CITY OF CARMEL
CONTRACT CHANGE ORDER NO.: #6
DATE: 6 -21 -11
PROJECT NAME: Cool Creek Trail
CITY REQ. NO.:
CITY PO NO.:
CITY PO DATE:
You are directed to make the following changes in this Contract:
Additional truss repair was needed upon removal of gusset plates. Additional angles on lower chord were
Deteriorated and had to be replaced.
ITEM AMOUNT OR DAYS
Structure Steel 8133.88
II. The following referenced Documents further describe the changes outlined in Paragraph 1, and
are to be considered a part of this Change Order: R.F.P.: W.D.C. No.:
Other:_CO #6
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order 605081.77
Contract Price will be increased /decreased by this Change Order +8133.88
New Contract Price including this Change Order 613215.65
Contract Time Prior to this Change Order Days 11/15/12 Completion Date
Net increased /decreased resulting from this Change Order 0_ Days
Current Contract Time including this Change Order Days 11/15/12 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are The Above Changes Are
Recommended Accepted:
B tGg rias t i 5� T Ggeg6,F R i.4ev so•✓
ENGINEER
845n r..���rFSrzo
Address
=s,
City /State /Zip
By:
ia.8c=ier S,,e1Det
Bt. vi)
(print name)
(sig nature)
Phone: 3)-1-3(0--Z
Date: 6.- t1
CONTRACTOR
94 /l. SR. 3?
Address
1)i41 u L jI✓ VP
City /State /Zip
By:
Gi eog6a ,6 i e ve.'Y
(print ame)
(signature)
Phone: 31 7'1S SIG 9
Date: G /23
Approved:
n Burke, tuber
Lo'r�atson, Member
ATTEST:
Diana Cord Clerk- Treasurer
Date:
Michael T. McBride
City Engineer
Date: .11106. 2K 26/1
Contract No:R -29657
INDIANA Department of Transportation
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -29657
District:GREENFIELD DISTRICT AE:Goldner, Rob
Change Order Information Change Order No.: 005
Date Generated: 00 /00 /0000 Date Approved: 00 /00 /0000
Reason Code: CHANGED COND, Staging Related
Description: Extra Mobilization HMA, Seeding
Original Contract Amount 583,765.77
Current Change Order Amount 4,620.00
Total Previous Approved Changes 16,696.00
Total Change To -Date 21,316.00
Modified Contract Amount 605,081.77
Time Extension Information
Date Initiated 00 /00 /0000
Original Contract Time
Time Element Description:
Current Time Extension
Previous Time Approved
Revised Contract Time
Date Completed 00 /00 /0000
Change Order No.: 005
Page: 1
Letting Date:02/09/2011
PE /S:Surber, Rob Status:Draft
EWA: Y or Force Acct: N
Percent: 0.791
Percent: 2.860
Percent: 3.651
SS Completion Date 00 /00 /0000 or SS Calendar/Work Days 0
SP Date 00 /00 /0000 or SP Days
(SS Standard Specification, SP Special Provision)
SS Days 0 SP Days 0 SP Days Value 0.00
SS Days by AE: DCE: SCE: DDCM:
SS Days SP Days Value
SS Completion Date 00 /00 /0000 or SS Calendar/Work Days 0
SS Date 00 /00 /0000 or SP Days 0
Contract No:R -29657
Change Order No.: 005
INDIANA Department of Transportation Page: 2
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority AE: DCE: SCE: DDCM:
($perChangeOrder) LE$ 250K-)(- LE$750K- LE$2M-- GT$2M
(Days per Contract) (50 SS days) 100 SS days) 200 SS Days) (GT 200 SS days)
Verbal Approval Required? Y N If Y, by Date Issued
Total Change To- Date >5 Y N If Y Copy to Program Budget Manager
Scope /Design Recommendation Y N If Y, Referred to Project Manager(PM)
Required?
