CITY OF CARMEL BOARD OF ZONING APPEALS
APPLICATION FOR ACTION APPEAL REQUEST
1 211
Fee: $148.00 t
DOCKET NO. DATE RECEIVED:
1) Applicant: Pulte Group, Inc. and Centex Homes f
Address: 11590 N. Meridian Street, Suite 530, Carmel, IN 46032
2) Project Name: Traditions on the Monon Phone:
Engineer /Architect: Phone:
Attorney: Timothy E. Ochs, Ice Miller LLP Phone: (317) 236 -5952
Contact Person: Tim Ochs Phone: (317) 236 -5952
Email: timothy.ochs @icemille Fax (317) 592 -4720
3) Applicant's Status: (Check the appropriate response)
X (a) The applicant's name is on the deed to the property
(b) The applicant is the contract purchaser of the property
X (c) Other: Recipient of letter from Director of Community Service
4) If Item 3) (c) is checked, please complete the following:
Owner of the property involved: Centex Homes
Owner's address: Same as Applicant phone:
5) Record of Ownership:
Deed Book No. /Instrument No. Instrument No. 200500033630
Page: Purchase date: May 2, 2005
6) Common address of the property involved: O Monon Lane, Carmel, Indiana 46032
Blocks 13, 15, 24 and Common Areas A and L of the Traditions on the Monon according to
Legal description: the plat thereof recorded as Instrument #2005063263 on September 26, 2005 as amended
in Instrument #2005080400 recorded on December 13, 2005-
Tax Map Parcel No.: 16- 09- 24- 04- 12- 151.000
7) State explanation of requested Appeal: (State what you want to do and cite the section number(s) of the
Carmel/Clay Zoning Ordinance which applies and/or creates the need for this appeal).
Sea Exhibit
8) State reasons supporting the Appeal: (Additionally, complete the attached question sheet entitled "Fmdi gs of Fad
Appeal"). See Exhibit
9) Present zoning classification of the property: PUD
BZA Appeal Application pg 1 rev. 12128/2010
10) Present use of the property: Town Home Development
11) Size of lot/parcel in question 3.3 acres
12) Describe the proposed use of the property Town Home Development
13) Is the property: Owner occupied X Renter occupied Other
14) Are there any restrictions, laws, covenants, variances, special uses, or appeals filed in connection with this
property that would relate or affect its use for the specific purpose of this application? If yes, give date and docket
number, decision rendered and pertinent explanation.
N/A
15) Has work for which this application is being filed already started? If answer is yes, give details:
Building Permit Number:
Builder:
16)
If proposed appeal is granted, when will the work commence? N/A
17) If the proposed appeal is granted, who will operate and /or use the proposed improvement for which this application
has been filed?
N/A
NOTE: LEGAL NOTICE shall be published in the Indianapolis Star MANDATORY twenty-five (25) days prior to the pubic
hearing date. The certified "Proof of Publication" affidavit for the newspaper must be available for inspection the right of the
hearing.
LEGAL NOTICE to all adjoining and abutting property owners is also MANDATORY, two methods of notice are
recommended:
1) CERTIFIED MAIL RETURN RECEIPT REQUESTED sent to adjoining property owners. (The white receipt
should be stamped by the Post Office at least twenty -five (25) days prior to the public hearing date)
2) HAND DELIVERED to adjoining and abutting property owners (A receipt signed by the adjoining and abutting
property owner acknowledging the twenty -five (25) day notice should be kept for verification that the notice was completed)
REALIZE THE BURDEN OF PROOF FOR ALL NOTICES IS THE RESPONSIBILITY OF THE APPLICANT. AGAIN, THIS
TASK MUST BE COMPLETED AT LEAST TWENTY -FIVE (25) DAYS PRIOR TO PUBLIC HEARING DATE.
The applicant understands that docket numbers will not be assigned until all supporting information has been
Applicant Signature: f
The applicant certifies by signing this appli i n that he /she has been advised that all representations of the Department of
Community Services are advisory only and t the applicant should rely on appropriate subdivision and zoning ordinance and/or
the legal advice of his/her attorney.
