Loading...
HomeMy WebLinkAboutHunt Paving/1/Village of Mt. Carmel Drainage/+$32,335.16CITY OF CARMEL TO: CONTRACT CHANGE ORDER NO.: 1 You are directed to make the following changes in this Contract: (Brief Description) ITEM AMOUNT 1. Sanitary Sewer Relocation Str 703 3,041.87 2. Sanitary Sewer Relocation 23 Bennett 2,009.94 3. 19 "x30" Elliptical Pipe on Village Dr. 4,087.68 4. 19 "x30" Elliptical Pipe End Sections Village Dr. 8,701.74 5. Connection to manhole at 146 Street 9,888.95 6. Water Line Relocations (2) on Bennett 4,604.88 The changes result in the following adjustment of Contract Price and Contract Time: Contract Price prior to this Change Order 751,825.05 Contract Price will be increased by this Change Order 32,335.16 New Contract Price including this Change Order 784,160.21 Contract Time Prior to this Change Order Days Completion Date Net increased /decreased resulting from this Change Order Days Current Contract Time including this Change Order Days Completion Date This Change Order is for full and final settlement of all direct, indirect, impact costs and time extensions incurred at any time resulting from the performance of the changed work. The Above Changes Are The Above Changes Are Recommended Accepted: Hannum, Wagle Cline The Hunt Paving Company, Inc. Engineering ENGINEER CONTRACTOR 151 N. Delaware, Suite 800 P.O. Box 42517 Address Address Indianapolis, IN 46204 Indianapolis, IN 46242 City /State /Zip City /State /Zip By: By: Matt Maple Justin Noltinc (pri am 7 (print name (signature) (sigrYature) Phone:317- 347 -3663 Date: 12/1/10 DATE: 12/1/10 PROJECT NAME: Village of Mt. Carmel Drainage Project CITY REQ. NO.: 10 -08D CITY PO NO.: 27450 CITY PO DATE: 9/3/10 AFPnov:p AS TO FORM BY Date: 12/1/10 Phone:317- 241 -8313 OR DAYS II. The following referenced Documents further describe the changes outlined in Paragraph I, and are to be considered a part of this Change Order: R.F.P.: W.D.C. No.: Other: Approved: Diana Cordray, C -Treasurer Date: T. McBride City Engine Date: /2 ,2 2A'P 1D 10/07/10 Gary Duncan City of Carmel Department of Engineering One Civic Square Carmel, IN 46032 RE: Sanitary Lateral Relocation at Sta. 3 +00 Bennett Road (Str. 703) Gary; Please find below our T &M Invoice for relocating the Sanitary lateral on 10/6/2010. approx. item description quantity unit unit price total price EWA Relocate Sanitary 1.00 ea 3,041.87 3,041.87 Lateral If you should have any questions or require any additional information please give me a call. Please let us know if this is approved, so we can plan our work. Thank you, THE HUNT PAVING COMPANY, INC. Justin Nolting cc: JF, EH The Hunt Paving Company, Inc. Post Office Box 42517 Indianapolis, IN 46242 -0517 317/241 -8313 Fax 317/487 -5779 COMPANY NAME THE HUNT PAVING COMPANY DATE: DAY: PAGE: 1 OF: 1 PURCHASE ORDER NO. NA RELEASE NO. NA A.R. NO. JOB NO. 648 1 ea JOB DESCRIPTION Relocate Sanitary Lateral LABOR EMPLOYEE NAME EMPLOYEE CRAFT REG HRS OT HRS DT HRS RATE REG HRS RATE OT HRS RATE DT HRS TOTAL laborer 4.5 0 35.57 47.95 160.07 forman 9 0 48.61 66.94 437.49 