Date to PM Date Returned
Approval Authority Concurs with PM? Y N If Y, Concurrence by Date
If N,Resolution: Approved Disapproved
Resolved by Date
LPA Signatures Required? Y N If Y, Date to LPA Date Returned
FHWA Signatures Required? Y N If Y, Date to FHWA Date Returned
Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer Date
Comments:
Contract No:R -29657
Change Order No:005
INDIANA
Department of Transportation
Contract: R -29657
Project: 0600390 State:0600390
Change Order Nbr: 005
Change Order Description: Extra Mobilization HMA, Seeding
Reason Code: CHANGED COND, Staging Related
CLN PCN PLN Item Code Unit Unit Price CO Qty Comment
0088 0600390 0088 621 -01004 EACH 825.000
Item Description: MOB AND DEMOB FOR SEEDING
Supplemental Descriptionl: Original contract did not have mob or demob. Discussed in
Supplemental Description2: Pre -Con Meeting to add Mob fees.
Date:06/20/2011
Page: 3
2.000 C
Amount Change
Amount:$ 1,650.00
0089 0600390 0089 110 -01001 LS 2,970.000 1.000 C Amount:$ 2,970.00
Item Description: MOBILIZATION AND DEMOBILIZATION
Supplemental Descriptionl: Extra Mob fee for HMA due utility conflicts on job. Unable
Supplemental Description2: to Drive piling. Paving along 136th Street
Total Value for Change Order 005 4,620.00
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
Mob and De -Mob for seeding was discussed in Pre -Con meeting and was to be added via change order.
General or Standard Change Order Explanation
Extra MOb fee for HMA is due to unable to drive piling until duke can de- energize power line over piling. This mob fee is to keep project moving
so contractor can still work.
Change Order Explanation for Specific Line Item
It is the intent of the parties that this change order is full and complete compensation for the work describe above.
Notification and consent to this change order is hereby acknowledged.
Contractor: Signed By:
Date:
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system.
Mr. Mike McBride P.E
City Engineer/ Traffic Engineer
One Civic Square
Carmel, IN 46032
RE: Contract No: R- 29657 -A
Subject: LPA Award Recommendation
Des No: 0600390
Dear Mr. McBride,
Please do not hesitate to contact me if you have any questions.
City of Cannel
DEPARTMENT INDIANA
Driving Indiana's Ecorro:lxmitc Growth
ays
4iz.?.4 440 »a d.. a :A'A' 7 k ,1 a,.a1k?41m. 4stab', M x .W '+i'""
Greenfield District
32 S. Broadway Street
Greenfield, IN 46140
PHONE: (317) 467 -3973
FAX: (317) 467 -3956
February 15, 2011
The above referenced contract received a low bid of 583,765.77 at the 02/09/2011 letting. This is
within INDOT LPA guidelines for approval.
Please sign and return this notification if the LPA is in agreement to Award Contract R- 29657 -A for
583,765.77
Sincerely,
gl
wwwin.gov/dot/
An Equal Opportunity Employer
Shahnaz Afzaal
LPA Program Coordinator
Greenfield District
Mitchell E. Daniels, Jr., Governor
Michael B. Cline, Commissioner
t
Contract No:R -29657
Change Order No:005
(SIGNATURE)
(SIGNATURE)
PENS
Approval Level
INDIANA
Department of Transportation
Name of Approver
APPROVED FOR LOCAL PUBLIC AGENCY
(TITLE) (DATE)
(TITLE) (DATE)
SUBMITTED FOR CONSIDERATION
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Date
Date:06/20/2011
Page: 4
Status
Monday, June 13, 2011
Rob Surber
Butler, Fairman and Seufert, Inc.
8450 Westfield Road
Suite 300
Indianapolis, IN 46240
RE: INDOT Contract No. R- 29657 -A; Extra Mobilization for HMA Seeding
Rob,
George R. Harvey Son, Inc. proposes the following:
1. Extra Mobilization for HMA; Qty (01) $2,970.00
Prep Crew $1,050.00
Paving Crew $1,650.00
10% Mark Up $270.00
2. Extra Mobilization for Seeding; Qty (02) $1,650.00
Earth Images for 1 Mobilization $750.00
10% Mark Up $75.00
The reason for two is because the original contract did not have a mobilization
and demobilization. This topic was brought up during the pre construction
meeting and the subcontractor was under the impression that the mobilization
would be added as needed.
Cordially,