HomeMy WebLinkAboutCorrespondence: Engr'g Dept email 11-1-11Conn, Angelina V
From: Eric Carter [cartere @weihe.net]
Sent: Tuesday, November 01, 2011 10:05 AM
To: Conn, Angelina V
Subject: FW: carmel hope phase 3
Angie, comments received from Engineering.
Thank you,
Eric
Eric A. Carter, R.L.A., ASLA
Project Manager, Commercial Development
Weihe Engineers, Inc.
317 846 6611
317 432 7639 cell
weihe.net
This message and any files transmitted with it are confidential, may contain privileged information which is intended solely forthe receipt, use and benefit of the intended
recipient of this email. If you are not the intended recipient, be advised that dissemination, distribution, printing orcopying of this message is strictly prohibited and may result
in legal liability on your behalf. If you receive this message in error, orare not the named recipient, please notify the sender at either the email address or telephone number
above and delete this email from your computer. Thank you.
From: Duncan, Gary R fmailto:gduncan @carmel.in.govl
Sent: Tuesday, November 01, 20119:31 AM
To: Eric Carter
Cc: Jamie Shinneman; Barnes, David R; Redden, Nick; Thomas, John G
Subject: RE: carmel hope phase 3
Good morning Eric. Just a few comments... these are in addition to any other comments that have been issued by
Engineering:
The temporary construction entrance requires BPW approval. I am not crazy about the location but don't see what else
is feasible.
Thank you for adding the MLAG and MFPG definitions... have you established the elevations?
Is Detail 10 -13 on Sheet C201 being used with this phase?
I recall that the passing blister on Gray Road has been installed; please confirm.
Thanks so much,
Gary
From: Eric Carter Finailto:cartere weihe.netl
Sent: Monday, October 31, 20119:50 AM
To: Duncan, Gary R
Cc: Jamie Shinneman
Subject: carmel hope phase 3
G a ry,
Good Morning.