Combo Man 9 0 46.33 63.52 416.97 TOTAL LABOR 1014.53 SUBCONTRACTOR NAME DESCRIPTION TOTAL Beaver trucking 4 hrs $65 /hr 260.00 TOTAL SUBCONTRACTOR 260.00 MATERIALS QUANTITY DESCRIPTION TOTAL 10' 6" SDR 35 42.03 2 6" 45's 16.42 1 6" Coupling 5.50 11.5 Cy of Flowable Fill 598.00 5 Cy of Class C Concrete 365.00 TOTAL MATERIALS 1026.95 EQUIPMENT and small tools EQUIPMENT HRS EQUIPMENT TYPE RATE TOTAL Markup: 3/4 ton pick up truck 4 hour 18.93 $75.72 Mini Exc. 4 hour 52.82 $211.28 TOTALS TOTAL LABOR 20% 1217.44 TOTAL MATERIAL 12% 1150.18 TOTAL EQUIPMENT 12% 321.44 TOTAL SUBS 7% 278.20 TOTAL INSURANCE TAXES 74.61 EQUIPMENT TOTAL 287.00 PAGE TOTAL 3041.87 INSPECTOR APPROVAL signature date 2010 10/08/10 Gary Duncan City of Carmel Department of Engineering One Civic Square Carmel, IN 46032 RE: Sanitary Lateral Relocation at 23 Bennett Road Gary; Please find below our T &M Invoice for relocating the Sanitary lateral on 10/7/2010. approx. item description quantity unit unit price total price EWA Relocate Sanitary 1.00 ea 2,009.94 2,009.94 Lateral If you should have any questions or require any additional information please give me a call. Please let us know if this is approved, so we can plan our work. Thank you, THE HUNT PAVING COMPANY, INC. Justin Nolting cc: JF, EH The Hunt Paving Company, Inc. Post Office Box 42517 Indianapolis, IN 46242 -0517 317/241 -8313 Fax 317/487 -5779 COMPANY NAME THE HUNT PAVING COMPANY DATE: DAY: PAGE: 1 OF: 1 PURCHASE ORDER NO. NA RELEASE NO. NA A.R. NO. JOB NO. 648 1 ea JOB DESCRIPTION Relocate Sanitary Lateral LABOR EMPLOYEE NAME EMPLOYEE CRAFT REG HRS OT HRS DT HRS RATE REG HRS RATE OT HRS RATE DT HRS TOTAL laborer 2 0 35.57 47.95 71.14 forman 4 0 48.61 66.94 194.44 Combo Man 4 0 46.33 63.52 185.32 TOTAL LABOR 450.90 SUBCONTRACTOR NAME DESCRIPTION TOTAL Beaver trucking 2 hrs $65 /hr 130.00 TOTAL SUBCONTRACTOR 130.00 MATERIALS QUANTITY DESCRIPTION TOTAL 1 TON #8 stone 14.85 2 6" 45's 16.42 1 6" Coupling 5.50 11.5 Cy of Flowable Fill 598.00 5 Cy of Class C Concrete 365.00 TOTAL MATERIALS 999.77 EQUIPMENT and small tools EQUIPMENT HRS EQUIPMENT TYPE RATE TOTAL Markup: 3/4 ton pick up truck 2 hour 18.93 $37.86 Mini Exc. 2 hour 52.82 $105.64 TOTALS TOTAL LABOR 20% 541.08 TOTAL MATERIAL 12% 1119.74 TOTAL EQUIPMENT 12% 160.72 TOTAL SUBS 7% 139.10 TOTAL INSURANCE TAXES 49.30 EQUIPMENT TOTAL 143.50 PAGE TOTAL 2009.94 INSPECTOR APPROVAL signature date 2010 1D 10/26/10 Gary Duncan City of Carmel Department of Engineering One Civic Square Carmel, IN 46032 The Hunt Paving Company, Inc. RE: 19" x 30" Elliptical Pipe and End Sections Gary; Please find below our price for changing 3 drive culverts to 19" x 30" Elliptical Pipe. Post Office Box 42517 Indianapolis, IN 46242 -0517 317/241 -8313 Fax 317/487 -5779 approx. item description quantity unit unit price total price EWA 19" x 30" Elliptical Pipe 48.00 LF 85.16 4,087.76 EWA 19" x 30" Elliptical Pipe End 6.00 EA $1,450.29 8,701.71 Sections If you should have any questions or require any additional information please give me a call. Please let us know if this