BZA Appeal Application pg 2 rev. 12/28/2010
EXHIBIT A
Explanation of requested Appeal: Applicant is appealing portions of that certain letter from
Michael Hollibaugh, the Director of Community Services of the City of Carmel (the "Director
to Mr. Tony Barbee of the PulteGroup, Inc., and Mr. Robert Parker of the Traditions on the
Monon HOA, dated October 18, 2011, a copy of which is attached to this Appeal Request (the
"Letter Each portion of the Letter which is being appealed and the reasons supporting each
portion are listed below. The sections appealed are listed in the order in which they appear in the
Letter and are referenced using the same headings as the Letter.
State Reasons supporting the Appeal:
1. Section 2A The Director has no authority under Carmel Zoning Ordinance, the PUD
Ordinance for the Traditions on the Monon (the "PUD Ordinance or any other
Ordinance of the City of Carmel to require the repair of cracks in the curbing. The
curbing was properly installed, and cracking is normal for concrete. Moreover, much of
the curbing referenced in the Letter is many years old, and the responsibility for
maintenance is that of the homeowners association. No basis exists for this
determination.
2. Section 2B The Applicant appeals the determination in the second part of Section 2B
which would require that the driveway pad to each unit in Building 7 be reinstalled to the
concrete flush with the asphalt pavement of the drive lane, and that new concrete
driveways be installed to be flush with the existing finish asphalt. Again, there is no
standard or requirement in the PUD Ordinance or the Carmel Zoning Ordinance to
support this determination. The Director does not have rule making authority, nor does
he have the ability to promulgate standards. This ability is solely within the discretion of
the duly elected legislative body of the City of Carmel. Ad hoc rule making is illegal and
inappropriate.
3. Section 2C The Applicant appeals the determination in 2C that the edge between the
asphalt and turf be improved by establishing a uniform clean, defined edge of pavement
and the establishment of turf in those areas. Absolutely no basis in the PUD Ordinance
or the Carmel Zoning Ordinance exists for this determination. While a straight edge may
be aesthetically pleasing, the Director does not have any authority to make such a
requirement.
4. Section 4B The Applicant appeals the determination in Section 4B. All landscaping
required in these areas under the PUD Ordinance were properly installed and survived for
a period of at least one year. Section 8.2 of the PUD Ordinance states that owners or
their agents are responsible for insuring proper maintenance of project landscaping. This
includes replacing of dead, diseased or overgrown plantings. The Director does not have
the ability and authority to determine that the Applicant and not the HOA is responsible
for the replacement of the landscaping. The responsibility to replace the identified
landscaping is that of the homeowners association, not the Applicant.
5. Section 4C The Applicant appeals the determination in Section 4C. All landscaping
required in these areas under the PUD Ordinance were properly installed and survived for
a period of at least one year. Section 8.2 of the PUD Ordinance states that owners or
their agents are responsible for insuring proper maintenance of project landscaping. This
includes replacing of dead, diseased or overgrown plantings. The Director does not have
the ability and authority to determine that the Applicant and not the HOA is responsible
for the replacement of the landscaping. The responsibility to replace the identified
landscaping is that of the homeowners association, not the Applicant.
6. Section 4D The Applicant appeals the determination in Section 4D. Nowhere in the
PUD Ordinance or the Carmel Zoning Ordinance do any standards exist with respect to
the placement of mulch around shade trees. The Director simply lacks authority to make
any determination, let alone one that splits the cost. A problem may exist and splitting
the cost may even seem like a fair solution to some people, but this completely misses the
point. The Director cannot make such a determination in the first instance since he
cannot make rules or regulations.
