate operational requirements, indicate safety
and emergency precautions, warn of hazards and improper operations, and identify units. 3. Locate labels where accessible and visible. Include labels for each piece of mechanical equipment
and for the following general categories of equipment: a. Fuel-burning units, including boilers, furnaces, heaters, stills, and absorption units. b. Pumps, compressors, chillers, condensers,
and similar motor-driven units. c. Heat exchangers, built-up coil banks, evaporators, cooling towers, heat recovery units, and similar equipment. d. Fans, blowers, primary balancing
dampers, and mixing boxes. e. Packaged HVAC central-station and zone-type units. f. Tanks and pressure vessels. g. Filters, humidifiers and water-treatment systems. h. Fire dampers and
fire/smoke dampers. i. Humidifiers and pressure reducing valves. B. Install access panel and door labels on equipment and shaft access panels. 3.3 PIPING IDENTIFICATION A. Install manufactured
pipe label indicating service on each piping system. Install with flow indication arrows showing direction of material flow in piping. 1. Pipes with OD, Including Insulation, Less Than
6 Inches (150 mm): Pretensioned pipe labels. Use size to ensure a tight fit. 2. Pipes with OD, Including Insulation, Less Than 6 Inches (150 mm): Self-adhesive pipe labels. Use color-coded,
self-adhesive plastic tape, covering full circumference of pipe. 3. Pipes with OD, Including Insulation, 6 Inches (150 mm) and Larger: Self-adhesive pipe labels. Use color-color-coded,
self-adhesive plastic tape, at least 1-1/2 inches (38 mm) wide, lapped at least 3 inches (75 mm) at both ends of pipe label, and covering full circumference of pipe. B. Locate pipe labels
as follows: 1. Near (within 24” of) each valve and control device. 2. Near each branch connection, excluding short takeoffs less than ten feet long for fixtures and terminal units. Where
flow pattern is not obvious, mark each pipe at branch. 3. Each side of penetrations through walls, floors, ceilings, and non-accessible enclosures. 4. At access doors, manholes, and
similar access points that permit view of concealed piping. 5. Near major equipment items and other points of origination and termination. 6. Spaced at maximum intervals of 15 feet (4.5
m) along each run.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 -6 7. At a minimum of once over each room for each piping system present over that room. Center the label in the pipe run over the
room, if pipe length over the room is less than 15 feet rather than install at each wall penetration. 3.4 DUCT IDENTIFICATION A. Install duct labels with permanent adhesive on air ducts
in the following color codes: 1. Green: For cold-air supply ducts. 2. Yellow: For hot-air supply ducts. 3. Blue: For exhaust-, outside-, relief-, return-, and mixed-air ducts. 4. Red:
For bio-hazard and isolation room exhaust ducts. 5. ASME A13.1 Colors and Designs: For hazardous material exhaust. 6. Letter Size: Minimum 1-inch (26 mm) and proportionately larger lettering
for greater viewing distances. Include secondary lettering two-thirds to three-fourths the size of principal lettering. B. Stenciled Duct Option: Stenciled labels, showing service and
direction of flow, may be provided instead of laminated-plastic duct labels, if lettering larger than 1 inch (25 mm) high is needed for proper identification because of distance from
normal location of required identification. C. Locate labels near points where ducts enter into concealed spaces and at maximum intervals of 15 feet (4.5 m) in each space where ducts
are exposed or concealed by removable ceiling system. D. Duct marker identification shall indicate the associated fan system (e.g., "EF-3 exhaust"). 3.5 VALVE-TAG INSTALLATION A. Install
tags on valves and control devices in piping systems, except check valves; valves within factory-fabricated equipment units; faucets; convenience hose connections; at HVAC terminal devices
and at similar roughing-in connections of end-use fixtures and units. List tagged valves in a valve schedule. 3.6 VALVE-SCHEDULE INSTALLATION A. Mount valve schedules on a wall in an
accessible location in each major equipment room. 3.7 CEILING LABEL AND TEMPERATURE SENSOR LABEL INSTALLATION A. Provide ceiling labels to locate items above T-bar type lay-in panel
ceilings. Locate at corner of T-bar grid closest to equipment. Provide ceiling labels for the following:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT 23 05 53 -7 1. HVAC terminal units (terminal boxes, reheat coils, etc.). 2. Fire dampers and fire/smoke dampers. 3. Steam traps, humidifiers
and steam pressure reducing valves. 4. Controls components: Control panels, duct static pressure sensors, humidifier sensors, control valves, control air reducing valves, etc. 5. Duct
smoke detectors. 6. Each valve which receives a valve tag. B. Provide thermostat labels on the inside cover of all thermostats with removable covers. For other sensors, install label
on top exterior surface. Label shall indicate equipment tag of controlled device (e.g., TB-311). Clarify location of label with controls submittal. 3.8 WARNING LABEL INSTALLATION A.
Write required message on and attach warning labels to equipment and other items (e.g. hazardous ductwork systems) where required. 3.9 ADJUSTING A. Relocate mechanical identification
materials and devices that have become visually blocked by other work. 3.10 CLEANING A. Clean faces of mechanical identification devices and glass frames of valve schedules. END OF SECTION
23 05 53
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -1 SECTION 23 05 93 -TESTING, ADJUSTING, AND BALANCING FOR HVAC PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions
of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes testing, adjusting
and balancing HVAC systems to produce design objectives, including the following: 1. Balancing airflow and water flow within distribution systems, including submains, branches, and terminals,
to indicated quantities according to specified tolerances. 2. Adjusting total HVAC systems to provide indicated quantities. 3. Measuring electrical performance of HVAC equipment. 4.
Setting quantitative performance of HVAC equipment. 5. Verifying that automatic control devices are functioning properly. 6. Reporting results of the activities and procedures specified
in this Section. B. The licensed Mechanical Contractor shall be responsible for scheduling, supervising, and coordinating the work in this section. 1.3 DEFINITIONS A. AABC: Associated
Air Balance Council. B. NEBB: National Environmental Balancing Bureau. C. TAB: Testing, adjusting, and balancing. D. TAB Specialist: An entity engaged to perform TAB Work. 1.4 SUBMITTALS
A. Qualification Data: Within 45 days of Contractor's Notice to Proceed, submit documentation that the TAB Contractor and this Project's TAB team members meet the qualifications specified
in "Quality Assurance" Article.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -2 B. Contract Documents Examination Report: Within 45 days of Contractor's Notice to Proceed, submit the Contract Documents review
report as specified in Part 3. C. Strategies and Procedures Plan: Within 90 days of Contractor's Notice to Proceed, submit TAB strategies and step-by-step procedures as specified in
"Preparation" Article. D. Certified TAB reports. E. Instrument calibration reports, to include the following: 1. Instrument type and make. 2. Serial number. 3. Application. 4. Dates
of use. 5. Dates of calibration. 1.5 QUALITY ASSURANCE A. TAB Contractor Qualifications: Engage a TAB entity certified by AABC or NEBB. 1. TAB Field Supervisor: Employee of the TAB contractor
and certified by AABC or NEBB. 2. TAB Technician: Employee of the TAB contractor and who is certified by AABC or NEBB as a TAB technician. B. TAB Conference: Meet with Engineer, Owner,
Construction Manager, and Commissioning Authority on approval of the TAB strategies and procedures plan to develop a mutual understanding of the details. Require the participation of
the TAB field supervisor and technicians. Provide seven days' advance notice of scheduled meeting time and location. 1. Agenda Items: a. The Contract Documents examination report. b.
The TAB plan. c. Coordination and cooperation of trades and subcontractors. d. Coordination of documentation and communication flow. C. Certify TAB field data reports and perform the
following: 1. Review field data reports to validate accuracy of data and to prepare certified TAB reports. 2. Certify that the TAB team complied with the approved TAB plan and the procedures
specified and referenced in this Specification. D. TAB Report Forms: Use standard TAB Contractor's forms.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -3 E. Instrumentation Type, Quantity, Accuracy, and Calibration: As described in ASHRAE 111, Section 5, "Instrumentation." 1.6 PROJECT
CONDITIONS A. Partial Owner Occupancy: Owner may occupy completed areas of building before Substantial Completion. Cooperate with Owner during TAB operations to minimize conflicts with
Owner's operations. 1.7 COORDINATION A. Notice: Provide seven days' advance notice for each test. Include scheduled test dates and times. B. Perform TAB
after leakage and pressure tests on air and water distribution systems have been satisfactorily completed. PART 2 -PRODUCTS (Not Applicable) PART 3 -EXECUTION 3.1 TAB SPECIALISTS A.
Subject to compliance with requirements, engage one of the following: 1. Central Indiana: a. Total Balance, Inc. 3.2 EXAMINATION A. Examine the Contract Documents to become familiar
with Project requirements and to discover conditions in systems' designs that may preclude proper TAB of systems and equipment. B. Examine systems for installed balancing devices, such
as test ports, gage cocks, thermometer wells, flow-control devices, balancing valves and fittings, and manual volume dampers. Verify that locations of these balancing devices are accessible.
C. Examine the approved submittals for HVAC systems and equipment.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -4 D. Examine design data including HVAC system descriptions, statements of design assumptions for environmental conditions and systems'
output, and statements of philosophies and assumptions about HVAC system and equipment controls. E. Examine ceiling plenums and underfloor air plenums used for supply, return, or relief
air to verify that they meet the leakage class of connected ducts as specified in Division 23 Section "Metal Ducts" and are properly separated from adjacent areas. Verify that penetrations
in plenum walls are sealed and fire-stopped if required. F. Examine equipment performance data including fan and pump curves. 1. Relate performance data to Project conditions and requirements,
including system effects that can create undesired or unpredicted conditions that cause reduced capacities in all or part of a system. 2. Calculate system-effect factors to reduce performance
ratings of HVAC equipment when installed under conditions different from the conditions used to rate equipment performance. To calculate system effects for air systems, use tables and
charts found in AMCA 201, "Fans and Systems," or in SMACNA's "HVAC Systems -Duct Design." Compare results with the design data and installed conditions. G. Examine system and equipment
installations and verify that field quality-control testing, cleaning, and adjusting specified in individual Sections have been performed. H. Examine test reports specified in individual
system and equipment Sections. I. Examine HVAC equipment and filters and verify that bearings are greased, belts are aligned and tight, and equipment with functioning controls is ready
for operation. J. Examine terminal units, such as variable-air-volume boxes, and verify that they are accessible and their controls are connected and functioning. functioning. K. Examine
strainers. Verify that startup screens are replaced by permanent screens with indicated perforations. L. Examine three-way valves for proper installation for their intended function
of diverting or mixing fluid flows. M. Examine heat-transfer coils for correct piping connections and for clean and straight fins. N. Examine system pumps to ensure absence of entrained
air in the suction piping. O. Examine operating safety interlocks and controls on HVAC equipment. P. Examine automatic temperature system components to verify the following: 1. Dampers,
valves and other controlled devices operate by the intended controller. 2. Dampers and valves are in the position indicated by the controller.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -5 3. Integrity of valves and dampers for free and full operation and for tightness of fully closed and fully open position. This
includes dampers in multi-zone units, mixing boxes and variable air volume terminals. 4. Automatic modulating and shutoff valves, including 2-way valves and 3-way mixing and diverting
valves, are properly connected. 5. Thermostats and humidistats are located to avoid adverse affects of sunlight, drafts, and cold walls. 6. Sensors are located to sense only the intended
conditions. 7. Sequence of operation for control modes is according to the Contract Documents. 8. Controller setpoints are set at design values. Observe and record system reactions to
changes in conditions. Record default setpoints if different from design values. 9. Interlocked systems are operating. 10. Changeover from heating to cooling mode occurs according to
design values. Q. Report deficiencies discovered before and during performance of TAB procedures. Observe and record system reactions to changes in conditions. Record default set points
if different from indicated values. 3.3 PREPARATION A. Prepare a TAB plan that includes strategies and step-by-step procedures. B. Complete system-readiness checks and prepare reports.
Verify the following: 1. Permanent electrical-power wiring is complete. 2. Hydronic systems are filled, clean, and free of air. 3. Automatic temperature-control systems are operational.
4. Equipment and duct access doors are securely closed. 5. Balance, smoke, and fire dampers are open. 6. Isolating and balancing valves are open and control valves are operational. 7.
Ceilings are installed in critical areas where air-pattern adjustments are required and access to balancing devices is provided. 8. Windows and doors can be closed so indicated conditions
for for system operations can be met. 3.4 GENERAL PROCEDURES FOR TESTING AND BALANCING A. Perform testing and balancing procedures on each system according to the procedures contained
in AABC's "National Standards for Total System Balance," ASHRAE 111 NEBB's "Procedural Standards for Testing, Adjusting, and Balancing of Environmental Systems," SMACNA's "HVAC Systems
-Testing, Adjusting, and Balancing" and in this Section. 1. Comply with requirements in ASHRAE 62.1-2004, Section 7.2.2, "Air Balancing."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -6 B. Cut insulation, ducts, pipes, and equipment cabinets for installation of test probes to the minimum extent necessary for TAB
procedures. 1. After testing and balancing, patch probe holes in ducts with same material and thickness as used to construct ducts. 2. After testing and balancing, install test ports
and duct access doors that comply with requirements in Division 23 Section "Air Duct Accessories." 3. Install and join new insulation that matches removed materials. Restore insulation,
coverings, vapor barrier, and finish according to Division 23 Section "HVAC Insulation." C. Mark equipment and balancing devices, including damper-control positions, valve position indicators,
fan-speed-control levers, and similar controls and devices, with paint or other suitable, permanent identification material to show final settings. D. Take and report testing and balancing
measurements in inch-pound (IP) units. 3.5 GENERAL PROCEDURES FOR BALANCING AIR SYSTEMS A. Prepare test reports for both fans and outlets. Obtain manufacturer's outlet factors and recommended
testing procedures. Crosscheck the summation of required outlet volumes with required fan volumes. B. Prepare schematic diagrams of systems' "as-built" duct layouts. C. For variable-air-volume
systems, develop a plan to simulate diversity. Submit this plan to all contractors to verify phasing and occupancy concerns. Submit plan to the Engineer prior to execution. D. Determine
the best locations in main and branch ducts for accurate duct-airflow measurements. E. Check airflow patterns from the outdoor-air louvers and dampers and the return-and exhaust-air
dampers through the supply-fan discharge and mixing dampers. Communicate concerns about potential stratification directly to the Engineer. F. Locate start-stop and disconnect switches,
electrical interlocks, and motor starters. G. Verify that motor starters are equipped with properly sized thermal protection. H. Check dampers for proper position to achieve desired
airflow path. I. Check for airflow blockages. J. Check condensate drains for proper connections and functioning. K. Check for proper sealing of air-handling-unit components.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -7 L. Verify that air duct system is sealed as specified in Division 23 Section "Metal Ducts." 3.6 PROCEDURES FOR CONSTANT-VOLUME
AIR SYSTEMS A. Adjust fans to deliver total indicated airflows within the maximum allowable fan speed listed by fan manufacturer. 1. Measure total airflow. a. Where sufficient space
in ducts is unavailable for Pitot-tube traverse measurements, measure airflow at terminal outlets and inlets and calculate the total airflow. 2. Measure fan static pressures as follows
to determine actual static pressure: a. Measure outlet static pressure as far downstream from the fan as practical and upstream from restrictions in ducts such as elbows and transitions.
b. Measure static pressure directly at the fan outlet or through the flexible connection. c. Measure inlet static pressure of single-inlet fans in the inlet duct as near the fan as possible,
upstream from the flexible connection, and downstream from duct restrictions. d. Measure inlet static pressure of double-inlet fans through the wall of the plenum that houses the fan.
3. Measure static pressure across each component that makes up an air-handling unit, rooftop unit, and other air-handling and -treating equipment. a. Report the cleanliness status of
filters and the time static pressures are measured. 4. Measure static pressures entering and leaving other devices, such as sound traps, heatrecovery equipment, and air washers, under
final balanced conditions. 5. Review Record Documents to determine variations in design static pressures versus actual static pressures. Calculate actual system-effect factors. Recommend
adjustments to accommodate actual conditions. 6. Obtain approval from Engineer for adjustment of fan speed higher or lower than indicated speed. Comply with requirements in Division
23 Sections for air-handling units for adjustment of fans, belts, and pulley sizes to achieve indicated air-handling-unit performance. 7. Do not make fan-speed adjustments that result
in motor overload. Consult equipment manufacturers about fan-speed safety factors. Modulate dampers and measure fan-motor amperage to ensure that no overload will occur. Measure amperage
in full-cooling, fullheating, economizer, and any other operating mode to determine the maximum required brake horsepower. 8. Replace sheaves and belts as required to deliver the necessary
airflow through the system accounting for all system losses. Coordinate final belt and sheave sizes with unit manufacturers. Refer to individual Division 23 specifications for additional
information.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -8 B. Adjust volume dampers for main duct, submain ducts, and major branch ducts to indicated airflows within specified tolerances.
1. Measure airflow of submain and branch ducts. a. Where sufficient space in submain and branch ducts is unavailable for Pitot-tube traverse measurements, measure airflow at terminal
outlets and inlets and calculate the total airflow for that zone. 2. Measure static pressure at a point downstream from the balancing damper, and adjust volume dampers until the proper
static pressure is achieved. 3. Remeasure each submain and branch duct after all have been adjusted. Continue to adjust submain and branch ducts to indicated airflows within specified
tolerances. C. Measure air outlets and inlets without making adjustments. 1. Measure terminal terminal outlets using a direct-reading hood or outlet manufacturer's written instructions
and calculating factors. D. Adjust air outlets and inlets for each space to indicated airflows within specified tolerances of indicated values. Make adjustments using branch volume dampers
rather than extractors and the dampers at air terminals. 1. Adjust each outlet in same room or space to within specified tolerances of indicated quantities without generating noise levels
above the limitations prescribed by the Contract Documents. 2. Adjust patterns of adjustable outlets for proper distribution without drafts. 3.7 PROCEDURES FOR VARIABLE-AIR-VOLUME SYSTEMS
A. Compensating for Diversity: When the total airflow of all terminal units is more than the indicated airflow of the fan, place a selected number of terminal units at a minimum set-point
airflow with the remainder at maximum-airflow condition until the total airflow of the terminal units equals the indicated airflow of the fan. Select the reduced-airflow terminal terminal
units so they are distributed evenly among the branch ducts. B. Pressure-Independent, Variable-Air-Volume Systems: After the fan systems have been adjusted, adjust the variable-air-volume
systems as follows: 1. Set outdoor-air dampers at minimum, and set return-and exhaust-air dampers at a position that simulates full-cooling load. 2. Select the terminal unit that is
most critical to the supply-fan airflow and static pressure. Measure static pressure. Adjust system static pressure so the entering static pressure for the critical terminal unit is
not less than the sum of the terminal-unit manufacturer's recommended minimum inlet static pressure plus the static pressure needed to overcome terminal-unit discharge system losses.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -9 3. Measure total system airflow. Adjust to within indicated airflow. 4. Set terminal units at maximum airflow and adjust controller
or regulator to deliver the designed maximum airflow. Use terminal-unit manufacturer's written instructions to make this adjustment. When total airflow is correct, balance the air outlets
downstream from terminal units the same as described for constant-volume air systems. 5. Set terminal units at minimum airflow and adjust controller or regulator to deliver the designed
minimum airflow. Check air outlets for a proportional reduction in airflow the same as described for constant-volume air systems. a. If air outlets are out of balance at minimum airflow,
report the condition but leave outlets balanced for maximum airflow. 6. Remeasure Remeasure the return airflow to the fan while operating at maximum return airflow and minimum outdoor
airflow. a. Adjust the fan and balance the return-air ducts and inlets the same as described for constant-volume air systems. 7. Measure static pressure at the most critical terminal
unit and adjust the static-pressure controller at the main supply-air sensing station to ensure that adequate static pressure is maintained at the most critical unit. 8. Record final
fan-performance data. 3.8 GENERAL PROCEDURES FOR HYDRONIC SYSTEMS A. Prepare test reports with pertinent design data, and number in sequence starting at pump to end of system. Check
the sum of branch-circuit flows against the approved pump flow rate. Correct variations that exceed plus or minus 5 percent. B. Prepare schematic diagrams of systems' "as-built" piping
layouts. C. Prepare hydronic systems for testing and balancing according to the following, in addition to the general preparation procedures specified above: 1. Open all manual valves
for for maximum flow. 2. Check liquid level in expansion tank. 3. Check makeup water-station pressure gage for adequate pressure for highest vent. 4. Check flow-control valves for specified
sequence of operation, and set at indicated flow. 5. Set differential-pressure control valves at the specified differential pressure. Do not set at fully closed position when pump is
positive-displacement type unless several terminal valves are kept open. 6. Set system controls so automatic valves are wide open to heat exchangers. 7. Check pump-motor load. If motor
is overloaded, throttle main flow-balancing device so motor nameplate rating is not exceeded. 8. Check air vents for a forceful liquid flow exiting from vents when manually operated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -10 3.9 PROCEDURES FOR HYDRONIC SYSTEMS A. Measure water flow at pumps. Use the following procedures except for positive-displacement
pumps: 1. Verify impeller size by operating the pump with the discharge valve closed. Read pressure differential across the pump. Convert pressure to head and correct for differences
in gage heights. Note the point on manufacturer's pump curve at zero flow and verify that the pump has the intended impeller size. a. If impeller sizes must be adjusted to achieve pump
performance, obtain approval from Engineer and comply with requirements in Division 23 Section "Hydronic Pumps." 2. Check system resistance. With all valves open, read pressure differential
across the pump and mark pump manufacturer's head-capacity curve. Measure and record system resistance with balance valve wide open. Adjust pump discharge valve until indicated water
flow is achieved. a. Monitor motor performance during procedures and do not operate motors in overload conditions. 3. Verify pump-motor brake horsepower. Calculate the intended brake
horsepower for the system based on pump manufacturer's performance data. Compare calculated brake horsepower with nameplate data on the pump motor. Report conditions where actual amperage
exceeds motor nameplate amperage. 4. Report flow rates that are not within plus or minus 10 percent of design. B. Measure flow at all automatic flow control valves to verify that valves
are functioning as designed. C. Measure flow at all pressure-independent characterized control valves, with valves in fully open position, to verify that valves are functioning as designed.
D. Set calibrated balancing valves, if installed, at calculated presettings. E. Measure flow at all stations and adjust, where necessary, to obtain first balance. 1. System components
that have Cv rating or an accurately cataloged flow-pressure-drop relationship may be used as a flow-indicating device. F. Measure flow at main balancing station and set main balancing
device, if installed, to achieve flow that is 5 percent greater than indicated flow. G. Adjust balancing stations to within specified tolerances of indicated flow rate as follows: 1.
Determine the balancing station with the highest percentage over indicated flow.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -11 2. Adjust each station in turn, beginning with the station with the highest percentage over indicated flow and proceeding to the
station with the lowest percentage over indicated flow. 3. Record settings and mark balancing devices. H. Measure pump flow rate and make final measurements of pump amperage, voltage,
pump, and motor rpm, pump heads, and systems' pressures and temperatures including outdoor-air temperature. I. Measure the differential-pressure-control-valve settings existing at the
conclusion of balancing. J. Check settings and operation of each safety valve. Record settings. 3.10 PROCEDURES FOR MOTORS A. Motors: Test at final balanced conditions and record the
following data: 1. Manufacturer's name, model number, and serial number. 2. Motor horsepower rating. 3. Motor rpm. 4. Efficiency rating. 5. Nameplate and measured voltage, each phase.
6. Nameplate and measured amperage, each phase. 7. Starter thermal-protection-element rating. B. Motors Driven by Variable-Frequency Controllers: Test for proper operation at speeds
varying from minimum to maximum. Test the manual bypass of the controller to prove proper operation. Record observations including name of controller manufacturer, model number, serial
number, and nameplate data. 3.11 PROCEDURES FOR HEAT-TRANSFER COILS A. Measure, adjust, and record the following data for each water coil: 1. Entering-and leaving-water temperature.
2. Water flow rate. 3. Water pressure drop. 4. Dry-bulb temperature of entering and leaving air. 5. Wet-bulb temperature of entering and leaving air for cooling coils. 6. Airflow. 7.
Air pressure drop.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -12 3.12 PROCEDURES FOR TESTING, ADJUSTING, AND BALANCING EXISTING SYSTEMS A. Perform a preconstruction inspection of existing equipment
that is to remain and be reused. 1. Measure and record the operating speed, airflow, and static pressure of each fan. 2. Measure motor voltage and amperage. Compare the values to motor
nameplate information. 3. Check the refrigerant charge. 4. Check the condition of filters. 5. Check the condition of coils. 6. Check the operation of the drain pan and condensate-drain
trap. 7. Check bearings and other lubricated parts for proper lubrication. 8. Report on the operating condition of the equipment and the results of the measurements taken. Report deficiencies.
B. Before performing testing and balancing of existing systems, inspect existing equipment that is to remain and be reused to verify that existing equipment has been cleaned and refurbished.
Verify the following: 1. New filters are installed. 2. Coils are clean and fins combed. 3. Drain pans are clean. 4. Fans are clean. 5. Bearings and other parts are properly lubricated.
6. Deficiencies noted in the preconstruction report are corrected. C. Perform testing and balancing of existing systems to the extent that existing systems are affected by the renovation
work. 1. Compare the indicated airflow of the renovated work to the measured fan airflows, and determine the new fan speed and the face velocity of filters and coils. 2. Verify that
the indicated airflows of the renovated work result in filter and coil face velocities and fan speeds that are within the acceptable limits defined by equipment manufacturer. 3. If calculations
increase or decrease the air flow rates and water flow rates by more than 5 percent, make equipment adjustments to achieve the calculated rates. If increase or decrease is 5 percent
or less, equipment adjustments are not required. 4. Balance each air outlet. 3.13 TEMPERATURE CONTROL VERIFICATION A. Verify that controllers are calibrated and commissioned. B. Check
transmitter and controller locations and note conditions that would adversely affect control functions.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -13 C. Record controller settings and note variances between setpoints and actual measurements. D. Verify operation of limiting controllers
(i.e., high and low temperature controllers). E. Verify free travel and proper operation of control devices such as damper and valve operators. F. Verify sequence of operation of control
devices. Note air pressures and device positions and correlate with airflow and water flow measurements. Note the speed of response to input changes. G. Confirm interaction of electrically
operated switch transducers. H. Confirm interaction of interlock and lockout systems. I. Verify main control supply air pressure and observe compressor and dryer operations. J. Record
voltages of power supply and controller output. Determine if the system operates on a ground or non-grounded power supply. K. Note operation of electric actuators using spring return
for proper fail safe operations. 3.14 TOLERANCES A. Set HVAC system's air flow rates and water flow rates within the following tolerances: 1. Supply, Return, and Exhaust Fans and Equipment
with Fans: Zero to plus 10 percent. 2. Air Outlets and Inlets: Plus or minus 5 percent. 3. Heating-Water Flow Rate: Zero to plus 5 percent. 3.15 REPORTING A. Initial Construction-Phase
Report: Based on examination of the Contract Documents as specified in "Examination" Article, prepare a report on the adequacy of design for systems' balancing devices. Recommend changes
and additions to systems' balancing devices to facilitate proper performance measuring and balancing. Recommend changes and additions to HVAC systems and general construction to allow
access for performance measuring and balancing devices. 3.16 FINAL REPORT A. General: Prepare a certified written report, tabulate and divide the report into separate sections for tested
systems and balanced systems. 1. Include a certification sheet at the front of the report's binder, signed and sealed by the certified testing and balancing engineer.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -14 2. Include a list of instruments used for procedures, along with proof of calibration. B. Final Report Contents: In addition to
certified field-report data, include the following: 1. Fan curves. 2. Manufacturers' test data. 3. Field test reports prepared by system and equipment installers. 4. Other information
relative to equipment performance; do not include Shop Drawings and product data. C. General Report Data: In addition to form titles and entries, include the following data: 1. Title
page. 2. Name and address of the TAB contractor. 3. Project name. 4. Project location. 5. Architect's name and address. 6. Engineer's name and address. 7. Contractor's name and address.
8. Report date. 9. Signature of TAB supervisor who certifies the report. 10. Table of Contents with the total number of pages defined for each section of the report. Number each page
in the report. 11. Summary of contents including the following: a. Indicated versus final performance. b. Notable characteristics of systems. c. Description of system operation sequence
if it varies from the Contract Documents. 12. Nomenclature sheets for each item of equipment. 13. Data for terminal units, including manufacturer's name, type, size, and fittings. 14.
Notes to explain why certain final data in the body of reports vary from indicated values. 15. Test conditions for fans and pump performance forms including the following: a. Settings
for outdoor-, return-, and exhaust-air dampers. b. Conditions of filters. c. Cooling coil, wet-and dry-bulb conditions. d. Face and bypass damper settings at coils. e. Fan drive settings
including settings and percentage of maximum pitch diameter. f. Inlet vane settings for variable-air-volume systems. g. Settings for supply-air, static-pressure controller. h. Other
system operating conditions that affect performance. D. System Diagrams: Include schematic layouts of air and hydronic distribution systems. Present each system with single-line diagram
and include the following:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -15 1. Quantities of outdoor, supply, return, and exhaust airflows. 2. Water and steam flow rates. 3. Duct, outlet, and inlet sizes.
4. Pipe and valve sizes and locations. 5. Terminal units. 6. Balancing stations. 7. Position of balancing devices. E. Air-Handling-Unit Test Reports: For air-handling units with coils,
include the following: 1. Unit Data: a. Unit identification.
b. Location. c. Make and type. d. Model number and unit size. e. Manufacturer's serial number. f. Unit arrangement and class. g. Discharge arrangement. h. Sheave make, size in inches
(mm), and bore. i. Center-to-center dimensions of sheave, and amount of adjustments in inches (mm). j. Number, make, and size of belts. k. Number, type, and size of filters. 2. Motor
Data: a. Motor make, and frame type and size. b. Horsepower and rpm. c. Volts, phase, and hertz. d. Full-load amperage and service factor. e. Sheave make, size in inches (mm), and bore.
f. Center-to-center dimensions of sheave, and amount of adjustments in inches (mm). 3. Test Data (Indicated and Actual Values): a. Total air flow rate in cfm (L/s). b. Total system static
pressure in inches wg (Pa). c. Fan rpm. d. Discharge static pressure in inches wg (Pa). e. Filter static-pressure differential in inches wg (Pa). f. Preheat-coil static-pressure differential
in inches wg (Pa). g. Cooling-coil static-pressure differential in inches wg (Pa). h. Heating-coil static-pressure differential in inches wg (Pa). i. Outdoor airflow in cfm (L/s). j.
Return airflow in cfm (L/s). k. Outdoor-air damper position. l. Return-air damper position.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -16 m. Vortex damper position. F. Apparatus-Coil Test Reports: 1. Test Data (Indicated and Actual Values): a. Air flow rate in cfm
(L/s). b. Average face velocity in fpm (m/s). c. Air pressure drop in inches wg (Pa). d. Outdoor-air, wet-and dry-bulb temperatures in deg F (deg C). e. Return-air, wet-and dry-bulb
temperatures in deg F (deg C). f. Entering-air, wet-and dry-bulb temperatures in deg F (deg C). g. Leaving-air, wet-and dry-bulb temperatures in deg F (deg C). G. Fan Test Reports: For
supply, return, and exhaust fans, include the following: 1. Fan Data: a. System identification. b. Location. c. Make and type. d. Model number and size. e. Manufacturer's serial number.
f. Arrangement and class. g. Sheave make, size in inches (mm), and bore. h. Center-to-center dimensions of sheave, and amount of adjustments in inches (mm). 2. Motor Data: a. Motor make,
and frame type and size. b. Horsepower and rpm. c. Volts, phase, and hertz. d. Full-load amperage and service factor. e. Sheave make, size in inches (mm), and bore. f. Center-to-center
dimensions of sheave, and amount of adjustments in inches (mm). g. Number, make, and size of belts. 3. Test Data (Indicated and Actual Values): a. Total airflow rate in cfm (L/s). b.
Total system static pressure in inches wg (Pa). c. Fan rpm. d. Discharge static pressure in inches wg (Pa). e. Suction static pressure in inches wg (Pa). H. Round, Flat-Oval, and Rectangular
Duct Traverse Reports: Include a diagram with a grid representing the duct cross-section and record the following:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -17 1. Report Data: a. System and air-handling-unit number. b. Location and zone. c. Traverse air temperature in deg F (deg C). d.
Duct static pressure in inches wg (Pa). e. Duct size in inches (mm). f. Duct area in sq. ft. (sq. m). g. Indicated air flow rate in cfm (L/s). h. Indicated velocity in fpm (m/s). i.
Actual air flow rate in cfm (L/s). j. Actual average velocity in fpm (m/s). k. Barometric pressure in psig (Pa). I. Air-Terminal-Device Reports: 1. Unit Data: a. System and air-handling
unit identification. b. Location and zone. c. Apparatus used for test. d. Area served. e. Make. f. Number from system diagram. g. Type and model number. h. Size. i. Effective area in
sq. ft. (sq. m). 2. Test Data (Indicated and Actual Values): a. Air flow rate in cfm (L/s). b. Air velocity in fpm (m/s). c. Preliminary air flow rate as needed in cfm (L/s). d. Preliminary
velocity as needed in fpm (m/s). e. Final air flow rate in cfm (L/s). f. Final velocity in fpm (m/s). g. Space temperature in deg F (deg C). J. System-Coil Reports: For reheat coils
and water coils of terminal units, include the following: 1. Unit Data: a. System and air-handling-unit identification. b. Location and zone. c. Room or riser served. d. Coil make and
size. e. Flowmeter type.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -18 2. Test Data (Indicated and Actual Values): a. Air flow rate in cfm (L/s). b. Entering-water temperature in deg F (deg C). c.
Leaving-water temperature in deg F (deg C). d. Water pressure drop in feet of head or psig (kPa). e. Entering-air temperature in deg F (deg C). f. Leaving-air temperature in deg F (deg
C). K. Instrument Calibration Reports: 1. Report Data: a. Instrument type and make. b. Serial number. c. Application. d. Dates of use. e. Dates of calibration. 3.17 INSPECTIONS A. Initial
Inspection: 1. After testing and balancing are complete, operate each system and randomly check measurements to verify that the system is operating according to the final test and balance
readings documented in the final report. 2. Check the following for each system: a. Measure airflow of at least 10 percent of air outlets. b. Measure water flow of at least 5 percent
of terminals. c. Measure room temperature at each thermostat/temperature sensor. Compare the reading to the set point. d. Verify that balancing devices are marked with final balance
position. e. Note deviations from the Contract Documents in the final report. B. Final Inspection: 1. After initial inspection is complete and documentation by random checks verifies
that testing and balancing are complete and accurately documented in the final report, request that a final inspection be made by Engineer. 2. The TAB contractor's test and balance engineer
shall conduct the inspection in the presence of Engineer of Record. 3. Engineer shall randomly select measurements, documented in the final report, to be rechecked. Rechecking shall
be limited to either 10 percent of the total measurements recorded or the extent of measurements that can be accomplished in a normal 8-hour business day.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
TESTING, ADJUSTING, AND BALANCING FOR HVAC 23 05 93 -19 4. If rechecks yield measurements that differ from the measurements documented in the final report by more than the tolerances
allowed, the measurements shall be noted as "FAILED." 5. If the number of "FAILED" measurements is greater than 10 percent of the total measurements checked during the final inspection,
the testing and balancing shall be considered incomplete and shall be rejected. C. TAB Work will be considered defective if it does not pass final inspections. If TAB Work fails, proceed
as follows: 1. Recheck all measurements and make adjustments. Revise the final report and balancing device settings to include all changes; resubmit the final report and request a second
final inspection. 2. If the second final inspection also fails, Owner may contract the the services of another TAB contractor to complete TAB Work according to the Contract Documents
and deduct the cost of the services from the original TAB contractor's final payment. D. Prepare test and inspection reports. END OF SECTION 23 05 93
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -1 SECTION 23 07 00 -HVAC INSULATION PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Insulation Materials: a. Mineral fiber. 2. Insulating cements. 3. Adhesives.
4. Mastics. 5. Sealants. 6. Factory-applied jackets. 7. Tapes. 8. Securements. 9. Corner angles. B. Related Sections: 1. Division 22 Section "Plumbing Insulation." 2. Division 23 Section
"Metal Ducts" for duct liners. 1.3 SUBMITTALS A. Product Data: For each type of product indicated. Include thermal conductivity, thickness, and jackets (both factory and field applied,
if any). Provide a scheduled listing in the submittal of each type of pipe service, service, duct service or equipment type that insulates with the thickness and jacket noted for each
service and type. B. Shop Drawings: 1. Detail application of protective shields, saddles, and inserts at hangers for each type of insulation and hanger. 2. Detail insulation application
at pipe expansion joints for each type of insulation.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -2 3. Detail insulation application at elbows, fittings, flanges, valves, and specialties for each type of insulation. 4. Detail removable insulation at piping
specialties, equipment connections, and access panels. 5. Detail application of field-applied jackets. 6. Detail application at linkages of control devices. 7. Detail field application
for each equipment type. C. Field quality-control reports. 1.4 QUALITY ASSURANCE A. Fire-Test-Response Characteristics: Insulation and related materials shall have fire-testresponse
characteristics indicated, as determined by testing identical products per ASTM E 84, by a testing and inspecting agency acceptable to authorities having jurisdiction. Factory label
insulation and jacket materials and adhesive, mastic, tapes, and cement material containers, with appropriate markings of applicable testing and inspecting agency. 1. Insulation Installed
Indoors: Flame-spread index of 25 or less, and smoke-developed index of 50 or less. 2. Insulation Installed Outdoors: Flame-spread index of 75 or less, and smoke-developed index of 150
or less. 1.5 DELIVERY, STORAGE, AND HANDLING A. Packaging: Insulation material containers shall be marked by manufacturer with appropriate ASTM standard designation, type and grade,
and maximum use temperature. B. Storage: Insulation material shall be stored to prevent dirt and moisture contamination. 1.6 COORDINATION A. Coordinate size and location of supports,
hangers, and insulation shields specified in Division 23 Section "Hangers and Supports for HVAC Piping and Equipment." B. Coordinate clearance requirements with piping Installer for
piping insulation application, duct Installer for duct insulation application, and equipment Installer for equipment insulation application. Before preparing piping and ductwork Shop
Drawings, establish and maintain clearance requirements for installation of insulation and field-applied jackets and finishes and for space required for maintenance.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -3 1.7 SCHEDULING A. Schedule insulation application after satisfactory pressure testing systems and, where required, after installing and testing heat tracing.
B. Complete installation and concealment of plastic materials as rapidly as possible in each area of construction. PART 2 -PRODUCTS 2.1 INSULATION MATERIALS A. Comply with requirements
in Part 3 schedule articles for where insulating materials shall be applied. B. Products shall not contain asbestos, lead, mercury, or mercury compounds. C. Products that come in contact
with stainless steel shall have a leachable chloride content of less than 50 ppm when tested according to ASTM C 871. D. Insulation materials for use on austenitic stainless steel shall
be qualified as acceptable according to ASTM C 795. E. Foam insulation materials shall not use CFC or HCFC blowing agents in the manufacturing process. F. Mineral-Fiber Blanket Insulation:
Mineral or glass fibers bonded with a thermosetting resin. Comply with ASTM C 553, Type II and ASTM C 1290, Type III with factory-applied FSK jacket. Factory-applied jacket requirements
are specified in "Factory-Applied Jackets" Article. 1. Products: Subject to compliance with requirements, provide one of the following: a. CertainTeed Corp.; Duct Wrap. b. Johns Manville;
Microlite. c. Knauf Insulation; Duct Wrap. d. Manson Insulation Inc.; Alley Wrap. e. Owens Corning; All-Service Duct Wrap. G. Mineral-Fiber, Preformed Pipe Insulation: 1. Products: Subject
to compliance with requirements, provide one of the following: a. Fibrex Insulations Inc.; Coreplus 1200. b. Johns Manville; Micro-Lok. c. Knauf Insulation; 1000 Pipe Insulation.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -4 d. Manson Insulation Inc.; Alley-K. e. Owens Corning; Fiberglas Pipe Insulation. 2. Type I, 850 deg F (454 deg C) Materials: Mineral or glass fibers bonded
with a thermosetting resin. Comply with ASTM C 547, Type I, Grade A, with factory-applied ASJ or with factory-applied ASJ-SSL. Factory-applied jacket requirements are specified in "Factory-Applied
Jackets" Article. 2.2 INSULATING CEMENTS A. Mineral-Fiber Insulating Cement: Comply with ASTM C 195. 1. Products: Subject to compliance with requirements, available products that may
be incorporated into the Work include, but are not limited to, the following: a. Insulco, Division of MFS, Inc.; Triple I. b. P. K. Insulation Mfg. Co., Inc.; Super-Stik. 2.3 ADHESIVES
A. Materials shall be compatible with insulation materials, jackets, and substrates and for bonding insulation to itself and to surfaces to be insulated, unless otherwise indicated.
B. Mineral-Fiber Adhesive: Comply with MIL-A-3316C, Class 2, Grade A. 1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work
include, but are not limited to, the following: a. Childers Products, Division of ITW; CP-82. b. Foster Products Corporation, H. B. Fuller Company; 85-20. c. ITW TACC, Division of Illinois
Tool Works; S-90/80. d. Marathon Industries, Inc.; 225. e. Mon-Eco Industries, Inc.; 22-25. 2. For indoor applications, use adhesive that has a VOC content of 80 g/L or less when calculated
according to 40 CFR 59, Subpart D (EPA Method 24). C. ASJ Adhesive, and FSK and PVDC Jacket Adhesive: Comply with MIL-A-3316C, Class 2, Grade A for bonding insulation jacket lap seams
and joints. 1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. Childers
Products, Division of ITW; CP-82. b. Foster Products Corporation, H. B. Fuller Company; 85-20.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -5 c. ITW TACC, Division of Illinois Tool Works; S-90/80. d. Marathon Industries, Inc.; 225. e. Mon-Eco Industries, Inc.; 22-25. 2. For indoor applications,
use adhesive that has a VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). 2.4 MASTICS A. Materials shall be compatible with insulation
materials, jackets, and substrates; comply with MIL-C-19565C, Type II. B. Vapor-Barrier Mastic: Water based; suitable for indoor and outdoor use on below ambient services. 1. Products:
Subject to compliance with requirements, provide one of the following: a. Childers Products, Division of ITW; CP-35. b. Foster Products Corporation, H. B. Fuller Company; 30-90. c. ITW
TACC, Division of Illinois Tool Works; CB-50. d. Marathon Industries, Inc.; 590. e. Mon-Eco Industries, Inc.; 55-40. f. Vimasco Corporation; 749. 2. Water-Vapor Permeance: ASTM E 96,
Procedure B, 0.013 perm (0.009 metric perm) at 43-mil (1.09-mm) dry film thickness. 3. Service Temperature Range: Minus 20 to plus 180 deg F (Minus 29 to plus 82 deg C). 4. Solids Content:
ASTM D 1644, 59 percent by volume and 71 percent by weight. 5. Color: White. 2.5 SEALANTS A. FSK and Metal Jacket Flashing Sealants: 1. Products: Subject to compliance with requirements,
available products that may be incorporated into the Work include, but are not limited to, the following: a. Childers Products, Division of ITW; CP-76-8. b. Foster Products Corporation,
H. B. Fuller Company; 95-44. c. Marathon Industries, Inc.; 405. d. Mon-Eco Industries, Inc.; 44-05. e. Vimasco Corporation; 750. 2. Materials shall be compatible with insulation materials,
jackets, and substrates. 3. Fire-and water-resistant, flexible, elastomeric sealant.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -6 4. Service Temperature Range: Minus 40 to plus 250 deg F (Minus 40 to plus 121 deg C). 5. Color: Aluminum. 6. For indoor applications, use sealants that have
a VOC content of 250 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). 2.6 FACTORY-APPLIED JACKETS A. Insulation system schedules indicate factory-applied
jackets on various applications. When factory-applied jackets are indicated, comply with the following: 1. FSK Jacket: Aluminum-foil, fiberglass-reinforced scrim with kraft-paper backing;
complying with ASTM C 1136, Type II. 2.7 TAPES A. FSK Tape: Foil-face, vapor-retarder tape matching factory-applied jacket with acrylic adhesive; complying with ASTM C 1136. 1. Products:
Subject to compliance with requirements, available products that may be incorporated incorporated into the Work include, but are not limited to, the following: a. Avery Dennison Corporation,
Specialty Tapes Division; Fasson 0827. b. Compac Corp.; 110 and 111. c. Ideal Tape Co., Inc., an American Biltrite Company; 491 AWF FSK. d. Venture Tape; 1525 CW, 1528 CW, and 1528 CW/SQ.
2. Width: 3 inches (75 mm). 3. Thickness: 6.5 mils (0.16 mm). 4. Adhesion: 90 ounces force/inch (1.0 N/mm) in width. 5. Elongation: 2 percent. 6. Tensile Strength: 40 lbf/inch (7.2 N/mm)
in width. 7. FSK Tape Disks and Squares: Precut disks or squares of FSK tape. B. Aluminum-Foil Tape: Vapor-retarder tape with acrylic adhesive. 1. Products: Subject to compliance with
requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. Avery Dennison Corporation, Specialty Tapes Division; Fasson
0800. b. Compac Corp.; 120. c. Ideal Tape Co., Inc., an American Biltrite Company; 488 AWF. d. Venture Tape; 3520 CW. 2. Width: 2 inches (50 mm). 3. Thickness: 3.7 mils (0.093 mm).
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -7 4. Adhesion: 100 ounces force/inch (1.1 N/mm) in width. 5. Elongation: 5 percent. 6. Tensile Strength: 34 lbf/inch (6.2 N/mm) in width. 2.8 SECUREMENTS A.
Bands: 1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. Childers Products;
Bands. b. PABCO Metals Corporation; Bands. c. RPR Products, Inc.; Bands. 2. Stainless Steel: ASTM A 167 or ASTM A 240/A 240M, Type 304 or Type 316; 0.015 inch (0.38 mm) thick, 3/4 inch
(19 mm) wide with wing seal . 3. Aluminum: ASTM B 209 (ASTM B 209M), Alloy 3003, 3005, 3105, or 5005; Temper H-14, 0.020 inch (0.51 mm) thick, 3/4 inch (19 mm) wide with wing seal .
B. Insulation Pins and Hangers: 1. Capacitor-Discharge-Weld Pins: Copper-or zinc-coated steel pin (or other material as required for stainless or aluminum ductwork), fully annealed for
capacitor-discharge welding, 0.135-inch-(3.5-mm-) diameter shank, length to suit depth of insulation indicated. a. Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the following: 1) AGM Industries, Inc.; CWP-1. 2) GEMCO; CD. 3) Midwest Fasteners, Inc.; CD. 4) Nelson Stud Welding;
TPA, TPC, and TPS. 2. Cupped-Head, Capacitor-Discharge-Weld Pins: Copper-or zinc-coated steel pin (or other material as required for stainless steel or aluminum duct), fully annealed
for capacitor-discharge welding, 0.135-inch-(3.5-mm-) diameter shank, length to suit depth of insulation indicated with integral 1-1/2-inch (38-mm) galvanized carbon-steel washer. a.
Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: 1) AGM Industries, Inc.;
CWP-1. 1. 2) GEMCO; Cupped Head Weld Pin. 3) Midwest Fasteners, Inc.; Cupped Head.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -8 4) Nelson Stud Welding; CHP. 3. Metal, Adhesively Attached, Perforated-Base Insulation Hangers: Baseplate welded to projecting spindle that is capable of
holding insulation, of thickness indicated, securely in position indicated when self-locking washer is in place. Comply with the following requirements: a. Products: Subject to compliance
with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: 1) AGM Industries, Inc.; Tactoo Insul-Hangers, Series T.
