HomeMy WebLinkAboutRieth Riley/1/106th Path Michigan to Ditch/+$26,306.40TO: Engineering Department
One Civic Square
Carmel, IN 46032
CITY OF CARMEL
I. You are directed to make the following changes in this Contract:
See Attached Exhibit A
SCHEDULED ADJUSTMENT
HEM AMOUNT OR DAYS
See Attached Change Order Fable $26,306.40 30 Days
II. The following referenced Documents further describe the changes outlined in Paragraph I,
and are to be considered a part of this Change Order: R.F.P.:_N /AW.D.C. NO.: N/A
Other:
The changes result in the following adjustment of Contract Price and Contract Time:
Contract Price prior to this Change Order $664,400.00
Contract Price will be increased /decreased by this Change Order $26,306.40
New Contract Price including this Change Order $690,706.40
Contract Time prior to this Change Order 100 Days 5/15/2011 Completion Date
Net increased/decreased resulting from this Change Order 30 Days
Current Contract Time including this Change Order 130 Days 6/13/2011 Completion Date
This Change Order is for full and final settlement of all direct, indirect, impact costs and time
extensions incurred at any time resulting from the performance of the changed work.
The Above Changes Are
Recommended
CROSSROAD ENGINEERS
ENGINEER
3417 Sherman Drive
Address
Beech Grove, IN 46107
City /State /Zip
The Above Changes Are
Accepted
Rieth -Riley Construction Co.
CONTRACTOR
1751 W. Minnesota
Address
Indianapolis, IN 46221
City /State /Zip
.John Wischme e
att Mc troy
B
Phone: 317- 780 -1555
Date: 2/4/2011
B
ea Manager
hone: 317 -634 -5 61.
Date: 2/4/2011
CONTRACT CHANGE ORDER NO.: 1
DATE:February 4, 2011
PROJECT NAME: #09 -05 106th St. Path Michigan Rd. to Ditch Rd.
CITY REQ. NO.:
CITY PO NO.: #27441
CITY PO DATE: 7/21/2010
Date:
Approved
fri
James Brai ard, Mayor
Me ier
liana Cordray, erk- Treasurer
ITEM NO.
DESCRIPTION
UNIT PRICE
ORIGINAL
QUANTITY
ORIGINAL
AMOUNT
FINAL
QUANTITY
FINAL
AMOUNT
OVER/UNDER
*41
3' x 5' Precast Concrete Box Culvert
$868.97
0
$0.00
16
$13,903.52
$13,903.52
*42
3' x 8' Precast Concrete Box Culvert
$387.59
0
$0.00
32
$12,402.88
$12,402.88
TOTAL OF CHANGE ORDER ITEMS
$0.00
$26,306:40
$26,306:40
CITY OF CARMEL
Project #09 -05: 106th Street Path Michigan Road to Ditch Road
CHANGE ORDER TABLE
TOTAL ORIGINAL CONTRACT PLUS CHANGE ORDER ITEMS
ORIGINAL CONTRACT PRICE
CHANGE ORDER #1
NEW CONTRACT AMOUNT INCLUDING APPROVED CHANGE ORDERS
Indicates additional item added to the contract.
$664,400.00
$26,306.40
$690,706.40
CITY OF CARMEL
106th Street Path Michigan Road to Ditch Road Project #09 -05
Exhibit A
You have been directed to make the following changes in this Contract:
Item 41 Additional path from Weston Drive to Shelborne Road requires a culvert crossing.
Item 42 Additional path from Weston Drive to Shelborne Road requires a culvert crossing.
Item 43 Additional time requested when additional path was added to the contract.