7. Sections 5A, 513 and 5C The Applicant appeals the determination in Sections 5A, 513
and 5C. The Director admits in the Letter that, "The PUD Ordinance for the Traditions
does not provide precise design specifications for an irrigation system, nor does it require
a plan submittal from which an objective evaluation can be made." Despite this, the
Director still provides three determinations with no apparent authority. While the PUD
Ordinance does require an irrigation system, standards do not exist and an irrigation
system was installed. Indiana law is clear that development standards or requirements
must be sufficiently definite to be understood with reasonable certainty. The City
Council was certainly allowed to exercise discretion with regard to the development
requirements when the PUD Ordinance was created, but any requirements adopted by the
Council must be sufficiently definite to be understood with reasonable certainty or they
are not enforceable. See, Hendricks County Board of Commissioners v. Rieth -Riley
Construction Company, 868 N.E.2d 844 (Ind. Ct. App. 2007); citing, T. W. Thom Const.,
Inc. v. City of Jeffersonville, j`ersonville, 721 N.E.2d 319, 327 (Ind. Ct. App. 1999). As the Director
admits, this standard was not met in the PUD Ordinance. The Directors determination,
therefore, is arbitrary and capricious since it has no legal basis.
October 18, 2011
Mr. Tony Barbee
PulteGroup.
11590 N. Meridian Street
Suite 530
Carmel, IN 46032
Mr. Robert Potakar
Traditions on the Monon HOA
Smoky Row
Carmel, IN 46032
Re: Traditions on the Monon Zoning and quality construction issues.
Dear Mr. Barbee and Mr. Potokar:
This letter is to inform you of a determination made by the Director of Community Services,
pursuant to the authority granted in Section 29.04 of the Carmel Zoning Ordinance, on the above
referenced matter. I have reviewed in detail the issues surrounding each complaint raised in the
"Traditions on the Monon Defects List" dated of August 29, 2011. After careful review and
analysis, including consultation with DOCS staff, Department of Engineering personnel, and
outside experts, I conclude the following:
1. Banked Parkine Area
A new parking area was constructed by PulteGroup (Pulte) in response to a complaint by the
Traditions HOA (HOA), per their previously submitted "Transition Report" of August 2010,
and subsequent action by the City of Carmel. This parking area was constructed in a location
and of a configuration consistent with the Development Plan for the project. The HOA has
identified in the HOA "Defects List" (Attachment A) four complaints to this parking lot
construction, as follows:
The parking area is not curbed
The parking area needs light pole
The parking areas drainage design should require an overflow curb
The parking area guard rail needs painted
Determination:
A. The parking lot was constructed without curbing pursuant to the Carmel Zoning
Ordinance requirements. It is determined that the developer shall install approximately
one hundred sixty (160) feet of curb along the sides of the eastern part of the lot,
according to the standards of the Department of Engineering.
B. The installation of a light for this area, while helpful for safety and security, is not a
requirement of City ordinances or of the PUD, and shall not be required.
C. The installation of an additional overflow curb adjacent to the retaining wall will not
result in an improvement to the drainage design and shall not be required.
Division of Planning Zoning One Civic Square Carmel, fN 46032.317 5712417
Michael P Hollibaugh, Director
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 2
D. The guard rail design must be completed, including installation of additional segments of
missing rail material, approximately eight (8) boards. An additional coating of black
paint shall be applied to the railing already in existence, with additional paint required for
the newer sections.
Upon completion of the above, the surety in place to ensure proper parking lot installation will
be released
2. Streets and Curbs
A lengthy list of pavement defects was presented by the HOA in the Traditions on the Monon
Transition Report of August 2010. While a number of the defects listed have been repaired
by the developer, there are nine items identified in the HOA "Defects List' of 8/29/11. Since
that list was issued, the Department has found seven items which remain incomplete or
unresolved:
Street Curb cracks 20
Bldg 15 No concrete curb on road end 36 feet
9th Street NW West end north side no curb =114 feet
11th Street NW East end no curb 45 feet
Monon Lane East end no concrete curb 66 feet
Monon Lane No street name sign has been installed
Bldg 7 Finish asphalt top coat missing
Bldg 14,15 Finish asphalt top coat missing
Determination:
A. The presence of 20 remaining cracks in the curbing has been identified and categorized as
to their severity by the City Engineer. The repair of those cracks is essential to the
longevity of the improvement, and for proper conveyance of storm water. The repair of
all curbs with cracks rated as "category 2, 3, 4, and 5" shall be required according to the
standards of the Carmel Department of Engineering.
B. The HOA identified that "finish asphalt top coat is missing from the areas around
Building 7, on 3' Ave. NW, and from the private drive servicing Buildings 14 15.