2) GEMCO; Perforated Base. 3) Midwest Fasteners, Inc.; Spindle. b. Baseplate: Perforated, galvanized carbon-steel sheet, 0.030 inch (0.76 mm) thick by 2 inches (50 mm) square. c. Spindle:
Fully annealed, 0.106-inch-(2.6-mm-) diameter shank, length to suit depth of insulation indicated. d. Adhesive: Recommended by hanger manufacturer. Product with demonstrated capability
to bond insulation hanger securely to substrates indicated without damaging insulation, hangers, and substrates. 4. Insulation-Retaining Washers: Self-locking washers formed from 0.016-inch-(0.41-mm)
thick, sheet, with beveled edge sized as required to hold insulation securely in place but not less than 1-1/2 inches (38 mm) in diameter. a. Products: Subject to compliance with requirements,
available products that may be incorporated into the Work include, but are not limited to, the following: 1) AGM Industries, Inc.; RC-150. 2) GEMCO; R-150. 3) Midwest Fasteners, Inc.;
WA-150. 4) Nelson Stud Welding; Speed Clips. b. Protect ends with capped self-locking washers incorporating a spring steel insert to ensure permanent retention of cap in exposed locations.
5. Nonmetal Insulation-Retaining Washers: Self-locking washers formed from 0.016-inch-(0.41-mm-) thick nylon sheet, with beveled edge sized as required to hold insulation securely in
place but not less than 1-1/2 inches (38 mm) in diameter. a. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but
are not limited to, the following: 1) GEMCO. 2) Midwest Fasteners, Inc.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -9 C. Staples: Outward-clinching insulation staples, nominal 3/4-inch-(19-mm-) wide, stainless steel or Monel. D. Wire: 0.062-inch (1.6-mm) soft-annealed, stainless
steel. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the
following: a. C & F Wire. b. Childers Products. c. PABCO Metals Corporation. d. RPR Products, Inc. 2.9 CORNER ANGLES A. Aluminum Corner Angles: 0.040 inch (1.0 mm) thick, minimum 1 by
1 inch (25 by 25 mm), aluminum according to ASTM B 209 (ASTM B 209M), Alloy 3003, 3005, 3105 or 5005; Temper H-14. PART 3 -EXECUTION 3.1 EXAMINATION A. Examine substrates and conditions
for compliance with requirements for installation and other conditions affecting performance of insulation application. 1. Verify that systems and equipment to be insulated have been
tested and are free of defects. 2. Verify that surfaces to be insulated are clean and dry. 3. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2
PREPARATION A. Surface Preparation: Clean and dry surfaces to receive insulation. Remove materials that will adversely affect insulation application. B. Mix insulating cements with clean
potable water; if insulating cements are to be in contact with stainless-steel surfaces, use demineralized water. C. Surface Preparation: Clean and prepare surfaces to be insulated.
Before insulating, apply a corrosion coating to insulated surfaces as follows:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -10 1. Carbon steel: Coat carbon steel operating at a service temperature below 60 deg F with an epoxy coating. Consult coating manufacturer for appropriate
coating materials and application methods for operating temperature range. 3.3 GENERAL INSTALLATION REQUIREMENTS A. Install insulation materials, accessories, and finishes with smooth,
straight, and even surfaces; free of voids throughout the length of equipment, ducts and fittings, and piping including fittings, valves, and specialties. B. Install insulation materials,
forms, vapor barriers or retarders, jackets, and thicknesses required for each item of equipment, duct system, and pipe system as specified in insulation system schedules. C. Install
accessories compatible with insulation materials and suitable for the service. Install accessories that do not corrode, soften, or otherwise attack insulation or jacket in either wet
or dry state. D. Install insulation with longitudinal seams at top and bottom of horizontal runs. E. Install multiple layers of insulation with longitudinal and end seams staggered.
F. Do not weld brackets, clips, or other attachment devices to piping, fittings, and specialties. G. Keep insulation materials dry during application and finishing. H. Install insulation
with tight longitudinal seams and end joints. Bond seams and joints with adhesive recommended by insulation material manufacturer. I. Install insulation with least number of joints practical.
J. Where vapor barrier is indicated, seal joints, seams, and penetrations in insulation at hangers, supports, anchors, and other projections with vapor-barrier mastic. 1. Install insulation
continuously through hangers and around anchor attachments. 2. For insulation application where vapor barriers are indicated, extend insulation on anchor legs from point of attachment
to supported item to point of attachment to structure. Taper and seal ends at attachment to structure with vapor-barrier mastic. 3. Install insert materials and install insulation to
tightly join the insert. Seal insulation to insulation inserts with adhesive or sealing compound recommended by insulation material manufacturer. 4. Cover inserts with jacket material
matching adjacent pipe insulation. Install shields over jacket, arranged to protect jacket from tear or puncture by hanger, support, and shield. K. Apply adhesives, mastics, and sealants
at manufacturer's recommended coverage rate and wet and dry film thicknesses.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -11 L. Install insulation with factory-applied jackets as follows: 1. Draw jacket tight and smooth. 2. Cover circumferential joints with 3-inch-(75-mm-) wide
strips, of same material as insulation jacket. Secure strips with adhesive and outward clinching staples along both edges
of strip, spaced 4 inches (100 mm) o.c. 3. Overlap jacket longitudinal seams at least 1-1/2 inches (38 mm). Install insulation with longitudinal seams at bottom of pipe. Clean and dry
surface to receive self-sealing lap. Staple laps with outward clinching staples along edge at 2 inches (50 mm) o.c. a. For below ambient services, apply vapor-barrier mastic over staples.
4. Cover joints and seams with tape as recommended by insulation material manufacturer to maintain vapor seal. 5. Where vapor barriers are indicated, apply vapor-barrier mastic on seams
and joints and at ends adjacent to duct and pipe flanges and fittings. M. Cut insulation in a manner to avoid compressing insulation more than 75 percent of its nominal thickness. N.
Finish installation with systems at operating conditions. Repair joint separations and cracking due to thermal movement. O. Repair damaged insulation facings by applying same facing
material over damaged areas. Extend patches at least 4 inches (100 mm) beyond damaged areas. Adhere, staple, and seal patches similar to butt joints. P. For above ambient services, do
not install insulation to the following: 1. Vibration-control devices. 2. Testing agency labels and stamps. 3. Nameplates and data plates. 4. Manholes. 5. Handholes. 6. Cleanouts. 3.4
PENETRATIONS A. Insulation Installation at Interior Wall and Partition Penetrations (That Are Not Fire Rated): Install insulation continuously through walls and partitions. B. Insulation
Installation at Fire-Rated Wall and Partition Penetrations: Install insulation continuously through penetrations of fire-rated walls and partitions. Terminate insulation at fire damper
sleeves for fire-rated wall and partition penetrations. Externally insulate damper sleeves to match adjacent insulation and overlap duct insulation at least 2 inches (50 mm).
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -12 1. Comply with requirements in Division 7 Section "Firestopping" and fire-resistive joint sealers. C. Insulation Installation at Floor Penetrations: 1. Duct:
Install insulation continuously through floor penetrations that are not fire rated. For penetrations through fire-rated assemblies, terminate insulation at fire damper sleeves and externally
insulate damper sleeve beyond floor to match adjacent duct insulation. Overlap damper sleeve and duct insulation at least 2 inches (50 mm). 2. Pipe: Install insulation continuously through
floor penetrations. 3. Seal penetrations through fire-rated assemblies. Comply with requirements in Division 7 Section "Firestopping." 3.5 GENERAL PIPE INSULATION INSTALLATION A. Requirements
in this article generally apply to all insulation materials except where more specific requirements are specified in various pipe insulation material installation articles. B. Insulation
Installation on Fittings, Valves, Strainers, Flanges, and Unions: 1. Install insulation over fittings, valves, strainers, flanges, unions, and other specialties with continuous thermal
and vapor-retarder integrity, unless otherwise indicated. 2. Insulate pipe elbows using preformed fitting insulation or mitered fittings made from same material and density as adjacent
pipe insulation. Each piece shall be butted tightly against adjoining piece and bonded with adhesive. Fill joints, seams, voids, and irregular surfaces with insulating cement finished
to a smooth, hard, and uniform contour that is uniform with adjoining pipe insulation. 3. Insulate tee fittings with preformed fitting insulation or sectional pipe insulation of same
material and thickness as used for adjacent pipe. Cut sectional pipe insulation to fit. Butt each section closely to the next and hold in place with tie wire. Bond pieces with adhesive.
4. Insulate valves using preformed fitting insulation or sectional pipe insulation of same material, density, and thickness as used for adjacent pipe. Overlap adjoining pipe insulation
by not less than two times the thickness of pipe insulation, or one pipe diameter, whichever is thicker. For valves, insulate up to and including the bonnets, valve stuffing-box studs,
bolts, and nuts. Fill joints, seams, and irregular surfaces with insulating cement. 5. Insulate strainers using preformed fitting insulation or sectional pipe insulation of same material,
density, and thickness as used for adjacent pipe. Overlap adjoining pipe insulation by not less than two times the thickness of pipe insulation, or one pipe diameter, whichever is thicker.
Fill joints, seams, and irregular surfaces with insulating cement. Insulate strainers so strainer basket flange or plug can be easily removed and replaced without damaging the insulation
and jacket. Provide a removable reusable insulation cover. For below ambient services, provide a design that maintains vapor barrier.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -13 6. Insulate flanges and unions using a section of oversized preformed pipe insulation. Overlap adjoining pipe insulation by not less than two times the thickness
of pipe insulation, or one pipe diameter, whichever is thicker. 7. Cover segmented insulated surfaces with a layer of finishing cement and coat with a mastic. Install vapor-barrier mastic
for below ambient services and a breather mastic for above ambient services. Reinforce the mastic with fabric-reinforcing mesh. Trowel the mastic to a smooth and well-shaped contour.
8. For services not specified to receive a field-applied jacket except for flexible elastomeric and polyolefin, install fitted PVC cover over elbows, tees, strainers, valves, flanges,
and unions. Terminate ends with PVC end caps. Tape PVC covers to adjoining insulation facing using PVC tape. 9. Stencil or label the outside insulation jacket of each union with the
word "UNION." Match size and color of pipe labels. C. Insulate instrument connections for thermometers, pressure gages, pressure temperature taps, test connections, flow meters, sensors,
switches, and transmitters on insulated pipes, vessels, and equipment. Shape insulation at these connections by tapering it to and around the connection with insulating cement and finish
with finishing cement, mastic, and flashing sealant. D. Install removable insulation covers at locations indicated. Installation shall conform to the following: 1. Make removable flange
and union insulation from sectional pipe insulation of same thickness as that on adjoining pipe. Install same insulation jacket as adjoining pipe insulation. 2. When flange and union
covers are made from sectional pipe insulation, extend insulation from flanges or union long at least two times the insulation thickness over adjacent pipe insulation on each side of
flange or union. Secure flange cover in place with stainlesssteel or aluminum bands. Select band material compatible with insulation and jacket. 3. Construct removable valve insulation
covers in same manner as for flanges except divide the two-part section on the vertical center line of valve body. 4. When covers are made from block insulation, make two halves, each
consisting of mitered blocks wired to stainless-steel fabric. Secure this wire frame, with its attached insulation, to flanges with tie wire. Extend insulation at least 2 inches (50
mm) over adjacent pipe insulation on each side of valve. Fill space between flange or union cover and pipe insulation with insulating cement. Finish cover assembly with insulating cement
applied in two coats. After first coat is dry, apply and trowel second coat to a smooth finish. 5. Unless a PVC jacket is indicated in field-applied jacket schedules, finish exposed
surfaces with a metal jacket. 3.6 MINERAL-FIBER INSULATION INSTALLATION A. Insulation Installation on on Straight Pipes and Tubes:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -14 1. Secure each layer of preformed pipe insulation to pipe with wire or bands and tighten bands without deforming insulation materials. 2. Where vapor barriers
are indicated, seal longitudinal seams, end joints, and protrusions with vapor-barrier mastic and joint sealant. 3. For insulation with factory-applied jackets on above ambient surfaces,
secure laps with outward clinched staples at 6 inches (150 mm) o.c. 4. For insulation with factory-applied jackets on below ambient surfaces, do not staple longitudinal tabs but secure
tabs with additional adhesive as recommended by insulation material manufacturer and seal with vapor-barrier mastic and flashing sealant. B. Insulation Installation on Pipe Flanges:
1. Install preformed pipe insulation to outer diameter of pipe flange. 2. Make width of of insulation section same as overall width of flange and bolts, plus twice the thickness of pipe
insulation. 3. Fill voids between inner circumference of flange insulation and outer circumference of adjacent straight pipe segments with mineral-fiber blanket insulation. 4. Install
jacket material with manufacturer's recommended adhesive, overlap seams at least 1 inch (25 mm), and seal joints with flashing sealant. C. Insulation Installation on Pipe Fittings and
Elbows: 1. Install preformed sections of same material as straight segments of pipe insulation when available. 2. When preformed insulation elbows and fittings are not available, install
mitered sections of pipe insulation, to a thickness equal to adjoining pipe insulation. Secure insulation materials with wire or bands. D. Insulation Installation on Valves and Pipe
Specialties: 1. Install preformed sections of same material as straight segments of pipe insulation when available. 2. When preformed sections are not available, install mitered sections
of pipe insulation to valve body. 3. Arrange insulation to permit access to packing and to allow valve operation without disturbing insulation. 4. Install insulation to flanges as specified
for flange insulation application. E. Blanket Insulation Installation on Ducts and Plenums: Secure with adhesive and insulation pins. 1. Apply adhesives according to manufacturer's recommended
coverage rates per unit area, for minimum 50 percent coverage of duct and plenum surfaces. 2. Apply adhesive to entire bottom surface of ducts and to all surfaces of fittings and transitions.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -15 3. Install either capacitor-discharge-weld pins and speed washers or cupped-head, capacitordischarge-weld pins on sides and bottom of horizontal ducts and
sides of vertical ducts as follows: a. On exposed ductwork where no ceiling is installed, on all duct sizes, place pins along longitudinal centerline of duct on both duct sides and on
the duct bottom. Space 3 inches (75 mm) maximum from insulation end joints, and 16 inches (400 mm) o.c. b. On concealed ductwork, on duct with dimensions larger than 24 inches, place
pins 16 inches (400 mm) o.c. each way, and 3 inches (75 mm) maximum from insulation joints. Install pins on any side or the bottom with dimension greater than 24”. Install additional
pins to hold insulation tightly against surface at cross bracing. c. Pins may be omitted from top surface of horizontal, rectangular ducts and plenums. d. Do not overcompress insulation
during installation. e. Impale insulation over pins and attach speed washers. f. Cut excess portion of pins extending beyond speed washers or bend parallel with insulation surface. Cover
exposed pins and washers with tape matching insulation facing. 4. For ducts and plenums with surface temperatures below ambient, install a continuous unbroken vapor barrier. Create a
facing lap for longitudinal seams and end joints with insulation by removing 2 inches (50 mm) from 1 edge and 1 end of insulation segment. Secure laps to adjacent insulation section
with 1/2-inch (13-mm) outward-clinching staples, 1 inch (25 mm) o.c. Install vapor barrier tape at each joint. Vapor barrier consisting of factory-or field-applied jacket, adhesive,
vapor-barrier mastic, and sealant may be used at joints, seams, and protrusions in lieu of vapor barrier tape. a. Repair punctures, tears, and penetrations with tape or mastic to maintain
vaporbarrier seal. b. Install vapor stops for ductwork and plenums operating below 50 deg F (10 deg C) at 18-foot (5.5-m) intervals. Vapor stops shall consist of vapor-barrier mastic
applied in a Z-shaped pattern over insulation face, along butt end of insulation, and over the surface. Cover insulation face and surface to be insulated a width equal to 2 times the
insulation thickness but not less than 3 inches (75 mm). 5. Overlap unfaced blankets a minimum of 2 inches (50 mm) on longitudinal seams and end joints. At end joints, secure with steel
bands spaced a maximum of 18 inches (450 mm) o.c. 6. Install insulation on rectangular duct elbows and transitions with a full insulation section for each surface. Install insulation
on round and flat-oval duct elbows with individually mitered gores cut to fit the elbow. 7. Insulate duct stiffeners, hangers, and flanges that protrude beyond insulation surface with
6-inch-(150-mm-) wide strips of same material used to insulate duct. Secure on alternating sides of stiffener, hanger, and flange with pins spaced 6 inches (150 mm) o.c. 8. Insulate
the external side of diffusers as noted on the details.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -16 3.7 FIELD QUALITY CONTROL A. Perform tests and inspections. B. All insulation applications will be considered defective Work if sample inspection reveals
noncompliance with requirements. 3.8 DUCT INSULATION SCHEDULE, GENERAL A. Plenums and Ducts Requiring Insulation: 1. Indoor, concealed supply air. 2. Indoor, concealed return located
in non-conditioned space. B. Items Not Insulated: 1. Fibrous-glass ducts. 2. Factory-insulated flexible ducts. 3. Factory-insulated plenums and casings. 4. Flexible connectors. 5. Vibration-control
devices. 6. Factory-insulated access panels and doors. 3.9 INDOOR DUCT AND PLENUM INSULATION SCHEDULE A. Concealed, rectangular, round and flat oval, supply air duct insulation shall
be the following: 1. Mineral-Fiber Blanket: 2 inches (50 mm) minimum thick and 0.75-lb/cu. ft. (12-kg/cu. m) or 1.0-lb/cu. ft. (24-kg/cu. m) nominal density to achieve a minimum installed
(at 25% compression) R value of 6.0 at 75 deg F. mean temperature. B. Concealed, rectangular, round and flat oval, return air duct insulation shall be the following: 1. Mineral-Fiber
Blanket: 1-1/2 inches minimum thick and 0.75-lb/cu. ft. (12-kg/cu. m) or 1.0-lb/cu. ft. (18-kg/cu. m) nominal density to achieve a minimum installed R value of 3.5 at 75 deg F. 3.10
PIPING INSULATION SCHEDULE, GENERAL A. Acceptable preformed pipe and tubular insulation materials and thicknesses are identified for each piping system and pipe size range. If more than
one material is listed for a piping system, selection from materials listed is Contractor's option.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC INSULATION 23 07 00 -17 B. Items Not Insulated: Unless otherwise indicated, do not install insulation on the following: 1. Drainage piping located in crawl spaces. 2. Underground
piping. 3. Chrome-plated pipes and fittings unless there is a potential for personnel injury. C. Heating Water Supply and Return, 200 Deg F (93 Deg C) and below: 1. NPS 1-1/2 and Smaller:
Insulation shall be the following: a. Mineral-Fiber, Preformed Pipe, Type I: 1 inch (25 mm) thick. 2. NPS 2 and Larger: Insulation shall be one of the following: a. Mineral-Fiber, Preformed
Pipe, Type I: 2 inches thick. END OF SECTION 23 07 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -1 (ELECTRIC/ELECTRONIC/DDC) SECTION 23 09 01 – ENVIRONMENTAL CONTROL SYSTEM (ELECTRIC/ELECTRONIC/DDC) PART 1 -GENERAL 1.1 WORK DESCRIPTION A. Scope
of Work: 1. Furnish, install complete, program, and place in totally acceptable operation an environmental control system as shown or implied on the Contract Documents. B. Work Included:
1. Furnish and install pneumatic and direct digital control temperature, controls and accessories as required to provide a complete operable system to obtain the operational sequence
described. 2. All control and interlock wiring by Environmental Control Contractor and to be in full compliance with all sections of electrical specifications. 3. Environmental Control
Contractor shall prepare electric flow diagram on all controls, starters, and mechanical equipment detailing all terminals in each component. 4. Any relays or auxiliary contacts required,
not furnished by suppliers of mechanical equipment or starters shall be furnished by Environmental Control Contractor. 5. Note that schematic control diagrams on drawings are presented
to show the intent of all control loops and to illustrate the operational sequences described. The electric signals are diagrammatic only and each bidder shall be required to furnish
such wires and air lines as required to meet their specific equipment. ECC is directed to building drawings and all schedules for complete coordination of project requirements. 6. All
standards of quality and operation shown, described and implied to be fully met. Any questions relative to deviations to be submitted in writing to the Architect/Engineer at least 14
days prior to bid date. 7. This Contractor/Supplier is directed to all General Conditions of the Contract. C. Work Not Included: 1. Electrical Contractor shall provide all power wiring
to to and from all motor starters and motor control centers. 2. Electrical Contractor to provide 120/60 power where directed. 3. Mechanical Contractor to install all control valves furnished
by the Environmental Control Contractor. D. Related Work Specified Elsewhere: 1. Basic Mechanical Materials and Methods. 2. Hangers and Supports.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -2 (ELECTRIC/ELECTRONIC/DDC) 3. Mechanical Identification. 4. Testing, Adjusting and Balancing. 5. Enclosed Switches and Circuit Breakers. 6. Enclosed
Controllers. 7. Motor Control Centers. 1.2 QUALITY ASSURANCE A. Acceptable Control Supplier/Engineering Contractor: 1. Johnson Controls, Inc. B. Acceptable Installation and Service Contractor:
1. Johnson Controls, Inc. C. The entire electric, electronic and direct digital control system shall be approved and listed by Underwriters Laboratories, Inc. All equipment and panels
shall bear the appropriate UL listing marking to insure compliance. Listing compliance shall include but not be limited to UL864. D. Except where certain controls are specified by manufacturer
and product numbers (and no substitute is permitted in those cases), all products shall be of a common manufacturer and no mixing of manufacturers is permitted. It should be noted that
all quality requirements noted in this specification shall be equally met; any variance shall be submitted in writing 14 days prior to bidding and, if approved, notice will be given
in writing. Failure to meet the 14-day requirement will negate any consideration of variance. E. All engineering, project management, system commissioning, and service shall be performed
by experienced full-time professional employees of the Control Supplier/Engineering Contractor. Installation of all electric, electronic, and DDC controls including all electric wiring
shall be the responsibility of the Installation Contractor. Installation may be subcontracted at the Contractor's discretion, but full and complete responsibility for the quality and
workmanship rests with the Installation Contractor. Where work is subcontracted, the Installation Contractor shall make a complete inspection before the system is placed in operation
to insure that all sections of Part 3 -Execution are met and such documentation shall be made a part of the final operation and maintenance manuals. F. The Control Supplier/Engineering
Contractor shall have a minimum of 15 years of experience in the design and installation of Environmental Control Systems equal in scope and size to that herein specified and shall be
prepared to provide documented proof of such history. Contractor to be full factory branch or provide written proof that control manufacturer assumes full liability for any product fault
or defect. G. Service and installation personnel to be permanently located within 100 miles of job site and to be available 24 hours each day within 4 hours' notice. Contractors who
rely on third party vendors for maintenance/service staff and expertise on any major component are not acceptable.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -3 (ELECTRIC/ELECTRONIC/DDC) H. The intent of the contractual division between the "Supplier/Engineering Contractor" and the "Control Installation
Contractor" is that under the former shall be supplied 100% of the control material and complete engineering drawings incorporating panels with numbered terminal strips along with an
engineering inspection of the final installation. This shall also include all system commissioning and service during the warranty period. Under the installation contract shall be supplied
all air piping and electrical communication networks to make the system 100% operative. 1.3 SUBMITTALS A. Product: 1. Submit descriptive literature and shop drawings in accordance with
Section 01300. 2. Submittals shall include the following data: a. Dimensions. b. Installation instructions. c. Product description and operational capacities. B. Shop Drawings: 1. Submit
shop drawings to the Architect/Engineer which show: a. Full schematic presentation of all systems with location of all sensors, relays, dampers, valves, and actuators. All components
to be designated to a code similar to Engineer's design on HPE drawings. b. Full wiring diagrams with point to point designation. Number, size, and type of wiring with designation as
to exact enclosure and support to be clearly noted. c. All DDC analog and binary points to be cross referenced to the same code designation (AI-X, AO-X, BI-X, and BO-X) shown on Engineer's
HPE drawings. d. All operating systems shall include the sequence of operation that will be employed. This will parallel, as a minimum, the sequence detailed on Engineer's HPE drawings.
e. All pneumatic sensing and activating air lines to be clearly denoted with sizing and reference to specified installation standards. 2. ECC to schedule a presubmittal presentation
of all proposed formal submittal diagrams and data with A/E prior to said formal submittal. This meeting shall be scheduled and conducted at BSA LifeStructures' Indianapolis office.
C. Maintenance Manuals: 1. Submit maintenance and operating manuals in accordance with Section 01730.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -4 (ELECTRIC/ELECTRONIC/DDC) D. Owner Instruction and Training Report: 1. Submit the written "Owner Instruction and Training Report" in accordance
with Part 3.01.D. of this specification section. 1.4 SEQUENCE OF OPERATION A. Note that all operational sequences are noted on the plans. PART 2 -PRODUCTS 2.1 EQUIPMENT A. Control Instruments:
1. All control instruments, unless otherwise specified, shall be fully proportioning with adjustable sensitivity. Note that P, PI, and PID loops shall be required wherever necessary
to afford final stable control within acceptable parameters to satisfaction of Architect/Engineer. B. Temperature Thermostats: 1. Space sensors for control of VAV/CAV terminal boxes
shall have exposed external adjustment in private offices and locked areas. In other areas, adjustment to be concealed. Adjustment to be plus and minus 4 from the null. All instruments
to have brushed stainless steel covers with thermometers where external adjustment is utilized and concealed adjustment elsewhere. C. Valves: 1. Valves shall be normally open or closed
as required by the application. All valves shall fail in the system "safe" position. 2. All valves, unless specified otherwise, to be fully modulating. Packing to be self-sealing V ring
design arranged to tighten the seal as water pressure increases, thus eliminating manual packing adjustment. All actuators to incorporate 100% surplus torque to allow full closing under
100% increase in system water. Valve bodies to be 125 psig bronze with inner plugs such that sizing is accomplished for a 5 psig pressure drop on water service and afford total linear
control. 3. Terminal box valves: a. Terminal box valves to be fully modulating ball or globe type, normally open except in animal room or where identified otherwise or where 3-way type
is noted on drawings, actuator having 200 percent torque with inserts for Cv characteristics to match design fluid flow. (ECC to note that valves having Cv ratings greater
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -5 (ELECTRIC/ELECTRONIC/DDC) than 10 percent variance with actual flow requirements are not acceptable.) Valve to fail at point of last position.
D. Air Supply: 1. Control air is to be taken from the existing JCO control air main run from the existing duplex air compressors with a 3/8” copper main and a separate 50-20 psig PRV
with air gauges and shut off valve. E. Operators Workstation Existing JCI to be utilized to monitor exhaust fans denoted): 1. The Operators Workstation shall provide direct communications
with all DDC controllers and other sensing and alarm points. 2. Basic interface description: a. Command entry/menu selection process: Operator interface software shall minimize operator
training through the use of English language prompting and English language point identification. b. Text-based displays: The Operator interface shall provide consistent text-based displays
of all system point and application data described in this specification. Point identification, engineering units, status indication, and application naming conventions shall be the
same at all operator devices. c. Password protection: Multiple-level password access protection shall be provided to allow the user/manager to limit control, display, and database manipulation
capabilities as he deems appropriate for each user, based upon an assigned password. 1) A minimum of four passwords shall be supported at each digital panel. 2) Operators will be able
to perform only those commands available for their respective passwords. Menu selections displayed at any operator device shall be limited to only those items defined for the access
level of the password used to log-on. d. Operator commands: The operator interface shall allow the operator to perform commands including, but not limited to, the following: 1) Start-up
or shutdown selected equipment. 2) Adjust set points. 3) Add/modify/delete time programming. 4) Enable/disable process execution. 5) Lock/unlock alarm reporting for each point. 6) Enable/disable
totalization for each point. 7) Enable/disable trending. 8) Enter temporary override schedules. 9) Define holiday schedules. 10) Change time/data. 11) Enter/modify analog alarm limits.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -6 (ELECTRIC/ELECTRONIC/DDC) 12) Enable/disable demand limiting. 13) Enable/disable duty cycle. e. Logs and summaries: Reports shall be generated
manually and directed to the displays. As a minimum, the system shall allow the user to easily obtain the following types of reports. -A general listing of all points in the network.
-List all points currently in alarm. -List of all off-line points. -List all points currently in override status. -List all Weekly Schedules. -List all Holiday Programming. Summaries
shall be provided for specific points, for a logical point group, for a user-selected group or groups, or for the entire facility without restriction due to the hardware configuration
of the facility management system. Under no conditions shall the operator need to specify the address of hardware controller to obtain system information. 3. Dynamic color graphic displays:
Color graphic floor plan displays and system schematics for each piece of mechanical equipment, including air handling units, chilled water systems, and hot water boiler systems, shall
be provided to optimize the system performance analysis and speed alarm recognition. All software engineering required to construct the graphics to be included under this contract. a.
System selection/penetration: The operator interface shall allow users to access the various system schematics and floor plans via a graphical penetration scheme, menu selection, or
text-based commands. b. Dynamic data displays: Dynamic temperature values, humidity values, flow values, and status indication shall be shown in their actual respective locations and
shall automatically update to represent current conditions without operator intervention. c. Graphics definition package: Graphic generation software shall be provided to allow the user
to add, modify, or delete system graphic displays. 1) This Contractor shall provide libraries of pre-engineered screens and symbols depicting standard air handling unit components (e.g.,
fans, cooling coils, filters, dampers, etc.), complete mechanical systems (e.g., constant volume-terminal reheat, VAV, etc.) and electrical symbols. 2) The graphic development package
shall use a mouse or similar pointing device in conjunction with a drawing program to allow the user to perform the following: -Define symbols. -Position and size symbols. -Define background
screens. -Define connecting lines and curves. -Locate, orient, and size descriptive text. -Define and display colors for all elements.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -7 (ELECTRIC/ELECTRONIC/DDC) -Establish correlation between symbols or text and associated. system points or other displays. 3) Graphic displays
can be created to represent any logical grouping of system points or calculated data based upon building function, mechanical system, building layout, or any other logical grouping of
points which aids the operator in the analysis of the facility. To accomplish this, the user shall be able to build graphic displays that include point data from multiple application
specific controllers. 4. Existing JCI OWs: a. The exhaust fans so noted to be wired into the existing OWS to denote when the fan is on or off. b. This contract shall tie in the exhaust
fans that will allow them to be turned on and off, but no other service of the existing BAS is is required. F. VAV/CAV Terminal Unit Control Components (DDC Control): Cost of Mounting
1. Component Furnished By Mounting & Wiring Power Supply Disconnect Switch Mfr. Mfr. Mfr. Damper Actuator Mfr. Mfr. Mfr. Flow Controller Mfr. Mfr. Mfr. Flow Sensing Ring Mfr. Mfr. Mfr.
Reheat Valve Body ECC MC MC Reheat Valve Actuator ECC ECC ECC Space Thermostat ECC ECC ECC Discharge Temperature Sensor ECC ECC ECC Misc. Accessories ECC ECC ECC ECC -Environmental Controls
Contractor Mfr. -Box Manufacturer (a) -Power Supply by EC as specified 2. Factory testing of components is acceptable as negotiated between ECC and Box Manufacturer, but full operational
responsibility rests with ECC who performs final operational testing on job site in company with Test and Balance Contractor. PART 3 -EXECUTION 3.1 INSTALLATION A. Instrumentation Mounting:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -8 (ELECTRIC/ELECTRONIC/DDC) 1. All sensing capillaries on coils shall be rigidly supported as directed by the Architect/Engineer to prevent capillary
vibration and to accurately sense coil temperature. 2. All sensors except where installed in finished areas shall have bakelite plates identifying their function keyed to control schematics.
3. Room thermostats shall be installed where shown on the Drawings. These components shall not be installed between a light switch and doorway when they are co-located on the Drawings.
These components shall be installed at a height of 48" above finished floor to the bottom, unless indicated otherwise. 4. All controllers and control panels shall utilize mounting support
that insures no vibration from the structure or mechanical equipment. Back boxes or backing panels are required as appropriate. Where walls are plaster or drywall, channels shall be
utilized screwed to studs with laminated panel facing to support instruments or control panels; all such assemblies to be crafted to present easy access to controls. Proper engraved
identification nameplates are required. 5. ECC is responsible to coordinate with Mechanical, Sheet Metal, and Electrical Contractors the proper location of all air, water, and steam
measurements and control components to insure that sizing and locations meet all manufacturer’s standards for maximum accuracy of sensing and control. Instances where piping or duct
sizing and location need be modified from what is shown on drawings to achieve required accuracy shall be brought to designer’s attention prior to bidding; failure to so notify designer
requires ECC to accommodate required field modifications. 6. All instrument operating assemblies for all controllers, readout components, and safety devices shall be installed at eye
level in locations that are easily accessible to maintenance and operating personnel. Locations such as those on remote sides of air handling units or other mechanical systems are not
acceptable. B. Electrical Wiring: 1. Under this division, furnish and install interlock, LAN, sensor, and actuator wiring. Connect controls in accordance with approved wiring diagrams.
Install wiring inside panels to terminal strips. 2. Configure LAN as either a bus, star, or combination of the two. Use twisted pair, coax, or fiberoptic cable to meet noise immunity
and/or distance requirements. Design system for data transfer rate of no less than 1 megabaud. LAN wiring requires shielded cable. All LAN wiring must meet supplier's standards of operation
and quality. a. Use Belden No. 22 gage or larger Beldfoil or equal for runs up to 250 feet. b. Use Belden No. 18 gage or larger Beldfoil or equal for runs 250 feet to 500 feet. c. All
input/output wiring shall have sufficient strength to meet all operational requirements. 3. Sensor wiring over 50 feet, where run in a common conduit or near inductive loads, shall be
shielded cable. a. Use Belden No. 24 gage or larger Beldfoil or equal for runs up to 100 feet. b. Use Belden No. 18 gage or larger Beldfoil or equal for runs up to 500 feet.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -9 (ELECTRIC/ELECTRONIC/DDC) c. All input/output wiring shall have sufficient strength to meet all operational requirements. 4. Install all control
and interlock wiring in addition to low voltage sensor and LAN wiring in accordance with local requirements, the National Electrical Code and Division 16000 of project specifications.
5. Installation minimum requirements: a. Mechanical and service areas plus any areas without finished ceilings: All wiring including cables in EMT. b. Space sensors and alarms: All wiring
and cables in EMT within wall construction. c. Ceiling returns (accessible or drop ceilings -ducted returns): Approved nonplenum cable. d. Ceilings (open returns): Approved plenum-rated
cable. e. Ceiling returns (non-accessible): EMT or code compliant equal solid conduit. f. Inside air handling units: All wiring including cables in EMT or code compliant equal solid
conduit. g. Note that the use of cable is limited to low voltage service less than 24 volt only. h. In no case shall cables be allowed to lay on ceiling grid. i. Note that all conduit
junctions and terminations shall utilize compression fittings. j. Installation of all cabling in ceilings and walls shall be run in a professional workmanlike fashion acceptable to Architect/Engineer
. Cables to be supported with tie wraps such that droop and sag is within acceptable degrees and shall be securely fastened to fixed members of the building structure at sufficient points
to avoid excessive freedom of movement. 6. Grounding: a. Provide suitable grounding for all digital equipment. b. Install a separate ground to earth using existing water piping or a
copper rod driven into the ground as indicated by the equipment manufacturer. In no situation may the ground be connected to the building neutral conductors, either at the breaker or
at the main feeder entrance to the building (no exceptions). 7. Transient Protection: a. All electronic equipment including processors, relays, monitoring devices, temperature sensors,
and other non-computerized solid state equipment will be adequately protected against power line transients or RFI interference. All components to meet IEEE/ANSI standards. b. Equipment
that fails to operate properly due to transient or other electrical interference, in the opinion of the Engineer, will be required to be retrofitted with the appropriate protection device(s).
c. Provide an isolation transformer as a separate component, on the 110 VAC power supply to the digital controllers to protect all controllers to manufacturer's requirements.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -10 (ELECTRIC/ELECTRONIC/DDC) 8. All control wiring must be routed in EMT separate from any power feed wiring. 9. The sizing type and provision
of cable, conduit, cable trays, and trunking shall be the design responsibility of the ECC. If complications arise, however, due to the incorrect selection of cable, cable trays, trunking,
and/or conduit by the ECC, the Contractor shall be responsible for all costs incurred in replacing the selected components. 10. Note that any disconnect switches between variable frequency
drives and operating motors shall be interlocked such that drive inverter returns to zero position when motor is disconnected. Interlock wiring between disconnect and VFD by EC. Refer
to Specifications Sections 262923 and 262816. C. General: 1. Any penetration of an air handling unit enclosure for passage of tubing, conduit, or sensing elements shall be sealed with
an appropriate grommet and caulked. 2. Contractor to insure that all instruments requiring reset or field adjustment are mounted with the operating heads located on the exterior of air
handling units in positions of ready access. In instances of rooftop assemblies, all such devices to be inside unit enclosures with access via manufacturer's access panels. D. Services:
1. The services of a qualified representative of the Control Contractor shall be provided to check the installation, startup of system and instruct the Owner's maintenance personnel
in the care and proper operation of the system. This shall require the Contractor to demonstrate the installed accuracy of all controlled variables as herein detailed, i.e., a. All temperature,
pressure, humidity and flow sensors, controllers, alarms, relays, and safety devices. b. All actuators functioning with control loops. All actuators to be demonstrated for complete travel
from full open to full closure; all actuators to have 200% power for intended functionality. c. All hardware and software of all DDC controllers and BAS control loops. d. Current sensors
to be field calibrated to insure alarm status on loss of electrical power or loss of drive sheaves or belts. e. Other control features installed as part of the contract and as requested
by Design Engineer. 2. The Installation and Service Contractor shall provide the Owner with 24 hours of instruction and training. This shall be done as follows: a. Job completion – 16
hours. b. 30 days later – 8 hours. 3. A written report shall be submitted to the Architect/Engineer Project Engineer detailing condition and operation of Environmental Control System
after target points D.2. (a) and (b).
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENVIRONMENTAL CONTROL SYSTEM 23 09 01 -11 (ELECTRIC/ELECTRONIC/DDC) E. Warranty: 1. At completion of final test of installation and acceptance by Owner, provide any service incidental
to proper performance for a period of 24 months. 2. Warrant equipment for 24 months for defects in workmanship and material under normal use and service. During warranty period, replace
or repair, free of charge, equipment proven to be defective in workmanship or material. 3. Certain electronic devices not manufactured by the Environmental Control Supplier, such as
computers, printers, and CRTs display, shall carry the same warranty as above. Pass any registration and warranty documents and warranty rights to the Owner. 4. All valve and damper
actuators to carry a warranty of 60 months after project acceptance. Warranty to cover both labor and material without exception. 5. Control Supplier/Engineering Contractor to provide
written documentation of availability of repair parts for all material installed under this contract for a period of 60 months after project acceptance. In the event a component is obsolete,
it shall be replaced with the new generation at no cost to the Owner. END OF SECTION 23 09 01
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -1 SECTION 23 21 13 -HYDRONIC PIPING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes piping, fittings and joining materials, joining methods, special-duty valves,
and hydronic specialties for heating water systems. 1.3 SUBMITTALS A. Product Data: For each type of valve and hydronic specialty indicated. Include flow and pressure drop curves based
on manufacturer's testing for diverting fittings, calibrated balancing valves, and automatic flow-control valves. Indicate materials and joining methods for each piping system in the
submittal. B. Shop Drawings: Detail fabrication of pipe anchors, hangers, special pipe support assemblies, alignment guides, expansion joints and loops, and their attachment to the building
structure. Detail location of anchors, alignment guides, and expansion joints and loops. Provide pipe coating submittal as required by Section "HVAC Insulation." C. Field Test Reports:
Written reports of tests specified in Part 3 of this Section. Include the following: 1. Test procedures used. 2. Test results that comply with requirements. 3. Failed test results and
corrective action taken to achieve requirements. D. Maintenance Data: For hydronic specialties and valves (including air control devices, hydronic specialties, expansion tanks, and special
duty valves) to include in maintenance manuals specified in Division 1. 1.4 QUALITY ASSURANCE A. Welding: Qualify processes and operators according to the ASME Boiler and Pressure Vessel
Code: Section IX, "Welding and Brazing Qualifications."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -2 B. ASME Compliance: Comply with ASME B31.9, "Building Services Piping," for materials, products, and installation. Safety valves and pressure vessels shall
bear the appropriate ASME label. Fabricate and stamp air separators and expansion tanks to comply with the ASME Boiler and Pressure Vessel Code, Section VIII, Division 1. C. Steel Support
Welding: Qualify processes and operators according to AWS D1.1/D1.1M "Structural Welding Code-Steel." 1.5 COORDINATION A. Coordinate layout and installation of hydronic piping and suspension
system components with other construction, including light fixtures, HVAC equipment, ductwork, plumbing, firesuppression-system components, and partition assemblies. B. Coordinate pipe
sleeve installations for foundation wall penetrations. C. Coordinate piping installation with roof curbs, equipment supports, and roof penetrations. D. Coordinate pipe fitting pressure
classes with products specified in related Sections. E. Coordinate size and location of concrete bases. F. Coordinate installation of pipe sleeves for penetrations through exterior walls
and floor assemblies. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Calibrated Balancing
Valves: a. Armstrong Pumps, Inc. b. Flow Design, Inc. c. Griswold Controls. d. ITT Bell & Gossett; ITT Fluid Technology Corp. e. MEPCO. f. Nexus. g. Preso. h. Taco, Inc. i. Tour and
Anderson.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -3 2. Hydronic Accessories (air vents, strainers): a. Amtrol. b. Amstrong Pumps, Inc. c. ITT Bell and Gossett; ITT Fluid Technology Corporation. d. Metraflex.
e. Mueller. 2.2 PIPING MATERIALS AND SYSTEM COMPONENTS A. General: Refer to Part 3 "Piping Applications" Article for applications of pipe and fitting materials. B. Hydronic piping components
and installation shall be selected to be suitable for the following minimum non-shock working pressures and temperatures: 1. Heating water: 125 psig, 225 deg F. C. System components
shall be rated for no less than that specified herein regardless of maximum working pressures and temperatures listed above. Select components with higher component ratings than those
listed herein as required to be suitable for working pressures and temperatures above. 2.3 COPPER TUBE AND FITTINGS A. Drawn-Temper Copper Tubing: ASTM B 88, Type L (ASTM B 88M, Type
B). B. Annealed-Temper Copper Tubing: ASTM B 88, Type K (ASTM B 88M, Type A). C. DWV Copper Tubing: ASTM B 306, Type DWV. D. Wrought-Copper Fittings: ASME B16.22. E. Wrought-Copper Unions:
ASME B16.22. F. Brazing Filler Metals: AWS A5.8, BCuP Series, copper phosphorous alloys for joining copper with copper; or BAg-1, silver alloy for joining copper with bronze or steel.
G. Flanges: Cast bronze of same pressure classification as connected piping system. 2.4 STEEL PIPE AND FITTINGS A. Steel Pipe, NPS 2 (DN 50) and Smaller: ASTM A53/A53M, Type F (furnace-butt
welded), Grade B, Schedule 40, black steel, plain ends.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -4 B. Steel Pipe, NPS 2-1/2 through NPS 10 (DN 65 through DN 250): ASTM A53/A53M, Type E (electric-resistance welded), Grade B, Schedule 40, black steel, plain
ends. C. Steel Pipe, NPS 12 through NPS 20 (DN 300 through DN 500): ASTM A53/A53M, Type E (electric-resistance welded) or Type S (seamless), Grade B, Standard weight, black steel, plain
ends. D. Steel Pipe Nipples: ASTM A 733, made of ASTM A53/A53M, Schedule 40, black steel; seamless for NPS 2 (DN 50) and smaller and electric-resistance welded for NPS 2-1/2 (DN 65)
and larger. E. Cast-Iron Threaded Fittings: ASME B16.4; Classes 125 and 250. F. Malleable-Iron Threaded Fittings: ASME B16.3, Classes 150 and 300. G. Malleable-Iron Unions: ASME B16.39;
Classes 150, 250, and 300. H. Cast-Iron Pipe Flanges and Flanged Fittings: ASME B16.1, Classes 125, and 250; raised ground face, and bolt holes spot faced. I. Wrought-Steel Fittings:
ASTM A 234/A 234M, wall thickness to match adjoining pipe. J. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated. K. Wrought Cast-and Forged-Steel Flanges
and Flanged Fittings: ASME B16.5, including bolts, nuts, and gaskets of the following material group, end connections, and facings: 1. Material Group: 1.1. 2. End Connections: Butt welding
or utilize slip-on flanges with multiple pass inner fillet weld radiused up to inside pipe diameter. 3. Facings: Raised face. L. Grooved Mechanical-Joint Fittings: ASTM A 536, Grade
65-45-12 ductile iron; ASTM A 47 (ASTM A 47M), Grade 32510 malleable iron; ASTM A 53, Type F, E, or S, Grade B fabricated steel; or ASTM A 106, Grade B steel fittings with grooves or
shoulders designed to accept grooved end couplings. M. Grooved Mechanical-Joint Couplings: Ductile-or malleable-iron housing and synthetic rubber gasket of central cavity pressure-responsive
design; with nuts, bolts, locking pin, locking toggle, or lugs to secure grooved pipe and fittings. Victaulic style 07 rigid coupling with type "E" EPDM gasket. N. Welding Materials:
Comply with Section II, Part C, of the ASME Boiler and Pressure Vessel Code for welding materials appropriate for wall thickness and for chemical analysis of pipe being welded.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -5 O. Gasket Material: Thickness, material, and type suitable for the chemical and thermal conditions of the fluid to be handled and design temperatures and
pressures. 2.5 PLASTIC PIPE AND FITTINGS A. PVC Plastic Pipe: ASTM D 1785, Schedules 40 and 80, plain ends. B. PVC Plastic Pipe Fittings: Socket-type pipe fittings, ASTM D 2466 for Schedule
40 pipe; ASTM D 2467 for Schedule 80 pipe. 1. PVC Solvent Cement: ASTM D 2564. 2.6 VALVES A. Gate, globe, check, ball, and butterfly valves are specified in Division 23 Section "Valves."