is approved, so we can plan our work. Thank you, THE HUNT PAVING COMPANY, INC. Justin Nolting cc: JF, EH COMPANY NAME THE HUNT PAVING COMPANY DATE: DAY: PAGE: 1 OF: 1 PURCHASE ORDER NO. NA RELEASE NO. NA A.R. NO. JOB NO. 648 48 LF JOB DESCRIPTION Elliptical Pipe LABOR EMPLOYEE NAME EMPLOYEE CRAFT REG HRS OT HRS DT HRS RATE REG HRS RATE OT HRS RATE DT HRS TOTAL laborer 8 35.57 284.56 forman 4 48.61 194.44 Combo Man 4 40.67 162.68 Operator 4 46.33 185.32 TOTAL LABOR 827.00 SUBCONTRACTOR NAME DESCRIPTION TOTAL Beaver trucking 4 hrs $65 /hr 260.00 TOTAL SUBCONTRACTOR 260.00 MATERIALS QUANTITY DESCRIPTION TOTAL 48 LF of 19" x 30" Elliptical Pipe $40.70/If 1953.60 1 LS Misc Material 75.00 TOTAL MATERIALS 2028.60 EQUIPMENT and small tools EQUIPMENT HRS EQUIPMENT TYPE RATE TOTAL Markup: 3/4 ton pick up truck 4 hour 18.93 $75.72 Flat Bed 4 hour 27.06 $108.24 710 Backhoe 4 hour 53.31 $213.24 TOTALS TOTAL LABOR 20% 992.40 TOTAL MATERIAL 12% 2272.03 TOTAL EQUIPMENT 12% 444.86 TOTAL SUBS 7% 278.20 TOTAL INSURANCE TAXES 100.27 EQUIPMENT TOTAL 397.20 PAGE TOTAL 4087.76 INSPECTOR APPROVAL signature date 2010 COMPANY NAME THE HUNT PAVING COMPANY DATE: DAY: PAGE: 1 OF: 1 PURCHASE ORDER NO. NA RELEASE NO. NA A.R. NO. JOB NO. 648 6 EA JOB DESCRIPTION Elliptical Pipe End Sections LABOR EMPLOYEE NAME EMPLOYEE CRAFT REG HRS OT HRS DT HRS RATE REG HRS RATE OT HRS RATE DT HRS TOTAL laborer 16 35.57 569.12 forman 8 48.61 388.88 Combo Man 8 40.67 325.36 Operator 8 46.33 370.64 TOTAL LABOR 1654.00 SUBCONTRACTOR NAME DESCRIPTION TOTAL TOTAL SUBCONTRACTOR 0.00 MATERIALS QUANTITY DESCRIPTION TOTAL 6 EA of 19" x 30" Elliptical Pipe End Sections $900.00 /EA 5400.00 TOTAL MATERIALS 5400.00 EQUIPMENT and small tools EQUIPMENT HRS EQUIPMENT TYPE RATE TOTAL Markup: 3/4 ton pick up truck 4.5 hour 18.93 $85.19 Flat Bed 4 hour 27.06 $108.24 710 Backhoe 4 hour 53.31 $213.24 TOTALS TOTAL LABOR 20% 1984.80 TOTAL MATERIAL 12% 6048.00 TOTAL EQUIPMENT 12% 455.46 TOTAL SUBS 7% 0.00 TOTAL INSURANCE TAXES 213.45 EQUIPMENT TOTAL 406.67 PAGE TOTAL 8701.71 INSPECTOR APPROVAL signature date 2010 11/16/10 Gary, 1D Gary Duncan City of Carmel Department of Engineering One Civic Square Carmel, IN 46032 RE: Village of Mt. Carmel, 146th St and Village Drive Please find our price for the work at 146th St. and Village Drive as a result of the grade bust and issues with existing pipe. item description quantity unit unit price total price EWA 146th and Village Drive 1 LSUM 9,888.95 9,888.95 Should you have any questions or comments, please call me at 317 241 -8313. Thank you, THE HUNT PAVING COMPANY, INC. Justin Nolting Project Manager cc: JF The Hunt Paving Company, Inc. Post Office Box 42517 Indianapolis, IN 46242 -0517 317/241 -8313 Fax 317/487 -5779 total 9,888.95 COMPANY NAME The Hunt Paving Company DATE: 11 -8, 11 -9 DAY: PAGE: 1 OF ONE 1 PURCHASE ORDER NO. RELEASE NO. A.R. NO. 3001 JOB NO. HPC 648 Village of Mt. Carmel EXTRA WORK DESCRIPTION Remove and replace structure 714 resulting from grade bust/issues Quantity: based on 1 Is with existing line. +insurance /taxes) LABOR (base wage +fringes EMPLOYEE NAME CODE CRAFT REG HRS OT HRS DT HRS RATE REG HRS RATE OT HRS RATE DT HRS TOTAL Hunt Labor see attached spreadsheet repairs 2,973.12 TOTAL LABOR 2,973.12 SUBCONTRACTOR NAME DESCRIPTION TOTAL Beaver Gravel Trucking, 8.25 hrs A $65 /hr 536.25 Hardcore Sawing Core holes for pipe in new structure 729.00 TOTAL SUBCONTRACTOR 1,265.25 MATERIALS QUANTITY DESCRIPTION 1 Is misc tools, supplies, equipment 250.00 40 If 24" RCP 598.00 1 ea 5' Manhole barrel section 460.00 2.5 cy Concrete Class C 182.50 18 cy Flowable fill 936.00 1 Is Permit Licensing bond for Hamilton County 100.00 TOTAL MATERIALS 2,526.50 EQUIPMENT HOURS TYPE OF EQUIPMENT RATE TOTAL T M markup: 0.1 Ditch Witch Hydro Excay. (month) 2,996.00 299.60 mini excv rental for the week 0.00 6 Cat 322 1450 102.15 612.90 3.5 backhoe 710GJD 1605 64.45 225.58 backhoe 710G 1604 0.00 curb machine 1602 0.00 Single axle dump 1187 0.00 finish truck 1426 0.00 1 breaker 1615 41,33 41.33 10.5 pickup truck 1600 18.89 198.35 TOTALS backhoe 1234 0.00 mech truck 1633 0.00 TOTAL LABOR 20% 3,567.74 breaker 1615 0.00 TOTAL MATERIAL 12% 2,829.68 10.5 pickup 1586 18.87 198.14 TOTAL EQUIPMENT 12% 1,857.18 Lowboy trailer 1530 0.00 TOTAL SUBS 7% 1,391.78 Lowboy 1526 0.00 TOTAL INS, BOND TAXES 242.57 pickup 1349 0.00 cure cart 1456 0.00 5 Air compressor /jack hammer 16.46 82.30 TOTAL EQUIPMENT 1658.20 PAGE TOTAL 9,888.95 TOTAL unitprice 9,888.95 per Is 9,888.95 CONTRACTOR'S APPROVAL 12/01/10 Gary Duncan City of Carmel Department of Engineering One Civic Square Carmel, IN 46032 RE: Water Service Relocation Gary; Please find below our price for relocating water services. approx. item description quantity unit unit price total price EWA Relocate Water 2.00 ea 2,302.44 4,604.88 Services If you should have any questions or require any additional information please give me a call. Please let us know if this is approved, so we can plan our work. Thank you, THE HUNT PAVING COMPANY, INC. Justin Nolting cc: JF, EH The Hunt Paving Company, Inc. Post Office Box 42517 Indianapolis, IN 46242 -0517 317/241 -8313 Fax 317/487 -5779 COMPANY NAME THE HUNT PAVING COMPANY DATE: DAY: PAGE: 1 OF: 1 PURCHASE ORDER NO. NA RELEASE NO. NA A.R. NO. JOB NO. 648 2 ea JOB DESCRIPTION Re locate Water Services LABOR EMPLOYEE NAME EMPLOYEE CRAFT REG HRS OT HRS DT HRS RATE REG HRS RATE OT HRS RATE DT HRS TOTAL 40.67 56.46 0.00 laborer 2 0 35.57 47.95 71.14 forman 2 0 48.61 66.94 97.22 operator 0 0 46.33 63.52 0.00 0.00 0.00 0.00 0.00 0.00 TOTAL LABOR 168.36 SUBCONTRACTOR NAME DESCRIPTION TOTAL Boring Sub 2 ea. $1923.60 3847.20 TOTAL SUBCONTRACTOR 3847.20 MATERIALS QUANTITY DESCRIPTION TOTAL 1 Is misc material for temporary splices 80.00 TOTAL MATERIALS 80.00 EQUIPMENT and small tools EQUIPMENT HRS EQUIPMENT TYPE RATE TOTAL Markup: 3/4 ton pick up truck 1 hour 18.96 $18.96 backhoe 1 hour 55.85 $55.85 TOTALS TOTAL LABOR 20% 202.03 TOTAL MATERIAL 12% 89.60 TOTAL EQUIPMENT 12% 83.80 TOTAL SUBS 7% 4116.50 TOTAL INSURANCE TAXES 112.95 EQUIPMENT TOTAL 74.81 PAGE TOTAL 4604.88 INSPECTOR APPROVAL signature date 2010