Finish asphalt has been installed throughout the project, including the areas identified by
the HOA. The addition of more pavement in the area of Building 7 will likely have a
negative effect on drainage in this area, and shall not be required.
However, it is observed that the concrete drives for Building 7 have been installed with a
finished grade approximately 1" above finished pavement, creating a problem for
maintenance, current and future.
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 3
In order to repair this, the driveway pad to each unit in Building 7 shall be reinstalled so
the concrete is flush with the asphalt pavement of the drive lane. This shall be in the form
of an entirely new driveway or a pad renovation by saw cutting and removal of the
existing concrete drive in the location of the mid -point control joint and new pour to
proper elevation.
New concrete driveways shall be poured to be flush with the existing finish asphalt,
consistent with other areas throughout the project.
A similar issue occurs in the area of Building 14 15, where the offset between the
concrete drive and top of asphalt is a maintenance problem and not consistent with the
standard for the property. This is especially evident at Building 14 where the joint
between asphalt and the concrete driveway holds sufficient moisture for moss to grow.
This area shall be repaired by the builder either through milling of existing asphalt and
the laying of new asphalt to the level of the drive, or through the reconstruction of
driveways, as detailed for Building 7.
C. The HOA identified the need to install curbs at the ends of drive lanes in four locations. It
is determined that the pavement design in those areas is per the approved plan for the
project, that the installation of curbs will have a detrimental effect on the conveyance of
storm water in those areas and shall not be required.
However, in the four identified locations the pavement/turf transition, i.e. the edge
between asphalt and turf, shall be improved by establishing a uniform clean, defined edge
of pavement, and through the careful establishment of turf in those areas, including:
proper soil preparation, removal of stones from the soil; placement of additional top soil
as may be required; seed application and mulching with clean straw.
3. Landscaoine and Grounds
A lengthy list of grounds and landscaping issues was presented by the HOA in the
"Traditions on the Monon Transition Report" of August 2010 (Attachment B). While a
number of the issues identified previously by the HOA have been fixed by the developer,
there were nine items identified in the HOA "Defects List' of 8/29/11. Since that list was
issued, there are six HOA items which remain unresolved.
Bldg 21 Sod missing Southwest corner by road
11 street NW Sod missing east end
All Grounds remove all plastic utility warning posts, white, yellow
North Retaining wall back fill with soil and sod 114 ft. x 8 ft.
New East Retaining Wall Insufficient adhesive on cap row
Monon entry sidewalk needs fill dirt on sides
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 4
Determination:
A. The missing sod in the area adjacent to Building 21 was primarily a result of construction
for the overflow parking. Since completion of that construction the irrigation to that area
has been restored and the grass has begun to grow in. It is determined this area, between
Building 7 and Building 20, shall require a comprehensive re- seeding effort by the Pulte
including proper soil preparation, seeding and straw mulch application. This shall occur
following installation of curbing for the new parking area.
B. Other areas throughout the project that shall require a comprehensive re- seeding include:
the area surrounding the new parking lot adjacent to Building 9;
the common area in SE corner of traffic circle (between Buildings 14 and 15);
the lawn area along the eastern side of the subdivision, especially in the common area
east of Building 14;
the end area between Building 16 and 17;
the end area between Building 18 and Building 23.
C. Sod replacement was attempted by Pulte during the summer months in areas where mail
boxes were installed and areas where metal fencing was erected. It is determined that
replacement sod shall be installed by Pulte in areas where it was previously installed and
failed during the dry summer months.
D. Portions of the North Retaining Wall were reconstructed to correct outward shifting. The
HOA Defects List identifies "back fill and sod issues" which, upon inspection, are
unidentifiable and shall not require repair by Pulte.
E. Portions of the East Retaining Wall were reconstructed to correct outward shifting. The
HOA Defects List indentifies insufficient adhesive on the wall's cap row. Our inspection
found at least one cap stone has been removed and left unattached, showing a minimum
amount of adhesive used to complete this repair. Other stones were found to be loose and
easily moved.
The east wall cap row stones shall be repaired by Pulte, including a pre repair inspection
by City and Pulte, and cap stones re- adhered by Pulte per manufacturer's specifications.