B. Refer to Part 3 "Valve Applications" Article for applications of each valve. C. Calibrated Balancing Valves, NPS 2 (DN 50) and Smaller: Cast bronze or forged brass body, ball or plug
type, minimum 125-psig CWP (860-kPa) working pressure, 250 deg F (121 deg C) maximum maximum operating temperature, TFE or PTFE seats and having threaded ends. Valves shall have calibrated
orifice and be full shut off, connections for portable differential pressure meter with integral seals, equipped with setting indication and a memory stop to retain set position, integral
points to register degree of valve position and preformed polyurethane insulation cover. Size to pass design flow at 85% of full open position with 12" wg pressure drop and an accuracy
of 5%. Utilize 1/2" calibrated ball valve line size when there is a choice of the proper flow range in two different body sizes and then utilize 1/2" by 3/4" increases to the coil,
control valve, or piping as required. D. Calibrated Balancing Valves, NPS 2-1/2 (DN 65) and Larger: Cast-iron or steel body, ball plug or globe type, minimum 125-psig CWP (860-kPa) working
pressure, 250 deg F (121 deg C) maximum operating temperature, and having flanged connections. Valves shall have calibrated orifice or venturi, connections for portable differential
pressure meter with integral seals, and be equipped with setting indication and a memory stop to retain set position. Size to pass design flow at 85% of full open position with 12" wg
pressure drop and an accuracy of 5%. 2.7 HYDRONIC SPECIALTIES A. Manual Air Vent: Bronze body and nonferrous internal parts; 150-psig (1035-kPa) working pressure; 225 deg F (107 deg
C) operating temperature; manually operated with screwdriver or thumbscrew; with NPS 1/8 (DN 6) discharge connection and NPS 1/2 (DN 15) inlet connection. B. Automatic Air Vent: Designed
to vent automatically with float principle; bronze body and nonferrous internal parts; 150-psig (1035-kPa) working pressure; 240 deg F (116 deg C)
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -6 operating temperature; with NPS 1/4 (DN 8) discharge connection and NPS 1/2 (DN 15) inlet connection. C. Y-Pattern Strainers: 1. Threaded Connections: 400-psig
(1,725-kPa) working water pressure; cast-iron body (ASTM A 126, Class B) in steel piping, bronze body in copper tubing, threaded connections for NPS 2 (DN 50) and smaller, No. 20 mesh
(1/31” openings), tapped blowoff plug. 2. Flanged Connections: 150-psig and 300-psig working water pressure to match pump construction; cast iron body (ASTM A126, Class B), flanged ends
for NPS 2-1/2 and larger, 1/16” mesh through 4” NPS, 1/8” mesh larger than 4” NPS, bolted cover flange with tapered seats, tapped blowoff plug. PART 3 -EXECUTION 3.1 PIPING APPLICATIONS
A. Heating Water, NPS 2 (DN 50) and Smaller: Above ground, use Type L (Type B) drawntemper copper tubing with brazed joints. Below ground or within slabs, use Type K (Type A) annealed-temper
copper tubing with brazed joints for sizes 1” through 2”. Use the fewest possible joints below ground and within floor slabs. Tubing shall be 3/4" minimum (including runouts to 1/2"
control valves) unless noted otherwise. Tubing size 3/4" only shall be soldered. B. Heating Water, NPS 2-1/2 (DN 65) and Larger: Standard weight steel pipe with welded and flanged joints
or Type L (Type B) drawn temper copper tubing with brazed joints. Victaulic couplings and fittings are an acceptable option. 3.2 VALVE APPLICATIONS A. General-Duty Valve Applications:
Unless otherwise indicated, use the following valve types: 1. Shutoff Duty: Gate, ball, and butterfly valves. B. Install shutoff duty valves at each branch connection to supply mains,
at supply connection to each piece of equipment, unless only one piece of equipment is connected in the branch line and branch line is less than 30 lineal feet long. C. Install calibrated
balancing valves in the return water line of each heating or cooling element, on constant speed pump discharges, at multiple bank coils, and elsewhere as required to facilitate system
balancing. Install calibrated balancing valves at the floor return main connection to a shaft riser where the floor main is 2” NPS and larger.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -7 D. Combination type calibrated balance valve consisting of: Strainer, drain valves, pressure/temperature ports, vent, shutoff valve shall be utilized at terminal
box reheat coils and only with an additional shutoff valve in addition to the combination balance valve installed. 3.3 PIPING INSTALLATIONS A. Refer to Division 23 Section "Common Work
Results for HVAC" for basic piping installation requirements including the use of fittings and dielectrics. B. Drawing plans, schematics and diagrams indicate general location and arrangement
of piping systems. Indicated piping locations and arrangements as such were used to size pipe and calculate friction loss, expansion,
pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved. C. Install piping in concealed locations unless otherwise indicated
and except in equipment rooms and service areas. D. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls.
Diagonal runs are prohibited unless specifically indicated otherwise. E. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal. F. Install piping
to permit valve servicing. G. Install groups of pipes parallel to each other, spaced to permit applying insulation and servicing of valves. H. Install drains, consisting of a tee fitting,
NPS 3/4 (DN 20) ball valve, and short NPS 3/4 (DN 20) threaded nipple with cap, at low points in piping system mains and elsewhere as required for system drainage. Install a drain on
each floor of the building in the heating water system and pipe the drain discharge to housekeeping closet mop sink. I. Install piping at a uniform grade of 1” in 40’-0” upward in direction
of non-gravity flow except condensate drain piping shall slope 1/8” in 1’-0” in the direction of discharge. Provide uniform slope on condensate drain piping runs. J. Install solder connections
in otherwise all-brazed tubing systems at threaded fitting adapters. K. Reduce pipe sizes using eccentric reducer fitting installed with level side up. L. Unless otherwise indicated,
install all branch connections to mains using tee fittings in main pipe, with the takeoff coming out the bottom of the main pipe. For up-feed risers, install the takeoff coming out the
top of the main pipe. Branch connections to terminal units (size 3/4" and 1") shall connect to the main pipe (top, side or bottom) as required for the best accessibility to piped components
and terminal unit.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -8 M. Install strainers on supply side of each control valve, pressure-reducing valve, solenoid valve, in-line pump, and elsewhere as indicated. Install NPS
3/4 (DN 20) nipple and ball valve in blowdown connection of strainers NPS 2 (DN 50) and larger. Match size of strainer blowoff connection for strainers smaller than NPS 2 (DN 50). N.
Anchor piping for proper direction of expansion and contraction. O. Maintain manufacturer’s recommended straight pipe upstream and downstream from each flow measuring device installation.
P. Unless otherwise indicated, install long radius elbows (radius equals 1.5 times diameter) for iron and steel piping. Q. Install valves according to Division 23 Section "General Duty
Valves for HVAC Piping." R. Install unions in piping, NPS 2 (DN 50) and smaller, adjacent to valves at final connections of equipment and elsewhere as indicated. S. Install flanges in
piping, NPS 2-1/2 (DN 65) and larger at final connections of equipment and elsewhere as indicated. T. Install expansion loops, expansion joints, anchors and pipe alignment guides as
specified in Division 23 Section "Expansion Fittings and Loops for HVAC Piping." U. Identify piping as specified in Division 23 Section "Identification for HVAC Piping and Equipment."
V. Install protective coating on the installed cold service piping if required by Division 23 Section "HVAC Insulation." W. Paint interior and exterior piping as noted on the drawings
and as specified in Division 9 Sections. 3.4 HANGERS AND SUPPORTS A. Hanger, support and anchor devices as specified in Division 23 Section "Hangers and Supports for HVAC Piping and
Equipment." Comply with requirements below for maximum spacing of supports. B. Seismic restraints are specified in Division 23 Section "Vibration and Seismic Controls for HVAC Piping
and Equipment." Equipment." C. Install the following pipe attachments: 1. Adjustable steel clevis hangers for heating water horizontal piping less than NPS 4” (DN100) and all other hydronic
piping.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -9 2. Adjustable roller hangers for hot water heating horizontal piping NPS 4” (DN 100) and larger. 3. Pipe Roller (where required): MSS SP-58, Type 44 for multiple
horizontal piping supported on a trapeze. D. Install hangers for steel piping with the following maximum spacing and minimum rod sizes: 1. NPS 3/4 (DN 20) – 1 (DN 25): Maximum span,
7 feet (2.1 m); minimum rod size, 1/4 inch (6.4 mm). 2. NPS 1-1/2 (DN 40): Maximum span, 9 feet (2.7 m); minimum rod size, 3/8 inch (10 mm). 3. NPS 2 –3 (DN 80) (DN 50): Maximum span,
10 feet (3 m); minimum rod size, 3/8 inch (10 mm). 4. NPS 4 (DN-100) –6 (DN 150): Maximum span, 10 feet (3 m); minimum rod size, 1/2 inch (13 mm). 5. NPS 8 (DN 200): Maximum span, 10
feet (3 m); minimum rod size, 5/8 inch (16 mm). 6. NPS 10 (DN 250): Maximum span, 10 feet ((3 m); minimum rod size, 3/4 inch (19 mm). 7. NPS 12 (DN 300): Maximum span, 10 feet (3 m);
minimum rod size, 7/8 inch (22 mm). 8. NPS 14 (DN 350) -16 (DN 400): Maximum span, 10 feet (3 m); minimum rod size, 1 inch (25 mm). 9. NPS 18 –20 (DN 450): Maximum span, 10 feet (3 m);
minimum rod size, 1-1/4 inches (32 mm). E. Install hangers for drawn-temper copper piping with the following maximum spacing and minimum rod sizes: 1. NPS 3/4 (DN 20): Maximum span,
5 feet (1.5 m); minimum rod size, 1/4 inch (6.4 mm). 2. NPS 1 (DN 25): Maximum span, 6 feet (1.8 m); minimum rod size, 1/4 inch (6.4 mm). 3. NPS 1-1/2 (DN 40): Maximum span, 8 feet (2.4
m); minimum rod size, 3/8 inch (10 mm). 4. NPS 2 (DN 50): Maximum span, 8 feet (2.4 m); minimum rod size, 3/8 inch (10 mm). 5. NPS 2-1/2 (DN 65): Maximum span, 9 feet (2.7 m); minimum
rod size, 3/8 inch (10 mm). 6. NPS 3 (DN 80): Maximum span, 10 feet (3 m); minimum rod size, 3/8 inch (10 mm). F. Plastic Piping Hanger Spacing: Space hangers according to pipe manufacturer's
written instructions for service conditions. Avoid point loading. Space and install hangers with the fewest practical rigid anchor points. G. Support vertical runs at roof and at each
floor and at 10 foot intervals between floors. 3.5 PIPE JOINT CONSTRUCTION A. Refer to Division 23 Section "Common Work Results for HVAC" for joint construction requirements for soldered
and brazed joints in copper tubing; threaded, welded, and flanged joints in steel piping; and solvent-welded joints for PVC and CPVC piping.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -10 3.6 HYDRONIC SPECIALTIES INSTALLATION A. Install manual air vents at high points in piping, at heat-transfer coils, and elsewhere as required for system
air venting. B. Install automatic air vents in mechanical equipment rooms only at high points of system piping, at heat-transfer coils, and elsewhere as required for system air venting.
C. Install strainers on the inlet side of each control valve, pressure reducing or regulating valve, and as shown on the Drawings with blowdown piping with ball valve and capped nipple
or extend to nearest drain as noted on the Drawings. 3.7 TERMINAL EQUIPMENT CONNECTIONS A. Size for supply and return piping connections shall not be smaller than equipment connections.
B. Install control valves, venturis, and temperature sensing wells in accessible locations locations close to connected equipment. C. Install ports for pressure and temperature gages
at coil inlet and outlet connections. 3.8 FIELD QUALITY CONTROL A. Prepare hydronic piping according to ASME B31.9 and as follows: 1. Leave joints, including welds, uninsulated and exposed
for examination during test. 2. Provide temporary restraints for expansion joints that cannot sustain reactions due to test pressure. If temporary restraints are impractical, isolate
expansion joints from testing. 3. Flush system with clean water. Clean strainers. 4. Isolate equipment from piping. If a valve is used to isolate equipment, its closure shall be capable
of sealing against test pressure without damage to valve. Install blinds in flanged joints to isolate equipment. 5. Install safety valve, set at a pressure no more than one-third higher
than test pressure, to protect against damage by expanding liquid or other source of overpressure during test. B. Perform the following tests on hydronic piping: 1. Use ambient temperature
water as a testing medium unless there is risk of damage due to freezing. Another liquid that is safe for workers and compatible with piping may be used. 2. While filling system, use
vents installed at high points of system to release trapped air. Use drains installed at low points for complete draining of liquid. 3. Check expansion tanks to determine that they are
not air bound and that system is full of water. Submit final air pressure as a field test report.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -11 4. Subject piping system to hydrostatic test pressure that is not less than 1.5 times the design pressure noted in Part 2 of this specification. Test pressure
shall not exceed maximum pressure for any vessel, pump, valve, or other component in system under test. Isolate pressure vessels (air separators, expansion tanks, heat exchangers, etc.)
as appropriate. Verify that stress due to pressure at bottom of vertical runs does not exceed either 90 percent of specified minimum yield strength or 1.7 times "SE" value in Appendix
A of ASME B31.9, "Building Services Piping." 5. After hydrostatic test pressure has been applied for at least 10 minutes, examine piping, joints, and connections for leakage. Eliminate
leaks by tightening, repairing, or replacing components and repeat hydrostatic test until there are no leaks. 6. Prepare written report of testing. Submit test reports. 3.9 ADJUSTING
A. Mark calibrated nameplates of pump discharge valves after hydronic system balancing has been completed, to permanently indicate final balanced position. B. Perform these adjustments
before operating the system: 1. Open valves to fully open position. Close coil bypass valves. 2. Check pump for proper direction of rotation. 3. Set automatic fill valves for required
system pressure. 4. Check air vents at high points of system and determine if all are installed and operating freely (automatic type), or bleed air completely (manual type). 5. Set temperature
controls so all coils are calling for full flow. 6. Check operation of automatic bypass valves. 7. Check and set operating temperatures of boilers, chillers, and cooling towers to design
requirements. 8. Lubricate motors and bearings. 3.10 FINAL SYSTEM CLEANING AND CHECKOUT A. After balancing of the entire system is complete and the system has been run at maximum controlled
temperature for eight hours, perform the following: 1. Remove and clean or replace all strainer screens. 2. Operate all manual air vents to remove trapped air. 3. Confirm automatic air
vents are functioning. 4. Operate all relief and safety valves. 5. Check system precharge, makeup pressure and relief valve settings. 6. Confirm that all ASME data sheets are provided
to the Owner’s maintenance staff. 7. Confirm that water treatment coupon racks and filters are installed.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HYDRONIC PIPING 23 21 13 -12 8. Confirm that all reheat valves are fully closed where there is no call for heat at the terminal unit. END OF SECTION 23 21 13
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -1 SECTION 23 31 13 -METAL DUCTS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes metal ducts for supply, return, outside, and exhaust air-distribution systems in pressure
classes from minus 2-to plus 10-inch wg. Metal ducts include the following: 1. Rectangular ducts and fittings. 2. Single-wall, round and flat-oval spiral-seam ducts and formed fittings.
3. Sheet metal materials. 4. Sealants and gaskets. 5. Hangers and supports. 6. Seismic restraint devices. B. Related Sections include the following: 1. Division 23 Section "Duct Accessories"
for dampers, sound-control devices, ductmounting access doors and panels, turning vanes, and flexible ducts. 2. Division 23 Section "Testing, Adjusting and Balancing for HVAC" for testing,
adjusting and balancing requirements for metal ducts. 3. Division 23 Section "Vibration and Seismic Controls for HVAC Piping and Equipment" for seismic hazard levels. 1.3 SYSTEM DESCRIPTION
A. Duct system design, as indicated, has been used to select size and type of air-moving and -distribution equipment and other air system components. Changes to layout or configuration
of duct system must be specifically approved in writing by Architect. Accompany requests for layout modifications with calculations showing that proposed layout will provide original
design results without increasing system total pressure. B. Structural Performance: Duct hangers and supports and seismic restraints shall withstand the effects of gravity and seismic
loads and stresses within limits and under conditions described in
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -2 SMACNA’s "HVAC Duct Construction Standards – Metal and Flexible" and SMACNA’s "Seismic Restraint Manual: Guidelines for Mechanical Systems." C. Airstream Surfaces:
Surfaces in contact with the airstream shall comply with requirements in ASHRAE 62.1-2004. 1.4 SUBMITTALS A. Product Data: For each type of the following products: 1. Liners and adhesives.
2. Sealants and gaskets. 3. Seismic restraint devices. B. Shop Drawings: CAD-generated and drawn at minimum 1/4” = 1’-0” scale. Shop drawings shall include the following: 1. Fabrication,
assembly, and installation, including plans, elevations, sections, components, and attachments to other work. 2. Duct layout indicating sizes and pressure classes. 3. Elevations of top
and bottom of ducts along with applicable elevations of structural elements. 4. Dimensions of main duct runs from building grid lines. 5. Fittings. 6. Reinforcement and spacing. 7. Seam
and joint construction. 8. Penetrations through fire-rated and other partitions. 9. Equipment installation based on equipment being used on Project. 10. Duct accessories, including access
doors and panels. 11. Hangers and supports, including methods for duct and building attachment, vibration isolation, and seismic restraints. 12. Ceiling suspension assembly members.
13. Other systems installed in same space as ducts. 14. Ceiling and wall-mounting access doors and panels required to provide access to dampers and other operating devices. 15. Ceiling-mounting
items, including lighting fixtures, diffusers, grilles, speakers, sprinklers, access panels, and special moldings. 16. Shop drawings shall be submitted prior to the fabrication or installation
of the ductwork and serve as the foundation for coordination between the various trades to maintain required ceiling heights. C. Field Test Reports: Written reports of tests specified
in Part 3 of this Section. Include the following: 1. Test procedures used. 2. Test results that comply with requirements.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -3 3. Failed test results and corrective action taken to achieve requirements. D. Coordination Drawings: Plans, drawn to scale, on which the following items are
shown and coordinated with each other, using input from installers of the items involved: 1. Duct installation in congested spaces, indicating coordination with general construction,
building components, and other building services. Indicate proposed changes to duct layout. Include plumbing, piping, electrical, and other building systems components including, but
not limited to, roof drain piping, sanitary piping, plumbing piping, heating and cooling water piping, condensate drains, steam and condensate return piping, conduit cable tray, etc.
2. Suspended ceiling components. 3. Structural members to which duct will be attached. 4. Size and and location of initial access modules for acoustical tile. 5. Penetrations of smoke
barriers and fire-rated construction. 6. Items penetrating finished ceiling including the following: a. Lighting fixtures. b. Air outlets and inlets. c. Speakers. d. Sprinklers. e. Access
panels. f. Perimeter moldings. E. Leak Testing Documentation: Contractor shall submit a written report to the authorities having jurisdiction which documents that 100% of the ducts designed
at static pressures in excess of 3” wg have been leak tested and that the air leakage class of less than 6.0 (see Energy Code). Provide duplicate submittal to the Owner and the Engineer.
1.5 QUALITY ASSURANCE A. NFPA Compliance: 1. NFPA 90A, "Installation of Air Conditioning and Ventilating Systems." 2. NFPA 90B, "Installation of Warm Air Heating and Air Conditioning
Systems." B. Welding Qualifications: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code -Steel," for hangers and supports, AWS D1.2/D1.2M, "Structural
Welding Code -Aluminum," for aluminum supports, AWS D9.1M/D9.1, "Sheet Metal Welding Code," for duct joint and seam welding. C. Welding Qualifications: Qualify procedures and personnel
according to the following: 1. AWS D1.1/D1.1M, "Structural Welding Code -Steel," for hangers and supports. 2. AWS D1.2/D1.2M, "Structural Welding Code -Aluminum," for aluminum supports.
3. AWS D9.1M/D9.1, "Sheet Metal Welding Code," for duct joint and seam welding.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -4 D. ASHRAE Compliance: Applicable requirements in ASHRAE 62.1-2004, Section 5 -"Systems and Equipment," and Section 7 -"Construction and System Start-Up." E. ASHRAE/IESNA
Compliance: Applicable requirements in ASHRAE/IESNA 90.1-2004, Section 6.4.4 -"HVAC System Construction and Insulation." 1.6 DELIVERY, STORAGE, AND HANDLING A. Store all ductwork and
associated ductwork components to prevent damage and to prevent entrance of dirt, debris, and moisture. B. Support all ductwork and associated ductwork components to prevent sagging
or bending. C. Provide temporary storage, delivery and handling in accordance with the SMACNA Duct Cleanliness Standard level specified herein. PART 2 -PRODUCTS 2.1 SINGLE WALL RECTANGULAR
DUCTS AND FITTINGS A. Fabricate ducts, elbows, transitions, offsets, branch connections, and other construction according to SMACNA's "HVAC Duct Construction Standards--Metal and Flexible"
and complying with requirements for metal thickness, reinforcing types and intervals, tie-rod applications, and joint types and intervals. 1. Lengths: Fabricate rectangular ducts in
lengths appropriate to reinforcement and rigidity class required for pressure class. 2. Deflection: Duct systems shall not exceed deflection limits according to SMACNA's "HVAC Duct Construction
Standards--Metal and Flexible." 3. Minimum sheet metal gage shall be 24. 4. Utilize radius elbows with centerline radius equal to 1.5 times the width unless specifically shown otherwise
on the drawings. 5. Square throat elbows where specifically shown on the drawings shall include turning vanes for all applications (supply, return, exhaust, relief, outdoor air, etc.)
except grease hood duct. 6. Utilize SMACNA Figure 4-6, 45 degree entry branch connections with a minimum "L" dimension of six inches or one quarter of "W" whichever is greater. B. Transverse
Joints: Prefabricated slide-on joints and components constructed using manufacturer's guidelines for material thickness, reinforcement size and spacing, and joint reinforcement, or roll
formed flange connection system TDC or TDF according to "SMACNA HVAC Duct Construction Standards – Metal and Flexible" maximum 24 inches long duct section whenever any side exceeds 96
inches.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -5 1. Manufacturers: a. Ductmate Industries, Inc. b. Nexus Inc. c. Ward Industries, Inc. C. Formed-On Flanges: Construct according to SMACNA's "HVAC Duct Construction
Standards--Metal and Flexible," Figure 1-4, using corner, bolt, cleat, and gasket details. 1. Manufacturers: a. Ductmate Industries, Inc. b. Lockformer. 2. Duct Size: Maximum 30 inches
wide and up to 2-inch wg pressure class. 3. Longitudinal Seams: Pittsburgh lock sealed with non-curing polymer sealant. D. Cross Breaking or Cross Beading: Cross break or cross bead
duct sides 19 inches and larger and 0.0359 inch thick or less, with more than 10 sq. ft. of non-braced panel area unless ducts are lined. Cross break or cross bead all pressure class
duct even where SMACNA Figure 2-9 says you do not need to. 2.2 SINGLE WALL, ROUND AND FLAT-OVAL, SPIRAL-SEAM DUCTS AND FORMED FITTINGS A. Diameter as applied to flat-oval ducts in this
Article is the diameter of a round duct with a circumference equal to the perimeter of a given size of flat-oval duct. B. Round, Spiral Lock-Seam Ducts: Fabricate supply ducts of galvanized
steel according to SMACNA's "HVAC DUCT Construction Standards—Metal and Flexible." 1. Minimum sheet metal gage shall be 24. 2. Mechanically fasten ducts by means of at least three sheet
metal screws spaced in approximately uniform intervals along the circumference of the ducts. C. Flat-Oval, Spiral Lock-Seam Ducts: Fabricate supply ducts according to SMACNA's "HVAC
Duct Construction Standards—Metal and Flexible." Fabricate ducts larger than 72 inches in diameter with butt-welded longitudinal seams. 1. Manufacturers: a. Eastern Sheet Metal. b. Foremost.
c. JTD Spiral. d. LaPine. e. Lindab, Inc.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -6 f. McGill Airflow LLC. g. SEMCO Incorporated. D. Duct Joints: 1. Ducts up to 20 Inches in Diameter: Interior, center-beaded slip coupling, sealed before and after
fastening, attached with sheet metal screws. 2. Ducts 21 to 72 Inches in diameter: Three-piece, gasketed, flanged joint consisting of two internal flanges with sealant and one external
closure band with gasket. 3. Ducts Larger Than 72 Inches in Diameter: Companion angle flanged joints per SMACNA "HVAC Duct Construction Standards—Metal and Flexible," Figure 3-2. 4.
Round Ducts (Optional): Prefabricated connection system consisting of double-lipped, EPDM rubber gasket. Manufacture ducts according to connection system manufacturer's tolerances. a.
Manufacturers: 1) Ductmate Industries, Inc. 2) Lindab Inc. 5. Flat-Oval Ducts: Prefabricated connection system consisting of two flanges and one synthetic rubber gasket. a. Manufacturers:
1) Ductmate Industries, Inc. 2) Lindab, Inc. 3) McGill Airflow LLC 4) SEMCO. E. Conical Tees, 90-Degree Tees, 45-Degree Laterals, Bellmouths and 45-Degree Entry Tees: Fabricate to comply
with SMACNA's "HVAC Duct Construction Standards—Metal and Flexible," with metal thicknesses specified for longitudinal-seam straight ducts. F. Diverging-Flow Fittings: Fabricate with
reduced entrance to branch taps and with no excess material projecting from fitting onto branch tap entrance. G. Fabricate elbows using die-formed, gored, pleated, or mitered construction.
Centerline bend radius of die-formed, gored, and pleated elbows shall be 1-1/2 times duct diameter. Unless elbow construction type is indicated, fabricate elbows as follows: 1. Mitered-Elbow
Radius and Number of Pieces: Welded construction complying with SMACNA's "HVAC Duct Construction Standards—Metal and Flexible," unless otherwise indicated. 2. Round Mitered Elbows: Welded
construction with the following metal thickness for pressure classes from 2-to 10-inch wg:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -7 a. Ducts 3 to 26 Inches in Diameter: 0.034 inch. b. Ducts 27 to 50 Inches in Diameter: 0.040 inch. c. Ducts 52 to 60 Inches in Diameter: 0.052 inch. d. Ducts
62 to 84 Inches in Diameter: 0.064 inch. 3. Flat-Oval Mitered Elbows: Welded construction with same metal thickness as longitudinal-seam flat-oval duct. 4. 90-Degree, 2-Piece, Mitered
Elbows: Use only for supply systems or for materialhandling Class A or B exhaust systems and only where space restrictions do not permit using radius elbows. Fabricate with single-thickness
turning vanes. 5. Round Elbows 8 Inches and Less in Diameter: Fabricate die-formed elbows for 45-and 90-degree elbows and pleated elbows for 30, 45, 60, and 90 degrees only. Fabricate
nonstandard bend-angle configurations or nonstandard diameter elbows with gored construction. 6. Round Elbows 9 through 14 Inches in Diameter: Fabricate gored or pleated elbows for 30,
40, 45, 60, and 90 degrees unless space restrictions require mitered elbows. Fabricate nonstandard bend-angle configurations or nonstandard diameter elbows with gored construction. 7.
Round Elbows Larger than 14 Inches in Diameter and All Flat-Oval Elbows: Fabricate gored elbows unless space restrictions require mitered elbows. 8. Die-Formed Elbows for Sizes through
8 Inches in Diameter and All Pressures 0.040 inch thick with 2-piece welded construction. 9. Round Gored-Elbow Metal Thickness: Same as non-elbow fittings specified above. 10. Flat-Oval
Elbow Metal Thickness: Same as longitudinal-seam flat-oval duct specified above. 11. Pleated Elbows for Sizes through 14 Inches in Diameter and Pressures through 10-Inch wg: 0.022 inch.
2.3 SHEET METAL MATERIALS A. Comply with SMACNA's "HVAC Duct Construction Standards--Metal and Flexible" for acceptable materials, material thicknesses, and duct construction methods,
unless otherwise indicated. Sheet metal materials shall be free of pitting, seam marks, roller marks, stains, discolorations, and other imperfections. B. Galvanized Sheet Steel: Lock-forming
quality; complying with ASTM A 653/A 653M and having G60 coating designation (G90, if exterior duct); ducts shall have mill-phosphatized finish for surfaces exposed to view. C. Reinforcement
Shapes and Plates: Galvanized-steel reinforcement where installed on galvanized sheet metal ducts. Aluminum reinforcement where installed on aluminum ducts. D. Tie Rods: Galvanized steel,
1/4-inch minimum diameter for lengths 36 inches or less; 3/8-inch minimum diameter for lengths longer than 36 inches. Aluminum material for aluminum ducts.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -8 2.4 SEALANT AND GASKETS A. Joint and Seam Sealants, General: The term "sealant" is not limited to materials of adhesive or mastic nature but includes tapes and
combinations of open-weave fabric strips and mastics. B. Water-Based Joint and Seam Sealant: Flexible, adhesive sealant, resistant to UV light when cured, UL 723 listed, and complying
with NFPA requirements for Class 1 ducts. C. Solvent-Based Joint and Seam Sealant: One-part, non-sag, solvent-release-curing, polymerized butyl sealant formulated with a minimum of 75
percent solids.
D. For indoor applications, use sealant that has a VOC content of 250 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24). E. Exterior duct sealants shall be
marketed specifically as forming a positive air and watertight seal, bonding well to the metal, remaining flexible with metal movement, having a service temperature range of -30 deg
F to 175 deg F, be ultraviolet ray and ozone resistant. F. Flanged Joint Sealant: Single component, acid-curing, silicone, elastomeric joint sealant complying with ASTM C 920, Type S,
Grade NS, Class 25, Use O. G. Flange Gaskets: Butyl rubber, neoprene or EPDM polymer with polyisobutylene plasticizer. H. Round Duct Joint O-Ring Seals: 1. Seal shall provide maximum
leakage class of 3 cfm/100 sq. ft. at 1-inch wg (0.14 L/s per sq. m at 250 Pa) and shall be rated for 10-inch wg (2500-Pa) static pressure class, positive or negative. 2. EPDM O-ring
to seal in concave bead in coupling or fitting spigot. 3. Double lipped, EPDM O-ring seal, mechanically fastened to factory fabricated couplings and fitting spigots. 4. Provide additional
sealant for ductwork of 2 inches wg pressure class or greater. 5. Install screw attachments, 12 inches on center at gasketed joints. 2.5 HANGERS AND SUPPORTS A. Building Attachments:
Concrete inserts, powder-actuated fasteners, or structural-steel fasteners appropriate for construction materials to which hangers are being attached. 1. Use powder-actuated concrete
fasteners for standard-weight aggregate concretes or for slabs more than 4 inches thick. 2. Exception: Do not use powder-actuated concrete fasteners for lightweight-aggregate concretes
or for slabs less than 4 inches thick. B. Hanger Rods for Non-Corrosive Environments: Cadmium plated steel rods and nuts.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -9 C. Hanger Rods for Corrosive Environments: Electro-galvanized, all thread rods or galvanized rods with threads painted with zinc-chromate primer after installation.
D. Strap and Rod Sizes: Comply with SMACNA's "HVAC Duct Construction Standards – Metal and Flexible," Table 4-1 (Table 4-1M), "Rectangular Duct Hangers Minimum Size" and Table 4-2, "Minimum
Hanger Sizes for Round Duct." E. Steel Cables for Galvanized Steel Ducts: Galvanized steel complying with ASTM A 603. F. Steel Cable End Connections: Cadmium plated steel assemblies
with brackets, swivel, and bolts designed for duct hanger services with an automatic locking and clamping device. G. Duct Attachments: Sheet metal screws, blind rivets, or self-tapping
metal screws; compatible with duct materials. H. Trapeze and Riser Supports: Steel shapes complying with ASTM A 36/A 36M. 1. Supports for Galvanized-Steel Ducts: Galvanized-steel shapes
and plates. 2. Supports for Stainless-Steel Ducts: Stainless-steel support materials. 3. Supports for Aluminum Ducts: Aluminum or galvanized steel coated with zinc chromate. 2.6 SEISMIC
RESTRAINT DEVICES A. Manufacturers: Subject to compliance with requirements: 1. Cooper B-Line, Inc.; a division of Cooper Industries. 2. Ductmate Industries, Inc. 3. Hilti Corp. 4. Kinetics
Noise Control. 5. Loos & Co.; Cableware Division. 6. Mason Industries. 7. TOLCO; a brand of NIBCO INC. 8. Unistrut Corporation; Tyco International, Ltd. 9. VIBRO-Acoustics. B. General
Requirements for Restraint Components: Rated strengths, features, and applications shall be as defined in reports by an agency acceptable to authorities having jurisdiction. 1. Structural
Safety Factor: Allowable strength in tension, shear, and pullout force of components shall be at least four times the maximum seismic forces to which they will be subjected. C. Channel
Support System: Shop-or field-fabricated support assembly made of slotted steel channels rated in tension, compression, and torsion forces and with accessories for attachment
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -10 to braced component at one end and to building structure at the other end. Include matching components and corrosion-resistant coating. D. Restraint Cables:
ASTM A 603, galvanized or ASTM A 492, stainless-steel cables with end connections made of cadmium-plated steel assemblies with brackets, swivel, and bolts designed for restraining cable
service; and with an automatic-locking and clamping device or doublecable clips. E. Hanger Rod Stiffener: Steel tube or steel slotted-support-system sleeve with internally bolted connections
or reinforcing steel angle clamped to hanger rod. F. Mechanical Anchor Bolts: Drilled-in and stud-wedge or female-wedge type. Select anchor bolts with strength required for anchor and
as tested according to ASTM E 488. PART 3 -EXECUTION 3.1 DUCT APPLICATIONS A. Static-Pressure Classes: Unless otherwise indicated, construct ducts according to the following: 1. Supply
Ducts (before Air Terminal Units): 4-inch wg. 2. Supply Ducts (after Air Terminal Units): 1-inch wg. 3. Return Ducts (above ceiling): 2-inch wg. 4. General Exhaust Ducts (Negative Pressure):
2-inch wg. 5. Isolation Room Exhaust Ducts (Negative Pressure): 4-inch wg. 6. Supply Ducts (Serving duct coils): 2-inch wg. 3.2 DUCT INSTALLATION A. Construct and install ducts according
to SMACNA's "HVAC Duct Construction Standards--Metal and Flexible," unless otherwise indicated. B. Install round and flat-oval ducts in lengths not less than 12 feet unless interrupted
by fittings. C. Install ducts with fewest possible joints. D. Cable hangers may only be used on low pressure (2-inch wg construction and lower) round spiral ductwork which is not insulated
and has a diameter of 10 inches or less. Utilize the double lock method such that the lower loop is cinched tight to the ductwork and the cable is vertical. Utilize manufacturer’s top
attachment device. E. Install fabricated fittings for changes in directions, size, and shape and for connections.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -11 F. Install couplings tight to duct wall surface with a minimum of projections into duct. Secure couplings with sheet metal screws. Install screws at maximum
intervals of 12 inches, with a minimum of 3 screws in each round metallic duct coupling. G. Install ducts, unless otherwise indicated, vertically and horizontally and parallel and perpendicular
to building lines; avoid diagonal runs. H. Install ducts close to walls, overhead construction, columns, and other structural and permanent enclosure elements of building. I. Install
ducts with a minimum clearance of 2 inches, plus allowance for insulation thickness, to all components. J. Install ductwork takeoffs at smoke dampers such that there is a minimum of
24 inches between the damper and the start of the first takeoff. K. Low pressure ductwork shall extend a minimum of 9 inches beyond last diffuser takeoff. L. Conceal ducts from view
in finished spaces. Do not encase horizontal runs in solid partitions unless specifically indicated. M. Do not penetrate ducts with conduit or piping. Provide SMACNA Figure E obstruction
fitting where structural members are shown penetrating ductwork. N. Coordinate layout with suspended ceiling, fire-and smoke-control dampers, lighting layouts, smoke partition rated
walls and similar finished work allowing for proper maintenance and installation. O. Seal all joints and seams. Apply sealant to male end connectors before insertion, and afterward to
cover entire joint and sheet metal screws. P. Electrical Equipment Spaces: Route ducts to avoid passing through transformer vaults and electrical equipment spaces and enclosures. Do
not route duct over motor control centers or panelboard. Q. Non-Fire-Rated Partition Penetrations: Where ducts pass through interior partitions and exterior walls and are exposed to
view, conceal spaces between construction openings and ducts or duct insulation with sheet metal flanges of same metal thickness as ducts. Overlap openings on 4 sides by at least 1-1/2
inches. R. Fire-Rated Partition Penetrations: Where ducts pass through interior partitions and exterior walls, install appropriately rated fire dampers, sleeves, and firestopping sealant.
Fire and smoke dampers are specified in Division 23 Section "Duct Accessories." Firestopping materials and installation methods are specified in Division 7 Section "Firestopping."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -12 S. Install ducts with hangers and braces designed to withstand, without damage to equipment, seismic force required by applicable building codes. Refer to SMACNA's
"Seismic Restraint Manual: Guidelines for Mechanical Systems." T. Protect duct interiors from the elements and foreign materials until the building envelope is fully enclosed and all
dust producing activities are complete. Follow SMACNA's "Duct Cleanliness for New Construction," intermediate level for all AHU systems. 3.3 SEAM AND JOINT SEALING A. Seal duct seams
and joints of all ductwork according to SMACNA's "HVAC Duct Construction Standards--Metal and Flexible" to meet seal Class A requirements. Supply ducts after terminal units shall be
sealed to meet seal Class B requirements. B. Seal ducts before external insulation is applied. C. Do not utilize pressure sensitive tapes to externally seal ductwork. 3.4 HANGING AND
SUPPORTING A. Support horizontal ducts within 24 inches of each elbow and within 48 inches of each branch intersection. B. Support vertical ducts at maximum intervals of 16 feet and
at each floor. C. Utilize trapeze hangers for all ductwork greater than 48 inches in width. D. Install upper attachments to structures with an allowable load not exceeding one-fourth
of failure (proof-test) load. E. Install concrete inserts before placing concrete. F. Install powder-actuated concrete fasteners after concrete is placed and completely cured. 1. Do
not use powder-actuated concrete fasteners for lightweight-aggregate concretes or for slabs less than 4 inches thick. G. Install flexible duct hanger at least once per segment such that
each flexible duct is supported a minimum of three times, counting the two end connections. Support at intervals no greater than 5 feet. Maximum permissible sag is 0.5 inch per foot
of spacing between supports. A connection to another duct or to equipment at each end is considered a support point. Flexible duct hangers shall be at least 1.0 inch wide.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -13 3.5 SEISMIC-RESTRAINT-DEVICE INSTALLATION A. Install ducts with hangers and braces designed to support the duct and to restrain against seismic forces required
by applicable building codes. Comply with SMACNA's "Seismic Restraint Manual: Guidelines for Mechanical Systems." Requirements of the Seismic Restraint Manual may require closer spacing
than the maximums described here. 1. Space lateral supports a maximum of 40 feet (12 m) o.c., and longitudinal supports a maximum of 80 feet (24 m) o.c. 2. Brace a change of direction
longer than 12 feet (3.7 m). B. Select seismic-restraint devices with capacities adequate to carry present and future static and seismic loads. C. Install cables so they do not bend
across edges of adjacent equipment or building structure. D. Install cable restraints on ducts that are suspended with vibration isolators. E. Install seismic-restraint devices using
methods approved by an agency acceptable to authorities having jurisdiction. F. Attachment to Structure: If specific attachment is not indicated, anchor bracing and restraints to structure,
to flanges of beams, to upper truss chords of bar joists, or to concrete members. G. Drilling for and Setting Anchors: 1. Identify position of reinforcing steel and other embedded items
prior to drilling holes for anchors. Do not damage existing reinforcement or embedded items during drilling. Notify the Architect if reinforcing steel or other embedded items are encountered
during drilling. Locate and avoid prestressed tendons, electrical and telecommunications conduit, and gas lines. 2. Do not drill holes in concrete or masonry until concrete, mortar,
or grout has achieved full design strength. 3. Wedge Anchors: Protect threads from damage during anchor installation. Heavy-duty sleeve anchors shall be installed with sleeve fully engaged
in the structural element to which anchor is to be fastened. 4. Set anchors to manufacturer's recommended torque, using a torque wrench. 5. Install zinc-coated steel anchors for interior
applications and stainless-steel anchors for applications exposed to weather. 3.6 PAINTING A. Paint interior of metal ducts that are visible through registers and grilles and that do
not have duct liner. Apply one coat of flat, black, latex paint over a compatible galvanized-steel primer. Paint materials and application requirements are specified in Division 9 painting
Sections.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -14 3.7 CONNECTIONS A. Make connections to equipment with flexible connectors according to Division 23 Section "Duct Accessories." B. Comply with SMACNA's "HVAC
Duct Construction Standards--Metal and Flexible" for branch, outlet and inlet, and terminal unit connections. 3.8 FIELD QUALITY CONTROL A. Perform the following field tests and inspections
according to SMACNA's "HVAC Air Duct Leakage Test Manual" and prepare test reports: 1. Disassemble, reassemble, and seal segments of systems to accommodate leakage testing and for compliance
with test requirements. 2. Conduct tests at static pressures equal to maximum design pressure of system or section being tested. If pressure classes are not indicated, test entire system
at maximum system design pressure. Do not pressurize systems above maximum design operating pressure. Give seven days' advance notice for testing. 3. All supply ductwork from fan or
AHU outlet to the inlet of every terminal unit or reheat coil shall be tested. The terminal unit and all ductwork downstream of the terminal unit shall not be tested. All return and
exhaust ductwork shall be tested from the fan to the end of the branch to every grille. Do not test flexible ductwork. 4. Maximum Allowable Leakage: a. In accordance with the following
total leakage quantity limitations, provide a leakage per square foot of ductwork for each fan or AHU to meet the following requirements: 1) Allowable Leakage, Supply Duct: 1.0 percent
of total scheduled supply fan design airflow. 2) Allowable Leakage, Return, Outside Air, and Relief Air Duct: 5.0 percent of total scheduled applicable fan design airflow. 3) Allowable
Leakage, General Exhaust Duct: 5.0 percent of total scheduled general exhaust fan design airflow. 4) Contractor shall identify fan or AHU total scheduled fan airflow, surface area of
ductwork to be tested, total duct surface area of the fan or AHU system and location of ductwork prior to testing. All testing shall be witnessed, documented, and submitted. Document
individual test sections, test pressure, orifice size, pressure drop across orifice, surface area of ductwork to be tested and tested leakage for each section tested. Summarize total
leakage by fan or AHU system. 5) Submit field test reports within two business days of the test date. Do not proceed with insulating ductwork until the test report demonstrating acceptable
leakage has been submitted and processed by the Architect.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
METAL DUCTS 23 31 13 -15 B. Duct System Cleanliness Tests: 1. Visually inspect duct system to ensure that no visible contaminants are present. 2. Test sections of metal duct system,
chosen randomly by Owner, for cleanliness according to "Vacuum Test" in NADCA ACR, "Assessment, Cleaning, and Restoration of HVAC Systems." a. Acceptable Cleanliness Level: Net weight
of debris collected on the filter media shall not exceed 0.75 mg/100 sq. cm. C. Duct system will be considered defective if it does not pass tests and inspections. D. Prepare test and
inspection reports. END OF SECTION 23 31 13
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -1 SECTION 23 33 00 -AIR DUCT ACCESSORIES PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Backdraft and pressure relief dampers. 2. Manual volume dampers.
3. Fire dampers. 4. Smoke dampers. 5. Combination fire and smoke dampers. 6. Duct silencers. 7. Turning vanes. 8. Duct-mounted access doors. 9. Flexible connectors. 10. Flexible ducts.
11. Duct accessory hardware. B. Related Sections: 1. Division 28 Section "Fire Detection and Alarm" for duct-mounted fire and smoke detectors. 1.3 SUBMITTALS A. Product Data: For each
type of product indicated. 1. For duct silencers, include pressure drop and dynamic insertion loss data. Include breakout noise calculations for high transmission loss casings. 2. For
fire dampers, smoke dampers and fire/smoke dampers, provide pressure drop at 1000 fpm, 1500 fpm and at 2000 fpm. B. Shop Drawings: For duct accessories. Include plans, elevations, sections,
details, and attachments to other work.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -2 1. Detail duct accessories fabrication and installation in ducts and other construction. Include dimensions, weights, loads, and required clearances;
and method of field assembly into duct systems and other construction. Include the following: a. Special fittings. b. Manual volume damper installations. c. Control damper installations.
d. Fire-damper, smoke-damper, combination fire-and smoke-damper, ceiling, and corridor damper installations, including sleeves; and duct-mounted access doors and remote damper operators.
e. Wiring Diagrams: For power, signal, and control wiring. 2. Detailed fire damper, smoke damper, combination fire and smoke damper installation requirements which incorporate manufacturer’s
and UL listing requirements for opening size, stud construction, opening framing and other required construction features. C. Coordination Drawings: Reflected ceiling plans, drawn to
scale, on which ceiling-mounted access panels and access doors required for access to duct accessories are shown and coordinated with each other, using input from Installers of the items
involved. D. Source quality-control reports. E. Operation and Maintenance Data: For air duct accessories to include in operation and maintenance manuals. F. Acceptance Test Reports:
Perform and submit NFPA 90A acceptance test reports for each fire damper and fire/smoke damper. Acceptance test demonstrating removal and reinstallation of fusible links shall be completed
after all above ceiling installations are complete to confirm acceptable access. Submit acceptance test report prior to occupancy of the building. 1.4 QUALITY ASSURANCE A. Comply with
NFPA 90A, "Installation of Air Conditioning and Ventilating Systems," and with NFPA 90B, "Installation of Warm Air Heating and Air Conditioning Systems." B. Comply with AMCA 500-D D
testing for damper rating. C. Perform NFPA 90A acceptance tests and document results. Replace fusible links at the completion of acceptance tests. 1.5 EXTRA MATERIALS A. Furnish extra
materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -3 1. Fusible Links: Furnish quantity equal to 10 percent of amount installed. PART 2 -PRODUCTS 2.1 MATERIALS A. Comply with SMACNA's "HVAC Duct Construction
Standards -Metal and Flexible" for acceptable materials, material thicknesses, and duct construction methods unless otherwise indicated. Sheet metal materials shall be free of pitting,
seam marks, roller marks, stains, discolorations, and other imperfections. B. Galvanized Sheet Steel: Comply with ASTM A 653/A 653M. 1. Galvanized Coating Designation: G90 (Z275). 2.
Exposed-Surface Finish: Mill phosphatized. C. Stainless-Steel Sheets: Comply with ASTM A 480/A 480M, Type 304, and having a No. 2 finish for concealed ducts and No. 3 finish for exposed
ducts. D. Aluminum Sheets: Comply with ASTM B 209 (ASTM B 209M), Alloy 3003, Temper H14; with mill finish for concealed ducts and standard, 1-side bright finish for exposed ducts. E.
Extruded Aluminum: Comply with ASTM B 221 (ASTM B 221M), Alloy 6063, Temper T6. F. Reinforcement Shapes and Plates: Galvanized-steel reinforcement where installed on galvanized sheet
metal ducts; compatible materials for aluminum and stainless-steel ducts. G. Tie Rods: Galvanized steel, 1/4-inch (6-mm) minimum diameter for lengths 36 inches (900 mm) or less; 3/8-inch
(10-mm) minimum diameter for lengths longer than 36 inches (900 mm). 2.2 BACKDRAFT AND PRESSURE RELIEF DAMPERS A. Manufacturers: Subject to compliance with requirements, provide products
by one of the following: 1. Air Balance Inc.; a division of Mestek, Inc. 2. American Warming and Ventilating; a division of Mestek, Inc. 3. Cesco Products; a division of Mestek, Inc.
4. Greenheck Fan Corporation. 5. Nailor Industries Inc. 6. NCA Manufacturing, Inc. 7. Pottorff; a division of PCI Industries, Inc. 8. Ruskin Company. 9. SEMCO Incorporated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -4 10. Vent Products Company, Inc. B. Description: Gravity balanced. C. Maximum Air Velocity: 2500 fpm. D. Maximum System Pressure: Matching ductwork design
pressure. E. Frame: 0.063-inch-(1.6-mm-) thick extruded aluminum, with welded corners and mounting flange. F. Blades: Multiple single-piece blades, maximum 6-inch (150-mm) width, 0.025-inch-(0.6-mm-)
thick, roll-formed aluminum with sealed edges. G. Blade Action: Parallel. H. Blade Seals: Extruded vinyl, mechanically locked. I. Blade Axles: 1. Material: Non-ferrous metal. 2. Diameter:
0.20 inch (5 mm). J. Tie Bars and Brackets: Aluminum. K. Return Spring: Adjustable tension. L. Bearings: Steel ball or synthetic pivot bushings. M. Accessories: 1. Adjustment device
to permit setting for varying differential static pressure. 2. Counterweights and spring-assist kits for vertical airflow installations. 3. Chain pulls. 4. Screen Mounting: Front mounted
in sleeve. a. Sleeve Thickness: 20-gage (1.0-mm) minimum. b. Sleeve Length: 6 inches (152 mm) minimum. 5. Screen Material: Aluminum. 6. Screen Type: Insect. 7. 90-degree stops. 2.3 MANUAL
VOLUME DAMPERS A. Standard, Steel, Manual Volume Dampers:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -5 1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: a. Air Balance Inc.; a division of Mestek, Inc.
b. American Warming and Ventilating; a division of Mestek, Inc. c. Cesco. d. Greenheck. e. Lindab. f. METALAIRE, Inc. g. Nailor Industries Inc. h. Pottorff; a division of PCI Industries,
Inc. i. Ruskin Company. j. Vent Products Company, Inc. 2. Standard leakage rating, with linkage outside airstream. 3. Suitable for horizontal or vertical applications. 4. Frames: a.
