Name of Project Headworks 106 Street Pump Station, Contract 70 Number 451 5996.002 Page 1 of 2
Contractor
Address
Jones Henry Engineers, Ltd.
Thieneman Construction, Inc.
17110 Westfield Park Road, Suite 1A; Westfield, Indiana 46074
Bid Amount
Net Change including Change Order 3
Present Contract Amount
Change in Time of Completion
Description of Change
Item 1 Pressure Injection of Horizontal Surfaces
Item 2 Joint Restraints for 12 -inch Water Line
Item 3 Exploratory Work and Additional Labor to Install New Work Under Unforeseen Existing Water Lines
Item 4 Delete Screenings Bagger
Item 5 Delete SK -16
Item 6 Solenoid Valves
3,586.00
897.00
4,856.00
1,126.00
500.00
3,409.00
Approved City of Carmel, Indiana
Owner
CHANGE ORDER
5,454,500.00
330,114.38
5,124,385.65
April 15, 2011 to
All claims against OWNER, which are incidental to or a consequence o >tChange Order, are satisfi
Prepared By: Jones Henry Engineers, Ltd. By
Engineer
Accepted Thieneman Construction, Inc. By
Contractor
Total Increase
Change Order No. 3
Date
April 24, 2011
March 16, 2011
11,122.00
Date
Date 3 /,30///
Date
Item 2 Joint Restraints for 12 -Inch Water Line
City of Carmel, Indiana
Wastewater Treatment Plant Expansion
Headworks and 106 Street Pump Station
Contract 70
451 5996.002
Change Order No. 3
Item 1 Pressure Injection of Horizontal Surfaces
The pressure injection of cracks of horizontal surfaces, per the letter of November 11,
2010 attached. The amount is $3,586.00. Injection of minor shrinkage cracks
completed to minimize channel leakage.
The Owner was unable to shut down the 12 -inch City water line, while the tie -in had to
be completed for the 42 -inch. We are in agreement with the $897 cost for the additional
joint restraints in the letter of February 10, 2011 attached.
Item 3 Exploratory Work and Additional Labor to Install New Work Under S 4,856.00
Unforeseen Existing Water Lines
The City of Carmel is in agreement with the exploratory work and additional labor to
install the 42 -inch under the 20 -inch raw water main and 12 -inch finish water. The cost
for this additional work is $4,856.00 per the letter of January 6, 2011 attached. The 20-
inch and 12 -inch lines were not shown on the Contract Drawings, as they were
installed after bidding.
Item 4 Delete Screenings Bagger S 1,126.00
The City of Carmel accepts the credit for the deletion of the bagger at $1,126.00 as
presented in the letter of February 17, 2011. The bagger was specified but not required.
Item 5 Delete SK -16
The City of Carmel accepts the credit for the deletion of baffle SK -16 of $500.00.
Baffle SK -16 was specified but is not required.
Item 6 Solenoid Valves
Added solenoid valves to reduce the plant water usage at the grit pumps. The solenoid
valves were not part of the original Contract.
Jones 8. Henry Engineers. Ltd.
Page 2 of 2
3,586.00
897.00
500.00
3,409.00