F. The HOA has requested the area immediately adjacent to their Monon Greenway egress
walk be filled by Pulte, citing a safety issue. The egress walk is currently a seven foot
wide concrete walk with drainage tile. The filling of the Monon egress point, already
initiated by the HOA, shall not be a requirement of Pulte.
Fill dirt by the HOA must be removed by the HOA, or its installation approved by the
City Engineer and the Parks Department.
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 5
4. Landscape Audit.
A separate landscape audit has been conducted by the Department of Community Services
beginning in November 2010, updated over the course of spring and summer 2011, and
finalized in October 2011. The DOCS audit was used to compare with a similar audit
performed by the Tradition HOA, dated August 2011. Full Landscape inspection reports can
be found in Appendix C.
A. Driveway landscaping Inspection report:
Spec es to MJtm rest
of building
Determination (Driveway plantings):
Replacement by Pulte of missing and dead driveway plant material for all buildings.
Replanting or replacement by Pulte of material noted as improperly installed.
Missing- Dead /Installed Improperly (II)
Bullding 1
3 grass
1 yew
Building 2
2 arborvitae
4 yew (3 ll)
Building 3
2 arborvitae
6 grass
2 yew
Building 4
1 grass
1 yew
Building 5
4 grass
1 yew
Building 6
3 grass
Building 7
Building 8
4 grass
3 yew (3 II)
Building 9
3 grass
Building 10
2 yew (1 II)
Building 11
4 grass
Building 12
Building 13
3 arborvitae
i bayberry
Building 14
2 arborvitae
2 grass
Building 15
2 arborvitae
Building 16
Building 17
2 arborvitae
1 grass
Building 18
1 yew (ill)
Building 19
1 grass
1 yew
Building 20
2 grass
Building 21
Building 22
1 yew
Building 23
TOTALS
13 arborvitae (M -D)
34 grass (M-D)
17 yew(9 M-D)(8 ll) /1 bayberry(1 M -D)
Spec es to MJtm rest
of building
Determination (Driveway plantings):
Replacement by Pulte of missing and dead driveway plant material for all buildings.
Replanting or replacement by Pulte of material noted as improperly installed.
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 6
B. Foundation landscaping Inspection report:
Building 13 2 yew; 1 spirea; 1 weigela
Building 14 2 holly; 4 boxwood; 1 burning bush
Building 15 —1 boxwood; 1 burning bush; 1 spirea; 1 maiden grass; 1 day lily
Building 16 3 yews; 3 spirea
Building 17 —1 weigela; 2 maiden grass
Building 23 —1 burning bush; 1 bayberry
Building 7 —1 barberry
Building 11— 2 barberry
Building 20 —1 boxwood; 1 euonymus; 1 burning bush; 1 spirea
Determination:
Replacement by Pulte of missing and dead plant material installed with construction in 2009
or later; Buildings 23, 17, 16, 15, 14, and 13.
Replacement by Pulte of missing and dead plant material installed with buildings
constructed without irrigation system: Buildings 7, 11, and 20.
C. Common Area Inspection report:
NE Corner (bldg. 23 and 18)
1 crab apple
4 arborvitae
Funeral Home Parking area (bldg. 17 and 16)
5 arborvitae
C.A. SE Corner 3 rd Ave and 10"' Street (bidgs 14 and 15)
1 crab apple
Center Green north half (bldgs 11 and 7)
2 red maple
Building 8 east fagade, south comers)
1 oak
SE Corner (by Duke substation)
6 arborvitae (top of wall)
2 arborvitae (foot of wall)
Determination:
Replacement by Pulte of dead common area plant material noted above.
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 7
D. Tree mulch.
It has been reported by the HOA and observed by DOCS that most shade trees and
ornamental trees have been over mulched, creating a problem described as "volcano
mulch which builds up a high level of mulch around the trunk, which encourages
insects and moisture related maladies.
The practice occurred while the HOA was operated by the developer, and has continued
under the management of the residents. The cost for repair is estimated to be twenty
dollars ($20) per tree.
Determination:
The cost for repair of 110 trees shall be split equally between the HOA and Pulte, amounting
to $1100 each.