Hat-shaped, galvanized-steel channels, 0.052-inch minimum thickness. b. Mitered and welded corners. c. Flanges for attaching to walls and flangeless frames for installing in ducts. d.
Maximum size 12” X 12”. 5. Blades: a. Multiple or single blade. b. Parallel-or opposed-blade design. c. Stiffen damper blades for stability. d. Galvanized-steel, 0.040-inch thick. 6.
Blade Axles: Galvanized steel. 7. Bearings: a. Molded synthetic. b. Dampers in ducts with pressure classes of 3-inch wg (750 Pa) or less shall have axles full length of damper blades
and bearings at both ends of operating shaft. 8. Tie Bars and Brackets: Galvanized steel. 9. Pressure classes of 3-inch wg or higher or 14” X 14” and larger duct size: a. Multiple opposed
blade design. b. End bearings or other seals for ducts with axles full length of damper blades and bearings at both ends of operating shaft. c. Suitable for 2000 fpm velocity at the
width and height required. d. Jackshaft to operate multi-section dampers from one side. e. Locking hand quadrant and 2” stand-off mounting bracket.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -6 10. Provide stainless and aluminum dampers where dampers are shown in stainless or aluminum ductwork. B. Jackshaft: 1. Size: 1-inch (25-mm) diameter.
2. Material: Galvanized-steel pipe rotating within pipe-bearing assembly mounted on supports at each mullion and at each end of multiple-damper assemblies. 3. Length and Number of Mountings:
As required to connect linkage of each damper in multiple-damper assembly. C. Damper Hardware: 1. Zinc-plated, die-cast core with dial and handle made of 3/32-inch-(2.4-mm-) thick zincplated
steel, and a 3/4-inch (19-mm) hexagon locking nut. 2. Include center hole to suit damper operating-rod size. 3. Include elevated platform for insulated duct mounting. 2.4 FIRE DAMPERS
A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Air Balance Inc.; a division of Mestek, Inc. 2. Cesco Products; a division of
Mestek, Inc. 3. Greenheck Fan Corporation. 4. Nailor Industries Inc. 5. NCA Manufacturing, Inc. 6. Pottorff; a division of PCI Industries, Inc. 7. Prefco; Perfect Air Control, Inc. 8.
Ruskin Company. 9. Vent Products Company, Inc. 10. Ward Industries, Inc.; a division of Hart & Cooley, Inc. B. Type: Dynamic; rated and labeled according to UL 555 by an NRTL. C. Closing
rating in ducts up to 4-inch wg (1-kPa) static pressure class and minimum 2000 fpm velocity. D. Fire Rating: 1-1/2 and 3 hours as required. E. Frame: Curtain type with blades outside
airstream; fabricated with roll-formed, 0.034-inch-(0.85-mm-) thick galvanized steel; with mitered and interlocking corners. F. Mounting Sleeve: Factory-or field-installed, galvanized
sheet steel.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -7 1. Minimum Thickness: 0.052 or 0.138 inch (1.3 or 3.5 mm) thick, as indicated, and of length to suit application. 2. Exception: Omit sleeve where damper-frame
width permits direct attachment of perimeter mounting angles on each side of wall or floor; thickness of damper frame must comply with sleeve requirements. G. Mounting Orientation: Vertical
or horizontal as indicated. H. Blades: Roll-formed, interlocking, 0.034-inch-(0.85-mm-) thick, galvanized sheet steel. In place of interlocking blades, use full-length, 0.034-inch-(0.85-mm-)
thick, galvanized-steel blade connectors. 1. Provide double wall airfoil blades for multiple segment dampers
located within supply ductwork upstream of the terminal boxes. I. Horizontal Dampers: Include blade lock and stainless-steel closure spring. J. Heat-Responsive Device: Replaceable, 165
deg F (74 deg C) rated, fusible links. 2.5 SMOKE DAMPERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Air Balance Inc.; a division
of Mestek, Inc. 2. Cesco Products; a division of Mestek, Inc. 3. Greenheck Fan Corporation. 4. Nailor Industries Inc. 5. Ruskin Company. 6. Vent Products. B. General Requirements: Label
according to UL 555S by an NRTL. C. Smoke Detector: By fire alarm provider, duct mounted. D. Frame: Multiple-blade type; fabricated with roll-formed, 0.034-inch-(0.85-mm-) thick galvanized
steel; with mitered and interlocking corners. E. Blades: Roll-formed, horizontal, interlocking, 0.034-inch-(0.85-mm-) thick, galvanized sheet steel. In place of interlocking blades,
use full-length, 0.034-inch-(0.85-mm-) thick, galvanizedsteel blade connectors. 1. Provide double wall airfoil blades for dampers located within supply ductwork upstream of the terminal
boxes. F. Leakage: Class I.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -8 G. Rated pressure and velocity to exceed design airflow conditions, minimum 2000 fpm and 4-inch water gauge. H. Mounting Sleeve: Factory-installed, 0.052-inch-(1.3-mm
-) thick, galvanized sheet steel; length to suit wall or floor application with factory-furnished UL listed silicone caulking. I. Damper Motors: Two-position action. J. Comply with NEMA
designation, temperature rating, service factor, enclosure type, and efficiency requirements for motors specified in Division 23 Section "Common Motor Requirements for HVAC Equipment."
1. Motor Sizes: Minimum size as indicated. If not indicated, large enough so driven load will not require motor to operate in service factor range above 1.0. 2. Controllers, Electrical
Devices, and Wiring: Comply with requirements for electrical devices and connections specified in Division 23 Section "Instrumentation and Control for HVAC" and Division 26 Sections.
3. Permanent-Split-Capacitor or Shaded-Pole Motors: With oil-immersed and sealed gear trains. 4. Spring-Return Motors: Equip with an integral spiral-spring mechanism where indicated.
Enclose entire spring mechanism in a removable housing designed for service or adjustments. Size for running torque rating of 150 in. x lbf (17 N x m) and breakaway torque rating of
150 in. x lbf (17 N x m). 5. Outdoor Motors and Motors in Outdoor-Air Intakes: Equip with O-ring gaskets designed to make motors weatherproof. Equip motors with internal heaters to permit
normal operation at minus 40 deg F (minus 40 deg C). 6. Electrical Connection: 115 V, single phase, 60 Hz. 7. Electrical Disconnect: Provide toggle switch non-fused disconnect mounted
to damper frame. K. Pneumatic Actuator: 1. Large enough to properly operate at a differential pressure equal to the ductwork construction in inches. 2. Utilize 20 psig control air. L.
Accessories: 1. Auxiliary switches for position indication. 2. Momentary test switch, damper or remote mounted. 2.6 COMBINATION FIRE AND SMOKE DAMPERS A. Manufacturers: Subject to compliance
with requirements, provide products by one of the following:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -9 1. Air Balance Inc.; a division of Mestek, Inc. 2. Cesco Products; a division of Mestek, Inc. 3. Greenheck Fan Corporation. 4. Nailor Industries Inc.
5. Ruskin Company. 6. Vent Products. B. Type: Dynamic; rated and labeled according to UL 555 and UL 555S by an NRTL. C. Closing rating in ducts up to 4-inch wg (1-kPa) static pressure
class and minimum 2000-fpm velocity. D. Fire Rating: 1-1/2 and 3 hours as required. E. Frame: Multiple-blade type; fabricated with roll-formed, 0.034-inch-(0.85-mm-) thick galvanized
steel; with mitered and interlocking corners. F. Heat-Responsive Device: Replaceable, 165 deg F (74 deg C) rated, fusible links as required. G. Heat-Responsive Device: Pneumatic resettable
link and switch package, factory installed, rated. H. Smoke Detector: By fire alarm provider, duct mounted. I. Blades: Roll-formed, horizontal, interlocking, 0.034-inch-(0.85-mm-) thick,
galvanized sheet steel. In place of interlocking blades, use full-length, 0.034-inch-(0.85-mm-) thick, galvanizedsteel blade connectors. 1. Provide double wall airfoil blades for dampers
located within supply ductwork upstream of the terminal boxes. J. Leakage: Class I. K. Rated pressure and velocity to exceed design airflow conditions. L. Mounting Sleeve: Factory-installed,
0.052-inch-(1.3-mm-) thick, galvanized sheet steel; length to suit wall or floor application with factory-furnished UL listed silicone caulking. M. Damper Motors: Two-position action.
N. Comply with NEMA designation, temperature rating, service factor, enclosure type, and efficiency requirements for motors specified in Division 23 Section "Common Motor Requirements
for HVAC Equipment." 1. Motor Sizes: Minimum size as indicated. If not indicated, large enough so driven load will not require motor to operate in service factor range above 1.0.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -10 2. Controllers, Electrical Devices, and Wiring: Comply with requirements for electrical devices and connections specified in Division 23 Section "Instrumentation
and Control for HVAC" and Division 26 Sections. 3. Permanent-Split-Capacitor or Shaded-Pole Motors: With oil-immersed and sealed gear trains. 4. Spring-Return Motors: Equip with an integral
spiral-spring mechanism where indicated. Enclose entire spring mechanism in a removable housing designed for service or adjustments. Size for running torque rating of 150 in. x lbf (17
N x m) and breakaway torque rating of 150 in. x lbf (17 N x m). 5. Outdoor Motors and Motors in Outdoor-Air Intakes: Equip with O-ring gaskets designed to make motors weatherproof. Equip
motors with internal heaters to permit normal operation at minus 40 deg deg F (minus 40 deg C). 6. Electrical Connection: 115 V, single phase, 60 Hz. 7. Electrical Disconnect: Provide
toggle switch non-fused disconnect mounted to damper frame. O. Pneumatic Actuator: 1. Large enough to function at a differential pressure equal to the ductwork construction in inches.
2. Utilize 20 psig control air. P. Accessories: 1. Auxiliary switches for position indication. 2. Momentary test switch, damper or remote mounted. 2.7 DUCT SILENCERS A. Manufacturers:
Subject to compliance with requirements, provide products by one of the following: 1. Aerosonics. 2. Commercial Acoustics. 3. Industrial Noise Control, Inc. 4. Ruskin Company. 5. SEMCO.
6. VAW Systems. 7. Vibro-Acoustics. B. General Requirements: 1. Factory fabricated. 2. Fire-Performance Characteristics: Adhesives, sealants, packing materials, and accessory materials
shall have flame-spread index not exceeding 25 and smoke-developed index not exceeding 50 when tested according to ASTM E 84.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -11 3. Airstream Surfaces: Surfaces in contact with the airstream shall comply with requirements in ASHRAE 62.1-2004. C. Shape: 1. Rectangular straight
with splitters or baffles. 2. Other shapes as scheduled and shown on the drawings. D. Rectangular Silencer Outer Casing: ASTM A 653/A 653M, G90 (Z275), galvanized sheet steel, 0.034
inch (0.85 mm) thick. E. Round Silencer Outer Casing: ASTM A 653/A 653M, G90 (Z275), galvanized sheet steel. 1. Sheet Metal Thickness for Units up to 24 Inches (600 mm) in Diameter:
0.034 inch (0.85 mm) thick. 2. Sheet Metal Thickness for Units 26 through 40 Inches (660 through 1000 mm) in Diameter: 0.040 inch (1.02 mm) thick. 3. Sheet Metal Thickness for Units
42 through 52 Inches (1060 through 1300 mm) in Diameter: 0.052 inch (1.3 mm) thick. 4. Sheet Metal Thickness for Units 54 through 60 Inches (1370 through 1500 mm) in Diameter: 0.064
inch (1.62 mm) thick. F. Inner Casing and Baffles: ASTM A 653/A 653M, G90 (Z275) galvanized sheet metal, 0.034 inch (0.85 mm) thick, and with 1/8-inch-(3-mm-) diameter perforations.
G. Connection Sizes: Match connecting ductwork unless otherwise indicated. H. Principal Sound-Absorbing Mechanism: 1. Controlled impedance membranes and broadly tuned resonators without
absorptive media. a. Fill Material: Moisture-proof non-fibrous material. b. Erosion Barrier: Polymer bag enclosing fill, and heat sealed before assembly. c. Lining: Mylar or tedlar.
I. Fabricate silencers to form rigid units that will not pulsate, vibrate, rattle, or otherwise react to system pressure variations. Do not use mechanical fasteners for unit assemblies.
1. Lock form and seal or continuously weld joints. 2. Suspended Units: Factory-installed suspension hooks or lugs attached to frame in quantities and spaced to prevent deflection or
distortion. 3. Reinforcement: Cross or trapeze angles for rigid suspension. J. Accessories: 1. Factory-installed end caps to prevent contamination during shipping.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -12 K. Source Quality Control: Test according to ASTM E 477. 1. Record acoustic ratings, including dynamic insertion loss and generated-noise power levels
with an airflow of at least 2000-fpm (10-m/s) face velocity. 2. Leak Test: Test units for airtightness at 200 percent of associated fan static pressure or 6-inch wg (1500-Pa) static
pressure, whichever is greater. 2.8 TURNING VANES A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Ductmate Industries, Inc. 2.
Duro Dyne Inc. 3. METALAIRE, Inc. 4. SEMCO Incorporated. 5. Ward Industries, Inc.; a division of Hart & Cooley, Inc. B. Manufactured Turning Vanes for Metal Ducts: Curved blades of galvanized
sheet steel; support with bars perpendicular to blades set; set into vane runners suitable for duct mounting. C. General Requirements: Comply with SMACNA's "HVAC Duct Construction Standards
-Metal and Flexible"; Figures 2-3, "Vanes and Vane Runners," and 2-4, "Vane Support in Elbows." D. Vane Construction: Double wall. 2.9 DUCT-MOUNTED ACCESS DOORS A. Manufacturers: Subject
to compliance with requirements, provide products by one of the following: 1. Air Balance. 2. American Warming and Ventilating; a division of Mestek, Inc. 3. Cesco Products; a division
of Mestek, Inc. 4. Ductmate Industries, Inc. 5. Flexmaster U.S.A., Inc. 6. Greenheck Fan Corporation. 7. Kees. 8. Nailor Industries Inc. 9. Pottorff; a division of PCI Industries, Inc.
10. Ruskin. 11. Ventfabrics, Inc. 12. Ward Industries, Inc.; a division of Hart & Cooley, Inc.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -13 B. Duct-Mounted Access Doors: Fabricate access panels according to SMACNA's "HVAC Duct Construction Standards -Metal and Flexible"; Figures 2-10, "Duct
Access Doors and Panels," and 2-11, "Access Panels -Round Duct." 1. Door: a. Double wall, rectangular. b. Galvanized sheet metal with insulation fill and thickness as indicated for duct
pressure class. c. Hinges and Latches: Piano hinge and cam latches with safety chain. d. Fabricate doors airtight and suitable for duct pressure class. e. Access doors for ductwork pressure
class 3-inch or greater shall include a 1” frame flange for duct mounting (access doors for ductwork pressure class 2-inch and less may be bent over tabs and foam gasketing). 2. Frame:
Galvanized sheet steel, with bend-over tabs and foam gaskets. 3. Number of Hinges and Locks: a. Access Doors Less Than 12 Inches (300 mm) Square: One hinge and two sash locks. b. Access
Doors up to 18 Inches (460 mm) Square: Two hinges and two sash locks. c. Access Doors up to 24 by 48 Inches (600 by 1200 mm): Three hinges and two compression latches. d. Access Doors
Larger Than 24 by 48 Inches (600 by 1200 mm): Four hinges and two compression latches with outside and inside handles. 2.10 FLEXIBLE CONNECTORS A. Manufacturers: Subject to compliance
with requirements, provide products by one of the following: 1. Ductmate Industries, Inc. 2. Duro Dyne Inc. 3. Ventfabrics, Inc. B. Materials: Flame-retardant or noncombustible fabrics.
C. Coatings and Adhesives: Comply with UL 181, Class 1. D. Metal-Edged Connectors: Factory fabricated with a fabric strip 3-1/2 inches (89 mm) wide attached to 2 strips of 2-3/4-inch-(70-mm-)
wide, 0.028-inch-(0.7-mm-) thick, galvanized sheet steel or 0.032-inch-(0.8-mm-) thick aluminum sheets. Provide metal compatible with connected ducts. E. Indoor System, Flexible Connector
Fabric: Glass fabric double coated with neoprene.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -14 1. Minimum Weight: 26 oz./sq. yd. (880 g/sq. m). 2. Tensile Strength: 480 lbf/inch (84 N/mm) in the warp and 360 lbf/inch (63 N/mm) in the filling.
3. Service Temperature: Minus 40 to plus 200 deg F (Minus 40 to plus 93 deg C). F. Outdoor System, Flexible Connector Fabric: Glass fabric double coated with weatherproof, synthetic
rubber (Hypalon) resistant to UV rays and ozone. 1. Minimum Weight: 24 oz./sq. yd. (810 g/sq. m). 2. Tensile Strength: 530 lbf/inch (93 N/mm) in the warp and 440 lbf/inch (77 N/mm) in
the filling. 3. Service Temperature: Minus 50 to plus 250 deg F (Minus 45 to plus 121 deg C). G. Thrust Limits: Combination coil spring and elastomeric insert with spring and insert
in compression, and with a load stop. Include rod and angle-iron brackets for attaching to fan discharge and duct. 1. Frame: Steel, fabricated for connection to threaded rods and to
allow for a maximum of 30 degrees of angular rod misalignment without binding or reducing isolation efficiency. 2. Outdoor Spring Diameter: Not less than 80 percent of the compressed
height of the spring at rated load. 3. Minimum Additional Travel: 50 percent of the required deflection at rated load. 4. Lateral Stiffness: More than 80 percent of rated vertical stiffness.
5. Overload Capacity: Support 200 percent of rated load, fully compressed, without deformation or failure. 6. Elastomeric Element: Molded, oil-resistant rubber or neoprene. 7. Coil Spring:
Factory set and field adjustable for a maximum of 1/4-inch (6-mm) movement at start and stop. 2.11 FLEXIBLE DUCTS A. Manufacturers: Subject to compliance with requirements, provide products
by one of the following: 1. Flexmaster U.S.A., Inc. 2. McGill AirFlow LLC. 3. Ward Industries, Inc.; a division of Hart & Cooley, Inc. B. Low Pressure Insulated, Flexible Duct: UL 181,
Class 1, 2-ply polymer film supported by helically wound, spring galvanized steel wire; fibrous-glass insulation; black polyethylene fire retardant vapor-barrier film. 1. Pressure Rating:
4-inch wg positive and 0.5-inch wg negative. 2. Maximum Air Velocity: 4000 fpm. 3. Temperature Range: Minus 20 to plus 175 deg F. 4. Insulation R-value: Comply with ASHRAE/IESNA 90.1-2004,
minimum R-6.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -15 C. Flexible Duct Connectors: 1. Clamps: Nylon strap in sizes 3 through 18 inches (75 through 460 mm), to suit duct size. 2.12 DUCT ACCESSORY HARDWARE
A. Instrument Test Holes: Cast iron or cast aluminum to suit duct material, including screw cap and gasket. Size to allow insertion of pitot tube and other testing instruments and of
length to suit duct-insulation thickness. B. Adhesives: High strength, quick setting, neoprene based, waterproof, and resistant to gasoline and grease. PART 3 -EXECUTION 3.1 INSTALLATION
A. Install duct accessories according to applicable details in SMACNA's "HVAC Duct Construction Standards -Metal and Flexible" for metal ducts and in NAIMA AH116, "Fibrous Glass Duct
Construction Standards," for fibrous-glass ducts. B. Install duct accessories of materials suited to duct materials; use galvanized-steel accessories in galvanized-steel and fibrous-glass
ducts, stainless-steel accessories in stainless-steel ducts, and aluminum accessories in aluminum ducts. C. Install backdraft dampers at inlet of exhaust fans or exhaust ducts as close
as possible to exhaust fan unless otherwise indicated. D. Install volume dampers at points on supply, return, and exhaust systems where branches extend from larger ducts. Where dampers
are installed in ducts having duct liner, install dampers with hat channels of same depth as liner, and terminate liner with nosing at hat channel. 1. Install steel volume dampers in
steel ducts. 2. Install aluminum volume dampers in aluminum ducts. E. Set dampers to fully open position before testing, adjusting, and balancing. F. Install test holes at fan inlets
and outlets and elsewhere as indicated. G. Install fire and smoke dampers according to UL listing written installation instructions. Install manufacturer’s UL listed optional sealant
around the full perimeter of the angle on both sides of the wall. H. Connect ducts to duct silencers rigidly.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -16 I. Install duct access doors on sides of ducts to allow for inspecting, adjusting, and maintaining accessories and equipment at the following locations:
1. On both sides of duct coils. 2. Downstream from control dampers, backdraft dampers, and equipment. 3. Adjacent to and close enough to fire or smoke dampers, to reset or reinstall
fusible links or to clean duct detectors. 4. Control devices requiring inspection, specifically humidity sensors, airflow sensors and pressure sensors. 5. Elsewhere as indicated. Note
that not all access doors required may be indicated on the drawings. Provide in bid to provide and install access doors as specified in addition to those shown on the drawings. J. Install
access doors with swing against duct static pressure. K. Install external angle duct reinforcement across the long side of the duct at each access door which is greater than 14” in dimension.
L. Label access doors according to Division 23 Section "Identification for HVAC Piping and Equipment" to indicate the purpose of access door. M. Install flexible connectors to connect
ducts to equipment supported by vibration isolators. N. For fans developing static pressures of 5-inch wg (1250 Pa) and more, cover flexible connectors with loaded vinyl sheet held in
place with metal straps. O. Connect terminal units to supply ducts directly or with maximum 12-inch (300-mm) lengths of flexible duct. Do not use flexible ducts to change directions.
P. Connect light troffer boots with maximum 60-inch (1500-mm) lengths of flexible duct clamped or strapped in place. Q. Connect diffusers to ducts with maximum 96-inch lengths of flexible
duct clamped or strapped in place unless indicated length differs on drawings. R. Connect flexible ducts to metal ducts with draw bands. S. Install duct test holes where required for
testing and balancing purposes. T. Install thrust limits at centerline of thrust, symmetrical on both sides of equipment. Attach thrust limits at centerline of thrust and adjust to a
maximum of 1/4-inch (6-mm) movement during start and stop of fans. 3.2 FIELD QUALITY CONTROL A. Tests and Inspections:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR DUCT ACCESSORIES 23 33 00 -17 1. Operate dampers to verify full range of movement. 2. Inspect locations of access doors and verify that purpose of access door can be performed. 3.
Operate fire, smoke, and combination fire and smoke dampers to verify full range of movement and verify that proper heat-response device is installed. 4. Inspect turning vanes for proper
and secure installation. 5. Operate remote damper operators to verify full range of movement of operator and damper. B. NFPA 90A Acceptance Testing: 1. Perform NFPA 90A acceptance testing
for each fire damper and each fire/smoke damper. 2. Acceptance test demonstrating removal and reinstallation of fusible links shall be completed only after all above ceiling installations
are complete to confirm acceptable access. 3. Relocate the work of any trade which which does not provide for required maintenance access to fusible links. See Division 23 Section "Common
Work Results for HVAC" coordination requirements. 4. Submit acceptance test report results prior to occupancy of the building. END OF SECTION 23 33 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC POWER VENTILATORS 23 34 23 -1 SECTION 23 34 23 -HVAC POWER VENTILATORS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General
and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Utility set fans. 2. Centrifugal roof
ventilators. 1.3 PERFORMANCE REQUIREMENTS A. Project Altitude: Base fan-performance ratings on 700 feet above sea level. B. Operating Limits: Classify according to AMCA 99. 1.4 SUBMITTALS
A. Product Data: Include rated capacities, furnished specialties, and accessories for each type of product indicated and include the following: 1. Certified fan performance curves with
system operating conditions indicated. 2. Certified fan sound-power ratings. 3. Motor ratings and electrical characteristics, plus motor and electrical accessories. 4. Material thickness
and finishes, including color charts. 5. Dampers, including housings, linkages, and operators. 6. Roof curbs. 7. Fan speed controllers. B. Shop Drawings: Detail equipment assemblies
and indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection. 1. Wiring Diagrams: Power, signal,
and control wiring.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC POWER VENTILATORS 23 34 23 -2 C. Operation and Maintenance Data: For power ventilators to include in emergency, operation, and maintenance manuals. 1.5 QUALITY ASSURANCE A. Electrical
Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended
use. B. AMCA Compliance: Products shall comply with performance requirements and shall be licensed to use the AMCA-Certified Ratings Seal. C. NEMA Compliance: Motors and electrical accessories
shall comply with NEMA standards. D. UL Standard: Power ventilators shall comply with UL 705. 1.6 DELIVERY, STORAGE, AND HANDLING A. Deliver fans as factory-assembled unit, to the extent
allowable by shipping limitations, with protective crating and covering. B. Disassemble and reassemble units, as required for moving to final location, according to manufacturer's written
instructions. C. Lift and support units with manufacturer's designated lifting or supporting points. 1.7 COORDINATION A. Coordinate size and location of structural-steel support members.
B. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases. Concrete, reinforcement, and formwork requirements are specified in Division 3. C. Coordinate
installation of roof curbs, equipment supports, and roof penetrations. 1.8 EXTRA MATERIALS A. Furnish extra materials described below that match products installed and that are packaged
with protective covering for storage and identified with labels describing contents. 1. Final Fan Belts: Two sets for each belt-driven fan. Field installed and sized by the Testing,
Adjusting, and Balancing Contractor. Sized as required to deliver the necessary airflow through the system accounting for all system losses.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC POWER VENTILATORS 23 34 23 -3 2. Final Fan Sheave: One set for each belt-driven fan. Field installed and sized by the Testing, Adjusting, and Balancing Contractor. Sized as required
to deliver the necessary airflow through the system accounting for all system losses. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide
products by one of the following: 1. Aerovent; a Twin City Fan Company. 2. Cook. 3. Greenheck. 4. JencoFan; Div. of Breidert Air Products. 2.2 UTILITY SET FANS A. Description: Belt-driven
centrifugal fans consisting of housing, wheel, fan shaft, bearings, motor and disconnect switch, drive assembly, and accessories. B. Housing: Fabricated of galvanized steel with side
sheets fastened with a deep lock seam or welded to scroll sheets. 1. Housing Discharge Arrangement: Adjustable to eight standard positions. C. Fan Wheels: Single-width, single inlet;
welded to cast-iron or cast-steel hub and spun-steel inlet cone, with hub keyed to shaft. 1. Blade Materials: Steel. 2. Blade Type: Backward inclined. D. Fan Shaft: Turned, ground, and
polished steel; keyed to wheel hub. Stainless steel where scheduled. E. Shaft Bearings: Prelubricated and sealed, self-aligning, pillow-block-type ball bearings with ABMA 9, L10 of 200,000
hours. F. Belt Drives: Factory mounted, with final alignment and belt adjustment made after installation. 1. Service Factor Based on Fan Motor Size: 1.5. 2. Motor Pulleys: Adjustable
pitch for use with motors through 5 hp; fixed pitch for use with larger motors. Select pulley so pitch adjustment is at the middle of adjustment range at fan design conditions.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC POWER VENTILATORS 23 34 23 -4 3. Belts: Oil resistant, non-sparking, and non-static; matched sets for multiple belt drives. 4. Belt Guards: Fabricate of steel for motors mounted
on outside of fan cabinet. G. Accessories: Refer to Fan Schedule on drawings for individual fan requirements. 2.3 CENTRIFUGAL ROOF VENTILATORS A. Description: Direct-or belt-driven centrifugal
fans consisting of housing, wheel, fan shaft, bearings, motor and disconnect switch, drive assembly, curb base, and accessories. B. Housing: Removable, spun-aluminum, dome top and outlet
baffle square, one-piece, aluminum base with venturi inlet cone. C. Fan Wheels: Aluminum hub and wheel with backward-inclined blades. D. Belt-Driven Drive Assembly: Resiliently mounted
to housing, with the following features: 1. Fan Shaft: Turned, ground, and polished steel; keyed to wheel hub. Stainless steel where scheduled. 2. Shaft Bearings: Permanently lubricated,
permanently sealed, self-aligning ball bearings. 3. Pulleys: Cast-iron, adjustable-pitch motor pulley. 4. Fan and motor isolated from exhaust airstream. E. Accessories: Refer to Fan
Schedule on drawings for individual fan requirements. 1. Disconnect Switch: Non-fusible type, with thermal-overload protection mounted inside fan housing, factory wired through an internal
aluminum conduit. F. Roof Curbs: Galvanized steel; mitered and welded corners;
1-1/2-inch thick, rigid, fiberglass insulation adhered to inside walls; and 1-1/2-inch wood nailer. Size as required to suit roof opening and fan base. 1. Overall Height: Minimum 16
inches. 2. Pitch Mounting: Manufacture curb for roof slope. 3. Metal Liner: Galvanized steel. 2.4 MOTORS A. Comply with requirements in Division 23 Section "Common Motor Requirements
for HVAC Equipment."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC POWER VENTILATORS 23 34 23 -5 2.5 SOURCE QUALITY CONTROL A. Sound-Power Level Ratings: Comply with AMCA 301, "Methods for Calculating Fan Sound Ratings from Laboratory Test Data."
Factory test fans according to AMCA 300, "Reverberant Room Method for Sound Testing of Fans." Label fans with the AMCA-Certified Ratings Seal. B. Fan Performance Ratings: Establish flow
rate, pressure, power, air density, speed of rotation, and efficiency by factory tests and ratings according to AMCA 210, "Laboratory Methods of Testing Fans for Rating." PART 3 -EXECUTION
3.1 INSTALLATION A. Install power ventilators level and plumb. B. Support units as scheduled on the drawings and as specified in Division 23 Section "Vibration and Seismic Controls for
HVAC Piping and Equipment." 1. Secure vibration and seismic controls to concrete bases using anchor bolts cast in concrete base. C. Secure roof-mounting fans to roof curbs with cadmium-plated
hardware. Refer to Division 7 Section "Roof Accessories" for installation of roof curbs. D. Install units with clearances for service and maintenance. E. Label units according to requirements
specified in Division 23 Section "Identification for HVAC Piping and Equipment." 3.2 CONNECTIONS A. Duct installation and connection requirements are specified in other Division 23 Sections.
Drawings indicate general arrangement of ducts and duct accessories. Make final duct connections with flexible connectors. Flexible connectors are specified in Division 23 Section "Air
Duct Accessories." B. Install ducts adjacent to power ventilators to allow service and maintenance. C. Ground equipment according to Division 26 Section "Grounding and Bonding for Electrical
Systems." D. Connect wiring according to Division 26 Section "Low-Voltage Electrical Power Conductors and Cables."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HVAC POWER VENTILATORS 23 34 23 -6 3.3 FIELD QUALITY CONTROL A. Perform the following field tests and inspections and prepare test reports: 1. Verify that shipping, blocking, and bracing
are removed. 2. Verify that unit is secure on mountings and supporting devices and that connections to ducts and electrical components are complete. Verify that proper thermal-overload
protection is installed in motors, starters, and disconnect switches. 3. Verify that cleaning and adjusting are complete. 4. Disconnect fan drive from motor, verify proper motor rotation
direction, and verify fan wheel free rotation and smooth bearing operation. Reconnect fan drive system, align and adjust belts, and install belt guards. 5. Adjust belt tension. 6. Adjust
damper linkages for proper damper operation. 7. Verify lubrication for bearings and and other moving parts. 8. Verify that manual and automatic volume control and fire and smoke dampers
in connected ductwork systems are in fully open position. 9. Disable automatic temperature-control operators, energize motor, and adjust fan to indicated rpm, and measure and record
motor voltage and amperage. 10. Shut unit down and reconnect automatic temperature-control operators. 11. Remove and replace malfunctioning units and retest as specified above. B. Test
and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment. 3.4 ADJUSTING A. Adjust damper linkages for proper damper operation. B. Adjust belt tension.
C. Refer to Division 23 Section "Testing, Adjusting, and Balancing for HVAC" for testing, adjusting, and balancing procedures. D. Replace fan and motor pulleys as required to achieve
design airflow. E. Lubricate bearings. END OF SECTION 23 34 23
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR TERMINAL UNITS 23 36 00 -1 SECTION 23 36 00 -AIR TERMINAL UNITS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Single-duct air terminal units. 1.3 SUBMITTALS A. Product Data: For each
type of the following products, including rated capacities, furnished specialties, sound-power ratings, and accessories. 1. Air terminal units. 2. Liners and adhesives. 3. Sealants and
gaskets. B. Shop Drawings: For air terminal units. Include plans, elevations, sections, details, and attachments to other work. 1. Detail equipment assemblies and indicate dimensions,
weights, loads, required clearances, method of field assembly, components, and location and size of each field connection. 2. Wiring Diagrams: For power, signal, and control wiring.
C. Operation and Maintenance Data: For air terminal units to include in emergency, operation, and maintenance manuals. 1.4 QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories:
Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application. B. ASHRAE Compliance: Applicable requirements in ASHRAE 62.1-2004,
Section 5 -"Systems and Equipment" and Section 7 -"Construction and System Start-Up."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR TERMINAL UNITS 23 36 00 -2 1.5 EXTRA MATERIALS A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified
with labels describing contents. 1. Fan-Powered-Unit Filters: Furnish one spare filter(s) for each filter installed. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance
with requirements, provide products by one of the following: 1. Anemostat. 2. Nailor. 3. Price. 4. Titus. 5. Tuttle and Bailey. 2.2 SINGLE-DUCT AIR TERMINAL UNITS A. Configuration: Volume-damper
assembly inside unit casing with control components inside a protective metal shroud. B. Casing: 0.032-inch (0.8-mm) steel, single wall. 1. Casing Lining: Adhesive attached, 3/4-inch-(19-mm-)
thick, polyurethane closed cell foam insulation complying with UL 181 erosion requirements, and having a maximum flame-spread index of 25 and a maximum smoke-developed index of 50, for
both insulation and adhesive, when tested according to ASTM E 84. 2. Air Inlet: Round stub connection or S-slip and drive connections for duct attachment. 3. Air Outlet: S-slip and drive
connections. 4. Access: Removable panels for access to parts requiring service, adjustment, or maintenance; with airtight gasket. 5. Airstream Surfaces: Surfaces in contact with the
airstream shall comply with requirements in ASHRAE 62.1-2004. 6. Hanging Tabs: For supporting terminal units. C. Volume Damper: Galvanized steel with peripheral gasket and self-lubricating
bearings. 1. Maximum Damper Leakage: ARI 880 rated, 2 percent of nominal airflow at 3-inch wg (750-Pa) inlet static pressure. 2. Damper Position: Normally open.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR TERMINAL UNITS 23 36 00 -3 D. Hydronic Coils: Minimum two row, copper tube, with mechanically bonded aluminum fins spaced no closer than 0.1 inch (2.5 mm), and rated for a minimum
working pressure of 200 psig (1380 kPa) and a maximum entering-water temperature of 220 deg F (104 deg C), factory installed. Include manual air vent and drain valve. E. Controls: Refer
to Division 23 Section "Environmental Control System" for control devices installed on all terminals. 1. Flow sensing: Integral center averaging flow ring to afford velocity pressure
measurement of air volume within 2% accuracy. 2. Pneumatic controller: Accommodate direct and reverse acting thermostats, normally open or normally closed damper position and have the
ability to adjust span and reset start point. 3. Damper actuator: Actuator to be sized to provide full damper shutoff at design (before air terminal unit) system static pressure. 2.3
HANGERS AND SUPPORTS A. Hanger Rods for Non-corrosive Environments: Cadmium-plated steel rods and nuts. B. Hanger Rods for Corrosive Environments: Electro-galvanized, all-thread rods
or galvanized rods with threads painted with zinc-chromate primer after installation. C. Steel Cables: Galvanized steel complying with ASTM A 603 or stainless steel complying with ASTM
A 492. D. Steel Cable End Connections: Cadmium-plated steel assemblies with brackets, swivel, and bolts designed for duct hanger service; with an automatic-locking and clamping device.
E. Air Terminal Unit Attachments: Sheet metal screws, blind rivets, or self-tapping metal screws; compatible with duct materials. Utilize hanging tabs rather than penetrating casing.
Allow for removal of control enclosure when hanging. F. Trapeze and Riser Supports: Steel shapes and plates for units with steel casings; aluminum for units with aluminum casings. 2.4
SOURCE QUALITY CONTROL A. Factory Tests: Test assembled air terminal units according to ARI 880. 1. Label each air terminal unit with plan number, nominal airflow, maximum and minimum
factory-set airflows, coil type, and ARI certification seal.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR TERMINAL UNITS 23 36 00 -4 PART 3 -EXECUTION 3.1 INSTALLATION A. Install air terminal units according to NFPA 90A, "Standard for the Installation of Air Conditioning and Ventilating
Systems." B. Install air terminal units level and plumb. Maintain sufficient clearance for normal service and maintenance. 3.2 HANGER AND SUPPORT INSTALLATION A. Comply with SMACNA's
"HVAC Duct Construction Standards -Metal and Flexible," Chapter 4, "Hangers and Supports." B. Building Attachments: Concrete inserts, powder-actuated fasteners, or structural-steel fasteners
appropriate for construction materials to which hangers are being attached. 1. Where practical, install concrete inserts before placing concrete. 2. Install powder-actuated concrete
fasteners after concrete is placed and completely cured. 3. Use powder-actuated concrete fasteners for standard-weight aggregate concretes and for slabs more than 4 inches (100 mm) thick.
4. Do not use powder-actuated concrete fasteners for lightweight-aggregate concretes and for slabs less than 4 inches (100 mm) thick. 5. Do not use powder-actuated concrete fasteners
for seismic restraints. C. Hangers Exposed to View: Threaded rod and angle or channel supports. D. Install upper attachments to structures. Select and size upper attachments with pull-out,
tension, and shear capacities appropriate for supported loads and building materials where used. 3.3 CONNECTIONS A. Install piping adjacent to air terminal unit to allow service and
maintenance. B. Hot-Water Piping: In addition to requirements in Division 23 Section "Hydronic Piping," connect heating coils to supply with shutoff valve, strainer, control valve, and
union or flange; and to return with balancing valve and union or flange. C. Connect ducts to air terminal units according to Division 23 Section "Metal Ducts." or Division 23 Section
""Nonmetal Ducts." D. Make connections to air terminal units with flexible connectors complying with requirements in Division 23 Section "Air Duct Accessories."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR TERMINAL UNITS 23 36 00 -5 3.4 IDENTIFICATION A. Label each air terminal unit with plan number, nominal airflow, and maximum and minimum factory-set airflows. Comply with requirements
in Division 23 Section "Identification for HVAC Piping and Equipment" for equipment labels and warning signs and labels. 3.5 FIELD QUALITY CONTROL A. Tests and Inspections: 1. After
installing air terminal units and after electrical circuitry has been energized, test for compliance with requirements. 2. Leak Test: After installation, fill water coils and test for
leaks. Repair leaks and retest until no leaks exist. 3. Operational Test: After electrical circuitry has been energized, start units to confirm proper motor rotation and unit operation.
4. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and and equipment. B. Air terminal unit will be considered defective if it does not pass tests and
inspections. C. Prepare test and inspection reports. 3.6 DEMONSTRATION A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate,
and maintain air terminal units. END OF SECTION 23 36 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
DIFFUSERS, REGISTERS, AND GRILLES 23 37 13 -1 SECTION 23 37 13 -DIFFUSERS, REGISTERS, AND GRILLES PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract,
including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section includes ceiling and wall mounted diffusers, registers,
and grilles. B. Related Sections: 1. Division 23 Section "Air Duct Accessories" for fire and smoke dampers and volumecontrol dampers not integral to diffusers, registers, and grilles.
1.3 SUBMITTALS A. Product Data: For each type of product indicated, include the following: 1. Data Sheet: Indicate materials of construction, finish, and mounting details; and performance
data including throw and drop, static-pressure drop, and noise ratings. 2. Diffuser, Register, and Grille Schedule: Indicate drawing designation, room location, quantity, model number,
size, and accessories furnished. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: 1. Anemostat Products; a Mestek company. 2. Donco. 3. Nailor Industries Inc. 4. Price Industries.
5. Titus. B. See drawing schedules, plans, and details for required materials, finishes, style, sizes, pattern, performance, and accessories.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
DIFFUSERS, REGISTERS, AND GRILLES 23 37 13 -2 1. Internal insulation of slot diffuser plenums is not allowed. All slot diffuser plenums shall be externally insulated. 2.2 SOURCE QUALITY
CONTROL A. Verification of Performance: Rate diffusers, registers, and grilles according to ASHRAE 70, "Method of Testing for Rating the Performance of Air Outlets and Inlets." PART
3 -EXECUTION 3.1 EXAMINATION A. Examine areas where diffusers, registers, and grilles are to be installed for compliance with requirements for installation tolerances and other conditions
affecting performance of equipment. B. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 INSTALLATION A. Install diffusers, registers, and grilles
level and plumb. B. Ceiling-Mounted Outlets and Inlets: Drawings indicate general arrangement of ducts, fittings, and accessories. Air outlet and inlet locations have been indicated
to achieve design requirements for air volume, noise criteria, airflow pattern, throw, and pressure drop. Make final locations where indicated, as much as practical. For units installed
in lay-in ceiling panels, locate units in the center of panel. Where architectural features or other items conflict with installation, notify Architect for a determination of final location.
C. Install diffusers, registers, and grilles with airtight connections to ducts and to allow service and maintenance of dampers, air extractors, and fire dampers. D. Do not modify slot
diffuser plenums nor penetrate slot diffuser plenums for piping or conduit interferences. E. Do not install diffuser neck mounted dampers, except where specifically scheduled as such.
3.3 ADJUSTING A. After installation, adjust diffusers, registers, and grilles to air patterns indicated, or as directed, before starting air balancing. END OF SECTION 23 37 13
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR COILS 23 82 16 -1 SECTION 23 82 16 -AIR COILS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Hot-water coils. 1.3 SUBMITTALS A. Product Data: Include rated capacities,
construction details, material descriptions, and finishes of selected models; pressure drop; shipping, and operating weights; installation instructions; and startup instructions for
each type of product indicated. B. Shop Drawings: Detail equipment assemblies and indicate dimensions, weights, loads, required clearances, method of field assembly, components, and
location and size of each field connection. C. Maintenance Data: For air coils to include in maintenance manuals specified in Division 1. D. Field quality control test reports. 1.4 QUALITY
ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction,
and marked for intended use. B. Comply with ARI 410, "Standard for Forced-Circulation Air-Cooling and Air-Heating Coils," for components, construction, and rating. 1. Certify coils to
ARI 410, "Standard for Forced-Circulation Air-Cooling and Air-Heating Coils."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR COILS 23 82 16 -2 C. ASHRAE Compliance: 1. Comply with ASHRAE 33 for methods of testing, cooling, and heating coils. 2. Comply with applicable requirements in ASHRAE 62.1, Section
5 "Systems and Equipment" and Section 7 "Construction and Startup." PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by
one of the following: 1. Water Coils: a. Aerofin Corporation. b. Carrier. c. Heatcraft Inc.; Heat Transfer Division. d. L.J. Wing Co. e. Marlo. f. Trane Co. (The). 2.2 HOT-WATER COILS
A. Description: Self-draining coil fabricated to ARI 410. 1. Arrangement: Horizonal tubes. 2. Dampers: Extruded-aluminum blades with full-length drive rod with edge and end seals. B.
Piping Connections: Threaded, on same end. C. Tubes: Copper, complying with ASTM B 743, minimum 0.025 inch thick. D. Fins: Aluminum, minimum 0.007-inch thick. E. Fin and Tube Joint:
Mechanical bond. F. Headers: Cast iron with cleaning plus and drain and air vent tapping or seamless copper tube with brazed joints, prime coated. G. Frames: Galvanized-steel channel
frame, 0.0625 inch (1.6 mm). H. Ratings: Design tested and rated according to ASHRAE 33 and ARI 410. 1. Working Pressure Ratings: 200 psig (1380 kPa), 325 deg F (163 deg C).
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR COILS 23 82 16 -3 I. Source Quality Control: Factory test to 300 psig (2070 kPa), and to 200 psig (1380 kPa) underwater. PART 3 -EXECUTION 3.1 EXAMINATION A. Examine ducts, plenums,
and units to receive air coils for compliance with requirements for installation tolerances and other conditions affecting coil performance. B. Examine roughing-in for piping systems
to verify actual locations of piping connections before coil installation. C. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 INSTALLATION A.
Install coils level and plumb. B. Install coils in metal ducts and casings constructed according to SMACNA's "HVAC Duct Construction Standards, Metal and Flexible." 3.3 CONNECTIONS A.
Piping installation requirements are specified in other Division 23 Sections. Drawings indicate general arrangement of piping, fittings, and specialties. B. Install piping adjacent to
coils to allow service and maintenance. C. Unless otherwise indicated, connect piping with unions and shutoff valves to allow coils to be disconnected without draining piping. Refer
to piping system Sections for specific valve and specialty arrangements. 3.4 ADJUSTING A. Adjust initial temperature and humidity set points. B. Straighten bent fins on each air coil.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
AIR COILS 23 82 16 -4 3.5 CLEANING A. After completing system installation, including outlet fitting and devices, inspect exposed finish. Remove burrs, dirt, and construction debris
and repair damaged finishes. B. Clean coils using materials and methods recommended in writing by manufacturers, and clean inside of casings and enclosures to remove dust and debris.
END OF SECTION 23 82 16
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR ELECTRICAL 26 05 00 -1 SECTION 26 05 00 -COMMON WORK RESULTS FOR ELECTRICAL PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract,
including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Electrical equipment coordination and
installation. 2. Sleeves for raceways and cables. 3. Sleeve seals. 4. Grout. 5. Common electrical installation requirements. 6. Electrical demolition. 7. Cutting and patching for electrical
construction. 1.3 DEFINITIONS A. EPDM: Ethylene-propylene-diene terpolymer rubber. B. NBR: Acrylonitrile-butadiene rubber. 1.4 SUBMITTALS A. Product Data: For sleeve seals. 1.5 QUALITY
ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction
and marked for intended used. B. Comply with NFPA 70. C. Include in the Work, as a part of the Bid Proposal, labor, materials, services, apparatus, drawings (in addition to the Contract
Documents) as required to complete the intended work.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR ELECTRICAL 26 05 00 -2 D. Work for the Project must be performed in accordance with Federal, State and Local Laws, Ordinances, Codes, Rules and Regulations, pertaining
to the Work which are hereby made a part of the Contract Documents by reference, the same as if repeated herein in their entity. Where Contract Documents exceed these requirements, the
Contract Documents shall govern. In no case shall Work be installed contrary to or below the minimum legal standards. 1.6 COORDINATION A. Coordinate arrangement, mounting, and support
of electrical equipment: 1. To allow maximum possible headroom unless specific mounting heights that reduce headroom are indicated. 2. To provide for ease of disconnecting the equipment
with minimum interference to other installations. 3. To allow right of way for piping and conduit installed at required slope. 4. So connecting raceways, cables, wireways, cable trays,
and busways will be clear of obstructions and of the working and access space of other equipment. B. Coordinate installation of required supporting devices and set sleeves in cast-in-place
concrete, masonry walls, and other structural components as they are constructed. C. Coordinate location of access panels and doors for electrical items that are behind finished surfaces
or otherwise concealed. Access doors and panels are specified in Division 8 Section "Access Doors and Frames." D. Coordinate sleeve selection and application with selection and application
of firestopping specified in Division 7 Section "Firestopping." PART 2 -PRODUCTS 2.1 SLEEVES FOR RACEWAYS AND CABLES A. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule
40, galvanized steel, plain ends. B. Cast-Iron Pipe Sleeves: Cast or fabricated "wall pipe," equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop, unless
otherwise indicated. C. Sleeves for Rectangular Openings: Galvanized sheet steel. 1. Minimum Metal Thickness: a. For sleeve cross-section rectangle perimeter less than 50 inches (1270
mm) and no side more than 16 inches (400 mm), thickness shall be 0.052 inch (1.3 mm).
