HomeMy WebLinkAboutTAC Minutes 12-19-01Carmel/Clay Technical Advisory Committee Minutes
December 19, 2001
9:00 a.m.
Members present'
Jon Dobosiewicz- Carmel DOCS
Chuck Shupperd - Vectren Energy
Gary Hoyt- Carmel Fire Department
JeffKendall - Carmel Bldg. Com.
Dick Hill - Carmel Engineering
Steve Broermann- Ham. Co. Highway
John South-Ham. Co. Soil & Water
Scott Brewer - Carmel Urban Forester
Steve Cash- Ham. Co. Surveyors
Mike McBride - Carmel Engineering
Bill Akers- Carmel Communications
s: TechnicalAdvisoryConurdtteeWlinutes\tac2001 dec
Plans)
~n the Villa
Unite Development.
Filed by Rich Kelly of EHMT for the Spanos Corporation.
PUD/Planned
Rich Kelly presented the case. He introduced Jim Kourafas and Jay DeMoss of A.G.
Spanos Corporation, Terry Hebor, Brenwick Development, Inc. and Keith Lash, The
Schneider Corporation. The multi-family development project is on two identical 2.5
acres parcel located in the Village of WestClay. A total of 182 apartment units are
proposed. Off-street parking will be provided behind buildings in addition to on-street
parking,
John South sent a comment letter. He needs an upgrade of construction sequence for the
erosion control plan. It is productive to place stone on the drive. The construction plan
needs this detail. Construction on all the buildings will start at the same time. Slabs will
be in place four to six weeks after site work starts. Mr. South wants a temporary
stabilization of the land around buildings. Too often crews tear up a site and do not
worry about stabilization during construction. Jay DeMoss said, generally, their
buildings are sequential. He made a commitment to keep the roads clean. The time
period between site pads is about ten days. Foundation work will be four to six weeks for
all of the buildings. The framing takes about 90 days. Then, the outside work will start.
Jim Kourafas stated there is not a great amount of site work. It is one city block.
Chuck Shupperd understands gas service is not required.
Scott Brewer faxed a comment letter. Basically, his comments deal with technical
aspects of plant schedules, specie comments, and additional trees in the parking lot. He
suggested a mix of shade trees with ornamentals. Rich Kelly inquired about the use of
evergreens too. Mr. Brewer suggested planting spruces. They do better than pines. The
developer wants the year-round appeal of evergreens. Scott Brewer suggested some soil
amendments and special fertilization treatments. The street trees are not planted yet.
Brenwick will supply the trees; Spanos will only install them.
Steve Broermann has not finished his review. Earlier, they spoke of additional street
parking. Rich Kelly said it has been eliminated. There are curb cuts on each end of the
site. Those cuts are in the wrong spots for this development. They will have to also
change some center islands. Steve Broermann wants the corners squared when they do
the cuts.
Steve Cash believes the site will have one owner. Spanos Corporation presently owns the
project. It will be sold some time in the future. However, it will not be platted and split.
It will be a one-owner property. They may become condos in the future. The lots will
not be subdivided beyond what they are today. Jon Dobosiewicz identified the parcel as
a single block. They must plat as a single block. Both blocks are recorded. They do
s: TechnicalAdvisorycommitteeXMinutes\tac2001 dec
14
exist as recorded tracts. An outlet permit will be recorded. If the project is split up as
townhouses, Mr. Cash request storm sewers become part of the regulated drain. This is
not a requirement at this time. Rich Kelly is making provisions for conversion to condos.
Common areas are still owned by the association.
Jeff Kendall understands a two-hour wall will be utilized. This project is considered
multi-family. Common walls must be from foundation to roof. The units will be
reviewed as multi family.
Bill Akers has spoken to Rich Kelly about this project and has assigned 20 addresses for
the 16 buildings. The units cannot be reached internally through a cemral hall. They will
be addressed off the streets they face. The mail boxes will be in the mail centers, such as
Building 5 and 16. The postal carrier must be able to locate the boxes easily.
Mike McBride will defer the County.
Gary Hoyt distributed his letter. He has met with Keith Lash and thinks all issues are
resolved. There are no trees in the emergency access drives. Only pavers and grass are
allowed in the emergency access area. Rich Kelly will use a three-inch chair back curb,
not a roll curb. A knock down type of fence might be allowed.
Jon Dobosiewicz requested an inventory of on street parking. No additional zoning
approvals are required. He also wants review letters from agencies before the project is
released for permits.
The meeting adjourned at 12:00.
s: TechnicalAdvisorycommitteeXMinutes\tac2 O01 dec
15
CARMEL/CLAY TECHNICAL ADVISORY COMMITTEE
AGENDA
Date: DECEMBER 19, 2001
Place: Department of Community Services Conference Room
3rd Floor - Carmel City HaH
9:00 a.m.
140 First Street NW (Land Use Variance)
The applicant seeks approval to convert an existing residence into a Beauty Salon. The site is
located at 140 First Street NW. The site is zoned R-4.
Filed by Richard Sanders.
9:30 a.m.
Shapiro's at City Center (Construction Plans)
The site is located at approximately 920 South Rangeline Road. The site is zoned C-1 (City
Center).
Filed by Christopher S. McComas of Roland Design, Inc. for Brian Shapiro.
10:00 a.m.
Dan Young Chevrolet (ADLS Amendment)
The site is located northeast of East 96m Street and Keystone Avenue. The site is zoned B-
3/business and is located partially within the SR 431/Keystone Avenue Overlay Zone.
Filed by Charles D. Frankenberger of Nelson & Frankenberger for D. Young Chevrolet, LLC.
10:30 a.m.
Parkwood Crossing East (College Hills PUD)
The site is located northwest of East 96t~ Street and North College Avenue. The site is zoned PUD
/ Planned Unit Development.
Filed by Charles D. Frankenberger of Nelson & Frankenberger for Duke Realty Corporation.
11:00 a.m.
3091 East 98a Street- Parking lot modifications
The site is located at 3091 East 98t~ Street. The site is zoned B-3 (Business).
Filed by Rich Kelly of EHMT.
~; ~I l'!~'a:m~~ ~ Village of WestClay, Apartments, 182 units (Construction Plans)
%~-~ ......... The site is located within the Village of West Clay. The site is zoned PUD/Planned Unit
Development.
Filed by Rich Kelly of EHMT for The Spanos Corporation.