E. Mulch bed restoration.
There are many areas across the property where drainage improvements were made at the
HOA's request, involving the removal of black corrugated drainage pipe was removed
from the gutter /downspout drainage system, then replaced with river stone and
downspout troughs.
Across the property are the remnants of this pipe removal which were left unfinished, in
many cases creating erosion channels, but, in general the result is an eight or ten inch
channel which needs to be backfilled and mulched.
Determination:
Pulte shall restore all mulch bed areas where the repair need exists, with a level of detail
indicating care for a quality outcome.
Upon completion of Landscape items A E above, the surety in place to ensure proper landscape
installation will be released.
5. Irrigation System.
A separate Irrigation System audit was conducted by the Department of Community Services
over the course of summer 2011, and finalized in October 2011. The DOCS audit utilized
the August walls -thru; the HOA report titled "Traditions on the Monon Irrigation Repair List"
(the List), personal field observation, the as -built irrigation plan prepared by Irrigation
Design Source for Pulte and general assistance from Automatic Irrigation, Fishers, Indiana.
The List submitted by the HOA following the August walk -thru detailed offered thirty-six
(36) specific recommendations for improvements to each of the forty -three (43) zones in the
system. The List was subsequently reviewed by Pulte who responded by resolving eighteen
(18) of the recommended changes, and concluding that many of the actions were HOA
responsibility, or not required by the PUD.
Mr. Tony Barbee Mr. Robert Potakar
Re: Traditions on the Monon Transition Report Zoning and quality construction issues
Page 8
The PUD ordinance for Traditions does not provide precise design specifications for an
irrigation system, nor does it require a plan submittal from which an objective evaluation can
be made.
The irrigation system audit is complicated by as -built plan which accounts for only forty (40)
zones of the forty -three (43) zones, and does not indicate the recent updates from the parking
construction, and/or subsequent resulting irrigation adjustments.
It is apparent from field inspection and review of the as -built plan the installed irrigation
system provides coverage to the vast majority of the property, including lawn areas and
landscape beds.
There are foundations plantings for buildings 7, 11 and 20 where irrigation conduit exists but
irrigation hardware was not provided. This is in contrast to a community standard for
landscaping foundation areas found at all other buildings within the property.
It is generally observed that the opportunity is without a location where a garden hose may be
used to water common area plants in parts of the property without irrigation, such as along
the eastern edge of the property where a number of plants have been lost likely to drought.
The neighborhood also appears to be challenged by a conflict between pet ownership and
availability of greenspace on the property. There are many areas where the turf and
shrubbery have been damaged by animal urine, as well as areas where animal feces had not
been cleaned. This HOA management issue conflicts with proper landscape maintenance
and degrades the positive effects from the irrigation system, in some cases obfuscates the
system effects completely, and in general undermines efforts to improve the quality of the
landscape.
Determination:
A. Irrigation system shall be installed by Pulte for foundation planting bed, Buildings 7, 11
and 20.
B. The Irrigation As -Built drawing shall be updated by Pulte to include the over -flow
parking areas, the irrigation adjustments, and missing zones, 41, 42 and 43.
C. The irrigation plan may need to be amended, following review of the updated Irrigation
As -built plan to ensure a high level of coverage in the amended areas noted above.
Upon completion of Irrigation System items A C above, the surety in place to ensure a proper
irrigation system installation will be released.
The Director's determinations in this letter may be appealed to the Carmel Board of
Zoning Appeals by you or any other interested party pursuant to Chapter 30.0 of the
21 7/17/11 NW retaining wall has improper placement of geo grid
Buiiding Defects
22 7/1/11 Bldg 7 W end Gas meters hanging at 30 degree angle
23 7/18/11 Bldg 16 W end Gas meter hanging high in bldg window
24 7/14/11 Bldg 7 N end Gas Meter Manifold support missing
25 6/30/11 All Bldgs all Front Door caulking installed incorrectly
26 7/3/11
27 7/18/11
28 7/8/11
All Bldgs front door Threshold no caulk at bottom by concrete
All Bldgs Front Door decks lack sealant by bldg wall
Type
Puite
Traditions on the Monon Defects List
Notes
PUD Violation
Updated 8 29 2011
No.