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR ELECTRICAL 26 05 00 -3 b. For sleeve cross-section rectangle perimeter equal to, or more than, 50 inches (1270 mm) and 1 or more sides equal to, or more than,
16 inches (400 mm), thickness shall be 0.138 inch (3.5 mm). 2.2 SLEEVE SEALS A. Description: Modular sealing device, designed for field assembly, to fill annular space between sleeve
and raceway or cable. 1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: a. Advance Products & Systems, Inc. b. Calpico, Inc. c. Metraflex
Co. d. Pipeline Seal and Insulator, Inc. 2. Sealing Elements: EPDM interlocking links shaped to fit surface of cable or conduit. Include type and number required for material and size
of raceway or cable. 3. Pressure Plates: Carbon steel. Include two for each sealing element. 4. Connecting Bolts and Nuts: Carbon steel with corrosion-resistant coating of length required
to secure pressure plates to sealing elements. Include one for each sealing element. 2.3 GROUT A. Nonmetallic, Shrinkage-Resistant Grout: ASTM C 1107, factory-packaged, nonmetallic aggregate
grout, non-corrosive, non-staining, mixed with water to consistency suitable for application and a 30-minute working time. PART 3 -EXECUTION 3.1 COMMON REQUIREMENTS FOR ELECTRICAL INSTALLATION
A. Comply with NECA 1. B. Measure indicated mounting heights to bottom of unit for suspended items and to center of unit for wall-mounting items. C. Headroom Maintenance: If mounting
heights or other location criteria are not indicated, arrange and install components and equipment to provide maximum possible headroom consistent with these requirements.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR ELECTRICAL 26 05 00 -4 D. Equipment: Install to facilitate service, maintenance, and repair or replacement of components of both electrical equipment and other
nearby installations. Connect in such a way as to facilitate future disconnecting with minimum interference with other items in the vicinity. E. Right of Way: Give to piping systems
installed at a required slope. 3.2 SLEEVE INSTALLATION FOR ELECTRICAL PENETRATIONS A. Electrical penetrations occur when raceways, cables, wireways, cable trays, or busways penetrate
concrete slabs, concrete or masonry walls, or fire-rated floor and wall assemblies. B. Concrete Slabs and Walls: Install sleeves for penetrations unless core-drilled holes or formed
openings are used. Install sleeves during erection of slabs and
walls. C. Use pipe sleeves unless penetration arrangement requires rectangular sleeved opening. D. Fire-Rated Assemblies: Install sleeves for penetrations of fire-rated floor and wall
assemblies unless openings compatible with firestop system used are fabricated during construction of floor or wall. E. Cut sleeves to length for mounting 2”-3” extending out of both
surfaces of walls. F. Extend sleeves installed in floors 2 inches (50 mm) above finished floor level. G. Size pipe sleeves to provide 1/4-inch (6.4-mm) annular clear space between sleeve
and raceway or cable, unless indicated otherwise. H. Seal space outside of sleeves with grout for penetrations of concrete and masonry 1. Promptly pack grout solidly between sleeve and
wall so no voids remain. Tool exposed surfaces smooth; protect grout while curing. I. Fire-Rated-Assembly Penetrations: Maintain indicated fire rating of walls, partitions, ceilings,
and floors at raceway and cable penetrations. Install sleeves and seal raceway and cable penetration sleeves with firestop materials. Comply with requirements in Division 7 Section "Firestopping."
J. Roof-Penetration Sleeves: Seal penetration of individual raceways and cables with flexible boot-type flashing units applied in coordination with roofing work. K. Above Ground, Exterior-Wall
Penetrations: Seal penetrations using cast-iron pipe sleeves and mechanical sleeve seals. Select sleeve size to allow for 1-inch (25-mm) annular clear space between pipe and sleeve for
installing mechanical sleeve seals.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR ELECTRICAL 26 05 00 -5 L. Underground, Exterior-Wall Penetrations: Install cast-iron pipe sleeves. Size sleeves to allow for 1-inch (25-mm) annular clear space
between raceway or cable and sleeve for installing mechanical sleeve seals. 3.3 SLEEVE-SEAL INSTALLATION A. Install to seal exterior wall penetrations. B. Use type and number of sealing
elements recommended by manufacturer for raceway or cable material and size. Position raceway or cable in center of sleeve. Assemble mechanical sleeve seals and install in annular space
between raceway or cable and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make watertight seal. 3.4 DEMOLITION A. Refer to Division 2 for general
demolition requirements and procedures. B. Protect existing electrical equipment and and installations indicated to remain. If damaged or disturbed in the course of the Work, remove
damaged portions and install new products of equal capacity, quality, and functionality. C. Accessible Work: 1. Remove exposed electrical equipment and installations, indicated to be
demolished, in their entirety. D. Abandoned Work: 1. Cut and remove buried raceway and wiring, indicated to be abandoned in place, 2 inches (50 mm) below the surface of adjacent construction.
Cap raceways and patch surface to match existing finish. E. Remove, store, clean, reinstall, reconnect and make operational components indicated for relocation. F. Locate and identify
electrical services passing through affected area and serving other areas outside the work limits. G. Services to areas outside work limits shall be maintained uninterrupted unless specifically
authorized otherwise in writing by the Owner. When transient services must be interrupted, provide temporary services for affected areas outside work limits. H. Existing raceway and
boxes may be reused where found to be suitable and meeting applicable codes and Contract Documents. Provide extension rings on existing boxes as required to be
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR ELECTRICAL 26 05 00 -6 compatible with new building finishes. Provide blank cover matching other devices plates on unused device boxes that must remain. I. All
reusable salvaged material shall remain the property of the Owner and be retained for his inspection. Only items so inspected and rejected by the Owner shall be disposed by the Contractor.
All other such items shall be turned over and deposited as directed by the Owner. J. Disposal of light fixture lamps and ballast shall be in strict accordance with Federal, State and
Local Laws, Ordinances, Codes, Rules and Regulations pertaining to such material. Include proper documentation in operation and maintenance manual of such material disposal. 3.5 CUTTING
AND PATCHING A. Refer to Division 2 for general cutting and patching requirements and procedures. B. Cut, channel, chase and drill floors, walls, partitions, ceilings and other surfaces
required to permit electrical installations. Perform cutting by skilled mechanics of trades involved. C. Repair and refinish disturbed finish materials and other surfaces to match adjacent
undisturbed surfaces. Install new fireproofing where existing firestopping has been disturbed. Repair and refinish materials and other surfaces by skilled mechanics of trades involved.
3.6 FIRESTOPPING A. Apply firestopping to penetrations of fire-rated floor and wall assemblies for electrical installations to restore original fire-resistance rating of assembly. Firestopping
materials and installation requirements are specified in Division 7 Section "Firestopping." 3.7 CLEANING AND PROTECTION A. On completion of installation, including outlets, fittings
and devices, inspect exposed finish. Remove burrs, dirt, paint spots, and construction debris. B. Protect equipment and installations and maintain conditions to ensure that coatings,
finishes, and cabinets are without damage or deterioration at time of Substantial Completion. END OF SECTION 26 05 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 26 05 19 -1 SECTION 26 05 19 -LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings
and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes
the following: 1. Building wires and cables rated 600 V and less. 2. Connectors, splices, and terminations rated 600 V and less. 1.3 SUBMITTALS A. Product Data: For each type of product
indicated. B. Field quality-control test reports. 1.4 QUALITY ASSURANCE A. Contractor with qualifications and minimum ten (10) years experience in installation, splicing and testing
of low voltage power conductors may be considered at discretion of Architect/Engineer, as acceptable agency. B. Electrical Components, Devices, and Accessories: Listed and labeled as
defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. C. Comply with NFPA 70. PART 2 -PRODUCTS 2.1 CONDUCTORS
AND CABLES A. Available Manufacturers: Subject to compliance with requirements, provide products by one of the following:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 26 05 19 -2 1. American Insulated Wire Corp.; a Leviton Company. 2. General Cable Corporation. 3. Senator Wire & Cable Company. 4.
Southwire Company. B. Copper Conductors: Comply with NEMA WC 70. C. Conductor Insulation: Comply with NEMA WC 70 for Types THW and THHN-THWN. 2.2 CONNECTORS AND SPLICES A. Available
Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. AFC Cable Systems, Inc. 2. Hubbell Power Systems, Inc. 3. O-Z/Gedney; EGS Electrical
Group LLC. 4. 3M; Electrical Products Division. 5. Tyco Electronics Corp. B. Description: Factory-fabricated connectors and splices of size, ampacity rating, material, type, and class
for application and service indicated. PART 3 -EXECUTION 3.1 CONDUCTOR MATERIAL APPLICATIONS A. A. Feeders: Copper. B. Branch Circuits: Copper, stranded. C. The minimum conductor size
shall be #12 AWG. 3.2 CONDUCTOR INSULATION AND MULTICONDUCTOR CABLE APPLICATIONS AND WIRING METHODS A. Feeders: Type THHN-THWN, single conductors in raceway. B. Branch Circuits (minimum
#12 AWG): Type THHN-THWN, single conductors in raceway. C. Cord Drops and Portable Appliance Connections: Type SO, hard service cord with stainlesssteel, wire-mesh, strain relief device
at terminations to suit application. D. Class 1 Control Circuits: Type THHN-THWN, in raceway.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 26 05 19 -3 E. Class 2 Control Circuits: Type THHN-THWN, in raceway. 3.3 INSTALLATION OF CONDUCTORS AND CABLES A. Conceal cables in
finished walls, ceilings, and floors, unless otherwise indicated. B. Use manufacturer-approved pulling compound or lubricant where necessary; compound used must not deteriorate conductor
or insulation. Do not exceed manufacturer's recommended maximum pulling tensions and sidewall pressure values. C. Use pulling means, including fish tape, cable, rope, and basket-weave
wire/cable grips, that will not damage cables or raceway. D. Install exposed cables parallel and perpendicular to surfaces of exposed structural members, and follow surface contours
where possible. E. Support cables according to Division 26 Section "Hangers and Supports for Electrical Systems." F. Identify and color-code conductors and cables according to Division
26 Section "Identification for Electrical Systems." G. Each branch circuit shall be provided with a dedicated neutral conductor. Sharing of the neutral conductor between multiple circuits
will not be allowed. H. A single raceway shall be limited to a maximum of six current carrying conductors. 3.4 CONNECTIONS A. Tighten electrical connectors and terminals according to
manufacturer's published torquetightening values. If manufacturer's torque values are not indicated, use those specified in UL 486A and UL 486B. B. Make splices and taps that are compatible
with conductor material and that possess equivalent or better mechanical strength and insulation ratings than unspliced conductors. C. Wiring at Outlets: Install conductor at each outlet,
with at least 6 inches (150 mm) of slack. 3.5 FIELD QUALITY CONTROL A. Perform tests and inspections and prepare test reports. B. Tests and Inspections: 1. After installing conductors
and cables and before electrical circuitry has been energized, test feeder conductors for compliance with requirements.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 26 05 19 -4 a. Megger Test for insulation integrity. b. Test all branch circuit wiring for leakage current requirements for NFPA 99
for isolation panelboard. 2. Perform each visual and mechanical inspection and electrical test stated in NETA Acceptance Testing Specification. Certify compliance with test parameters.
C. Test Reports: Prepare a written report to record the following: 1. Test procedures used. 2. Test results that comply with requirements. 3. Test results that do not comply with requirements
and corrective action taken to achieve compliance with requirements. D. Remove and replace malfunctioning units and retest as specified above. END OF SECTION 26 05 19
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 05 26 -1 SECTION 26 05 26 -GROUNDING AND BONDING FOR ELECTRICAL SYSTEM PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions
of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes methods and materials
for grounding systems and equipment. 1.3 SUBMITTALS A. Product Data: For each type of product indicated. B. Field quality-control test reports. 1.4 QUALITY ASSURANCE A. Electrical Components,
Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. B. Comply
with UL 467 for grounding and bonding materials and equipment. PART 2 -PRODUCTS 2.1 CONDUCTORS A. Insulated Conductors: Tinned-copper wire or cable insulated for 600 V unless otherwise
required by applicable Code or authorities having jurisdiction. B. Bare Copper Conductors: 1. Solid Conductors: ASTM B 3. 2. Stranded Conductors: ASTM B 8. 3. Tinned Conductors: ASTM
B 33.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 05 26 -2 4. Bonding Cable: 28 kcmil, 14 strands of No. 17 AWG conductor, 1/4 inch (6 mm) in diameter. 5. Bonding Conductor: No. 4 or No.
6 AWG, stranded conductor. 6. Bonding Jumper: Copper tape, braided conductors, terminated with copper ferrules; 1-5/8 inches (41 mm) wide and 1/16 inch (1.6 mm) thick. 7. Tinned Bonding
Jumper: Tinned-copper tape, braided conductors, terminated with copper ferrules; 1-5/8 inches (41 mm) wide and 1/16 inch (1.6 mm) thick. 2.2 CONNECTORS A. Listed and labeled by a nationally
recognized testing laboratory acceptable to authorities having jurisdiction for applications in which used, and for specific types, sizes, and combinations of conductors and other items
connected. B. Bolted Connectors for Conductors and Pipes: Copper or copper alloy, bolted pressure-type, with at least two bolts. 1. Pipe Connectors: Clamp type, sized for pipe. C. Welded
Connectors: Exothermic-welding kits of types recommended by kit manufacturer for materials being joined and installation conditions. PART 3 -EXECUTION 3.1 APPLICATIONS A. Conductors:
Install solid conductor for No. 8 AWG and smaller, and stranded conductors for No. 6 AWG and larger, unless otherwise indicated. B. Conductor Terminations and Connections: 1. Pipe and
Equipment Grounding Conductor Terminations: Bolted connectors. 2. Connections to Structural Steel: Welded connectors. 3.2 EQUIPMENT GROUNDING A. Install insulated equipment grounding
conductors for all electrical distribution, in addition to those required by NFPA 70 and as follows: 1. Feeders and branch circuits. 2. Lighting circuits. 3. Receptacle circuits. 4.
Single-phase motor and appliance branch circuits.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 05 26 -3 5. Three-phase motor and appliance branch circuits. 6. Flexible raceway runs. 7. Computer and rack-mounted electronic equipment
circuits. 8. X-Ray Equipment Circuits: Install insulated equipment grounding conductor in circuits supplying x-ray equipment. 9. Cable tray system. 3.3 INSTALLATION A. Grounding Conductors:
Route along shortest and straightest paths possible, unless otherwise indicated or required by Code. Avoid obstructing access or placing conductors where they may be subjected to strain,
impact, or damage. B. Bonding Straps and Jumpers: Install in locations accessible for inspection and maintenance, except where routed through short lengths of conduit. 1. Bonding to
Structure: Bond straps directly to basic structure, taking care not to penetrate any adjacent parts. 2. Bonding to Equipment Mounted on Vibration Isolation Hangers and Supports: Install
so vibration is not transmitted to rigidly mounted equipment. C. Grounding and Bonding for Piping: 1. Metal Water Service Pipe: Provide bonding as per NEC 250, install insulated copper
grounding conductors, in conduit, from building's main service equipment, or grounding bus, to main metal water service entrances to building. Connect grounding conductors to main metal
water service pipes, using a bolted clamp connector or by bolting a lug-type connector to a pipe flange, using one of the lug bolts of the flange. Where a dielectric main water fitting
is installed, connect grounding conductor on street side of fitting. Bond metal grounding conductor conduit or sleeve to conductor at each end. 2. Water Meter Piping: Use braided-type
bonding jumpers to electrically bypass water meters. Connect to pipe with a bolted connector. 3. Bond each above ground portion of gas piping system downstream from equipment shutoff
shutoff valve. D. Grounding for Steel Building Structure: Install a driven ground rod at base of each corner column and at intermediate exterior columns at distances not more than 60
feet (18 m) apart. 3.4 FIELD QUALITY CONTROL A. Perform the following tests and inspections and prepare test reports: 1. After installing grounding system but before permanent electrical
circuits have been energized, test for compliance with requirements.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 26 05 26 -4 B. Report measured ground resistances that exceed the following values: 1. Power and Lighting Equipment or System with Capacity
500 kVA and Less: 10 ohms. C. Excessive Ground Resistance: If resistance to ground exceeds specified values, notify Architect promptly and include recommendations to reduce ground resistance.
END OF SECTION 26 05 26
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 05 29 -1 SECTION 26 05 29 -HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions
of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Hangers
and supports for electrical equipment and systems. 2. Construction requirements for concrete bases. 1.3 DEFINITIONS A. EMT: Electrical metallic tubing. B. IMC: Intermediate metal conduit.
C. RMC: Rigid metal conduit. 1.4 PERFORMANCE REQUIREMENTS A. Delegated Design: Design supports for multiple raceways, including comprehensive engineering analysis by a qualified professional
engineer, using performance requirements and design criteria indicated. B. Design supports for multiple raceways capable of supporting combined weight of supported systems and its contents.
C. Design equipment supports capable of supporting combined operating weight of supported equipment and connected systems and components. 1.5 SUBMITTALS A. Product Data: For the following:
1. Steel slotted support systems.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 05 29 -2 B. Shop Drawings: Show fabrication and installation details and include calculations for the following: 1. Trapeze hangers. Include
Product Data for components. 2. Steel slotted channel systems. Include Product Data for components. 3. Equipment supports. C. Welding certificates. 1.6 QUALITY ASSURANCE A. Welding:
Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code -Steel." B. Comply with NFPA 70. C. Comply with IBC and UBC. 1.7 COORDINATION A. Coordinate size
and location of concrete bases. Cast anchor-bolt inserts into bases. Concrete, reinforcement, and formwork requirements are specified in Division 3. B. Coordinate installation of roof
curbs, equipment supports, and roof penetrations. These items are specified in Division 7 Section "Roof Accessories." PART 2 -PRODUCTS 2.1 SUPPORT, ANCHORAGE, AND ATTACHMENT COMPONENTS
A. Steel Slotted Support Systems: Comply with MFMA-4, factory-fabricated components for field assembly. 1. Available Manufacturers: Subject to compliance with requirements, provide product
by one of the following: a. Allied Tube & Conduit. b. Cooper B-Line, Inc.; a division of Cooper Industries. c. ERICO International Corporation. d. GS Metals Corp. e. Thomas & Betts Corporation.
f. Unistrut; Tyco International, Ltd. g. Wesanco, Inc.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 05 29 -3 2. Metallic Coatings: Hot-dip galvanized after fabrication and applied according to MFMA-4. 3. Nonmetallic Coatings: Manufacturer's
standard PVC, polyurethane, or polyester coating applied according to MFMA-4. 4. Painted Coatings: Manufacturer's standard painted coating applied according to MFMA-4. 5. Channel Dimensions:
Selected for applicable load criteria. B. Raceway and Cable Supports: As described in NECA 1 and NECA 101. C. Conduit and Cable Support Devices: Steel and malleable-iron hangers, clamps,
and associated fittings, designed for types and sizes of raceway or cable to be supported. D. Support for Conductors in Vertical Conduit: Factory-fabricated assembly consisting of threaded
body and insulating wedging plug or plugs for non-armored electrical conductors or cables in riser conduits. Plugs shall have number, size, and shape of conductor gripping pieces as
required to suit individual conductors or cables supported. Body shall be malleable iron. E. Structural Steel for Fabricated Supports and Restraints: ASTM A 36/A 36M, steel plates, shapes,
and bars; black and galvanized. F. Mounting, Anchoring, and Attachment Components: Items for fastening electrical items or their supports to building surfaces include the following:
1. Powder-Actuated Fasteners: Threaded-steel stud, for use in hardened portland cement concrete, steel, or wood, with tension, shear, and pullout capacities appropriate for supported
loads and building materials where used. a. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include,
but are not limited to, the following: 1) Hilti Inc. 2) ITW Ramset/Red Head; a division of Illinois Tool Works, Inc. 3) MKT Fastening, LLC. 4) Simpson Strong-Tie Co., Inc.; Masterset
Fastening Systems Unit. 2. Mechanical-Expansion Anchors: Insert-wedge-type, stainless steel, for use in hardened portland cement concrete with tension, shear, and pullout capacities
appropriate for supported loads and building materials in which used. a. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be
incorporated into the Work include, but are not limited to, the following: 1) Cooper B-Line, Inc.; a division of Cooper Industries. 2) Empire Tool and Manufacturing Co., Inc.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 05 29 -4 3) Hilti Inc. 4) ITW Ramset/Red Head; a division of Illinois Tool Works, Inc. 5) MKT Fastening, LLC. 3. Concrete Inserts: Steel
or malleable-iron, slotted support system units similar to MSS Type 18; complying with MFMA-4 or MSS SP-58. 4. Clamps for Attachment to Steel Structural Elements: MSS SP-58, type suitable
for attached structural element. 5. Through Bolts: Structural type, hex head, and high strength. Comply with ASTM A 325. 6. Toggle Bolts: All-steel springhead type. 7. Hanger Rods: Threaded
steel. 2.2 FABRICATED METAL EQUIPMENT SUPPORT ASSEMBLIES A. Description: Welded or bolted, structural-steel shapes, shop or field fabricated to fit dimensions of supported equipment.
B. Materials: Comply with requirements in Division 5 Section "Metal Fabrications" for steel shapes and plates. PART 3 -EXECUTION 3.1 APPLICATION A. Comply with NECA 1 and NECA 101 for
application of hangers and supports for electrical equipment and systems except if requirements in this Section are stricter. B. Maximum Support Spacing and Minimum Hanger Rod Size for
Raceway: Space supports for EMT, IMC, and RMC as required by NFPA 70. Minimum rod size shall be 1/4 inch (6 mm) in diameter. Support conduit within 10” from box and bend, maximum 10’
apart and minimum of one support for conduit length. C. Multiple Raceways or Cables: Install trapeze-type supports fabricated with steel slotted support system, sized so capacity can
be increased by at least 25 percent in future without exceeding specified design load limits. 1. Secure raceways and cables to these supports with single-bolt conduit clamps using spring
friction action for retention in support channel. D. Spring-steel clamps designed for supporting single conduits without bolts may be used for 1-1/2-inch (38-mm) and smaller raceways
serving branch circuits and communication systems above suspended ceilings and for fastening raceways to trapeze supports.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS 26 05 29 -5 E. Use of power actuated fasteners may only be permitted at scheduled portions of the day or week. Obtain written approval from
Owner on acceptable times for use. 3.2 SUPPORT INSTALLATION A. Comply with NECA 1 and NECA 101 for installation requirements except as specified in this Article. B. Raceway Support Methods:
In addition to methods described in NECA 1, EMT, IMC, and RMC may be supported by openings through structure members, as permitted in NFPA 70. C. Strength of Support Assemblies: Where
not indicated, select sizes of components so strength will be adequate to carry present and future static loads within specified loading limits. Minimum static design load used for strength
determination shall be weight of supported components plus 200 lb (90 kg). D. Mounting and Anchorage of Surface-Mounted Equipment and Components: Anchor and fasten electrical items and
their supports to building structural elements by the following methods unless otherwise indicated by code: 1. To Wood: Fasten with lag screws or through bolts. 2. To New Concrete: Bolt
to concrete inserts. 3. To Masonry: Approved toggle-type bolts on hollow masonry units and expansion anchor fasteners on solid masonry units. 4. To Existing Concrete: Expansion anchor
fasteners. 5. Instead of expansion anchors, powder-actuated driven threaded studs provided with lock washers and nuts may be used in existing standard-weight concrete 4 inches (100 mm)
thick or greater. Do not use for anchorage to lightweight-aggregate concrete or for slabs less than 4 inches (100 mm) thick. 6. To Steel: Beam clamps (MSS Type 19, 21, 23, 25, or 27)
complying with MSS SP-69. 7. To Light Steel: Sheet metal screws. 8. Items Mounted on Hollow Walls and Nonstructural Building Surfaces: Mount cabinets, panelboards, disconnect switches,
control enclosures, pull and junction boxes, transformers, and other devices on slotted-channel racks attached to substrate by means that meet seismic-restraint strength and anchorage
requirements. E. Drill holes for expansion anchors in concrete at locations and to depths that avoid reinforcing bars. 3.3 INSTALLATION OF FABRICATED METAL SUPPORTS A. Comply with installation
requirements in Division 5 Section "Metal Fabrications" for sitefabricated metal supports.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
HANGERS AND SUPPORTS
FOR ELECTRICAL SYSTEMS 26 05 29 -6 B. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor electrical materials and
equipment. C. Field Welding: Comply with AWS D1.1/D1.1M. 3.4 CONCRETE BASES A. Construct concrete bases of dimensions indicated but not less than 4 inches (100 mm) larger in both directions
than supported unit, and so anchors shall be a minimum of 10 bolt diameters from edge of the base. Chamfer concrete pad 3/4 inch. B. Use 3000-psi (20.7-MPa), 28-day compressive-strength
concrete. Concrete materials, reinforcement, and placement requirements are specified in Division 3 Section "Cast-in-Place Concrete." C. Anchor equipment to concrete base. 1. Place and
secure anchorage devices. Use supported equipment manufacturer's manufacturer's setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.
2. Install anchor bolts to elevations required for proper attachment to supported equipment. 3. Install anchor bolts according to anchor-bolt manufacturer's written instructions. 3.5
PAINTING A. Touchup: Clean field welds and abraded areas of shop paint. Paint exposed areas immediately after erecting hangers and supports. Use same materials as used for shop painting.
Comply with SSPC-PA 1 requirements for touching up field-painted surfaces. 1. Apply paint by brush or spray to provide minimum dry film thickness of 2.0 mils (0.05 mm). B. Touchup: Comply
with requirements in Division 9 painting sections for cleaning and touchup painting of field welds, bolted connections, and abraded areas of shop paint on miscellaneous metal. C. Galvanized
Surfaces: Clean welds, bolted connections, and abraded areas and apply galvanizing-repair paint to comply with ASTM A 780. END OF SECTION 26 05 29
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 05 33 -1 SECTION 26 05 33 -RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions
of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Raceways,
fittings, boxes, enclosures, and cabinets for electrical wiring. 2. Surface raceway. 3. Conduit sleeve and firestop. 4. Core drill for electrical work. B. Related Section includes the
following: 1. Division 26 "Underground Ducts and Raceway for Electrical Systems." 1.3 DEFINITIONS A. EMT: Electrical metallic tubing. B. ENT: Electrical nonmetallic tubing. C. EPDM:
Ethylene-propylene-diene terpolymer rubber. D. FMC: Flexible metal conduit. E. IMC: Intermediate metal conduit. F. LFMC: Liquidtight flexible metal conduit. G. LFNC: Liquidtight flexible
nonmetallic conduit. H. NBR: Acrylonitrile-butadiene rubber. I. RNC: Rigid nonmetallic conduit.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 05 33 -2 1.4 SUBMITTALS A. Product Data: For surface raceways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.
B. Shop Drawings: For the following raceway components. Include plans, elevations, sections, details, and attachments to other work. C. Source quality-control test reports. 1.5 QUALITY
ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction,
and marked for intended use. B. Comply with NFPA 70, 79. C. Product shall be UL approved. D. Comply with ANSI C2. PART 2 -PRODUCTS 2.1 METAL CONDUIT AND TUBING A. Available Manufacturers:
Subject to compliance with requirements, provide product by one of the following: 1. Allied Tube & Conduit; a Tyco International Ltd. Co. 2. Anamet Electrical, Inc.; Anaconda Metal Hose.
3. Manhattan/CDT/Cole-Flex. 4. Maverick Tube Corporation. 5. O-Z Gedney; a unit of General Signal. 6. Wheatland Tube Company. B. Rigid Steel Conduit: ANSI C80.1. C. IMC: ANSI C80.6.
D. EMT: ANSI C80.3. E. FMC: Zinc-coated steel. F. LFMC: Flexible steel conduit with PVC jacket and UL label.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 05 33 -3 G. Fittings for Conduit (Including all Types and Flexible and Liquidtight): NEMA FB 1; listed for type and size raceway with which
used, and for application and environment in which installed. 1. Conduit Fittings for Hazardous (Classified) Locations: Comply with UL 886. 2. Fittings for EMT: Steel or die-cast, set-screw
type. 3. Fittings for Rigid and Intermediate Steel Conduit: Threaded rigid steel conduit. H. Joint Compound for Rigid Steel Conduit or IMC: Listed for use in cable connector assemblies,
and compounded for use to lubricate and protect threaded raceway joints from corrosion and enhance their conductivity. 2.2 NONMETALLIC CONDUIT AND TUBING A. Manufacturers: Subject to
compliance with requirements, provide product by one of the following: 1. AFC Cable Systems, Inc. 2. Anamet Electrical, Inc.; Anaconda Metal Hose. 3. Arnco Corporation. 4. CANTEX Inc.
5. CertainTeed Corp.; Pipe & Plastics Group. 6. Condux International, Inc. 7. ElecSYS, Inc. 8. Electri-Flex Co. 9. Lamson & Sessions; Carlon Electrical Products. 10. Manhattan/CDT/Cole-Flex.
11. RACO; a Hubbell Company. 12. Thomas & Betts Corporation. B. ENT: NEMA TC 13. C. RNC: NEMA TC 2, Type EPC-40-PVC, unless otherwise indicated. D. LFNC: UL 1660. E. Fittings for ENT
and RNC: NEMA TC 3; match to conduit or tubing type and material. F. Fittings for LFNC: UL 514B. 2.3 METAL WIREWAYS A. Available Manufacturers: Subject to compliance with requirements,
manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following: 1. Cooper B-Line, Inc.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 05 33 -4 2. Hoffman. 3. Square D; Schneider Electric. B. Description: Sheet metal sized and shaped as indicated, NEMA 250, Type 1, unless
otherwise indicated. 1. Indoor, JIC type, minimum 16 gage, 14 gage for 6” X 6” or larger, finish with gray enamel finish. C. Fittings and Accessories: Include couplings, offsets, elbows,
expansion joints, adapters, holddown straps, end caps, and other fittings to match and mate with wireways as required for complete system. D. Wireway Covers: Screw-cover type. E. Finish:
Manufacturer's standard enamel finish. 2.4 SURFACE RACEWAYS A. Surface Metal Raceways: Galvanized steel with snap-on covers. Manufacturer's standard enamel finish in color selected by
Architect. 1. Manufacturers: Subject to compliance with requirements, provide product by by one of the following: a. Thomas & Betts Corporation. b. Walker Systems, Inc.; Wiremold Company
(The). c. Wiremold Company (The); Electrical Sales Division. 2.5 BOXES, ENCLOSURES, AND CABINETS A. Available Manufacturers: Subject to compliance with requirements, provide product
by one the following: 1. Cooper Crouse-Hinds; Div. of Cooper Industries, Inc. 2. EGS/Appleton Electric. 3. Erickson Electrical Equipment Company. 4. Hoffman. 5. Hubbell Incorporated;
Killark Electric Manufacturing Co. Division. 6. O-Z/Gedney; a unit of General Signal. 7. RACO; a Hubbell Company. 8. Robroy Industries, Inc.; Enclosure Division. 9. Scott Fetzer Co.;
Adalet Division. 10. Spring City Electrical Manufacturing Company. 11. Thomas & Betts Corporation.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 05 33 -5 12. Walker Systems, Inc.; Wiremold Company (The). 13. Woodhead, Daniel Company; Woodhead Industries, Inc. Subsidiary. B. Sheet Metal
Outlet and Device Boxes: NEMA OS 1, minimum 4” X 4” X 2-1/8” deep. Provide with single gang plaster ring unless two gang plaster ring is specifically noted elsewhere to be provided.
C. Cast-Metal Outlet and Device Boxes: NEMA FB 1, Type FD, with gasketed cover. Minimum 4” X 4” X 2-1/8” deep. Provide with single gang plaster ring unless two gang plaster ring is specifically
noted elsewhere to be provided. D. Small Sheet Metal Pull and Junction Boxes: NEMA OS 1. E. Cast-Metal Access, Pull, and Junction Boxes: NEMA FB 1 gasketed cover. F. The box support
bracket shall be with support leg to eliminate movement of box in wall. The box support shall be attached to metal stud by using screw gun. The box support shall have an offset for drywall.
G. Device rough-in boxes shall be securely and rigidly attached and supported plumb, level and true to the building lines using one of the following: 1. Screw Gun Box Brackets: Preset
for metal stud 16” or 24” on center, depth set for 2-1/2” deep electrical box. Install using screw gun. 2. Box Mounting Bracket: Allow 4” or 4-11/16” boxes. Bendable leg serves as a
bracket stabilizer. 3. Extension Plate Bracket: Allow outlet boxes 12” or 18” offset from either metal stud track or a stud. Allow 4” or 4-11/16” outlet boxes, 2-1/8” deep, bracket with
bendable stabilizer leg for use on 2-1/2” and 3-1/2” metal studs for bracket sterilizer. H. Hinged-Cover Enclosures: Continuous hinged door in front cover with flush latch and concealed
hinge (door-in-door) unless otherwise indicated. 1. Metal Enclosures: NEMA 250, Type 1, galvanized-steel box with removable interior panel and removable front, finished inside and and
out with manufacturer's standard enamel. 2. Key latch to match panelboards. 3. Metal barriers to separate wiring of different systems and voltage. 4. Accessory feet where required for
freestanding equipment. PART 3 -EXECUTION 3.1 RACEWAY APPLICATION A. Outdoors: Apply raceway products as specified below, unless otherwise indicated:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 05 33 -6 1. Exposed Conduit: Rigid steel conduit. 2. Concealed Conduit, Aboveground: Rigid steel conduit. 3. Connection to Vibrating Equipment
(Including Transformers and Hydraulic, Pneumatic, Electric Solenoid, or Motor-Driven Equipment): LFMC. 4. Boxes and Enclosures, Aboveground: NEMA 250, Type 3R. B. Indoors: Apply raceway
product as specified herein, unless otherwise indicated: 1. Exposed in Mechanical Room: IMC. 2. Branch Circuit: EMT. 3. Concrete Wall/Column: GRC. 4. Refrigerated Area: GRC. 5. Panel
Feeder: IMC. 6. Equipment Feeder, 2” and larger: IMC. 7. Connection to Vibrating Equipment (including transformers and hydraulic, pneumatic, electric solenoid, or motor-driven equipment):
LFMC. 8. Damp or Wet Locations: Rigid steel conduit. C. Minimum Raceway Size: 3/4-inch (21-mm) trade size. 3.2 INSTALLATION A. Comply with NECA 1 for installation requirements applicable
to products specified in Part 2 except where requirements on Drawings or in this Article are stricter. B. Keep raceways at least 6 inches (150 mm) away from parallel runs of flues and
steam or hotwater pipes. Install horizontal raceway runs above water and steam piping. C. Complete raceway installation before starting conductor installation. D. Support raceways as
specified in Division 26 Section "Hangers and Supports for Electrical System" and "Vibration and Seismic Controls for Electrical Work." E. Arrange stub-ups so curved portions of bends
are not visible above the finished slab. F. Install no more than the equivalent of three 90-degree bends in any conduit run except for communications conduits, for which fewer bends
are allowed. G. Conceal conduit within finished walls and ceilings, unless otherwise indicated. H. Raceways embedded in slabs or below slab inside the building envelope are not permitted
unless shown on Contract Documents. I. Threaded Conduit Joints, Exposed to Wet, Damp, Corrosive, or Outdoor Conditions: Apply listed compound to threads of raceway and fittings before
making up joints. Follow compound manufacturer's written instructions.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 05 33 -7 J. Raceway Terminations at Locations Subject to Moisture or Vibration: Use insulating bushings to protect conductors, including
bushing for size No. 6 AWG and larger conductors. K. Install pull wires in empty raceways. Use polypropylene or monofilament plastic line with not less than 200-lb (90-kg) tensile strength.
Leave at least 12 inches (300 mm) of slack at each end of pull wire. L. Install raceway sealing fittings at suitable, approved, and accessible locations and fill them with listed sealing
compound. For concealed raceways, install each fitting in a flush steel box with a blank cover plate having a finish similar to that of adjacent plates or surfaces. Install raceway sealing
fittings at the following points: 1. Where conduits pass from warm to cold locations, such as boundaries of refrigerated spaces. 2. Where otherwise required by NFPA 70. M. Flexible Conduit
Connections: Use maximum of 72 inches (1830 mm) of flexible conduit for recessed and semi-recessed lighting fixtures, use LFMC for equipment subject to vibration, noise transmission,
or movement; transformers, motors and damp/wet location. N. Recessed Boxes in Masonry Walls: Saw-cut opening for box in center of cell of masonry block, and install box flush with surface
of wall. 3.3 DEVICE ROUGH-IN BOX A. Finish plates shall not span different types of wall finishes either vertically or horizontally. Plates shall cover mortar joints and cut openings
completely. B. Outlet, junction and pull boxes, and their covers shall have corrosion protection suitable for the atmosphere in which they are installed. Provide gaskets for all boxes
installed outside and other wet or damp locations (tunnels, crawl spaces, pits, etc.). C. Outlet boxes shall be protected to prevent entrance of plaster, and debris shall be thoroughly
cleaned from the box prior to installation of conductors. D. Single gang opening outlet boxes shall be mounted with the long axis vertical unless otherwise noted for horizontal mounting.
Three or more gang boxes shall be mounted with the long axis horizontal. E. Finish plates shall be a type designed, intended, and appropriate for the use and location. F. Existing outlet
boxes are being reused, provide extension rings compatible with new wall surfaces or finishes. G. Provide outlet box with barrier for grouped or ganged light switched where voltage between
adjacent switches exceeds 300 volt AC per NEC Article 380.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 26 05 33 -8 H. Provide outlet box with barrier and separate conduit feed for switches grouped or ganged where connected to utility power and
standby power. 3.4 METAL RACEWAY A. Metal raceway duct shall be installed level and true to building construction lines such that removable or hinged covers can be operated to be fully
accessible. B. Routing shall be pre-planned by the Contractor to assure right-of-way and accessibility; routing indicated by Contract Documents shall be considered schematic in nature
and may require job site alteration to avoid interference. C. Metal raceway duct shall be adequately supported at not more than 5'-0" intervals. The support accessories shall be of the
same manufacturer as metal raceway. D. Metal raceway duct penetrations of walls shall be unbroken lengths, scaled to the wall opening; dead ends shall be closed with manufactured closures.
E. Metal raceway duct to be installed surface mounted; flush in wall or in floor as indicated by the Contract Documents. F. Provide approved wall flanges and fully seal all penetrations
of fire and smoke rated walls and partitions, cutting and patching as needed. G. Provide divider to compartment the metal raceway duct as indicated by Contract Documents. 3.5 FIRESTOPPING
A. Apply firestopping to electrical penetrations of fire-rated floor and wall assemblies to restore original fire-resistance rating of assembly. Firestopping materials and installation
requirements are specified in Division 7 Section "Firestopping." END OF SECTION 26 05 33
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
CABLE TRAYS FOR ELECTRICAL SYSTEMS 26 05 36 -1 SECTION 26 05 36 -CABLE TRAYS FOR ELECTRICAL SYSTEMS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract,
including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes wire basket cable trays and accessories.
1.3 SUBMITTALS A. Product Data: Include data indicating dimensions and finishes for each type of cable tray indicated. B. Shop Drawings: For each type of cable tray. 1. Show fabrication
and installation details of cable tray, including plans, elevations, and sections of components and attachments to other construction elements. Designate components and accessories,
including clamps, brackets, hanger rods, splice-plate connectors, expansion-joint assemblies, straight lengths, and fittings. C. Field quality-control reports. D. Operation and Maintenance
Data: For cable trays to include in emergency, operation, and maintenance manuals. 1.4 QUALITY ASSURANCE A. Source Limitations: Obtain cable tray components through one source from a
single manufacturer. B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction,
and marked for intended use. C. Comply with NFPA 70.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
CABLE TRAYS FOR ELECTRICAL SYSTEMS 26 05 36 -2 1.5 DELIVERY, STORAGE, AND HANDLING A. Wire basket may be stored outside without cover, but shall be loosely stacked, elevated off the
ground, and ventilated to prevent staining during storage. B. Store indoors to prevent water or other foreign materials from staining or adhering to cable tray. Unpack and dry wet materials
before storage. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Allied Company (Cope). 2. Cablofil,
Inc. 3. Chalfant Manufacturing Company. 4. Cooper B-Line, Inc. 5. GS Metals Corp.; GLOBETRAY Products. 6. MPHusky. 7. PW Industries. 2.2 MATERIALS AND FINISHES A. Cable Trays, Fittings,
and Accessories: Wire basket, complying with NEMA VE1. 1. High strength wires, formed into a minimum of 2” X 4” wire mesh pattern with intersection wires welded together. All ends of
wires on side flanges shall be rounded during manufacturing. 2. Hardware shall be bolted on type or snapping type, and comply with ASTM B633 SC2 or AISI Type 304 stainless steel. B.
Cable Trays, Fittings, and Accessories: Stainless steel, Type 304, complying with NEMA VE 1. C. Sizes and Configurations: Minimum 12” wide X 3” deep unless noted otherwise 1. Wire basket.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
CABLE TRAYS FOR ELECTRICAL SYSTEMS 26 05 36 -3 2.3 CABLE TRAY ACCESSORIES A. Fittings: Tees, crosses, risers, elbows, and other fittings as indicated, of same materials and finishes
as cable tray. B. Barrier Strips: Same materials and finishes as cable tray. C. Cable tray supports and connectors, including bonding jumpers, as recommended by cable tray manufacturer.
2.4 WARNING SIGNS A. Lettering: 1-1/2-inch-(40-mm-) high, black letters on yellow background with legend "WARNING! NOT TO BE USED AS WALKWAY, LADDER, OR SUPPORT FOR LADDERS OR PERSONNEL."
B. Materials and fastening are specified in Division 26 Section "Electrical Identification." 2.5 SOURCE QUALITY CONTROL A. Perform design and production tests according to NEMA VE 1.
PART 3 -EXECUTION 3.1 CABLE TRAY INSTALLATION A. Comply with recommendations in NEMA VE 2. 2. Install as a complete system, including all necessary fasteners, hold-down clips, splice-plate
support systems, barrier strips, hinged horizontal and vertical splice plates, elbows, reducers, tees, and crosses. B. Remove burrs and sharp edges from cable trays. C. Fasten cable
tray supports to building structure and install seismic restraints. 1. Design each fastener and support to carry load indicated by seismic requirements and to comply with seismic-restraint
details according to Division 26 Section "Vibration and Seismic Controls for Electrical Systems." 2. Place supports so that spans do not exceed maximum spans on schedules. 3. Construct
supports from channel members, threaded rods, and other appurtenances furnished by cable tray manufacturer. Arrange supports in trapeze or wall-bracket form as required by application.
4. Support bus assembly to prevent twisting from eccentric loading.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
CABLE TRAYS FOR ELECTRICAL SYSTEMS 26 05 36 -4 5. Manufacture center-hung support, designed for 60 percent versus 40 percent eccentric loading condition, with a safety factor of 3. 6.
Locate and install supports according to NEMA VE 1. D. Make connections to equipment with flanged fittings fastened to cable tray and to equipment. Support cable tray independent of
fittings. Do not carry weight of cable tray on equipment enclosure. E. Install expansion connectors where cable tray crosses building expansion joint and in cable tray runs that exceed
dimensions recommended in NEMA VE 1. Space connectors and set gaps according to applicable standard. F. Make changes in direction and elevation using standard fittings. G. Make cable
tray connections using standard fittings. H. Seal penetrations through fire and smoke barriers according to Division 7 Section "Firestopping." using UL approved firestop material. I.
Sleeves for Future Cables: Install capped sleeves for future cables through firestop-sealed cable tray penetrations of fire and smoke barriers. J. Workspace: Install cable trays with
enough space to permit access for installing cables. K. Install barriers to separate cables of different systems, such as power, communications, and data processing; or of different
insulation levels, such as 600, 5000, and 15 000 V. L. After installation of cable trays is completed, install warning signs in visible locations on or near cable trays. 3.2 CABLE INSTALLATION
A. Install cables only when cable tray installation has been completed and inspected. B. On vertical runs, fasten cables to tray every 18 inches (457 mm). Install intermediate supports
when cable weight exceeds the load-carrying capacity of the tray rungs. C. In existing construction, remove inactive or dead cables from cable tray. D. Install covers after installation
of cable is completed.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
CABLE TRAYS FOR ELECTRICAL SYSTEMS 26 05 36 -5 3.3 CONNECTIONS A. Ground cable trays according to manufacturer's written instructions and with minimum #8 AWG. Connect at minimum two
(2) locations from cable tray to building ground reference point and as required by NFPA 70. 3.4 FIELD QUALITY CONTROL A. After installing cable trays and after electrical circuitry
has been energized, survey for compliance with requirements. Perform the following field quality-control survey: 1. Visually inspect cable insulation for damage. Correct sharp corners,
protuberances in cable tray, vibration, and thermal expansion and contraction conditions, which may cause or have caused damage. 2. Verify that the number, size, and voltage of cables
in cable tray do not exceed that permitted by NFPA 70. Verify that communication or data-processing circuits are separated from power circuits by barriers. 3. Verify that there is no
intrusion of such items as pipe, hangers, or other equipment that could damage cables. 4. Remove deposits of dust, industrial process materials, trash of any description, and any blockage
of tray ventilation. 5. Visually inspect each cable tray joint and each ground connection for mechanical continuity. Check bolted connections between sections for corrosion. Clean and
retorque in suspect areas. 6. Check for missing or damaged bolts, bolt heads, or nuts. When found, replace with specified hardware. 7. Perform visual and mechanical checks for adequacy
of cable tray grounding; verify that all takeoff raceways are bonded to cable tray. B. Report results in writing. END OF SECTION 26 05 36
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 05 53 -1 SECTION 26 05 53 – IDENTIFICATION FOR ELECTRICAL SYSTEMS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of
the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Identification
for raceway. 2. Identification for conductors and communication and control cable. 3. Warning labels and signs. 4. Instruction signs. 5. Equipment identification labels. 6. Miscellaneous
identification products. 1.3 SUBMITTALS A. Product Data: For each electrical identification product indicated. B. Identification Schedule: An index of nomenclature of electrical equipment
and system components used in identification signs and labels. 1.4 QUALITY ASSURANCE A. Comply with ANSI A13.1 and ANSI C2. B. Comply with NFPA 70. C. Comply with 29 CFR 1910.145. 1.5
COORDINATION A. Coordinate identification names, abbreviations, colors, and other features with requirements in the Contract Documents, Shop Drawings, manufacturer's wiring diagrams,
and the Operation and Maintenance Manual, and with those required by codes, standards, and 29 CFR 1910.145. Use consistent designations throughout Project.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 05 53 -2 B. Coordinate installation of identifying devices with completion of covering and painting of surfaces where devices are to be applied.
C. Coordinate installation of identifying devices with location of access panels and doors. D. Install identifying devices before installing acoustical ceilings and similar concealment.
PART 2 -PRODUCTS 2.1 RACEWAY IDENTIFICATION MATERIALS A. Comply with ANSI A13.1 for minimum size of letters for legend and for minimum length of color field for each raceway and cable
size. B. Color for Printed Legend: 1. Power Circuits: a. Utility power: Black letters on a white field. b. Standby Power: White letters on a red field. 2. Legend: Indicate system or
service and voltage, if applicable. C. Self-Adhesive Vinyl Labels: Preprinted, flexible label laminated with a clear, weather-and chemical-resistant coating and matching wraparound adhesive
tape for securing ends of legend label. 2.2 CONDUCTOR AND COMMUNICATION-AND CONTROL-CABLE IDENTIFICATION MATERIALS A.
Color-Coding Conductor Tape: Colored, self-adhesive vinyl tape not less than 3 mils (0.08 mm) thick by 1 to 2 inches (25 to 50 mm) wide. B. Marker Tapes: Vinyl or vinyl-cloth, self-adhesive
wraparound type, with circuit identification legend machine printed by thermal transfer or equivalent process. 2.3 WARNING LABELS AND SIGNS A. Comply with NFPA 70 and 29 CFR 1910.145.
B. Metal-Backed, Butyrate Warning Signs: Weather-resistant, non-fading, preprinted, celluloseacetate butyrate signs with 0.0396-inch (1-mm) galvanized-steel backing; and with colors,
legend, and size required for application. 1/4-inch (6.4-mm) grommets in corners for mounting. Nominal size, 10 by 14 inches (250 by 360 mm).
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 05 53 -3 C. Warning label and sign shall include, but are not limited to, the following legends: 1. Multiple Power Source Warning: "DANGER -ELECTRICAL
SHOCK HAZARD -EQUIPMENT HAS MULTIPLE POWER SOURCES." 2. Workspace Clearance Warning: "WARNING -OSHA REGULATION -AREA IN FRONT OF ELECTRICAL EQUIPMENT MUST BE KEPT CLEAR FOR 42." 2.4
INSTRUCTION SIGNS A. Engraved, laminated acrylic or melamine plastic, minimum 1/16 inch (1.6 mm) thick for signs up to 20 sq. in. (129 sq. cm) and 1/8 inch (3.2 mm) thick for larger
sizes. 1. Engraved legend with black letters on white face. 2. Punched or drilled for mechanical fasteners. 3. Framed with mitered acrylic molding and arranged for attachment at applicable
equipment. 2.5 EQUIPMENT IDENTIFICATION LABELS A. Engraved, Laminated Acrylic or Melamine Label: Punched or drilled for screw mounting. Black letters on a white background for utility
power and white letters on a red background for standby power. Minimum letter height shall be 3/8 inch (10 mm). 2.6 DEVICE, RECEPTACLE AND SWITCH LABELS A. Label shall be self-adhesive
vinyl and shall be computer or machine printed. Minimum size shall be 1/4” label with 1/8” letter. 1. Label background shall be clear or match to device plate. 2. Black letter for normal
power. 3. Red letter for emergency power. 4. Legend: Indicates panel and circuit number. B. Special Receptacles: 1. Special purpose receptacles shall include an engraved or embossed
legend appropriate for load serviced and labeled as specified in Paragraph A. 2. Receptacles not available with factory red color for emergency power circuits shall be identified with
engraved or embossed label with the word "EMERGENCY POWER." 2.7 MISCELLANEOUS IDENTIFICATION PRODUCTS A. Cable Ties: Fungus-inert, self-extinguishing, 1-piece, self-locking, Type 6/6
nylon cable ties.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 05 53 -4 1. Minimum Width: 3/16 inch (5 mm). 2. Tensile Strength: 50 lb (22.6 kg), minimum. 3. Temperature Range: Minus 40 to plus 185 deg F
(Minus 40 to plus 85 deg C). 4. Color: Black, except where used for color-coding. B. Paint: Paint materials and application requirements are specified in Division 9 painting Sections.
C. Fasteners for Labels and Signs: Self-tapping, stainless-steel screws or stainless-steel machine screws with nuts and flat and lock washers. PART 3 -EXECUTION 3.1 APPLICATION A. Accessible
Raceways, 600 V or Less, for Feeder and Branch Circuits: Identify with preprinted self-adhesive vinyl label. B. Accessible Raceway for Standby System: Identify with self-adhesive vinyl
tape and comply with NFPA 70-700.9(A). C. Color for Printed Legend: The following color color codes are general. Verify with Owner’s standard before implementation. If Owner’s do not
have the standard then following these standards. 1. Fire Alarm System: Red. 2. Fire-Suppression Supervisory and Control System: Red and yellow. 3. Combined Fire Alarm and Security System:
Red and blue. 4. Security System: Blue and yellow. 5. Mechanical and Electrical Supervisory System: Green and blue. 6. Telecommunication System: Green and yellow. 7. Control Wiring:
Green and red. D. Power-Circuit Conductor Identification: For primary and secondary conductors No. 1/0 AWG and larger in vaults, pull and junction boxes, manholes, and handholes use
marker tape. Identify source and circuit number of each set of conductors. For single conductor cables, identify phase in addition to the above. E. Branch-Circuit Conductor Identification:
Where there are conductors for more than three branch circuits in same junction or pull box, use marker tape. Identify each ungrounded conductor according to source and circuit number.
F. Conductors to Be Extended in the Future: Attach write-on tags to conductors and list source and circuit number.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 05 53 -5 G. Auxiliary Electrical Systems Conductor Identification: Identify field-installed alarm, control, signal, sound, intercommunications,
voice, and data connections. 1. Identify conductors, cables, and terminals in enclosures and at junctions, terminals, and pull points. Identify by system and circuit designation. 2.
Use system of marker tape designations that is uniform and consistent with system used by manufacturer for factory-installed connections. 3. Coordinate identification with Project Drawings,
manufacturer's wiring diagrams, and Operation and Maintenance Manual. H. Instruction Signs: 1. Operating Instructions: Install instruction signs to facilitate proper operation and maintenance
of electrical systems and items to which they connect. Install instruction signs signs with approved legend where instructions are needed for system or equipment operation. 2. Emergency
Operating Instructions: Install instruction signs with white legend on a red background with minimum 3/8-inch-(10-mm-) high letters for emergency instructions at equipment used for power
transfer. I. Equipment Identification Labels: On each unit of equipment, install unique designation label that is consistent with wiring diagrams, schedules, and Operation and Maintenance
Manual. Apply labels on each power and system equipment/panel power equipment. Label shall include device identification and source. 1. Labeling Instructions: a. Indoor Equipment: Engraved,
laminated acrylic or melamine label. Unless otherwise indicated, provide a single line of text with 1/2-inch-(13-mm-) high letters on 1-1/2-inch-(38-mm-) high label; where 2 lines of
text are required, use labels 2 inches (50 mm) high. b. Outdoor Equipment: Engraved, laminated acrylic or melamine label. c. Elevated Components: Increase sizes of labels and letters
to those appropriate for viewing from the floor. 2. Equipment to Be Labeled: a. Panelboards, electrical cabinets, and enclosures. b. Access doors and panels for concealed electrical
items. c. Emergency system boxes and enclosures. d. Disconnect switches. e. Enclosed circuit breakers. f. Motor starters. g. Push-button stations. h. Contactors. i. Remote-controlled
switches, dimmer modules, and control devices. j. Voice and data cable terminal equipment.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 05 53 -6 k. Intercommunication and call system master and staff stations. l. Television/audio components, racks, and controls. m. Fire-alarm
control panel and annunciators. n. Security and intrusion-detection control stations, control panels, terminal cabinets, and racks. o. Monitoring and control equipment. p. Audio/paging
system. q. Video surveillance. 3. Equipment Schedule: a. Panelboards shall include correct, typewritten circuit directly cards identifying load served by branch circuit protective devices.
b. Panelboards located in a renovated area shall have their schedules updated for all spares, spaces and circuits connected to the panelboard. 3.2 INSTALLATION A. Verify identity of
each item before installing identification products. B. Location: Install identification materials and devices at locations for most convenient viewing without interference with operation
and maintenance of equipment. C. Apply identification devices to surfaces that require finish after completing finish work. D. Self-Adhesive Identification Products: Clean surfaces before
application, using materials and methods recommended by manufacturer of identification device. E. Attach non-adhesive signs and plastic labels with screws and auxiliary hardware appropriate
to the location and substrate. F. System Identification Color Banding for Raceways and Cables: Each color band shall completely encircle cable or conduit. Place adjacent bands of two-color
markings in contact, side by side. Locate bands at changes in direction, at penetrations of walls and floors, at 50-foot (15-m) maximum intervals in straight runs, and at 25-foot (7.6-m)
maximum intervals in congested areas. G. Color-Coding for Phase and Voltage Level Identification, 600 V and Less: Use the colors listed below for feeder and branch-circuit conductors.
1. Color shall be factory applied or, for sizes larger than No. 10 AWG if authorities having jurisdiction permit, field applied. 2. Colors for 208/120-V Circuits: a. Phase A: Black.
b. Phase B: Red.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
IDENTIFICATION FOR ELECTRICAL SYSTEMS 26 05 53 -7 c. Phase C: Blue. d. Neutral: White. e. Ground: Green. 3. Colors for 480/277-V Circuits: a. Phase A: Brown. b. Phase B: Orange. c. Phase
C: Yellow. d. Neutral: White with yellow strips or tape. e. Ground: Green with yellow strips or tape. 4. Field-Applied, Color-Coding Conductor Tape: Apply in half-lapped turns for a
minimum distance of 6 inches (150 mm) from terminal points and in boxes where splices or taps are made. Apply last two turns of tape with no tension to prevent possible unwinding. Locate
bands to avoid obscuring factory cable markings. H. Painted Identification: Prepare surface and apply paint according to Division 9 painting Sections. END OF SECTION 26 05 53
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PANELBOARDS 26 24 16 -1 SECTION 26 24 16 -PANELBOARDS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Distribution panelboards. 2. Lighting and appliance branch-circuit panelboards. 1.3
DEFINITIONS A. TVSS: Transient voltage surge suppressor. 1.4 SUBMITTALS A. Product Data: For each type of panelboard, switching and overcurrent protective device, transient voltage suppression
device, accessory, and component indicated. Include dimensions and manufacturers' technical data on features, performance, electrical characteristics, ratings, and finishes. B. Shop
Drawings: For each panelboard and related equipment. 1. Include dimensioned plans, elevations, sections, and details. Show tabulations of installed devices, equipment features, and ratings.
2. Detail enclosure types and details for types other than NEMA 250, Type 1. 3. Detail bus configuration, current, and voltage ratings. 4. Short-circuit current rating of panelboards
and overcurrent protective devices. 5. Devices shall be fully rated for available fault current. 6. Detail features, characteristics, ratings, and factory settings of individual overcurrent
protective devices and auxiliary components. 7. Include wiring diagrams for power, signal, and control wiring. 8. Include time-current coordination curves for each type and rating of
overcurrent protective device included in panelboards. Submit on translucent log-log graft paper; include selectable ranges for each type of overcurrent protective device.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PANELBOARDS 26 24 16 -2 C. Field Quality-Control Reports: 1. Test procedures used. 2. Test results that comply with requirements. 3. Results of failed tests and corrective action taken
to achieve test results that comply with requirements. D. Panelboard Schedules: For installation in panelboards. Submit final versions after load balancing. E. Operation and Maintenance
Data: For panelboards and components to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 1 Section "Operation and Maintenance Data,"
include the following: 1. Manufacturer's written instructions for testing and adjusting overcurrent protective devices. 2. Time-current curves, including selectable ranges for each type
of overcurrent protective device that allows adjustments. 1.5 QUALITY ASSURANCE A. Source Limitations: Obtain panelboards, overcurrent protective devices, components, and accessories
from single source from single manufacturer. B. Product Selection for Restricted Space: Drawings indicate maximum dimensions for panelboards including clearances between panelboards
and adjacent surfaces and other items. Comply with indicated maximum dimensions. C. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified
testing agency, and marked for intended location and application. D. Comply with NEMA PB 1. E. Comply with NFPA 70. 1.6 DELIVERY, STORAGE, AND HANDLING A. Handle and prepare panelboards
for installation according to NECA 407 and NEMA PB 1. 1.7 PROJECT CONDITIONS A. Environmental Limitations:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PANELBOARDS 26 24 16 -3 1. Do not deliver or install panelboards until spaces are enclosed and weathertight, wet work in spaces is complete and dry, work above panelboards is complete,
and temporary HVAC system is operating and maintaining ambient temperature and humidity conditions at occupancy levels during the remainder of the construction period. B. Interruption
of Existing Electric Service: Do not interrupt electric service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging
to provide temporary electric service according to requirements indicated: 1. Notify Owner no fewer than five days in advance of proposed interruption of electric service. 2. Do not
proceed with interruption of electric service without Owner's written permission. 3. Comply with NFPA 70E. 1.8 COORDINATION A. Coordinate layout and installation of panelboards and components
with other construction that penetrates walls or is supported by them, including electrical and other types of equipment, raceways, piping, encumbrances to workspace clearance requirements,
and adjacent surfaces. Maintain required workspace clearances and required clearances for equipment access doors and panels. B. Coordinate sizes and locations of concrete bases with
actual equipment provided. Cast anchorbolt inserts into bases. Concrete, reinforcement, and formwork requirements are specified in Division 3. PART 2 -PRODUCTS 2.1 GENERAL REQUIREMENTS
FOR PANELBOARDS A. Fabricate and test panelboards according to IEEE 344 to withstand seismic forces defined in Division 26 Section "Vibration and Seismic Controls for Electrical Systems."
B. Enclosures: Flush-and surface-mounted cabinets as per schedule in Contract Documents. 1. Rated for environmental conditions at installed location. a. Indoor Dry and Clean Locations:
NEMA 250, Type 1. b. Outdoor Locations: NEMA 250, Type 3R. c. Indoor Locations Subject to Dust, Falling Dirt, and Dripping Non-corrosive Liquids: NEMA 250, Type 12. 2. Hinged Front Cover:
Entire front trim hinged to box and with standard door within hinged trim cover.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PANELBOARDS 26 24 16 -4 3. Finishes: a. Panels and Trim: Steel factory finished immediately after cleaning and pretreating with manufacturer's standard two-coat, baked-on finish consisting
of prime coat and thermosetting topcoat. b. Back Boxes: Galvanized steel. 4. Directory Card: Inside panelboard door with protective cover. C. Incoming Mains Location: Top and bottom
as per schedule and also coordinate with install contractor. D. Phase, Neutral, and Ground Buses: 1. Material: Hard-drawn copper, 98 percent conductivity. 2. Equipment Ground Bus: Adequate
for feeder and branch-circuit equipment grounding conductors; bonded to box. E. Conductor Connectors: Suitable for use with conductor material and sizes. 1. Main and Neutral Lugs: Mechanical
type. 2. Ground Lugs and Bus-Configured Terminators: Mechanical type. 3. Feed-Through Lugs: Mechanical type, suitable for use with conductor material. Locate at opposite end of bus from
incoming lugs or main device. 4. Subfeed (Double) Lugs: Mechanical type suitable for use with conductor material. Locate at same end of bus as incoming lugs or main device. F. Future
Devices: Mounting brackets, bus connections, filler plates, and necessary appurtenances required for future installation of devices. G. Panelboard Short-Circuit Current Rating: Fully
rated to interrupt symmetrical short-circuit current available at terminals. 2.2 LIGHTING AND APPLIANCE BRANCH-CIRCUIT PANELBOARDS A. Manufacturers: Subject to compliance with requirements,
provide products by one of the following: 1. Eaton Electrical Inc.; Cutler-Hammer Business Unit. 2. General Electric Company; GE Consumer & Industrial -Electrical Distribution. 3. Siemens
Energy & Automation, Inc. 4. Square D; a brand of Schneider Electric. B. Panelboards: NEMA PB 1, lighting and appliance branch-circuit type. C. Mains: Circuit breaker or lugs only as
per Panelboard Schedule.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PANELBOARDS 26 24 16 -5 D. Branch Overcurrent Protective Devices: Bolt-on circuit breakers, replaceable without disturbing adjacent units. E. Contactors in Main Bus: NEMA ICS 2, Class
A, mechanically held, general-purpose controller, with same short-circuit interrupting rating as panelboard. 1. Internal Control-Power Source: Control-power transformer, with fused primary
and secondary terminals, connected to main bus ahead of contactor connection. F. Doors: Concealed hinges; secured with flush latch with tumbler lock; keyed alike. G. Column-Type Panelboards:
Narrow gutter extension, with cover, to overhead junction box equipped with ground and neutral terminal buses. 2.3 DISCONNECTING AND OVERCURRENT PROTECTIVE DEVICES A. Manufacturers:
Subject to compliance with requirements, provide products by one of the following: 1. Eaton Electrical Inc.; Cutler-Hammer Business Unit. 2. General Electric Company; GE Consumer & Industrial
-Electrical Distribution. 3. Siemens Energy & Automation, Inc. 4. Square D; a brand of Schneider Electric. B. Molded-Case Circuit Breaker (MCCB): Comply with UL 489, with interrupting
capacity to meet available fault currents. 1. Thermal-Magnetic Circuit Breakers: Inverse time-current element for low-level overloads, and instantaneous magnetic trip element for short
circuits. Adjustable instantaneous trip setting for circuit-breaker frame sizes 150 A and larger. 2. Molded-Case Circuit-Breaker (MCCB) Features and Accessories: a. Standard frame sizes,
trip ratings, and number of poles. b. Lugs: Mechanical style, suitable for number, size, trip ratings, and conductor materials. c. Multi-pole units enclosed in a single housing or factory
assembled to operate as a single unit. d. Handle Padlocking Device: Fixed attachment, for locking circuit-breaker handle in on or off position. e. Handle Clamp: Loose attachment, for
holding circuit-breaker handle in the "on" position.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PANELBOARDS 26 24 16 -6 PART 3 -EXECUTION 3.1 EXAMINATION A. Receive, inspect, handle, and store panelboards according to NECA 407 and NEMA PB 1.1. B. Examine panelboards before installation.
Reject panelboards that are damaged or rusted or have been subjected to water saturation. C. Examine elements and surfaces to receive panelboards for compliance with installation tolerances
and other conditions affecting performance of the Work. D. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 INSTALLATION A. Install panelboards
and accessories according to NECA 407 and NEMA PB 1.1. B. Equipment Mounting: Install panelboards on concrete bases, 4-inch (100-mm) nominal thickness. Comply with requirements for concrete
base specified in Division 3 Section "Miscellaneous Cast-in-Place Concrete." 1. Install dowel rods to connect concrete base to concrete floor. Unless otherwise indicated, install dowel
rods on 18-inch (450-mm) centers around full perimeter of base. 2. For panelboards, install epoxy-coated anchor bolts that extend through concrete base and anchor into structural concrete
floor. 3. Place and secure anchorage devices. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded. 4. Install anchor bolts to
elevations required for proper attachment to panelboards. 5. Attach panelboard to the vertical finished or structural surface behind the panelboard. C. Temporary Lifting Provisions:
Remove temporary lifting eyes, channels, and brackets and temporary blocking of moving parts from panelboards. D. Comply with mounting and anchoring requirements specified in Division
26 Section "Vibration and Seismic Controls for Electrical Systems." E. Mount top of trim 90 inches (2286 mm) above finished floor unless otherwise indicated. Top mat switch or circuit
breaker in "on" position shall not be higher than 75 inches (3000 mm) above finished floor or grade. F. Mount panelboard cabinet plumb and rigid without distortion of box. Mount recessed
panelboards with fronts uniformly flush with wall finish and mating with back box.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PANELBOARDS 26 24 16 -7 G. Install overcurrent protective devices and controllers not already factory installed. 1. Set field-adjustable, circuit-breaker settings. H. Install filler
plates in unused spaces. I. Stub four 1-inch (27-GRC) empty conduits from panelboard into accessible ceiling space or space designated to be ceiling space in the future. Stub four 1-inch
(27-GRC) empty conduits into raised floor space or below slab not on grade. J. Arrange conductors in gutters into groups and bundle and wrap with wire ties after completing load balancing.
K. Comply with NECA 1. 3.3 IDENTIFICATION A. Identify field-installed conductors, interconnecting wiring, and components; provide warning signs complying with Division 26 Section "Identification
for Electrical Systems." B. Create a directory to indicate installed circuit circuit loads after balancing panelboard loads; incorporate Owner's final room designations. Obtain approval
before installing. Use a computer or typewriter to create directory; handwritten directories are not acceptable. C. Panelboard Nameplates: Label each panelboard with a nameplate complying
with requirements for identification specified in Division 26 Section "Identification for Electrical Systems." 3.4 FIELD QUALITY CONTROL A. Perform tests and inspections. B. Acceptance
Testing Preparation: 1. Test insulation resistance for each panelboard bus, component, connecting supply, feeder, and control circuit. 2. Test continuity of each circuit. C. Tests and
Inspections: 1. Perform each visual and mechanical inspection and electrical test as follows: a. Certify compliance with test parameters. 2. Circuit Breakers, Air, Insulated-Case/Molded-Case:
a. Visual and Mechanical Inspection:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PANELBOARDS 26 24 16 -8 1) Compare equipment nameplate data with drawings and specifications. 2) Inspect physical and mechanical condition. 3) Inspect anchorage and alignment. 4) Verify
the unit is clean. 5) Operate the circuit breaker to insure smooth operation. 6) Inspect bolted electrical connections for high resistance using bolted electrical connections by calibrated
torque-wrench method in accordance with manufacturer’s published data or Table 100.12. 7) Inspect operating mechanism, contacts, and arc chutes in unsealed units. 8) Verify correct operation
of any auxiliary features such as trip and pickup indicators, zone interlocking, electrical close and trip operation, trip-free and anti-pump functions. b. Electrical Tests: 1) Perform
adjustments for final setting in accordance with coordination study. 3. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace
with new units and retest. D. Prepare test and inspection reports, including a certified report that identifies panelboards included and that describes scanning results. Include notation
of deficiencies detected, remedial action taken and observations after remedial action. 3.5 ADJUSTING A. Adjust moving parts and operable component to function smoothly, and lubricate
as recommended by manufacturer. B. Load Balancing: After Substantial Completion, but not more than 60 days after Final Acceptance, measure load balancing and make circuit changes. 1.
Measure as directed during period of normal system loading. 2. Perform load-balancing circuit changes outside normal occupancy/working schedule of the facility and at time directed.
Avoid disrupting critical 24-hour services such as fax machines and on-line data processing, computing, transmitting, and receiving equipment. 3. After circuit changes, recheck loads
loads during normal load period. Record all load readings before and after changes and submit test records. 4. Tolerance: Difference exceeding 20 percent between phase loads, within
a panelboard, is not acceptable. Rebalance and recheck as necessary to meet this minimum requirement. END OF SECTION 26 24 16
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -1 SECTION 26 27 26 -WIRING DEVICES PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Receptacles, receptacles with integral GFCI, and associated
device plates. 2. Indoor occupancy sensors. 3. Hospital-grade receptacles. 4. Snap switches and wall-box dimmers. 5. Pendant cord-connector devices. 6. Cord and plug sets. 7. Floor service
outlets, poke-through assemblies, service poles, and multi-outlet assemblies. 8. Safety type receptacle (tamperproof). 1.3 DEFINITIONS A. EMI: Electromagnetic interference. B. GFCI:
Ground-fault circuit interrupter. C. Pigtail: Short lead used to connect a device to to a branch-circuit conductor. D. RFI: Radio-frequency interference. E. TVSS: Transient voltage surge
suppressor. F. UTP: Unshielded twisted pair. G. IG: Isolated ground type. H. ST: Safety type (tamperproof).
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -2 1.4 SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: List of legends and description of materials and process used for premarking
wall plates. C. Field quality-control test reports. D. Operation and Maintenance Data: For wiring devices to include in all manufacturers' packing label warnings and instruction manuals
that include labeling conditions. 1.5 QUALITY ASSURANCE A. Source Limitations: Obtain each type of wiring device and associated wall plate through one source from a single manufacturer.
Insofar as they are available, obtain all wiring devices and associated wall plates from a single manufacturer and one source. B. Electrical Components, Devices, and Accessories: Listed
and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to to authorities having jurisdiction, and marked for intended use. C. Comply with NFPA 70. 1.6 COORDINATION
A. Receptacles for Owner-Furnished Equipment: Match plug configurations. 1. Cord and Plug Sets: Match equipment requirements. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers' Names:
Shortened versions (shown in parentheses) of the following manufacturers' names are used in other Part 2 articles: 1. Cooper Wiring Devices; a division of Cooper Industries, Inc. (Cooper).
2. Hubbell Incorporated; Wiring Device-Kellems (Hubbell). 3. Leviton Mfg. Company Inc. (Leviton). 4. Pass & Seymour/Legrand; Wiring Devices & Accessories (Pass & Seymour).
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -3 2.2 STRAIGHT BLADE RECEPTACLES A. Hospital-Grade, Duplex Convenience Receptacles, 125 V, 20 A: Comply with NEMA WD 1, NEMA WD 6 configuration 5-20R, and UL
498 Supplement SD. 1. Products: Subject to compliance with requirements, provide one of the following: a. Cooper; 8300 (duplex). b. Hubbell; HBL8310 (single), HBL8300H (duplex). c. Leviton;
8310 (single), 8300 (duplex). d. Pass & Seymour; 9301-HG (single), 9300-HG (duplex). 2.3 SAFETY TYPE (TAMPER-RESISTANT) RECEPTACLES A. Tamper-Resistant Hospital grade duplex receptacles,
125 V, 20 A: Comply with NEMA WD 1, NEMA WD 6 configuration 5-20R, and UL 498. 1. Products: Subject to compliance with requirements, provide one of the following: a. Cooper; TR8300.
b. Hubbell; HBL8300SG. c. Leviton; 8300-SGG. d. Pass & Seymour; 63H. 2. Description: Labeled to comply with NFPA 70, "Health Care Facilities" Article, "Pediatric Locations" Section.
2.4 GFCI RECEPTACLES A. General Description: Straight blade, non-feed-through type. Comply with NEMA WD 1, NEMA WD 6, UL 498, and UL 943, Class A, and include indicator light that is
lighted when device is tripped. B. Hospital-Grade, Duplex GFCI Convenience Receptacles, 125 V, 20 A: Comply with UL 498 Supplement SD. 1. Products: Subject to compliance with requirements,
provide one of the following: a. Cooper; HGF20. b. Hubbell; HGF8300. c. Leviton; 6898-HG. d. Pass & Seymour; 2091-SHG.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -4 2.5 TWIST-LOCKING RECEPTACLES A. Single Convenience Receptacles, 125 V, 20 A: Comply with NEMA WD 1, NEMA WD 6 configuration L5-20R, and UL 498. 1. Products:
Subject to compliance with requirements, provide one of the following: a. Cooper; L520R. b. Hubbell; HBL2310. c. Leviton; 2310. d. Pass & Seymour; L520-R. 2.6 PENDANT CORD-CONNECTOR
DEVICES A. Description: Matching, locking-type plug and receptacle body connector; NEMA WD 6 configurations L5-20P and L5-20R, heavy-duty grade. 1. Body: Nylon with screw-open cable-gripping
jaws and provision for attaching external cable grip. 2. External Cable Grip: Woven wire-mesh type made of high-strength galvanized-steel wire strand, matched to cable diameter, and
with attachment provision designed for corresponding connector. 2.7 CORD AND PLUG SETS A. A. Description: Match voltage and current ratings and number of conductors to requirements of
equipment being connected. 1. Cord: Rubber-insulated, stranded-copper conductors, with Type SOW-A jacket; with green-insulated grounding conductor and equipment-rating ampacity plus
a minimum of 30 percent. 2. Plug: Nylon body and integral cable-clamping jaws. Match cord and receptacle type for connection. 2.8 SNAP SWITCHES A. Comply with NEMA WD 1 and UL 20. B.
Switches, 120/277 V, 20 A: 1. Products: Subject to compliance with requirements, provide one of the following: a. Cooper; 2221 (single pole), 2222 (two pole), 2223 (three way), 2224
(four way).
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -5 b. Hubbell; HBL1221 (single pole), HBL1222 (two pole), HBL1223 (three way), HBL1224 (four way). c. Leviton; 1221-2 (single pole), 1222-2 (two pole), 1223-2
(three way), 1224-2 (four way). d. Pass & Seymour; 20AC1 (single pole), 20AC2 (two pole), 20AC3 (three way), 20AC4 (four way). C. Single-Pole, Double-Throw, Momentary Contact, Center-Off
Switches, 120/277 V, 20 A; for use with mechanically held lighting contactors. 1. Products: Subject to compliance with requirements, provide one of the following: a. Cooper; 1995. b.
Hubbell; HBL1557. c. Leviton; 1257. d. Pass & Seymour; 1251. 2.9 WALL-BOX DIMMERS A. Dimmer Switches: Modular, full-wave, solid-state units with integral, quiet on-off switches, with
audible frequency and EMI/RFI suppression filters. B. Control: Continuously adjustable toggle toggle switch; with single-pole or three-way switching. Comply with UL 1472. C. Incandescent
Lamp Dimmers: 120 V; control shall follow square-law dimming curve. On-off switch positions shall bypass dimmer module. 1. 600W; dimmers shall require no derating when ganged with other
devices. Illuminated when "OFF." D. Fluorescent Lamp Dimmer Switches: Modular; compatible with dimmer ballasts; trim potentiometer to adjust low-end dimming; dimmer-ballast combination
capable of consistent dimming with low end not greater than 20 percent of full brightness. 2.10 INDOOR OCCUPANCY SENSORS A. Manufacturers: Subject to compliance with requirements, provide
products by one of the following: 1. Hubbell Lighting. 2. Leviton Mfg. Company Inc. 3. Lithonia Lighting; Acuity Lighting Group, Inc. 4. Sensor Switch, Inc. 5. Watt Stopper (The).
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -6 B. General Description: Wall-or ceiling-mounting, solid-state units with a separate relay unit. 1. Operation: Unless otherwise indicated, turn lights on when
covered area is occupied and off when unoccupied; with a time delay for turning lights off, adjustable over a minimum range of 1 to 30 minutes. 2. Sensor Output: Contacts rated to operate
the connected relay, complying with UL 773A. Sensor shall be powered from the relay unit. 3. Relay Unit: Dry contacts rated for 20-A ballast load at 120-and 277-V ac, for 13-A tungsten
at 120-V ac, and for 1 hp at 120-V ac. Power supply to sensor shall be 24-V dc, 150-mA, Class 2 power source as defined by NFPA 70. 4. Mounting: a. Sensor: Suitable for mounting in any
position on a standard outlet box. b. Relay: Externally mounted through a 1/2-inch (13-13-mm) knockout in a standard electrical enclosure. c. Time-Delay and Sensitivity Adjustments:
Recessed and concealed behind hinged door. 5. Indicator: LED, to show when motion is being detected during testing and normal operation of the sensor. 6. Bypass Switch: Override the
on function in case of sensor failure. 7. Automatic Light-Level Sensor: Adjustable from 2 to 200 fc (21.5 to 2152 lx); keep lighting off when selected lighting level is present. C. PIR
Type: Wall mounting; detect occupancy by sensing a combination of heat and movement in area of coverage. 1. Detector Sensitivity: Detect occurrences of 6-inch-(150-mm-) minimum movement
of any portion of a human body that presents a target of not less than 36 sq. in. (232 sq. cm). 2. Detection Coverage (Room): 110 degree field of view, and a minimum coverage area of
1200 sq.ft. (111 sq.m). D. Ultrasonic Type: Ceiling mounting; detect occupancy by sensing a change in pattern of reflected ultrasonic energy in area of coverage. 1. Detector Sensitivity:
Detect a person of average size and weight moving not less than 12 inches (305 mm) in either a horizontal or a vertical manner at an approximate speed of 12 inches/s (305 mm/s). 2. Detection
Coverage (Small Room): Detect occupancy anywhere within a circular area of 600 sq. ft. (56 sq. m) when mounted on a 96-inch-(2440-mm-) high ceiling. 3. Detection Coverage (Standard Room):
Detect occupancy anywhere within a circular area of 1000 sq. ft. (93 sq. m) when mounted on a 96-inch-(2440-mm-) high ceiling. 4. Detection Coverage (Large Room): Detect occupancy anywhere
within a circular area of 2000 sq. ft. (186 sq. m) when mounted on a 96-inch-(2440-mm-) high ceiling.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -7 2.11 WALL PLATES A. Single and combination types to match corresponding wiring devices. 1. Plate-Securing Screws: Metal with head color to match plate finish.
2. Material for Finished Spaces: Smooth, high-impact thermoplastic. 3. Material for Unfinished Spaces: Smooth, high-impact thermoplastic. 4. Material for Damp Locations: Thermoplastic
with spring-loaded lift cover, and listed and labeled for use in "wet locations." B. Wet-Location, Weatherproof Cover Plates: NEMA 250, complying with type 3R weatherresistant thermoplastic
with lockable cover. 2.12 POKE-THROUGH ASSEMBLIES A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Hubbell Incorporated; Wiring
Device-Kellems. 2. Pass & Seymour/Legrand; Wiring Devices & Accessories. 3. Square D/Schneider Electric. 4. Thomas & Betts Corporation. 5. Wiremold Company (The). B. Description: Factory-fabricated
and -wired assembly of below-floor junction box with multichanneled, through-floor raceway/firestop unit and detachable matching floor service outlet assembly. 1. Service Outlet Assembly:
Flush type with two simplex receptacles and space for two RJ-45 jacks. 2. Size: Selected to fit nominal 3-inch (75-mm) cored holes in floor and matched to floor thickness. 3. Fire Rating:
Unit is listed and labeled for fire rating of floor-ceiling assembly. 4. Closure Plug: Arranged to close unused 3-inch (75-mm) cored openings and reestablish fire rating of floor. 5.
Wiring Raceways and Compartments: For a minimum of four No. 12 AWG conductors and a minimum of four, 4-pair, Category 6 voice and data communication cables. 2.13 MULTIOUTLET ASSEMBLIES
A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Hubbell Incorporated; Wiring Device-Kellems. 2. Isoduct.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -8 3. Panduit. 4. Wiremold Company (The). B. Components of Assemblies: Products from a single manufacturer designed for use as a complete, matching assembly of
raceways and receptacles. C. Raceway Material: Metal, with manufacturer's standard finish. D. Wire: No. 12 AWG. 2.14 SERVICE POLES A. Description: Factory-assembled and -wired units
to extend power and voice and data communication from distribution wiring concealed in ceiling to devices or outlets in pole near floor. 1. Poles: Nominal 2.5-inch-(65-mm-) square cross
section, with height adequate to extend from floor to at least 6 inches (150 mm) above ceiling, and with separate channels for power wiring and voice and data communication cabling.
2. Mounting: Ceiling trim flange with concealed bracing arranged for positive connection to ceiling supports; with pole foot and carpet pad attachment. 3. Finishes: Satin-anodized aluminum.
4. Wiring: Sized for minimum of five No. 12 AWG power and ground conductors and a minimum of four, 4-pair, Category 3 or 5 voice and data communication cables. 5. Power Receptacles:
Two duplex, 20-A, heavy-duty, NEMA WD 6 configuration 5-20R units. 6. Voice and Data Communication Outlets: Blank insert with bushed cable opening. 2.15 FINISHES A. Color: Wiring device
catalog numbers in Section Text do not designate device color. 1. Wiring Devices Connected to Normal Power System: Ivory, unless otherwise indicated or required by NFPA 70 or device
listing. 2. Wiring Devices Connected to Emergency Power System: Red. PART 3 -EXECUTION 3.1 INSTALLATION A. Comply with NECA 1, including the mounting heights listed in that standard,
unless otherwise noted.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -9 1. Receptacles: 18” A.F.F. to center unless noted otherwise. 2. Switches/dimmer/wall occupancy sensor: 48” A.F.F. to center unless noted otherwise. B. Coordination
with Other Trades: 1. Take steps to insure that devices and their boxes are protected. Do not place wall finish materials over device boxes and do not cut holes for boxes with routers
that are guided by riding against outside of the boxes. 2. Keep outlet boxes free of plaster, drywall joint compound, mortar, cement, concrete, dust, paint, and other material that may
contaminate the raceway system, conductors, and cables. 3. Install device boxes in brick or block walls so that the cover plate does not cross a joint unless the joint is troweled flush
with the face of the wall. 4. Install wiring devices after all wall preparation, including painting, is complete. C. Conductors: 1. Do not strip insulation from conductors until just
before they are spliced or terminated on devices. 2. Strip insulation evenly around the conductor using tools designed for the purpose. Avoid scoring or nicking of solid wire or cutting
strands from stranded wire. 3. The length of free conductors at outlets for devices shall meet provisions of NFPA 70, Article 300, without pigtails. 4. Existing Conductors: a. Cut back
and pigtail, or replace all damaged conductors. b. Straighten conductors that remain and remove corrosion and foreign matter. c. Pigtailing existing conductors is permitted provided
the outlet box is large enough. D. Device Installation: 1. Replace all devices that have been in temporary use during construction or that show signs that they were installed before
building finishing operations were complete. 2. Keep each wiring device in its package or otherwise protected until it is time to connect conductors. 3. Do not remove surface protection,
such as plastic film and smudge covers, until the last possible moment. 4. Connect devices to branch circuits using pigtails that are not less than 6 inches (152 mm) in length. 5. When
there is a choice, use side wiring with binding-head screw terminals. Wrap solid conductor tightly clockwise, 2/3 to 3/4 of the way around terminal screw. 6. Use a torque screwdriver
when a torque is recommended or required by the manufacturer. 7. When conductors larger than No. 12 AWG are installed on 15-or 20-A circuits, splice No. 12 AWG pigtails for device connections.
8. Tighten unused terminal screws on the device. 9. When mounting into metal boxes, remove the fiber or plastic washers used to hold device mounting screws in yokes, allowing metal-to-metal
contact.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -10 E. Device Plates: Do not use oversized or extra-deep plates. Repair wall finishes and remount outlet boxes when standard device plates do not fit flush or
do not cover rough wall opening. F. Dimmers: 1. Install dimmers within terms of their listing. 2. Verify that dimmers used for fan speed control are listed for that application. 3. Install
unshared neutral conductors on line and load side of dimmers according to manufacturers' device listing conditions in the written instructions. G. Arrangement of Devices: Unless otherwise
indicated, mount flush, with long dimension vertical and with grounding terminal of receptacles on top. Group adjacent switches under single, multigang wall plates. H. Adjust locations
of floor service outlets and service poles to suit arrangement of partitions and furnishings. 3.2 IDENTIFICATION A. Comply with Division 26 Section "Electrical Identification." 1. Receptacles:
Identify panelboard and circuit number from which served using durable wire markers or tags inside outlet boxes. 3.3 FIELD QUALITY CONTROL A. Perform tests and inspections and prepare
test reports. 1. In healthcare facilities, prepare reports that comply with recommendations in NFPA 99. 2. Test Instruments: Use instruments that comply with UL 1436. 3. Test Instrument
for Convenience Receptacles: Digital wiring analyzer with digital readout or illuminated LED indicators of measurement. B. Tests for Convenience Receptacles: 1. Line Voltage: Acceptable
range is 105 to 132 V. 2. Percent Voltage Drop under 15-A Load: A value of 6 percent or higher is not acceptable. 3. Ground Impedance: Values of up to 2 ohms are acceptable. 4. GFCI
Trip: Test for tripping values specified in UL 1436 and UL 943. 5. Using the test plug, verify that the device and its outlet box are securely mounted. 6. The tests shall be diagnostic,
indicating damaged conductors, high resistance at the circuit breaker, poor connections, inadequate fault current path, defective devices, or similar problems. Correct circuit conditions,
remove malfunctioning units and replace with new ones, and retest as specified above.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
WIRING DEVICES 26 27 26 -11 C. Test straight blade hospital-grade convenience outlets for the retention force of the grounding blade according to NFPA 99. Retention force shall be not
less than 4 oz. (115 g). END OF SECTION 26 27 26
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FUSES 26 28 13 -1 SECTION 26 28 13 -FUSES PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Cartridge fuses rated 600 V and less for use in switches and controllers.
1.3 SUBMITTALS A. Product Data: Include the following for each fuse type indicated: 1. Dimensions and manufacturer's technical data on features, performance, electrical characteristics,
and ratings. 2. Let-through current curves for fuses with current-limiting characteristics. 3. Time-current curves, coordination charts and tables, and related data. B. Operation and
Maintenance Data: For fuses to include in emergency, operation, and maintenance manuals. 1. In addition to items specified in Division 1 Section "Operation and Maintenance Data," include
the following: a. Let-through current curves for fuses with current-limiting characteristics. b. Time-current curves, coordination charts and tables, and related data. c. Ambient temperature
adjustment information. 1.4 QUALITY ASSURANCE A. Source Limitations: Obtain fuses from a single manufacturer. B. Electrical Components, Devices, and Accessories: Listed and labeled as
defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FUSES 26 28 13 -2 C. Comply with NEMA FU 1. D. Comply with NFPA 70. 1.5 PROJECT CONDITIONS A. Where ambient temperature to which fuses are directly exposed is less than 40 deg F (5 deg
C) or more than 100 deg F (38 deg C), apply manufacturer's ambient temperature adjustment factors to fuse ratings. 1.6 COORDINATION A. Coordinate fuse ratings with utilization equipment
nameplate limitations of maximum fuse size. 1.7 EXTRA MATERIALS A. Furnish extra materials described below that match products installed and that are packaged with protective covering
for storage and identified with labels describing contents. 1. Fuses: Quantity equal to 10 percent of each fuse type and size, but no fewer than 3 of each type and size. PART 2 -PRODUCTS
2.1 MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. Cooper Bussman, Inc. 2. Eagle Electric Mfg. Co., Inc.; Cooper
Industries, Inc. 3. Ferraz Shawmut, Inc. 4. Tracor, Inc.; Littelfuse, Inc. Subsidiary. 2.2 CARTRIDGE FUSES A. Characteristics: NEMA FU 1, nonrenewable cartridge fuse; class and current
rating indicated; voltage rating consistent with circuit voltage.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FUSES 26 28 13 -3 PART 3 -EXECUTION 3.1 EXAMINATION A. Examine utilization equipment nameplates and installation instructions. Install fuses of sizes and with characteristics appropriate
for each piece of equipment. B. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 FUSE APPLICATIONS A. Motor Branch Circuits: Class RK1, time delay.
B. Other Branch Circuits: Class RK1, time delay. 3.3 INSTALLATION A. Install fuses in fusible devices. Arrange fuses so rating information is readable without removing fuse. 3.4 IDENTIFICATION
A. Install labels indicating fuse replacement information on inside door of each fused switch. END OF SECTION 26 28 13
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED SWITCHES AND CIRCUIT BREAKERS 26 28 16 -1 SECTION 26 28 16 -ENCLOSED SWITCHES AND CIRCUIT BREAKERS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of
the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following individually
mounted, enclosed switches and circuit breakers: 1. Fusible switches. 2. Non-fusible switches. 3. Molded-case circuit breakers. 4. Enclosures. 1.3 DEFINITIONS A. GFCI: Ground-fault circuit
interrupter. B. HD: Heavy duty. C. RMS: Root mean square. D. SPDT: Single pole, double throw. 1.4 SUBMITTALS A. Product Data: For each type of enclosed switch, circuit breaker, accessory,
and component indicated. Include dimensioned elevations, sections, weights, weights, and manufacturers' technical data on features, performance, electrical characteristics, ratings,
and finishes. 1. Enclosure types and details for types other than NEMA 250, Type 1. 2. Current and voltage ratings. 3. Short-circuit current rating. 4. Features, characteristics, ratings,
and factory settings of individual overcurrent protective devices and auxiliary components. B. Shop Drawings: Diagram power, signal, and control wiring.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED SWITCHES AND CIRCUIT BREAKERS 26 28 16 -2 C. Field quality-control test reports including the following: 1. Test procedures used. 2. Test results that comply with requirements.
3. Results of failed tests and corrective action taken to achieve test results that comply with requirements. D. Manufacturer's field service report. E. Operation and Maintenance Data:
For enclosed switches and circuit breakers to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 1 Section "Operation and Maintenance
Data," include the following: 1. Manufacturer's written instructions for testing and adjusting enclosed switches and circuit breakers. 2. Time-current curves, including selectable ranges
for each type of circuit breaker. 1.5 QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency
acceptable to authorities having jurisdiction, and marked for intended use. B. Comply with NFPA 70. C. Product Selection for Restricted Space: Drawings indicate maximum dimensions for
enclosed switches and circuit breakers, including clearances between enclosures, and adjacent surfaces and other items. Comply with indicated maximum dimensions. 1.6 PROJECT CONDITIONS
A. Environmental Limitations: Rate equipment for continuous operation under the following conditions, unless otherwise indicated: 1. Ambient Temperature: Not less than minus 22 deg F
(minus 30 deg C) and not exceeding 104 deg F (40 deg C). 2. Altitude: Not exceeding 6600 feet (2010 m). 1.7 COORDINATION A. Coordinate layout and installation of switches, circuit breakers,
and components with other construction, including conduit, piping, equipment, and adjacent surfaces. Maintain required workspace clearances and required clearances for equipment access
doors and panels.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED SWITCHES AND CIRCUIT BREAKERS 26 28 16 -3 PART 2 -PRODUCTS 2.1 MANUFACTURERS A. In other Part 2 articles where titles below introduce lists, the following requirements apply
to product selection: 1. Manufacturers: Subject to compliance with requirements, provide products by one of the manufacturers specified. 2.2 FUSIBLE AND NONFUSIBLE SWITCHES A. Manufacturers:
1. Eaton Corporation; Cutler-Hammer Products. 2. General Electric Co.; Electrical Distribution & Control Division. 3. Siemens Energy & Automation, Inc. 4. Square D/Group Schneider. B.
Fusible Switch, 600 A and Smaller: NEMA KS 1, Type HD, with clips or bolt pads to accommodate specified fuses, lockable handle with capability to accept two padlocks, and interlocked
with cover in closed position. C. Non-fusible Switch, 600 A and Smaller: NEMA KS 1, Type Type HD, lockable handle with capability to accept two padlocks, and interlocked with cover in
closed position. D. Accessories: 1. Equipment Ground Kit: Internally mounted and labeled for copper and aluminum ground conductors. 2. Neutral Kit: Internally mounted; insulated, capable
of being grounded, and bonded; and labeled for copper and aluminum neutral conductors. 3. Auxiliary Contact Kit: Auxiliary set of contacts arranged to open before switch blades open.
2.3 MOLDED-CASE CIRCUIT BREAKERS A. Manufacturers: 1. Eaton Corporation; Cutler-Hammer Products. 2. General Electric Co.; Electrical Distribution & Control Division. 3. Moeller Electric
Corporation. 4. Siemens Energy & Automation, Inc. 5. Square D/Group Schneider.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED SWITCHES AND CIRCUIT BREAKERS 26 28 16 -4 B. Molded-Case Circuit Breaker: NEMA AB 1, with interrupting capacity to meet available fault currents. 1. Thermal-Magnetic Circuit
Breakers: Inverse time-current element for low-level overloads and instantaneous magnetic trip element for short circuits. Adjustable instantaneous trip setting for circuit-breaker frame
sizes 150 A and larger. 2. Lugs: Mechanical style suitable for number, size, trip ratings, and conductor material. 2.4 ENCLOSURES A. NEMA AB 1 and NEMA KS 1 to meet environmental conditions
of installed
location. 1. Outdoor Locations: NEMA 250, Type 3R. 2. Kitchen Areas: NEMA 250, Type 4X, stainless steel. 3. Other Wet or Damp Indoor Locations: NEMA 250, Type 4. 4. Hazardous Areas Indicated
on Drawings: NEMA 250, Type 7C. PART 3 -EXECUTION 3.1 EXAMINATION EXAMINATION A. Examine elements and surfaces to receive enclosed switches and circuit breakers for compliance with installation
tolerances and other conditions affecting performance. B. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 CONCRETE BASES A. Coordinate size and
location of concrete bases. Verify structural requirements with structural engineer. B. Concrete base is specified in Division 26 Section "Hangers and Supports for Electrical Systems,"
and concrete materials and installation requirements are specified in Division 3. 3.3 INSTALLATION A. Comply with applicable portions of NECA 1, NEMA PB 1.1, and NEMA PB 2.1 for installation
of enclosed switches and circuit breakers. B. Mount individual wall-mounting switches and circuit breakers with tops at uniform height, unless otherwise indicated. Anchor floor-mounting
switches to concrete base.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED SWITCHES AND CIRCUIT BREAKERS 26 28 16 -5 C. Temporary Lifting Provisions: Remove temporary lifting eyes, channels, and brackets and temporary blocking of moving parts from
enclosures and components. 3.4 IDENTIFICATION A. Identify field-installed conductors, interconnecting wiring, and components; provide warning signs as specified in Division 26 Section
"Identification for Electrical Systems." B. Enclosure Nameplates: Label each enclosure with engraved metal or laminated-plastic nameplate as specified in Division 26 Section "Identification
for Electrical Systems." 3.5 FIELD QUALITY CONTROL A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust field-assembled components
and equipment installation, including connections, and to assist in field testing. testing. Report results in writing. B. Prepare for acceptance testing as follows: 1. Inspect mechanical
and electrical connections. 2. Verify switch and relay type and labeling verification. 3. Verify rating of installed fuses. 4. Inspect proper installation of type, size, quantity, and
arrangement of mounting or anchorage devices complying with manufacturer's certification. C. Perform the following field tests and inspections and prepare test reports: 1. Perform each
electrical test and visual and mechanical inspection. Certify compliance with test parameters. 2. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance;
otherwise, replace with new units and retest. 3.6 ADJUSTING A. Set field-adjustable switches and circuit-breaker trip ranges. 3.7 CLEANING A. On completion of installation, vacuum dirt,
and debris from interiors; do not use compressed air to assist in cleaning.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED SWITCHES AND CIRCUIT BREAKERS 26 28 16 -6 B. Inspect exposed surfaces and repair damaged finishes. END OF SECTION 26 28 16
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED CONTROLLERS 26 29 13 -1 SECTION 26 29 13 -ENCLOSED CONTROLLERS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and
Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes ac, enclosed controllers rated 600 V and less, of the following
types: 1. Across-the-line, manual and magnetic controllers. 1.3 SUBMITTALS A. Product Data: For each type of enclosed controller. Include dimensions and manufacturer's technical data
on features, performance, electrical characteristics, ratings, and finishes. B. Shop Drawings: For each enclosed controller. 1. Include dimensioned plans, elevations, sections, and details,
including required clearances and service space around equipment. Show tabulations of installed devices, equipment features, and ratings. Include the following: a. Each installed unit's
type and details. b. Nameplate legends. c. Short-circuit current rating of integrated unit. d. Features, characteristics, ratings, and factory settings of individual overcurrent protective
devices in combination controllers. 2. Wiring Diagrams: Power, signal, and control wiring. C. Field quality-control test reports. D. Operation and Maintenance Data: For enclosed controllers
to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 1 Section "Operation and Maintenance Data," include the following: 1. Routine
maintenance requirements for enclosed controllers and all installed components. 2. Manufacturer's written instructions for testing and adjusting overcurrent protective devices.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED CONTROLLERS 26 29 13 -2 E. Load-Current and List of Settings of Adjustable Overload Relays: Compile after motors have been installed and arrange to demonstrate that settings
for motor running overload protection suit actual motor to be protected. 1.4 QUALITY ASSURANCE A. Source Limitations: Obtain enclosed controllers of a single type through one source
from a single manufacturer. B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having
jurisdiction, and marked for intended use. C. Comply with NFPA 70. D. Product Selection for Restricted Space: Drawings indicate maximum dimensions for enclosed controllers, minimum clearances
between enclosed controllers, and for adjacent surfaces and other items. Comply with with indicated maximum dimensions and clearances. 1.5 DELIVERY, STORAGE, AND HANDLING A. Store enclosed
controllers indoors in clean, dry space with uniform temperature to prevent condensation. Protect enclosed controllers from exposure to dirt, fumes, water, corrosive substances, and
physical damage. B. If stored in areas subject to weather, cover enclosed controllers to protect them from weather, dirt, dust, corrosive substances, and physical damage. Remove loose
packing and flammable materials from inside controllers; install electric heating of sufficient wattage to prevent condensation. 1.6 PROJECT CONDITIONS A. Interruption of Existing Electrical
Service: Do not interrupt electrical service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary
electrical service according to requirements indicated: 1. Notify Owner no fewer than two days in advance of proposed interruption of electrical service. 2. Indicate method of of providing
temporary utilities. 3. Do not proceed with interruption of electrical service without Owner's written permission.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED CONTROLLERS 26 29 13 -3 1.7 COORDINATION A. Coordinate layout and installation of enclosed controllers with other construction including conduit, piping, equipment, and adjacent
surfaces. Maintain required workspace clearances and required clearances for equipment access doors and panels. B. Coordinate size and location of concrete bases. Cast anchor-bolt inserts
into bases. Concrete, reinforcement, and formwork requirements are specified in Division 3 Section "Cast-in-Place Concrete." C. Coordinate installation of roof curbs, equipment supports,
and roof penetrations. These items are specified in Division 7 Section "Roof Accessories." D. Coordinate features, accessories, and functions of each enclosed controller with ratings
and characteristics of supply circuit, motor, required control sequence, and duty cycle of motor and load. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Manufacturers: Subject to compliance
with requirements, provide products by one of the following: 1. Eaton Corporation; Cutler-Hammer Products. 2. General Electrical Company; GE Industrial Systems. 3. Rockwell Automation;
Allen-Bradley Co.; Industrial Control Group. 4. Siemens/Furnas Controls. 5. Square D. 2.2 ACROSS-THE-LINE ENCLOSED CONTROLLERS A. Manual Controller: NEMA ICS 2, general purpose, Class
A, with "quick-make, quick-break" toggle or pushbutton action, and marked to show whether unit is "OFF," "ON," or "TRIPPED." 1. Overload Relay: Ambient-compensated type with inverse-time-current
characteristics and NEMA ICS 2, Class 10 tripping characteristics. Relays shall have heaters and sensors in each phase, matched to nameplate, full-load current of specific motor to which
they connect and shall have appropriate adjustment for duty cycle. B. Magnetic Controller: NEMA ICS 2, Class A, full voltage, non-reversing, across the line, unless otherwise otherwise
indicated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED CONTROLLERS 26 29 13 -4 1. Control Circuit: 120 V; obtained from integral control power transformer with a control power transformer of sufficient capacity to operate connected
pilot, indicating and control devices, plus additional 50 VA capacity. 2. Adjustable Overload Relay: Solid state selectable for motor running overload protection with NEMA ICS 2, Class
20 tripping characteristic, and selected to protect motor against voltage and current unbalance and single phasing. C. Combination Magnetic Controller: Factory-assembled combination
controller with NEMA AB 1, motor-circuit protector with field-adjustable (3X to 10X) short-circuit trip coordinated with motor locked-rotor amperes. 2.3 ENCLOSURES A. Description: Surface-mounting
cabinets as indicated. NEMA 250, Type 1, unless otherwise indicated to comply with environmental conditions at installed location. 1. Outdoor Locations: NEMA 250, Type 3R. 2. Kitchen
Areas: NEMA 250, Type 4X, stainless steel. 3. Other Wet or Damp Indoor Locations: NEMA 250, Type 4. 4. Hazardous Areas Indicated on Drawings: NEMA 250, Type 7C. 2.4 ACCESSORIES A. Devices
shall be factory installed in controller enclosure, unless otherwise indicated. B. Push-Button Stations: NEMA ICS 2, heavy-duty type. C. Hand-Off-Auto Selector Switches: NEMA ICS2, heavy
duty type. D. Control Relays: Auxiliary and adjustable time-delay relays. E. Pilot Lights: LED lamps, push to test, red for run, green for "OFF." 2.5 FACTORY FINISHES A. Finish: Manufacturer's
standard paint applied to factory-assembled and -tested enclosed controllers before shipping. PART 3 -EXECUTION 3.1 EXAMINATION
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED CONTROLLERS 26 29 13 -5 A. Examine areas and surfaces to receive enclosed controllers for compliance with requirements, installation tolerances, and other conditions affecting
performance. 1. Proceed with installation only after unsatisfactory conditions have been corrected. 3.2 APPLICATIONS A. Select features of each enclosed controller to coordinate with
ratings and characteristics of supply circuit and motor; required control sequence; duty cycle of motor, controller, and load; and configuration of pilot device and control circuit affecting
controller functions. B. Select horsepower rating of controllers to suit motor controlled. 3.3 INSTALLATION A. For control equipment at walls, bolt units to wall or mount on lightweight
structural-steel channels bolted to wall. For controllers not at walls, provide freestanding racks complying with Division 26 Section "Hangers and Supports for Electrical Systems." B.
Install freestanding equipment on concrete bases. 3.4 CONCRETE BASES A. Coordinate size and location of concrete bases. Verify structural requirements with structural engineer. B. Concrete
base is specified in Division 26 Section "Hangers and Supports for Electrical Systems," and concrete materials and installation requirements are specified in Division 3. 3.5 IDENTIFICATION
A. Identify enclosed controller, components, and control wiring according to Division 26 Section "Identification for Electrical Systems." 3.6 CONTROL WIRING INSTALLATION A. Install wiring
between enclosed controllers according to Division 26 Section "Low-Voltage Electrical Power Conductors and Cables." B. Bundle, train, and support wiring in enclosures. C. Connect hand-off-automatic
switch and other automatic-control devices where applicable.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
ENCLOSED CONTROLLERS 26 29 13 -6 3.7 CONNECTIONS A. Conduit installation requirements are specified in other Division 26 Sections. Drawings indicate general arrangement of conduit, fittings,
and specialties. B. Ground equipment according to Division 26 Section "Grounding and Bonding for Electrical Systems." 3.8 FIELD QUALITY CONTROL A. Prepare for acceptance tests as follows:
1. Test insulation resistance for each enclosed controller element, bus, component, connecting supply, feeder, and control circuit. 2. Test continuity of each circuit. B. Manufacturer's
Field Service: Engage a factory-authorized service representative to perform the following: 1. Inspect controllers, wiring, components, connections, and equipment installation. Test
and adjust controllers, components, and equipment. 2. Assist in field testing of equipment including pretesting and adjusting of solid-state controllers. 3. Report results in writing.
C. Perform the following field tests and inspections and prepare test reports: 1. Perform each electrical test and visual and mechanical inspection. Certify compliance with test parameters.
2. Correct malfunctioning units on-site, where possible, and retest to demonstrate compliance; otherwise, replace with new units and retest. 3.9 ADJUSTING A. Set field-adjustable switches
and circuit-breaker trip ranges. 3.10 DEMONSTRATION A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain enclosed
controllers. Refer to Division 1 Section "Demonstration and Training." END OF SECTION 26 29 13
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
INTERIOR LIGHTING 26 51 00 -1 SECTION 26 51 00 -INTERIOR LIGHTING PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Interior lighting fixtures, lamps, and ballasts. 2. Emergency
lighting units. 3. Exit signs. 4. Lighting fixture supports. B. Related Sections include the following: 1. Division 26 Section "Wiring Devices" for manual wall-box dimmers for incandescent
lamps. 1.3 DEFINITIONS A. BF: Ballast factor. B. CRI: Color-rendering index. C. CU: Coefficient of utilization. D. HID: High-intensity discharge. E. LER: Luminaire efficacy rating. F.
Luminaire: Complete lighting fixture, including ballast housing if provided. G. RCR: Room cavity ratio.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
INTERIOR LIGHTING 26 51 00 -2 1.4 SUBMITTALS A. Product Data: For each type of lighting fixture, arranged in order of fixture designation. Include data on features, accessories, finishes,
and the following: 1. Physical description of lighting fixture including dimensions. 2. Emergency lighting units. 3. Ballast. 4. Energy-efficiency data. 5. Life, output, and energy-efficiency
data for lamps. 6. Photometric data, in IESNA format, based on laboratory tests of each lighting fixture type, outfitted with lamps, ballasts, and accessories identical to those indicated
for the lighting fixture as applied in this Project. B. Shop Drawings: Show details of nonstandard or custom lighting fixtures. Indicate dimensions, weights, methods of field assembly,
components, features, and accessories. C. Product Certificates: For each type of ballast for bi-level and dimmer-controlled fixtures, signed by product manufacturer. D. Field quality-control
test reports. E. Operation and Maintenance Data: For lighting equipment and fixtures to include in emergency, operation, and maintenance manuals. F. Warranties: Special warranties specified
in this Section. 1.5 QUALITY ASSURANCE A. Luminaire Photometric Data Testing Laboratory Qualifications: Provided by manufacturers' laboratories that are accredited under the National
Volunteer Laboratory Accreditation Program for Energy Efficient Lighting Products. B. Defined by OSHA in 29 CFR 1910.7. C. Electrical Components, Devices, and Accessories: Listed and
labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. D. Comply with NFPA 70. E. FMG Compliance:
Lighting fixtures for hazardous locations shall be listed and labeled for indicated class and division of hazard by FMG.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
INTERIOR LIGHTING 26 51 00 -3 1.6 COORDINATION A. Coordinate layout and installation of lighting fixtures and suspension system with other construction that penetrates ceilings or is
supported by them, including HVAC equipment, firesuppression system, and partition assemblies. B. Coordinate ceiling type with reflected ceiling plan and provide appropriate mounting
frame for specified light fixture. Light fixture model/series on fixture schedule on drawing does not specify type of trim. 1.7 WARRANTY A. Special Warranty for Ballasts: Manufacturer's
standard form in which ballast manufacturer agrees to repair or replace ballasts that fail in materials or workmanship within specified warranty period. 1. Warranty Period for Electronic
Ballasts: Five years from date of Substantial Completion. 1.8 EXTRA MATERIALS A. Furnish extra materials described below that match products installed and that are packaged with protective
covering for storage and identified with labels describing contents. 1. Lamps: 10 for every 100 of each type and rating installed. Furnish at least one of each type. 2. Ballasts: 1 for
every 100 of each type and rating installed. Furnish at least one of each type. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. In Interior Lighting Fixture Schedule where titles below are column
or row headings that introduce lists, the following requirements apply to product selection: 1. Basis-of-Design Product: The design for each lighting fixture is based on the product
series. Subject to compliance with requirements, provide either the light series named product or a comparable product by one of the other manufacturers specified. 2.2 LIGHTING FIXTURES
AND COMPONENTS, GENERAL REQUIREMENTS A. Recessed Fixtures: Comply with NEMA LE 4 for ceiling compatibility for recessed fixtures.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
INTERIOR LIGHTING 26 51 00 -4 B. Incandescent Fixtures: Comply with UL 1598. Where LER is specified, test according to NEMA LE 5A. C. Fluorescent Fixtures: Comply with UL 1598. Where
LER is specified, test according to NEMA LE 5 and NEMA LE 5A as applicable. D. HID Fixtures: Comply with UL 1598. Where LER is specified, test according to NEMA LE 5B. E. Metal Parts:
Free of burrs and sharp corners and edges. F. Sheet Metal Components: Steel, unless otherwise indicated. Form and support to prevent warping and sagging. G. Doors, Frames, and Other
Internal Access: Smooth operating, free of light leakage under operating conditions, and designed to permit relamping without use of tools. Designed to prevent doors, frames, lenses,
diffusers, and other components from falling accidentally during relamping and when secured in operating position. H. Reflecting surfaces shall have minimum reflectance as follows, unless
otherwise indicated: 1. White Surfaces: 85 percent. 2. Specular Surfaces: 83 percent. 3. Diffusing Specular Surfaces: 75 percent. 4. Laminated Silver Metallized Film: 90 percent. I.
Plastic Diffusers, Covers, and Globes: 1. Acrylic Lighting Diffusers: 100 percent virgin acrylic plastic. High resistance to yellowing and other changes due to aging, exposure to heat,
and UV radiation. a. Lens Thickness: At least 0.125 inch (3.175 mm) minimum unless different thickness is indicated. b. UV stabilized. 2. Glass: Annealed crystal glass, unless otherwise
indicated. 2.3 BALLASTS FOR LINEAR FLUORESCENT LAMPS A. Electronic Ballasts: Comply with ANSI C82.11; programmed-start type, unless otherwise indicated, and designed for type and quantity
of lamps served. Ballasts shall be designed for full light output unless dimmer or bi-level control is indicated. 1. Sound Rating: A. 2. Total Harmonic Distortion Rating: Less than 10
percent. 3. Transient Voltage Protection: IEEE C62.41, Category A or better.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
INTERIOR LIGHTING 26 51 00 -5 4. Operating Frequency: 20 kHz or higher. 5. Lamp Current Crest Factor: 1.7 or less. 6. BF: 0.85 or higher. 7. Power Factor: 0.98 or higher. 8. Parallel
Lamp Circuits: Multiple lamp ballasts shall comply with ANSI C 82.11 and shall be connected to maintain full light output on surviving lamps if one or more lamps fail. B. Electronic
Programmed-Start Ballasts for T5 and T5HO Lamps: Comply with ANSI C82.11 and the following: 1. Lamp end-of-life detection and shutdown circuit for T5 diameter lamps. 2. Automatic lamp
starting after lamp replacement. 3. Sound Rating: A. 4. Total Harmonic Distortion Rating: Less than 20 percent. 5. Transient Voltage Protection: IEEE C62.41, Category A or better. 6.
Operating Frequency: 20 kHz or higher. 7. Lamp Current Crest Factor: 1.7 or less. 8. BF: 0.95 or higher, unless otherwise indicated. 9. Power Factor: 0.98 or higher. C. Electromagnetic
Ballasts: Comply with ANSI C82.1; energy saving, high-power factor, Class P, and having automatic-reset thermal protection. 1. Ballast Manufacturer Certification: Indicated by label.
D. Ballasts for Low-Temperature Environments: 1. Temperatures 0 Deg F (Minus 17 Deg C) and Higher: Electronic type rated for 0 deg F (minus 17 deg C) starting and operating temperature
with indicated lamp types. 2. Temperatures Minus 20 Deg F (Minus 29 Deg C) and Higher: Electromagnetic type designed for use with indicated lamp types. E. Ballasts for Dimmer-Controlled
Lighting Fixtures: Electronic type. 1. Dimming Range: 100 to 10 percent of rated lamp lumens. 2. Ballast Input Watts: Can be reduced to 20 percent of normal. 3. Compatibility: Certified
by manufacturer for use with specific dimming control system and lamp type indicated. 2.4 BALLASTS FOR COMPACT FLUORESCENT LAMPS A. Description: Electronic programmed rapid-start type,
complying with ANSI C 82.11, designed for type and quantity of lamps indicated. Ballast shall be designed for full light output unless dimmer or bi-level control is indicated:
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
INTERIOR LIGHTING 26 51 00 -6 1. Lamp end-of-life detection and shutdown circuit. 2. Automatic lamp starting after lamp replacement. 3. Sound Rating: A. 4. Total Harmonic Distortion
Rating: Less than 10 percent. 5. Transient Voltage Protection: IEEE C62.41, Category A or better. 6. Operating Frequency: 20 kHz or higher. 7. Lamp Current Crest Factor: 1.7 or less.
8. BF: 0.95 or higher, unless otherwise indicated. 9. Power Factor: 0.98 or higher. 10. Interference: Comply with 47 CFR, Chapter 1, Part 18, Subpart C, for limitations on electromagnetic
and radio-frequency interference for non-consumer equipment. 11. Ballast Case Temperature: 75 deg C, maximum. B. Ballasts for Dimmer-Controlled Lighting Fixtures: Electronic type. 1.
Dimming Range: 100 to 10 percent of rated lamp lumens. 2. Ballast Input Watts: Can be reduced reduced to 20 percent of normal. 3. Compatibility: Certified by manufacturer for use with
specific dimming control system and lamp type indicated. 2.5 BALLASTS FOR HID LAMPS A. Electromagnetic Ballast for Metal-Halide Lamps: Comply with ANSI C82.4 and UL 1029. Include the
following features, unless otherwise indicated: 1. Ballast Circuit: Constant-wattage autotransformer or regulating high-power-factor type. 2. Minimum Starting Temperature: Minus 22 deg
F (Minus 30 deg C) for single-lamp ballasts. 3. Normal Ambient Operating Temperature: 104 deg F (40 deg C). 4. Open-circuit operation that will not reduce average life. 5. Low-Noise
Ballasts: Manufacturers' standard epoxy-encapsulated models designed to minimize audible fixture noise. B. Electronic Ballast for Metal-Halide Lamps: Include the following features unless
otherwise indicated: 1. Lamp end-of-life detection and shutdown circuit. 2. Sound Rating: A. 3. Total Harmonic Distortion Rating: Less than 15 percent. 4. Transient Voltage Protection:
IEEE C62.41, Category A or better. 5. Lamp Current Crest Factor: 1.5 or less. 6. Power Factor: .90 or higher. 7. Interference: Comply with 47 CFR, Chapter 1, Part 18, Subpart C, for
limitations on electromagnetic and radio-frequency interference for non-consumer equipment. 8. Protection: Class P thermal cutout.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
INTERIOR LIGHTING 26 51 00 -7 C. Auxiliary Instant-On Quartz System: Factory-installed feature automatically switches quartz lamp on when fixture is initially energized and when power
outages occur. System automatically turns quartz lamp off when HID lamp reaches approximately 60 percent light output. 2.6 EXIT SIGNS A. Description: Comply with UL 924; for sign colors,
visibility, luminance, and lettering size, comply with authorities having jurisdiction. B. Internally Lighted Signs: 1. Lamps for AC Operation: Fluorescent, 2 for each fixture, 20,000
hours of rated lamp life. 2. Lamps for AC Operation: LEDs, 70,000 hours minimum rated lamp life. 2.7 FLUORESCENT LAMPS A. Low-Mercury Lamps: Comply with EPA's toxicity characteristic
leaching procedure test; shall yield less than 0.2 mg of mercury per liter when tested according to NEMA LL 1. B. T8 rapid-start low-mercury lamps, rated 32 W maximum, nominal length
of 48 inches (1220 mm), 2800 initial lumens (minimum), CRI 75 (minimum), color temperature 3500 K, and average rated life 20,000 hours, unless otherwise indicated. C. T8 rapid-start
low-mercury lamps, rated 17 W maximum, nominal length of 24 inches (610 mm), 1300 initial lumens (minimum), CRI 75 (minimum), color temperature 3500 K, and average rated life of 20,000
hours, unless otherwise indicated. D. T5 rapid-start low-mercury lamps, rated 28 W maximum, nominal length of 45.2 inches (1150 mm), 2900 initial lumens (minimum), CRI 85 (minimum),
color temperature 3500 K, and average rated life of 20,000 hours, unless otherwise indicated. E. T5 rapid-start low-mercury lamps, rated 14W maximum, nominal length, 21 inches, 1300
initial lumens (minimum), CRI 85 (minimum), color temperatures 4100 K and average
rated life of 20,000 hours, unless otherwise indicated. F. TT5, Biax low-mercury lamps, rated 40 W maximum, nominal length of 24 inches, 3150 initial lumens (minimum), CRI of 75, color
temperature of 3500 K and average rated life of 20,000 hours, unless otherwise indicated. G. TT5, Biax low-mercury lamps, rated 50 W maximum, nominal length of 24 inches, 4000 initial
lumens (minimum), CRI of 75, color temperature of 3500 K and average rated life of 20,000 hours, unless otherwise indicated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
INTERIOR LIGHTING 26 51 00 -8 H. Compact Fluorescent Lamps: 4-Pin, low mercury, CRI 80 (minimum), color temperature 3500 K, average rated life of 10,000 hours at 3 hours operation per
start, and suitable for use with dimming ballasts, unless otherwise indicated. 1. 13 W: T4, double tube rated 900 initial lumens (minimum). 2. 18 W: T4, double tube rated 1200 initial
lumens (minimum). 3. 26 W: T4, double tube rated 1800 initial lumens (minimum). 4. 32 W: T4, triple tube, rated 2400 initial lumens (minimum). 5. 42 W: T4, triple tube, rated 3200 initial
lumens (minimum). 6. 55 W: T4, triple tube, rated 4300 initial lumens (minimum). 2.8 HID LAMPS A. Metal-Halide Lamps: ANSI C78.1372, with a minimum CRI 65, and color temperature 4000
K. B. Pulse-Start, Metal-Halide Lamps: Minimum CRI 65, and color temperature 4000 K. C. Ceramic, Pulse-Start, Metal-Halide Lamps: Minimum CRI 80, and color temperature 4000 K. 2.9 LIGHTING
FIXTURE SUPPORT COMPONENTS A. Comply with Division 26 Section "Hangers and Supports for Electrical Systems" for channeland angle-iron supports and nonmetallic channel and angle supports.
B. Single-Stem Hangers: 1/2-inch (13-mm) steel tubing with swivel ball fittings and ceiling canopy. Finish same as fixture. C. Twin-Stem Hangers: Two, 1/2-inch (13-mm) steel tubes with
single canopy designed to mount a single fixture. Finish same as fixture. D. Wires: ASTM A 641/A 641M, Class 3, soft temper, zinc-coated steel, 12 gage (2.68 mm). E. Wires for Humid
Spaces: ASTM A 580/A 580M, Composition 302 or 304, annealed stainless steel, 12 gage (2.68 mm). F. Rod Hangers: 3/16-inch (5-mm) minimum diameter, cadmium-plated, threaded steel rod.
G. Hook Hangers: Integrated assembly matched to fixture and line voltage and equipped with threaded attachment, cord, and locking-type plug.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
INTERIOR LIGHTING 26 51 00 -9 PART 3 -EXECUTION 3.1 INSTALLATION A. Lighting fixtures: Set level, plumb, and square with ceilings and walls. Install lamps in each fixture. B. Support
for Lighting Fixtures in or on Grid-Type Suspended Ceilings: Use grid as a support element. 1. Install a minimum of two four ceiling support system rods or wires for each fixture. Locate
not more than 6 inches (150 mm) from lighting fixture corners. 2. Support Clips: Fasten to lighting fixtures and to ceiling grid members at or near each fixture corner with clips that
are UL listed for the application. 3. Fixtures of Sizes Less Than Ceiling Grid: Install as indicated on reflected ceiling plans or center in acoustical panel, and support fixtures independently
with at least two 3/4-inch (20-mm) metal channels spanning and secured to ceiling ceiling tees. 4. Install at least one independent support rod or wire from structure to a tab on lighting
fixture. Wire or rod shall have breaking strength of the weight of fixture at a safety factor of 3. C. Suspended Lighting Fixture Support: 1. Pendants and Rods: Where longer than 48
inches (1200 mm), brace to limit swinging. 2. Stem-Mounted, Single-Unit Fixtures: Suspend with twin-stem hangers. 3. Continuous Rows: Use tubing or stem for wiring at one point and tubing
or rod for suspension for each unit length of fixture chassis, including one at each end. D. Adjust aimable lighting fixtures to provide required light intensities. E. Connect wiring
according to Division 26 Section "Low-Voltage Electrical Power Conductors and Cables." 3.2 FIELD QUALITY CONTROL A. Test for Emergency Lighting: Interrupt power supply to demonstrate
proper operation. Verify transfer from normal power to battery and retransfer to normal. B. Prepare a written report of tests, inspections, observations, and verifications indicating
and interpreting results. If adjustments are made to lighting system, retest to demonstrate compliance with standards. END OF SECTION 26 51 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR COMMUNICATIONS 27 05 00 -1 SECTION 27 05 00 -COMMON WORK RESULTS FOR COMMUNICATIONS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of
the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Communications equipment
coordination and installation. 2. Sleeves for pathways and cables. 3. Sleeve seals. 4. Grout. 5. Common communications installation requirements. 1.3 DEFINITIONS A. EPDM: Ethylene-propylene-diene
terpolymer rubber. B. NBR: Acrylonitrile-butadiene rubber. 1.4 SUBMITTALS A. Product Data: For sleeve seals. 1.5 COORDINATION A. Coordinate arrangement, mounting, and support of communications
equipment: 1. To allow maximum possible headroom unless specific mounting heights that reduce headroom are indicated. 2. To provide for ease of disconnecting the equipment with minimum
interference to other installations. 3. To allow right of way for piping and conduit installed at required slope. 4. So connecting pathways, cables, wireways, cable trays, and busways
will be clear of obstructions and of the working and access space of other equipment.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR COMMUNICATIONS 27 05 00 -2 B. Coordinate installation of required supporting devices and set sleeves in cast-in-place concrete, masonry walls, and other structural
components as they are constructed. C. Coordinate location of access panels and doors for communications items that are behind finished surfaces or otherwise concealed. Access doors
and panels are specified in Division 8 Section "Access Doors and Frames." D. Coordinate sleeve selection and application with selection and application of firestopping specified in Division
7 Section "Firestopping." PART 2 -PRODUCTS 2.1 SLEEVES FOR PATHWAYS AND CABLES A. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40, galvanized steel, plain ends. B.
Sleeves for Rectangular Openings: Galvanized sheet steel. 1. Minimum Metal Thickness: a. For sleeve cross-section rectangle perimeter less than 50 inches (1270 mm) and no side more than
16 inches (400 mm), thickness shall be 0.052 inch (1.3 mm). b. For sleeve cross-section rectangle perimeter equal to, or more than, 50 inches (1270 mm) and 1 or more sides equal to,
or more than, 16 inches (400 mm), thickness shall be 0.138 inch (3.5 mm). 2.2 SLEEVE SEALS A. Description: Modular sealing device, designed for field assembly, to fill annular space
between sleeve and pathway or cable. 1. Manufacturers: Subject to compliance with requirements, provide products by one of the following: a. Advance Products & Systems, Inc. b. Calpico,
Inc. c. Metraflex Co. d. Pipeline Seal and Insulator, Inc. 2. Sealing Elements: EPDM interlocking links shaped to fit surface of cable or conduit. Include type and number required for
material and size of pathway or cable. 3. Pressure Plates: Carbon steel. Include two for each sealing element.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR COMMUNICATIONS 27 05 00 -3 4. Connecting Bolts and Nuts: Carbon steel with corrosion-resistant coating of length required to secure pressure plates to sealing
elements. Include one for each sealing element. 2.3 GROUT A. Nonmetallic, Shrinkage-Resistant Grout: ASTM C 1107, factory-packaged, nonmetallic aggregate grout, noncorrosive, nonstaining,
mixed with water to consistency suitable for application and a 30-minute working time. PART 3 -EXECUTION 3.1 COMMON REQUIREMENTS FOR COMMUNICATIONS INSTALLATION A. Comply with NECA 1.
B. Measure indicated mounting heights to bottom of unit for suspended items and to center of unit for wall-mounting items. C. Headroom Maintenance: If mounting heights or other location
criteria are not indicated, arrange and install components and equipment to provide maximum possible headroom consistent with these requirements. D. Equipment: Install to facilitate
service, maintenance, and repair or replacement of components of both communications equipment and other nearby installations. Connect in such a way as to facilitate future disconnecting
with minimum interference with other items in the vicinity. E. Right of Way: Give to piping systems installed at a required slope. 3.2 SLEEVE INSTALLATION FOR COMMUNICATIONS PENETRATIONS
A. Communications penetrations occur when pathways, cables, wireways, or cable trays penetrate concrete slabs, concrete or masonry walls, or fire-rated floor and wall assemblies. B.
Concrete Slabs and Walls: Install sleeves for penetrations unless core-drilled holes or formed openings are used. Install sleeves during erection of slabs and walls. C. Use pipe sleeves
unless penetration arrangement requires rectangular sleeved opening. D. Fire-Rated Assemblies: Install sleeves for penetrations of fire-rated floor and wall assemblies unless openings
compatible with firestop system used are fabricated during construction of floor or wall. E. Cut sleeves to length for mounting flush with both surfaces of walls.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR COMMUNICATIONS 27 05 00 -4 F. Extend sleeves installed in floors 2 inches (50 mm) above finished floor level. G. Size pipe sleeves to provide 1/4-inch (6.4-mm)
annular clear space between sleeve and pathway or cable, unless indicated otherwise. H. Seal space outside of sleeves with grout for penetrations of concrete and masonry 1. Promptly
pack grout solidly between sleeve and wall so no voids remain. Tool exposed surfaces smooth; protect grout while curing. I. Fire-Rated-Assembly Penetrations: Maintain indicated fire
rating of walls, partitions, ceilings, and floors at pathway and cable penetrations. Install sleeves and seal pathway and cable penetration sleeves with firestop materials. Comply with
requirements in Division 7 Section "Firestopping." 3.3 SLEEVE-SEAL INSTALLATION A. Use type and number of sealing elements recommended by manufacturer for pathway or cable material and
size. Position pathway or cable in center of sleeve. Assemble mechanical sleeve seals and install in annular space between pathway or cable and sleeve. Tighten bolts against pressure
plates that cause sealing elements to expand and make watertight seal. 3.4 FIRESTOPPING A. Apply firestopping to penetrations of fire-rated floor and wall assemblies for communications
installations to restore original fire-resistance rating of assembly. Firestopping materials and installation requirements are specified in Division 7 Section "Firestopping." END OF
SECTION 27 05 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -1 SECTION 27 41 33 -MASTER ANTENNA TELEVISION SYSTEM PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract,
including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Master antenna television
systems using cable television service as the signal source. 2. Broadband coaxial cabling for distributing television signal to interface points. 1.3 DEFINITIONS A. Agile Receiver: A
broadband receiver that can be tuned to any desired channel. B. Broadband: For the purposes of this Section, wide bandwidth equipment or systems that can carry signals occupying in the
frequency range of 54 to 1002 MHz. A broadband communication system can simultaneously accommodate television, voice, data, and many other services. C. Carrier: A pure-frequency signal
that is modulated to carry information. In the process of modulation, it is spread out over a wider band. The carrier frequency is the center frequency on any television channel. D.
CATV: Community antenna television; a communication system that simultaneously distributes several different channels of broadcast programs and other information to customers via a coaxial
cable. E. CEA: Consumer Electronics Association. F. dBmV: Decibels relative to 1 mV across 75 ohms. Zero dBmV is defined as 1 mV across 75 ohms. dBmV = 20 log 10(V1/V2) where V1 is the
measurement of voltage at a point having identical impedance to V2 (0.001 V across 75 ohms). G. Headend: The control center of the master antenna television system, where incoming signals
are amplified, converted, processed, and combined into a common cable along with any locally originated television signals, for transmission to user-interface points. It is also called
the "Central Retransmission Facility."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -2 H. MATV: Master antenna television; a small television antenna distribution system usually restricted to one or two buildings. I. RF: Radio
frequency. J. User Interface: End point of Contractor's responsibility for Work of this Section. User interfaces are the 75-ohm terminals on device plates. 1.4 SYSTEM DESCRIPTION A.
System shall consist of cable television service and a coaxial cable distribution system. B. Distribution of direct broadcast satellite service signals, which includes coordinating with
Owner's selected service provider for installation of its dish-type antennas and processing the signals as needed to provide specified services combined into a single-feed point ready
for connection into the distribution system. Obtain signal levels, and noise and distortion characteristics from service provider as the point of departure for system layout and final
equipment selection. C. Cable distribution system consisting of coaxial cables, user interfaces, signal taps and splitters, RF amplifiers, signal equalizers, power supplies, and required
hardware complying with IEEE 802.7 and resulting in performance parameters specified in this Section. 1.5 PERFORMANCE REQUIREMENTS A. Minimum acceptable distribution system performance
at all user-interface points shall be as follows: 1. RF Video Carrier Level: Between 6 and 12 dBmV. 2. Relative Video Carrier Level: Within 3 dB to adjacent channel. 3. Carrier Level
Stability, Short Term: Level shall not change more than 0.5 dB during a 60-minute period. 4. Carrier Level Stability, Long Term: Level shall not change more than 2 dB during a 24-hour
period. 5. Channel Frequency Response: Across any 6-MHz channel in 54-to 220-MHz frequency range, referenced to video, signal amplitude shall be plus or minus 1 dB, maximum. 6. Carrier-to-Noise
Ratio: 45 dB or more. 7. RF Visual Signal-to-Noise Ratio: 43 dB or more. 8. Cross Modulation: Less than minus 50 dB. 9. Carrier-to-Echo Ratio: More than 40 dB. 10. Composite Triple Beat:
Less than minus 53 dB. 11. Second Order Beat: Less than minus 60 dB. 12. Terminal Isolation from Television to Television: 25 dB, minimum. 13. Terminal Isolation between Television and
FM: 35 dB, minimum. 14. Hum Modulation: 2 percent, maximum.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -3 15. RF FM Carrier Level: 13 to 17 dB below video carrier level. 16. FM Frequency Response: More than the 88-to 108-MHz frequency range, signal
amplitude is plus or minus 0.75 dB, maximum. 17. FM Carrier-to-Noise Ratio: More than 24 dB. 1.6 SUBMITTALS A. Product Data: For each type of product indicated. B. Equipment List: Include
every piece of equipment by model number, manufacturer, serial number, location, and date of original installation. Add testing record of each piece of adjustable equipment, listing
name of person testing, date of test, and description of as-left set points. C. Source quality-control test reports on coaxial cable sweep tests. D. Field quality-control test reports.
E. Operation and Maintenance Data: For distribution system to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 1 Section "Operation
and Maintenance Data," include the following: 1. Lists of spare parts and replacement components recommended to be stored at the site for ready access. 2. Include dimensioned plan and
elevation views of components and enclosures. Show access and workspace requirements. 1.7 QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as
defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. B. Comply with NECA 1. C. Comply with NFPA 70. 1.8 PROJECT
CONDITIONS A. Environmental Limitations: System components shall be equipped and rated for the environments where installed.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -4 1.9 COORDINATION A. Coordinate size and location of raceway system, and provisions for electrical power to equipment of this Section. B.
Coordinate Work of this Section with requirements of cable television service provider. 1.10 MAINTENANCE SERVICE A. Initial Maintenance Service: Beginning at Substantial Completion,
provide 12 months' full maintenance by skilled employees of MATV system Installer. Include quarterly adjusting as required for optimum system performance. PART 2 -PRODUCTS 2.1 MANUFACTURERS
A. In other Part 2 articles where titles below introduce lists, the following requirements apply to product selection: 1. Available Manufacturers: Subject to compliance with requirements,
manufacturers offering products that may be incorporated into the Work include, but are are not limited to, manufacturers specified. 2.2 SYSTEMS REQUIREMENTS A. Components: Modular plug-in,
heavy-duty, industrial-or commercial-grade units. B. Equipment: Silicon-based, solid-state, integrated circuit devices. C. Power Supply Characteristics: Devices shall be within specified
parameters for ac supply voltages within the range of 105 to 130 V. D. Protect signal cables and connected components against transient-voltage surges by suppressors and absorbers designed
specifically for the purpose. Comply with Division 26 Section "Transient-Voltage Suppression for Low-Voltage Electrical Power Circuits." E. Provide ac-powered equipment with integral
surge suppressors, complying with UL 1449. F. RF and Video Impedance Matching: Signal-handling components, including connecting cable, shall have end-to-end impedance-matched signal
paths. Match and balance devices used at connections where it is impossible to avoid impedance mismatch or mismatch of balanced circuits to unbalanced circuits.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -5 2.3 MATV EQUIPMENT A. Description: Signal-source components, signal-processing and amplifying equipment, distribution components, and interconnecting
wiring. System shall receive signals from sources, amplify and process them, and distribute them to outlets for receiving sets. B. MATV System Qualitative Performance Requirements: Reception
quality of color-television program transmissions at each system outlet from each designated channel and source shall be equal to or superior than that obtained with performance checks
specified in Part 3 "Field Quality Control" Article, using a standard, commercial, cable-ready, color-television receiver. 2.4 MATV HEADEND COMPONENTS A. Available Manufacturers: 1.
Blonder Tongue Laboratories, Inc. 2. Canare Corporation of America. 3. Channel Master, Inc. 4. Leviton Voice & Data Division. 5. Motorola Broadband Communications Sector. 6. Quality
RF Services, Inc. 7. Scientific-Atlanta, Inc. B. Broadband Amplifier: 1. Frequency Range: 54 to 220 MHz. 2. Frequency Response: Plus or minus 1.0 dB across passband. 3. Maximum Noise:
10 dB. 4. Minimum Return Loss: 16 dB. 5. I/O Impedance: 75 ohms. 2.5 DISTRIBUTION COMPONENTS A. Available Manufacturers: 1. Blonder-Tongue Laboratories, Inc. 2. Canare Corporation of
America. 3. Leviton Voice & Data Division. 4. Motorola Broadband Communications Sector. 5. Quality RF Services, Inc. 6. Scientific-Atlanta, Inc. B. Distribution components shall be for
signal processing and distribution downstream from headend equipment.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -6 C. Signal Power Splitters and Isolation Taps: Metal-enclosed directional couplers with brass connector parts. Where installed in signal circuits
used to supply cable-powered amplifiers, power throughput capacity shall exceed load by at least 25 percent. 1. Return Loss: 17 dB. 2. RFI Shielding: 100 dB. 3. Isolation: 25 dB. 4.
Impedance: 75 ohms for input and output terminals. 5. Electrically powered components shall be UL labeled. D. Distribution System Amplifiers: Powered by coaxial cable system, equipped
with surge protection device and external test points to allow convenient signal monitoring. E. Cable System Power Supplies: Plug-in modular construction, with surge, short circuit,
and overload protection. F. Signal Traps: Packaged filters tuned to interference frequencies encountered in Project. G. Attenuators: Passive, of fixed value, used to balance signal levels.
H. Terminating Resistors: Enclosed units rated 0.5 W and matched for coaxial impedance. I. User-Interface Device: Flush, female-type outlets, designed to mimic power duplex outlet, for
mounting in standard outlet box, with metallic parts of anodized brass, beryllium copper, or phosphor bronze. 1. Cable Connector: Female, Type F. 2. Wall Plates: Match materials and
finish of power outlets in same space. 3. Attenuation: Less than 0.1 dB. 4. Voltage Standing-Wave Ratio: Less than 1.15 to 1. 2.6 CABLES A. Available Manufacturers: 1. Alpha Wire Company.
2. Belden Inc.; Electronics Division. 3. Coleman Cable. 4. CommScope Properties, LLC. 5. Helix/HiTemp Cables, Inc.; Draka USA. 6. West Penn Wire/CDT; a division of Cable Design Technologies,
Inc. B. Cable Characteristics: Broadband type, recommended by cable manufacturer specifically for broadband MATV applications. Coaxial cable and accessories shall have 75-ohm nominal
impedance with a return loss of 20 dB minimum from 7 to 806 MHz, and shall be listed to comply with NFPA 70, Articles 810 and 820.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -7 C. RG-11/U, Indoor Riser Lead-In Cable: No. 14 AWG, solid, copper-covered steel conductor; gas-injected foam-PE insulation. Double shielded
with 100 percent aluminum polyester tape, and 60 percent aluminum braid. Jacketed with sunlight-resistant black PVC or PE. Suitable for outdoor installations in ambient temperatures
ranging from minus 40 to plus 85 deg C; NFPA 70, Type CATV. D. RG-6/U, Indoor Distribution Cable: No. 16 AWG, solid, copper-covered steel conductor; gasinjected foam-PE insulation. Double
shielded with 100 percent aluminum-foil shield, 60 percent aluminum braid. Jacketed with black PVC or PE. Suitable for indoor installations; NFPA 70, Type CATV or CM. 2.7 CABLE CONNECTORS
A. Available Manufacturers: 1. Amphenol Corporation. 2. B&L Coaxial Connections, Ltd. 3. Connect-Tech Products. 4. Leviton Voice & Data Division. B. MATV Coaxial Cable Connectors: Type
F, 75 ohms. 2.8 SOURCE QUALITY CONTROL A. Cable products shall be sweep tested at the factory before shipping at frequencies from 5 MHz to 1 GHz. Sweep test shall test the frequency
response, or attenuation over frequency, of a cable by generating a voltage whose frequency is varied through the specified frequency range and graphing the results. PART 3 -EXECUTION
3.1 EXAMINATION A. Examine pathway elements intended for coaxial cable installation. Check raceways, cables, trays, and other elements for compliance with accessibility for installation
and maintenance, and other conditions affecting installation. B. Examine walls, floors, roofs, equipment bases, and roof supports for suitable conditions where television equipment is
to be installed. C. Proceed with installation only after unsatisfactory conditions have been corrected.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -8 3.2 GENERAL WIRING A. Wiring Method: Install cables in raceways except in accessible indoor ceiling spaces, attics, and as otherwise indicated.
Conceal raceways and wiring except in unfinished spaces. B. Wiring within Enclosures: Bundle, lace, and train conductors to terminal points with no excess and without exceeding manufacturer's
limitations on bending radii. Provide and use lacing bars and distribution spools. C. Splices, Taps, and Terminations: For power and control wiring, use numbered terminal strips in junction,
pull, and outlet boxes; terminal cabinets; and equipment enclosures. D. Grounding: According to recommendations in IEEE 142 and IEEE 1100. 3.3 COAXIAL CABLE INSTALLATION A. Cold-Weather
Installation: Bring cable to room temperature before dereeling. Heat lamps may not be used for heating. B. Cable may not be installed in same raceway with power cable. C. Coaxial cable
shall not be spliced except on plywood backboards in wire closets, or in cabinets designated for the purpose. D. Do not use water-based cable pulling lubricants with PVC-jacketed cable.
E. Do not exceed manufacturer's recommended minimum bending radiuses F. Pulling Cable: Do not exceed manufacturer's recommended pulling tensions. Do not install bruised, kinked, scored,
deformed, or abraded cable. Do not splice cable between termination, tap, or junction points. Remove and discard cable if damaged during installation and replace it with new cable. G.
Exposed Cable: Install parallel to building lines, follow surface contours, and support cable according to manufacturer's written instructions. Do not run adjacent and parallel to power
or data cables. H. Cable Support: Install supports at intervals recommended in writing by cable manufacturer. Install supports within 6 inches (150 mm) of connector so so no weight of
cable is carried by connector. Use no staples or wire ties, pull tie-wrap snug, and do not over tighten. I. Signal Equalization: Where system performance may be degraded in certain operating
modes, revise component connections and install distribution amplifiers and attenuators as required, providing a balanced signal across the system.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01
____________________________________________________________________________________ MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -9 J. Install passive circuit devices, such as splitters
and attenuators, in wire closets or cabinets. Do not install attenuators as part of user-interface device outlets. 3.4 ANTENNA AND HEADEND INSTALLATION A. Arrange equipment to facilitate
access for maintenance and to preserve headroom and passage space. Parts that require periodic service or maintenance shall be readily accessible. Headend components that require tuning
adjustments shall be accessible from the front of equipment cabinets. 3.5 IDENTIFICATION A. Identify system components, wiring, cabling, and terminals according to Division 26 Section
"Identification for Electrical Systems." 3.6 FIELD QUALITY CONTROL A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust field-assembled
components and equipment installation, including connections, and to assist in field testing. Report results in writing. B. Inspection: Verify that units and controls are properly installed,
connected, and labeled, and that interconnecting wires and terminals are identified. C. Pretesting: Align and adjust system and pretest components, wiring, and functions to verify that
they comply with specified requirements. Replace malfunctioning or damaged items. Retest until satisfactory performance and conditions are achieved. Prepare television equipment for
acceptance and operational testing as follows: 1. Use an agile receiver and signal strength meter or spectrum analyzer for testing. 2. CATV Sources: Connect receiver to an agile demodulator
or CATV set-top converter at CATV service entrance to the facility. D. Test Schedule: Schedule tests after pretesting has successfully been completed and system has been in normal functional
operation for at least 14 days. Provide a minimum of 10 days' days' notice of test schedule. E. Operational Tests: Perform operational system tests to verify that system complies with
Specifications. Include all modes of system operation. Test equipment for proper operation in all functional modes.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -10 F. Distribution System Acceptance Tests: 1. Field-Strength Instrument: Rated for minus 40-dBmV measuring sensitivity and a frequency range
of 54 to 812 MHz, minimum. Provide documentation of recent calibration against recognized standards. 2. Signal Level and Picture Quality: Use a field-strength meter or spectrum analyzer,
and a standard TV receiver to measure signal levels and check picture quality at all. Userinterface outlets. a. Test the signal strength in dBmV at 55 and 750 MHz. b. Minimum acceptable
signal level is 0 dBmV (1000 mV). c. Maximum acceptable signal level over the entire bandwidth is 15 dBmV. d. Television receiver shall show no evidence of cross-channel intermodulation,
ghost images, or beat interference. 3. Signal-to-Noise-Ratio Test: Use a field-strength meter to make a sequence of measurements at the output of the last distribution amplifier or of
another agreed-on location in system. With system operating at normal levels, tune meter to the picture carrier frequency of each of the designated channels in turn and record the level.
With signal removed and input to corresponding headend amplifier terminated at 75 ohms, measure the level of noise at same tuning settings. With meter correction factor added to last
readings, differences from first set must not be less than 45 dB. G. Qualitative and Quantitative Performance Tests: Demonstrate reception quality of colortelevision program transmissions
at each user interface from each designated channel and source. Quality shall be equal to or superior than that obtained with performance checks specified below, using a standard, commercial,
cable-ready, color-television receiver. Level and quality of signal at each outlet and from each designated channel and source shall comply with the following Specifications Specifications
when tested according to 47 CFR 76: 1. RF video-carrier level. 2. Relative video-carrier level. 3. Carrier level stability, 60-minute and 24-hour periods. 4. Broadband frequency response.
5. Channel frequency response. 6. Carrier-to-noise ratio. 7. RF visual signal-to-noise ratio. 8. Cross modulation. 9. Carrier-to-echo ratio. 10. Composite triple beat. 11. Second order
beat. 12. Terminal isolation. 13. Terminal isolation between television and FM. 14. Hum modulation. 15. RF FM carrier level. 16. FM frequency response. 17. FM carrier-to-noise ratio.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
MASTER ANTENNA TELEVISION SYSTEM 27 41 33 -11 H. Record test results. I. Retest: Correct deficiencies identified by tests and observations and retest until requirements specified in
Part 1 are met. END OF SECTION 27 41 33
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS 27 51 16 -1 SECTION 27 51 16 -PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general
provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Loudspeakers.
2. Conductors and cables. 3. Raceways. B. New system will be connected to existing multi-zone paging system currently used for amplifying and distributing voice communications via telephone
dial-up throughout the existing facility and other satellite facility. 1.3 DEFINITIONS A. Channels: Separate parallel signal paths, from sources to loudspeakers or loudspeaker zones,
with separate amplification and switching that permit selection between paths for speaker alternative program signals. B. VU: Volume unit. C. Zone: Separate group of loudspeakers and
associated supply wiring that may be arranged for selective switching between different channels. 1.4 PERFORMANCE REQUIREMENTS A. Delegated Design: Design supports and seismic restraints
for control consoles, equipment cabinets and racks, and components, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements
and design criteria indicated. 1.5 SUBMITTALS A. Product Data: For each type of product indicated.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS 27 51 16 -2 B. Shop Drawings: For supports and seismic restraints for control consoles, equipment cabinets and racks, and components. Include
plans, elevations, sections, details, and attachments to other work. 1. Detail equipment assemblies and indicate dimensions, weights, required clearances, method of field assembly, components,
and location and size of each field connection. C. Field quality-control reports. 1.6 QUALITY ASSURANCE A. Electrical Components, Devices, and Accessories: Listed and labeled as defined
in NFPA 70, by a qualified testing agency, and marked for intended location and application. B. Comply with NFPA 70. 1.7 COORDINATION A. Coordinate layout and installation of system
components and suspension system with other construction that penetrates ceilings ceilings or is supported by them, including light fixtures, HVAC equipment, fire-suppression system,
and partition assemblies. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Available Manufacturers: Subject to compliance with requirements: 1. Alpha Communications. 2. Altec Lansing Technologies,
Inc. 3. Atlas Sound LP. 4. Bogen Communications, Inc. 5. Dukane Communication Systems; part of GE Infrastructure, Security. 6. Edwards Signaling & Security Systems; part of GE Infrastructure,
Security. 7. Electro-Voice; Telex Communications, Inc. 8. Peavey Electronics. 9. Rauland-Borg Corporation.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS 27 51 16 -3 2.2 FUNCTIONAL DESCRIPTION OF SYSTEM A. System Functions: 1. Reproduce high-quality sound that is free of noise and distortion
at all loudspeakers at all times during equipment operation including standby mode with inputs off; output free of non-uniform coverage of amplified sound. 2.3 GENERAL EQUIPMENT AND
MATERIAL REQUIREMENTS A. Compatibility of Components: Coordinate component features to form an integrated system. Match components and interconnections for optimum performance of specified
functions. B. Equipment: Comply with UL 813. Equipment shall be modular, using solid-state components, and fully rated for continuous duty unless otherwise indicated. Select equipment
for normal operation on input power usually supplied at 110 to 130 V, 60 Hz. 2.4 LOUDSPEAKERS A. Cone-Type Loudspeakers: 1. Minimum Axial Sensitivity: 91 dB at one meter, with 1-W input.
2. Frequency Response: Within plus or minus 3 dB from 50 to 15,000 Hz. 3. Size: 8 inches (200 mm) with 1-inch (25-mm) voice coil and minimum 5-oz. (140-g) ceramic magnet. 4. Minimum
Dispersion Angle: 100 degrees. 5. Rated Output Level: 10W. 6. Matching Transformer: Full-power rated with four taps. Maximum insertion loss of 0.5 dB. 7. Surface-Mounting Units: Ceiling,
wall, or pendant mounting, as indicated, in steel back boxes, acoustically dampened. Front face of at least 0.0478-inch (1.2-mm) steel and whole assembly rust proofed and shop primed
for field painting. 8. Flush-Ceiling-Mounting Units: In steel back boxes, acoustically dampened. Metal ceiling grille with white baked enamel. 2.5 CONDUCTORS AND CABLES A. Jacketed,
twisted pair and twisted multi-pair, untinned solid copper. 1. Insulation for Wire in Conduit: Thermoplastic, not less than 1/32 inch (0.8 mm) thick. 2. Microphone Cables: Neoprene jacketed,
not less than 2/64 inch (0.8 mm) thick, over shield with filled interstices. Shield No. 34 AWG, tinned, soft-copper strands formed into a braid or approved equivalent foil. Shielding
coverage on conductors is not less than 60 percent.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS 27 51 16 -4 3. Plenum Cable: Listed and labeled for plenum installation. 2.6 RACEWAYS A. Conduit and Boxes: Comply with Division 26 Section
"Raceway and Boxes for Electrical Systems." 1. Outlet boxes shall be not less than 2 inches (50 mm) wide, 3 inches (75 mm) high, and 2-1/2 inches (64 mm) deep. PART 3 -EXECUTION 3.1
WIRING METHODS A. Wiring Method: Install cables in raceways and cable trays except within consoles, cabinets, desks, and counters. Conceal raceway and cables except in unfinished spaces.
1. Install plenum cable in environmental air spaces, including plenum ceilings. 2. Comply with requirements for raceways and boxes specified in Division 26 Section "Raceway and Boxes
for Electrical Systems." B. Wiring within Enclosures: Bundle, lace, and train cables to terminal points with no excess and without exceeding manufacturer's limitations on bending radii.
Provide and use lacing bars and distribution spools. 3.2 INSTALLATION OF RACEWAYS A. Comply with requirements in Division 26 Section "Raceway and Boxes for Electrical Systems" for installation
of conduits and wireways. B. Install manufactured conduit sweeps and long-radius elbows whenever possible. 3.3 INSTALLATION OF CABLES A. Comply with NECA 1. B. General Cable Installation
Requirements: 1. Terminate conductors; no cable shall contain unterminated elements. Make terminations only at outlets and terminals. 2. Splices, Taps, and Terminations: Arrange on numbered
terminal strips in junction, pull, and outlet boxes; terminal cabinets; and equipment enclosures. Cables may not be spliced.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS 27 51 16 -5 3. Secure and support cables at intervals not exceeding 30 inches (760 mm) and not more than 6 inches (150 mm) from cabinets,
boxes, fittings, outlets, racks, frames, and terminals. 4. Bundle, lace, and train conductors to terminal points without exceeding manufacturer's limitations on bending radii. Install
lacing bars and distribution spools. 5. Do not install bruised, kinked, scored, deformed, or abraded cable. Do not splice cable between termination, tap, or junction points. Remove and
discard cable if damaged during installation and replace it with new cable. 6. Cold-Weather Installation: Bring cable to room temperature before dereeling. Heat lamps shall not be used.
C. Open-Cable Installation: 1. Install cabling with horizontal and vertical cable guides in in telecommunications spaces with terminating hardware and interconnection equipment. 2. Suspend
speaker cable not in a wireway or pathway a minimum of 8 inches (200 mm) above ceiling by cable supports not more than 60 inches (1524 mm) apart. 3. Cable shall not be run through structural
members or be in contact with pipes, ducts, or other potentially damaging items. D. Separation of Wires: Separate speaker-microphone, line-level, speaker-level, and power wiring runs.
Install in separate raceways or, where exposed or in same enclosure, separate conductors at least 12 inches (300 mm) apart for speaker microphones and adjacent parallel power and telephone
wiring. Separate other intercommunication equipment conductors as recommended by equipment manufacturer. 3.4 INSTALLATION A. Match input and output impedances and signal levels at signal
interfaces. Provide matching networks where required. B. Identification of Conductors and Cables: Color-code conductors and apply wire and cable marking tape to designate wires and cables
so they identify media in coordination with system wiring diagrams. C. Wall-Mounted Outlets: Flush mounted. D. Conductor Sizing: Unless otherwise indicated, size speaker circuit conductors
from racks to loudspeaker outlets not smaller than No. 18 AWG and conductors from microphone receptacles to amplifiers not smaller than No. 22 AWG. E. Speaker-Line Matching Transformer
Connections: Make initial connections using tap settings indicated on Drawings. F. Connect wiring according to Division 26 Section "Low-Voltage Electrical Power Conductors and Cables."
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS 27 51 16 -6 3.5 GROUNDING A. Ground cable shields and equipment to eliminate shock hazard and to minimize ground loops, common-mode returns,
noise pickup, cross talk, and other impairments. B. Signal Ground Terminal: Locate at main equipment cabinet. Isolate from power system and equipment grounding. C. Install grounding
electrodes as specified in Division 26 Section "Grounding and Bonding for Electrical Systems." 3.6 FIELD QUALITY CONTROL A. Manufacturer's Field Service: Engage a factory-authorized
service representative to inspect, test, and adjust components, assemblies, and equipment installations, including connections and to assist in testing. B. Tests and Inspections: 1.
Schedule tests with at least seven days' advance notice of test performance. 2. After installing public address and mass notification systems and after electrical circuitry has been
energized, test for compliance with requirements. 3. Operational Test: Perform tests that include originating program and page messages at microphone outlets, preamplifier program inputs,
and other inputs. Verify proper routing and volume levels and that system is free of noise and distortion. 4. Signal-to-Noise Ratio Test: Measure signal-to-noise ratio of complete system
at normal gain settings as follows: a. Disconnect microphone at connector or jack closest to it and replace it in the circuit with a signal generator using a 1000-Hz signal. Replace
all other microphones at corresponding connectors with dummy loads, each equal in impedance to microphone it replaces. Measure signal-to-noise ratio. b. Repeat test for each separately
controlled zone of loudspeakers. c. Minimum acceptance ratio is 50 dB. 5. Distortion Test: Measure distortion at normal gain settings and rated power. Feed signals at frequencies of
50, 200, 400, 1000, 3000, 8000, and 12,000 Hz into each preamplifier channel. For each frequency, measure distortion in the paging and all-call amplifier outputs. Maximum acceptable
distortion at any frequency is 3 percent total harmonics. 6. Acoustic Coverage Test: Feed pink noise into system using octaves centered at 500 and 4000 Hz. Use sound-level meter with
octave-band filters to measure level at five locations in each zone. For spaces with seated audiences, maximum permissible variation in level is plus or minus 2 dB. In addition, the
levels between locations in same zone and between locations in adjacent zones must not vary more than plus or minus 3 dB.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
PUBLIC ADDRESS AND MASS NOTIFICATION SYSTEMS 27 51 16 -7 7. Power Output Test: Measure electrical power output of each power amplifier at normal gain settings of 50, 1000, and 12,000
Hz. Maximum variation in power output at these frequencies must not exceed plus or minus 1 dB. 8. Signal Ground Test: Measure and report ground resistance at pubic address equipment
signal ground. Comply with testing requirements specified in Division 26 Section "Grounding and Bonding for Electrical Systems." C. Inspection: Verify that units and controls are properly
labeled and interconnecting wires and terminals are identified. Prepare a list of final tap settings of paging speaker-line matching transformers. D. Public address and mass notification
systems will be considered defective if they do not pass tests and inspections. E. Prepare test and inspection reports. 1. Include a record of final speaker-line matching transformer-tap
settings, and signal ground-resistance measurement certified by Installer. 3.7 STARTUP SERVICE A. Engage a factory-authorized service representative to perform startup service. 1. Verify
that electrical wiring installation complies with manufacturer's submittal and installation requirements. 2. Complete installation and startup checks according to manufacturer's written
instructions. 3.8 ADJUSTING A. On-Site Assistance: Engage a factory-authorized service representative to provide on-site assistance in adjusting sound levels, resetting transformer taps,
and adjusting controls to meet occupancy conditions. B. Occupancy Adjustments: When requested within 12 months of date of Substantial Completion, provide on-site assistance in adjusting
system to suit actual occupied conditions. Provide up to two visits to Project during other-than-normal occupancy hours for this purpose. 3.9 DEMONSTRATION A. Train Owner's maintenance
personnel to adjust, operate, and maintain the public address and mass notification systems and equipment. END OF SECTION 27 51 16
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
NURSE CALL/CODE BLUE SYSTEMS 27 52 23 -1 SECTION 27 52 23 -NURSE CALL/CODE BLUE SYSTEMS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including
General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes audiovisual equipment using voice communications
and microprocessor control and following: 1. The system shall be based on proven distributed processing and dynamic memory allocations techniques utilizing a multi-drop cable architecture,
where all devices are effectively in parallel with each other. Each device shall receive the data that was sent by any other device on the same multi-drop without interference or blockage
from another. If any one device should fail, only that device would quit transmitting and receiving; the rest of the devices on the same multi-drop shall be free to continue communicating
with each other. 2. System supervision shall detect a non-reporting device and annunciate that fact. Each multi-drop shall be carefully specified to ensure reliability. 3. The system
shall include, but not be limited to, the following components designed and manufactured in the United States, a combination of group control and specialized interface network hubs,
power supplies with attached backup battery units, master console stations, single bed and dual bed patient stations, bedside Code Blue/Staff Assist stations, fire alarm smoke detector
interface module, auxiliary input plates for ancillary signaling from IV pumps, emergency stations, dome (corridor side) lights, passive and active modular splitters, universal interface
modules, conduit and/or cable tray, and passive devices such as cable and modular connectors, pillow speakers, standard and specialized call cords, and bedside 37-pin feature-bed to
nurse call interface connector plates. 1.3 SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: Detail the system including the following: 1. Cabling Diagrams:
Single-line block diagrams showing cabling interconnection of all components for this specific equipment. Include cable type for each interconnection.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
NURSE CALL/CODE BLUE SYSTEMS 27 52 23 -2 2. Wiring Diagrams: Power, signal, and control wiring. 3. Station Installation Details: For built-in equipment; dimensioned and to scale. 4.
Equipment Cabinet Drawings: Dimensioned and to scale. C. Field Tests Reports and Observations: Include record of final adjustments certified by Installer. D. Operation and Maintenance
Data: For nurse call equipment to include in emergency, operation, and maintenance manuals. In addition to items specified in Division 1 Section "Operation and Maintenance Data," include
the following: 1. Operating instructions. 2. Troubleshooting guide. 3. Wiring diagrams and terminal identification. 4. Equipment parts list. 5. Product data for types and sizes of wires
and cables used. E. Warranty: Special warranty specified in this Section. 1.4 QUALITY ASSURANCE A. Installer Qualifications: Manufacturer's authorized representative who is trained and
approved for installation of units required for this Project. B. Source Limitations: Obtain nurse call equipment components through one source from a single manufacturer. C. Electrical
Components, Devices, and Accessories: Listed and labeled according to UL 1069 as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and
marked for intended use. 1.5 COORDINATION A. Coordinate patient control units with items controlled that are not part of nurse call equipment. 1. TV: Channel selection and volume. 2.
Lights: Up light and down light at patient location. 3. Patient room smoke detector. PART 2 -PRODUCTS 2.1 MANUFACTURERS A. Products in this section are Owner furnished, Contractor installed.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
NURSE CALL/CODE BLUE SYSTEMS 27 52 23 -3 PART 3 -EXECUTION 3.1 INSTALLATION A. Wiring Method: Install wiring in raceway except within consoles, desks, and counters; and except in accessible
ceiling spaces where cable wiring method may be used. Use UL-listed plenum cable in environmental air spaces including plenum ceilings. Conceal cable and raceway wiring except in unfinished
spaces. B. Install cables without damaging conductors, shield, or jacket. C. Do not bend cables, in handling or in installing, to smaller radii than minimums recommended by manufacturer.
D. Pull cables without exceeding cable manufacturer's recommended pulling tensions. 1. Pull cables simultaneously if more than one is being installed in same raceway. 2. Use pulling
compound or lubricant if necessary. Use compounds that will not damage conductor conductor or insulation. 3. Use pulling means, including fish tape, cable, rope, and basket-weave wire
or cable grips, that will not damage media or raceway. E. Install exposed raceways and cables parallel and perpendicular to surfaces or exposed structural members, and follow surface
contours. Secure and support cables by straps, staples, or similar fittings designed and installed so as not to damage cables. Secure cable at intervals not exceeding 30 inches (760
mm) and not more than 6 inches (150 mm) from cabinets, boxes, or fittings. F. Wiring within Enclosures: Provide adequate length of conductors. Bundle, lace, and train conductors to terminal
points with no excess. Provide and use lacing bars in cabinets. G. Separation of Wires: Separate speaker-microphone, line-level, speaker-level, and power-wiring runs. Run in separate
raceways or, if exposed or in same enclosure, provide 12-inch (300-mm) minimum separation between conductors to speaker microphones and adjacent parallel power and telephone wiring.
wiring. Provide separation as recommended by equipment manufacturer for other conductors. H. Splices, Taps, and Terminations: Make splices, taps, and terminations on numbered terminal
strips in junction, pull, and outlet boxes, terminal cabinets, and equipment enclosures. Install terminal cabinets where there are splices, taps, or terminations for eight or more conductors.
I. Impedance and Level Matching: Carefully match input and output impedances and signal levels at signal interfaces. Provide matching networks if required. J. Identification of Conductors
and Cables: Retain color-coding of conductors and apply wire and cable marking tape to designate wires and cables so all media are identified in coordination with
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
NURSE CALL/CODE BLUE SYSTEMS 27 52 23 -4 system wiring diagrams. Label stations, controls, and indications using approved consistent nomenclature. 1. Label each cable within 4 inches
(100 mm) of each termination and tap, where it is accessible in a cabinet or junction or outlet box, and elsewhere as indicated. 2. Label exposed cables at intervals not exceeding 15
feet (4.5 m). 3. Prepare cable administration drawings to show building floor plans with cable administration point labeling. Identify labeling convention and show labels for terminal
hardware and positions, cables, stations and devices and equipment grounding conductors. 3.2 EXISTING SYSTEMS A. Examine existing systems for proper operation, compatibility with new
equipment, and deficiencies. If discrepancies or impairments to successful connection and operation of interconnected equipment are found, report them and do not proceed with installation
until directed. Schedule existing systems' examination so there is reasonable time to resolve problems without delaying construction. 3.3 GROUNDING A. Ground cable shields and equipment
to eliminate shock hazard and to minimize ground loops, common-mode returns, noise pickup, cross talk, and other signal impairments. B. Signal Ground Terminal: Locate at main equipment
cabinet. Isolate from power system and equipment grounding except at connection to main building ground bus. C. Grounding Provisions: Comply with requirements in Division 26 Section
"Grounding." END OF SECTION 27 52 23
ST. VINCENT
CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________ SYSTEM
ROUGH-IN REQUIREMENTS 27 60 00 -1 SECTION 27 60 00 — SYSTEM ROUGH-IN REQUIREMENTS PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and General Provisions of the Contract, including
General and Supplementary Conditions and Division 1 Specification Sections, apply to this section. 1.2 SUMMARY A. This Section includes miscellaneous raceway system as shown or implied
on the Contract Documents for the following systems: 1. Communication horizontal cabling. 2. Voice, data, dictation, patient information and patient monitoring system. B. Related Sections
include the following: 1. Division 26 Section “Grounding and Bonding Electrical Systems.” 2. Division 26 Section “Raceway and Boxes for Electrical Systems.” 3. Division 26 Section “Cable
Trays for Electrical Systems.” 4. Division 26 Section “Identification for Electrical Systems.” PART 2 -PRODUCTS 2.1 MATERIALS A. Raceway shall be EMT with set screw fitting and conduit
bushing at both ends. Rough-in box will be minimum 2-1/4” deep. Minimum size shall be as follows: 1. Communication horizontal cabling: 1” conduit trade size. B. Rough-In Box: 1. Communication
horizontal cabling rough-ins shall be 2-gang, deep rough-in box with single plaster ring and single blank plate.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
SYSTEM ROUGH-IN REQUIREMENTS 27 60 00 -2 PART 3 -EXECUTION 3.1 INSTALLATION A. Raceways shall be installed from outlets to accessible area above ceiling (outside return air plenum) as
indicated by Contract Documents. Conduit shall terminate with bushing. B. Outlet mounting height shall be as follows unless indicated otherwise by Contract Documents: 1. Communication
horizontal cables: +18" above finished floor to center and 2” above back splace, wall mounted telephone at +48" AFF unless noted otherwise. C. Provide nylon pullcord in raceway system.
END OF SECTION 27 60 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY 28 05 00 -1 SECTION 28 05 00 -COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings
and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes:
1. Electronic safety and security equipment coordination and installation. 2. Sleeves for raceways and cables. 3. Sleeve seals. 4. Grout. 5. Common electronic safety and security installation
requirements. 1.3 DEFINITIONS A. EPDM: Ethylene-propylene-diene terpolymer rubber. B. NBR: Acrylonitrile-butadiene rubber. 1.4 SUBMITTALS A. Product Data: For sleeve seals. 1.5 COORDINATION
A. Coordinate arrangement, mounting, and support of electronic safety and security equipment: 1. To allow maximum possible headroom unless specific mounting heights that reduce headroom
are indicated. 2. To provide for ease of disconnecting the equipment with minimum interference to other installations. 3. To allow right of way for piping and conduit installed at required
slope. 4. So connecting raceways, cables, wireways, cable trays, and busways will be clear of obstructions and of the working and access space of other equipment.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY 28 05 00 -2 B. Coordinate installation of required supporting devices and set sleeves in cast-in-place concrete, masonry walls,
and other structural components as they are constructed. C. Coordinate location of access panels and doors for electronic safety and security items that are behind finished surfaces
or otherwise concealed. Access doors and panels are specified in Division 8 Section "Access Doors and Frames." D. Coordinate sleeve selection and application with selection and application
of firestopping specified in Division 7 Section "Firestopping." PART 2 -PRODUCTS 2.1 SLEEVES FOR RACEWAYS AND CABLES A. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule
40, galvanized steel, plain ends. B. Sleeves for Rectangular Openings: Galvanized sheet steel. 1. Minimum Metal Thickness: a. For sleeve cross-section rectangle perimeter less than 50
inches (1270 mm) and no side more than 16 inches (400 mm), thickness shall be 0.052 inch (1.3 mm). b. For sleeve cross-section rectangle perimeter equal to, or more than, 50 inches (1270
mm) and 1 or more sides equal to, or more than, 16 inches (400 mm), thickness shall be 0.138 inch (3.5 mm). 2.2 SLEEVE SEALS A. Description: Modular sealing device, designed for field
assembly, to fill annular space between sleeve and raceway or cable. 1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be
incorporated into the Work include, but are not limited to, the following: a. Advance Products & Systems, Inc. b. Calpico, Inc. c. Metraflex Co. d. Pipeline Seal and Insulator, Inc.
2. Sealing Elements: EPDM interlocking links shaped to fit surface of cable or conduit. Include type and number required for material and size of raceway or cable. 3. Pressure Plates:
Carbon steel. Include two for each sealing element.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY 28 05 00 -3 4. Connecting Bolts and Nuts: Carbon steel with corrosion-resistant coating of length required to secure pressure plates
to sealing elements. Include one for each sealing element. 2.3 GROUT A. Nonmetallic, Shrinkage-Resistant Grout: ASTM C 1107, factory-packaged, nonmetallic aggregate grout, noncorrosive,
nonstaining, mixed with water to consistency suitable for application and a 30-minute working time. PART 3 -EXECUTION 3.1 COMMON REQUIREMENTS FOR ELECTRONIC SAFETY AND SECURITY INSTALLATION
A. Comply with NECA 1. B. Measure indicated mounting heights to bottom of unit for suspended items and to center of unit for wall-mounting items. C. Headroom Maintenance: If mounting
heights or other location criteria are not indicated, arrange and install components and equipment to provide maximum possible headroom consistent with these requirements. D. Equipment:
Install to facilitate service, maintenance, and repair or replacement of components of both electronic safety and security equipment and other nearby installations. Connect in such a
way as to facilitate future disconnecting with minimum interference with other items in the vicinity. E. Right of Way: Give to piping systems installed at a required slope. 3.2 SLEEVE
INSTALLATION FOR ELECTRONIC SAFETY AND SECURITY PENETRATIONS A. Electronic safety and security penetrations occur when raceways, pathways, cables, wireways, or cable trays penetrate
concrete slabs, concrete or masonry walls, or fire-rated floor and wall assemblies. B. Concrete Slabs and Walls: Install sleeves for penetrations unless core-drilled holes or formed
openings are used. Install sleeves during erection of slabs and walls. C. Use pipe sleeves unless penetration arrangement requires rectangular sleeved opening.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY 28 05 00 -4 D. Fire-Rated Assemblies: Install sleeves for penetrations of fire-rated floor and wall assemblies unless openings
compatible with firestop system used are fabricated during construction of floor or wall. E. Cut sleeves to length for mounting flush with both surfaces of walls. F. Extend sleeves installed
in floors 2 inches (50 mm) above finished floor level. G. Size pipe sleeves to provide 1/4-inch (6.4-mm) annular clear space between sleeve and raceway or cable, unless indicated otherwise.
H. Seal space outside of sleeves with grout for penetrations of concrete and masonry 1. Promptly pack grout solidly between sleeve and wall so no voids remain. Tool exposed surfaces
smooth; protect grout while curing. I. Fire-Rated-Assembly Penetrations: Maintain indicated fire rating of walls, partitions, ceilings, and floors at raceway and cable penetrations.
Install sleeves and seal raceway and cable penetration sleeves with firestop materials. Comply with requirements in Division 7 Section "Firestopping." 3.3 SLEEVE-SEAL INSTALLATION A.
Install to seal exterior wall penetrations. B. Use type and number of sealing elements recommended by manufacturer for raceway or cable material and size. Position raceway or cable in
center of sleeve. Assemble mechanical sleeve seals and install in annular space between raceway or cable and sleeve. Tighten bolts against pressure plates that cause sealing elements
to expand and make watertight seal. 3.4 FIRESTOPPING A. Apply firestopping to penetrations of fire-rated floor and wall assemblies for electronic safety and security installations to
restore original fire-resistance rating of assembly. Firestopping materials and installation requirements are specified in Division 7 Section "Firestopping." END OF SECTION 28 05 00
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -1 SECTION 28 31 00 -FIRE ALARM SYSTEM PART 1 -GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes extension of existing Simplex 4100 fire alarm systems. B. Related Sections
include the following: 1. Division 8 Section "Door Hardware" for door closers and holders with associated smoke detectors, electric door locks, and release devices that interface with
the fire alarm system. 1.3 DEFINITIONS A. FACP: Fire alarm control panel. B. LED: Light-emitting diode. C. NICET: National Institute for Certification in Engineering Technologies. D.
Definitions in NFPA 72 apply to fire alarm terms used in this Section. E. FGCC: Fire Alarm Graphic Command Center. F. FANP: Fire Alarm Power Extender Panel. G. FAAP: Fire Alarm Annunciator
(LCD). 1.4 SYSTEM DESCRIPTION A. Non-coded, addressable system; multiplexed signal transmission dedicated to fire alarm service only. 1. Interface with existing fire alarm system.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -2 1.5 PERFORMANCE REQUIREMENTS A. Comply with NFPA 72. B. Fire alarm signal initiation shall be by one or more of the following devices: 1. Manual stations.
2. Verified automatic alarm operation of smoke detectors. 3. Automatic sprinkler system water flow. C. Fire alarm signal shall initiate the following actions: 1. Alarm notification appliances
shall operate continuously. 2. Identify alarm at the FACP. 3. De-energize electromagnetic door holders. 4. Transmit an alarm signal to the remote alarm receiving station. 5. Unlock electric
door locks in designated egress paths. 6. Release fire and smoke doors held open by magnetic door holders. 7. Activate voice/alarm communication system. 8. Switch heating, ventilating,
and air-conditioning equipment controls to fire alarm mode. 9. Close smoke dampers in air ducts of system serving zone where alarm was initiated. 10. Record events in the system memory.
11. Record events by the system printer. 12. Activation of any alarm verified smoke detector in a single elevator lobby or an elevator equipment room shall cause the recall of that bank
of elevators to the terminal floor and the lock out of controls. In the event of recall initiation by a detector in the first floor lobby, the recall shall be to the alternate floor.
Recall signal shall activate all required hoistway vents and mechanical ventilation fans. 13. Initiation of an alarm from a smoke detector installed in the supply air stream of any air
handling unit smoke removal system shall cause the shutdown of that fan. D. Supervisory signal initiation shall be by one or more of the following devices or actions: 1. Operation of
a fire-protection system valve tamper. E. System trouble signal initiation shall be by one or more of the following devices or actions: 1. Open circuits, shorts and grounds of wiring
for initiating device, signaling line, and notification-appliance circuits. 2. Opening, tampering, or removal of alarm-initiating and supervisory signal-initiating devices. 3. Loss of
primary power at the FACP. 4. Ground or a single break in FACP internal circuits. 5. Abnormal ac voltage at the FACP and FAAP. 6. A break in standby battery circuitry. 7. Failure of
battery charging. 8. Abnormal position of any switch at the FACP and FAAP.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -3 9. Fire-pump power failure, including a dead-phase or phase-reversal condition. 10. Low-air-pressure switch operation on a dry-pipe or preaction sprinkler
system. 11. Removal of an alarm initiating device. F. System Trouble and Supervisory Signal Actions: Ring trouble bell and annunciate at the FACP and FAAP. Record the event on system
printer. 1.6 SUBMITTALS A. Product Data: For each type of product indicated. B. Shop Drawings: 1. Shop Drawings shall be prepared by persons with the following qualifications: a. Trained
and certified by manufacturer in fire alarm system design. 2. System Operation Description: Detailed description for this Project, including method of operation and supervision of each
type of circuit and sequence of operations for manually and automatically initiated system inputs and outputs. Manufacturer's standard descriptions for generic systems are not acceptable.
3. Device Address List: Coordinate with final system programming. 4. System riser diagram with device addresses, conduit sizes, and cable and wire types and sizes. 5. Wiring Diagrams:
Power, signal, and control wiring. Include diagrams for equipment and for system with all terminals and interconnections identified. Show wiring color code. 6. Batteries: Size calculations.
7. Duct Smoke Detectors: Performance parameters and installation details for each detector, verifying that each detector is listed for the complete range of air velocity, temperature,
and humidity possible when air-handling system is operating. 8. Floor Plans: Indicate final outlet locations showing address of each addressable device. Show size and route of cable
and conduits. C. Qualification Data: For Installer. D. Field quality-control test reports. E. Operation and Maintenance Data: For fire alarm system to include in emergency, operation,
and maintenance manuals. Comply with NFPA 72, Appendix A, recommendations for Owner's manual. Include abbreviated operating instructions for mounting at the FACP. F. Submittals to Authorities
Having Jurisdiction: In addition to distribution requirements for submittals specified in Division 1 Section "Submittals," make an identical submittal to authorities having jurisdiction.
To facilitate review, include copies of annotated Contract Drawings as needed to depict component locations. Resubmit if required to make clarifications
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -4 or revisions to obtain approval. On receipt of comments from authorities having jurisdiction, submit them to Architect for review. G. Documentation: 1.
Approval and Acceptance: Provide the "Record of Completion" form according to NFPA 72 to Owner. 2. Record of Completion Documents: Provide the "Permanent Records" according to NFPA 72
to Owner. Format of the written sequence of operation shall be the optional input/output matrix. a. Hard copies on paper to Owner. 1.7 QUALITY ASSURANCE A. Installer Qualifications:
Personnel shall be trained and certified by manufacturer for installation of units required for this Project. B. Electrical Components, Devices, and Accessories: Listed and labeled as
defined in NFPA 70, Article 100 and acceptable to authorities having jurisdiction, and marked for for intended use. C. Requirement of Regulatory Agencies: 1. Factory Mutual (FM) AG Approval
Guide. 2. National Fire Protection Association (NFPA). a. NFPA 70 National Electrical Code. b. NFPA 72 National Fire Alarm Code. c. NFPA 90A Standard for the Installation of Air Conditioning
and Ventilating Systems. d. NFPA 101 Life Safety Code. 3. Underwriters Laboratories, Inc. (UL). a. Appropriate UL equipment standards. b. UL FPED. c. UL 1971, standard for visual signaling
appliances. Uniform Building Code and the Uniform Fire Code or other State and Local Building Codes as adopted and/or amended by the authority having jurisdiction. d. Department of Justice
rules for building accessibility by the handicapped, and/or State and local equivalency standards as adopted by local AHJ's.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -5 1.8 PROJECT CONDITIONS A. Interruption of Existing Fire Alarm Service: Do not interrupt fire alarm service to facilities occupied by Owner or others unless
permitted under the following conditions and then only after arranging to provide temporary guard service according to requirements indicated: 1. Notify Owner no fewer than two days
in advance of proposed interruption of fire alarm service. 2. Do not proceed with interruption of fire alarm service without Owner's written permission. 1.9 SEQUENCING AND SCHEDULING
A. Existing Fire Alarm Equipment: Maintain fully operational until new equipment has been tested and accepted. As new equipment is installed, label it "NOT IN SERVICE" until it is accepted.
Remove labels from new equipment when put into service and label existing fire alarm equipment "NOT IN SERVICE" until removed from the building. B. Equipment Removal: After acceptance
of the new fire alarm system, remove existing disconnected fire alarm equipment. 1.10 EXTRA MATERIALS A. Furnish extra materials described below that match products installed and that
are packaged with protective covering for storage and identified with labels describing contents. 1. Lamps for Remote Indicating Lamp Units: Quantity equal to 10 percent of amount installed,
but not less than 1 unit. 2. Lamps for Strobe Units: Quantity equal to 10 percent of amount installed, but not less than 1 unit. 3. Smoke Detectors: Quantity equal to 10 percent of amount
of each type installed, but not less than 1 unit of each type. 4. Detector Bases: Quantity equal to 2 percent of amount of each type installed, but not less than 1 unit of each type.
5. Keys and Tools: One extra set for access to locked and tamperproofed components. 6. Audible and Visual Notification Appliances: One of each type installed. 7. Fuses: Two of each type
installed in the system. B. Furnish extra materials and labor. Describe below that matches products installed. 1. Submit unit price to install and wire additional devices. This price
will be applied to additional devices to be installed. Include as part of the scope of work the installation of the following additional devices, above and beyond the number of devices
shown on the plans. The Architect/Engineer will direct the Contractor where to install such devices
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -6 during construction. Architect/Engineer shall have the latitude to have devices installed anywhere within the project area. a. Manual pull station: 1. b.
Area detector: 3. c. Duct detector: 2. d. Chime/strobe: 2. e. Strobe: 3. 1.11 WARRANTY A. Written warranty, executed by manufacturer agency to repair or replace equipment, devices, and
auxiliary components that fail in material or workmanship within specified warranty period. 1. Warranty Period: Two years from the date of substantial completion. PART 2 -PRODUCTS 2.1
MANUFACTURERS A. Manufacturers: Subject to compliance with requirements, provide products by one of the following: 1. FACP and Equipment: a. SimplexGrinnell LP; a Tyco International
Company. 2. Wire and Cable: a. Comtran Corporation. b. West Penn Wire/CDT; a division of Cable Cable Design Technologies. 2.2 EXISTING FIRE ALARM SYSTEM A. Compatibility with Existing
Equipment: Fire alarm system and components shall operate as an extension of an existing system. 2.3 MANUAL FIRE ALARM BOXES A. Description: UL 38 listed; finished in red with molded,
raised-letter operating instructions in contrasting color. Station shall show visible indication of operation. Mounted on recessed outlet box; if indicated as surface mounted, provide
manufacturer's surface back box.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -7 1. Double-action mechanism requiring two actions to initiate an alarm, pull-lever type. With integral addressable module, arranged to communicate manual-station
status (normal, alarm, or trouble) to the FACP. 2. Station Reset: Key-or wrench-operated switch. 2.4 SYSTEM SMOKE DETECTORS A. General Description: 1. UL 268 listed, operating at 24-V
dc, nominal. 2. Integral Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble) to the FACP. 3. Multipurpose type, containing the following: a. Integral
Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble) to the FACP. b. Photoelectric sensor, tested according to UL 268A. c. Heat sensor, combination
rate-of-rise and fixed temperature. 4. Plug-in Arrangement: Detector and associated electronic components shall be mounted in a plug-in module that connects to a fixed base. Provide
terminals in the fixed base for connection of building wiring. 5. Self-Restoring: Detectors do not require resetting or readjustment after actuation to restore them to normal operation.
6. Integral Visual-Indicating Light: LED type. Indicating detector has operated and poweron status. B. Photoelectric Smoke Detectors: 1. Sensor: LED or infrared light source with matching
silicon-cell receiver. 2. Detector Sensitivity: Between 2.5 and 3.5 percent/foot (0.008 and 0.011 percent/mm) smoke obscuration when tested according to UL 268A. C. Ionization Smoke
Detector: 1. Sensor: Responsive to both visible and invisible products of combustion. Selfcompensating for changes in environmental conditions. 2. Detector Sensitivity: Between 0.5 and
1.7 percent/foot (0.0016 and 0.0056 percent/mm) smoke obscuration when tested according to UL 268A. D. Duct Smoke Detectors: 1. Photoelectric Smoke Detectors: a. Sensor: LED or infrared
infrared light source with matching silicon-cell receiver.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -8 b. Detector Sensitivity: Between 2.5 and 3.5 percent/foot (0.008 and 0.011 percent/mm) smoke obscuration when tested according to UL 268A. 2. UL 268A listed,
operating at 24-V dc, nominal. 3. Integral Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble) to the FACP. 4. Plug-in Arrangement: Detector and associated
electronic components shall be mounted in a plug-in module that connects to a fixed base. The fixed base shall be designed for mounting directly to the air duct. Provide terminals in
the fixed base for connection to building wiring. a. Weatherproof Duct Housing Enclosure: UL listed for use with the supplied detector. The enclosure shall comply with NEMA 250 requirements
for Type 4X. 5. Self-Restoring: Detectors shall not require resetting or readjustment after actuation to restore them to normal operation. 6. Integral Visual-Indicating Light: LED type.
Indicating detector has operated and poweron status. 7. Sampling Tubes: Design and dimensions as recommended by manufacturer for the specific duct size, air velocity, and installation
conditions where applied. 8. Relay Fan Shutdown: Rated to interrupt fan motor-control circuit. 2.5 HEAT DETECTORS A. General: UL 521 listed. B. Heat Detector, Combination Type: Actuated
by either a fixed temperature of 135 deg F (57 deg C) or rate-of-rise of temperature that exceeds 15 deg F (8 deg C) per minute, unless otherwise indicated. 1. Mounting: Plug-in base,
interchangeable with smoke-detector bases. 2. Integral Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble) to the FACP. C. Heat Detector, Fixed-Temperature
Type: Actuated by temperature that exceeds a fixed temperature of 190 deg F (88 deg C). 1. Mounting: Plug-in base, interchangeable with smoke-detector bases. 2. Integral Addressable
Module: Arranged to communicate detector status (normal, alarm, or trouble) to the FACP.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -9 2.6 NOTIFICATION APPLIANCES A. Description: Equipped for mounting as indicated and with screw terminals for system connections. 1. Combination Devices:
Factory-integrated audible and visible devices in a singlemounting assembly. B. Chimes, High-Level Output: Electronic type, 81-dBA minimum rated output, minimum of ten (10) selectable
tone. C. Visible Alarm Devices: Xenon strobe lights listed under UL 1971, with clear or nominal white polycarbonate lens mounted on an aluminum faceplate. The word "FIRE" is engraved
in minimum 1-inch-(25-mm-) high letters on the lens. 1. Rated Light Output: Field selectable from 15 candela to 110 candela. 2. Strobe Leads: Factory connected to screw terminals. 2.7
SPRINKLER SYSTEM REMOTE INDICATORS A. Remote status and alarm indicator and test stations, with LED indicating lights. Light is connected to flash when the associated device is in an
alarm or trouble mode. Lamp is flush mounted in a single-gang wall plate. A red, laminated, phenolic-resin identification plate at the indicating light identifies, in engraved white
letters, device initiating the signal and room where the smoke detector or valve is located. For water-flow switches, the identification plate also designates protected spaces downstream
from the water-flow switch. 2.8 ADDRESSABLE INTERFACE DEVICE A. Description: Microelectronic monitor module listed for use in providing a system address for listed alarm-initiating devices
for wired applications with normally open contacts. 2.9 NOTIFICATION APPLIANCE PANEL (FANP) A. Extender panel shall provide up to 8 amps of power with up to four supervised reverse polarity
circuit. Extender panel shall be UL listed and FM approved. B. Extender panel shall be activated by the host fire alarm control panel. C. FANP panel shall be capable of providing synchronization
for all connected visible notification strobes. D. FANP panels shall provide status monitoring of battery, input power, and earth faults.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -10 E. Alarms from the host panel will
activate all FANP extender circuits. 2.10 WIRE AND CABLE A. Wire and cable for fire alarm systems shall be UL listed and labeled as complying with NFPA 70, Article 760. B. Signaling
Line Circuits: Twisted, shielded pair, No. 18 AWG. 1. Circuit Integrity Cable: Twisted shielded pair, NFPA 70 Article 760, Classification CI, for power-limited fire alarm signal service.
UL listed as Type FPL, and complying with requirements in UL 1424 and in UL 2196 for a 2-hour rating. C. Non-Power-Limited Circuits: Solid-copper conductors with 600-V rated, 75 deg
C, color-coded insulation. 1. Low-Voltage Circuits: No. 16 AWG, minimum. 2. Line-Voltage Circuits: No. 12 AWG, minimum. PART 3 -EXECUTION 3.1 EQUIPMENT INSTALLATION A. Connecting to
Existing Equipment: Verify that existing fire alarm system is operational before making changes or connections. 1. Connect new equipment to the existing control panel in the existing
part of the building. 2. New components shall be capable of merging with the existing configuration without degrading the performance of either system. B. Smoke or Heat Detector Spacing:
1. Smooth ceiling spacing shall not exceed the rating of the detector. 2. Spacing of heat detectors for irregular areas, for irregular ceiling construction, and for high ceiling areas,
shall be determined according to Appendix A in NFPA 72. 3. Spacing of heat detectors shall be determined based on guidelines and recommendations in NFPA 72. C. HVAC: Locate detectors
not closer than 3 feet (1 m) from air-supply diffuser or return-air opening. D. Duct Smoke Detectors: Comply with NFPA 72 and NFPA 90A. Install sampling tubes so they extend the full
width of the duct.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -11 E. Remote Status and Alarm Indicators: Install near each smoke detector and each sprinkler waterflow switch and valve-tamper switch that is not readily
visible from normal viewing position. F. Audible/Visible Alarm-Indicating Devices: Install at 80” above finished floor horns on flushmounted back boxes with the device-operating mechanism
concealed behind a grille. G. Visible Alarm-Indicating Devices: Install at 80” above finished floor. H. Device Location-Indicating Lights: Locate in public space near the device they
monitor. 3.2 WIRING INSTALLATION A. Install wiring according to the following: 1. NECA 1. 2. TIA/EIA 568-A. B. Wiring Method: Install wiring in metal raceway according to Division 26
Section "Raceways and Boxes." 1. Fire alarm circuits and equipment control wiring associated associated with the fire alarm system shall be installed in a dedicated raceway system. This
system shall not be used for any other wire or cable. C. Wiring Method: 1. Cables and raceways used for fire alarm circuits, and equipment control wiring associated with the fire alarm
system, may not contain any other wire or cable. 2. Signaling Line Circuits: Power-limited fire alarm cables may be installed in the same cable or raceway as signaling line circuits.
D. Wiring within Enclosures: Separate power-limited and non-power-limited conductors as recommended by manufacturer. Install conductors parallel with or at right angles to sides and
back of the enclosure. Bundle, lace, and train conductors to terminal points with no excess. Connect conductors that are terminated, spliced, or interrupted in any enclosure associated
with the fire alarm system to terminal blocks. Mark each terminal according to the system's wiring diagrams. Make all connections with approved crimp-on terminal spade lugs, pressure-type
terminal blocks, or plug connectors. E. Cable Taps: Use numbered terminal strips in junction, pull, and outlet boxes, cabinets, or equipment enclosures where circuit connections are
made. F. Color-Coding: Color-code fire alarm conductors differently from the normal building power wiring. Use one color-code for alarm circuit wiring and a different color-code for
supervisory circuits. Color-code audible alarm-indicating circuits differently from alarm-initiating circuits.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -12 Use different colors for visible alarm-indicating devices. Paint fire alarm system junction boxes and covers red. 3.3 IDENTIFICATION A. Identify system
components, wiring, cabling, and terminals according to Division 26 Section "Electrical Identification." B. Install address label at each device according to Division 26 Section "Electrical
Identification." 3.4 GROUNDING A. Ground the FACP and associated circuits; comply with IEEE 1100. Install a ground wire from main service ground to the FACP. 3.5 FIELD QUALITY CONTROL
A. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust field-assembled components and equipment installation, including connections,
and to assist in field testing. Report results in writing. B. Perform the following field tests and inspections and prepare test reports: 1. Before requesting final approval of the installation,
submit a written statement using the form for Record of Completion shown in NFPA 72. 2. Perform each electrical test and visual and mechanical inspection listed in NFPA 72. Certify compliance
with test parameters. All tests shall be conducted under the direct supervision of a NICET technician certified under the Fire Alarm Systems program at Level III. a. Include the existing
system in tests and inspections. 3. Visual Inspection: Conduct a visual inspection before any testing. Use as-built drawings and system documentation for the inspection. Identify improperly
located, damaged, or nonfunctional equipment, and correct before beginning tests. 4. Testing: Follow procedure and record results complying with requirements in NFPA 72. a. Detectors
that are outside their marked sensitivity range shall be replaced. 5. Test and Inspection Records: Prepare according to NFPA 72, including demonstration of sequences of operation by
using the matrix-style form in Appendix A in NFPA 70.
ST. VINCENT CARMEL HOSPITAL Carmel, Indiana 3rd Floor East & South Renovation BSA LifeStructures #461066.01 ____________________________________________________________________________________
FIRE ALARM SYSTEM 28 31 00 -13 3.6 ADJUSTING A. Occupancy Adjustments: When requested within 12 months of date of Substantial Completion, provide on-site assistance in adjusting system
to suit actual occupied conditions. Provide up to two visits to Project outside normal occupancy hours for this purpose. B. Follow-Up Tests and Inspections: After date of Substantial
Completion, test the fire alarm system complying with testing and visual inspection requirements in NFPA 72. Perform tests and inspections listed for three monthly, and one quarterly,
periods. C. Annual Test and Inspection: One year after date of Substantial Completion, test the fire alarm system complying with the testing and visual inspection requirements in NFPA
72. Perform tests and inspections listed for monthly, quarterly, semiannual, and annual periods. Use forms developed for initial tests and inspections. END OF SECTION 28 31 00