Date
Defect Description
Not Required
IN OUT
HOA Maintenance
PUD Violation
Not Required
Banked Parking Defects
1
7/20/11
Banked Parking not curbed
2
7/20/11
Banked Parking lot needs Light Pole
3
7/20/11
Banked Parking (catch basin) overflow curb 40 feet
4
7/20/11
Banked Parking Wood Guard Rail Seal Paint coat
Street and Curb Defects
5
7/3/11
10th NW South side by funeral home Sidewalk Crack
6
7/3/11
Street Curb cracks 20
7
7/21/11
Bldg 15 No concrete curb on road end 36 feet
8
7/20/11
9th Street NW West end north side no curb 114 feet
9
7/20/11
11th Street NW East end no curb 45 feet
10
7/20/11
Monon Lane East end no concrete curb 66 feet
11
7/25/11
Monon Lane No Street Name Sign
12
7/3/11
Bldg 7 Finish Asphalt Top Coat missing
13
7/3/11
Bldg 14, 15 Finish Asphalt Top Coat Missing
Grounds Defects
14
7/13/11
Bldg 21 Sod missing Southwest corner by road
15
7/13/11
11 street NW Sod missing east end
16
7/14/11
All Grounds remove all plastic utility warning posts, wht, yellow
17
7/17/11
North Retaining wall back fill with soil and sod 114X8 feet
18
7/20/11
New East Retaining Wall Insufficiet adhesive on cap row
19
7/20/11
Missing Shutters 2 sets of 2 shuttlers each ground floor
20
7/20/11
Monon entry sidewalk needs fill dirt on sides
21 7/17/11 NW retaining wall has improper placement of geo grid
Buiiding Defects
22 7/1/11 Bldg 7 W end Gas meters hanging at 30 degree angle
23 7/18/11 Bldg 16 W end Gas meter hanging high in bldg window
24 7/14/11 Bldg 7 N end Gas Meter Manifold support missing
25 6/30/11 All Bldgs all Front Door caulking installed incorrectly
26 7/3/11
27 7/18/11
28 7/8/11
All Bldgs front door Threshold no caulk at bottom by concrete
All Bldgs Front Door decks lack sealant by bldg wall
Type
Puite
Landscape ISSUE
Notes
PUD Violation
Not Required
PUD Violation
Not Required
Code Violation
Not Required
Quality issue
HOA Maintenance
Quality issue
Complete
Landscape ISSUE
Not Pulte
Quality issue
Responsibility
PUD Violation
Not Required
PUD Violation
Not Required
PUD Violation
Not Required
PUD Violation
Not Required
Quality Issue
Pulte will install
PUD Violation
Complete
PUD Violation
Complete
Landsca a ISSUE
p
soa vnu oe resmtauea as
previously stated. Will
Landscape ISSUE
commence mid to late
Not Pulte
Quality Issue
Responsibility
Code Violation
Is backfilled properly
PUD Violation
Has been re- adhered
If missing, Pulte will
Quality Issue
install
Code Viloaton
Not Required
Carmel perfromed
PUD Violation
construction inspection
Quality issue
Code Violation
Code Violation
Quality issue
Quality issue
Quality issue
Bldg 4,5 2 units Sidewalk cracked (settling from threshold Quality issue
29 7/14/11 Bldg 3 Unit 15 Major foundation Settling /Exterior bldg cracks Code Violation
Meters installed by
utility company not
Pulte responsibility
Meters installed by
utility company not
Pulte responsibility
Meters installed by
utility company not
Pulte responsibility
Not considered by
Pulte to be a building
defect
Not considered by
Pulte to be a building
defect
Warranty Period for
settlement is 2 years
from original closing
date these buildings
are past the warranty
period
Under review issue to
be inspected by a
structural engineer
Cost
to Remedy
3080
5000
880
500
300
2000
792
2508
990
1452
1000
3500
7000
300
200
300
3000
500
200
2000
5000
500
500
200
6300
3150
3150
200
10,000
30 7/14/11
31 7/14/11
32 7/14/11
33 7/19/11
34 7/19/11
35 7/19/11
36 7/25/11
Bldgs 18, 19 Concrete drives have surface flaking
37 7/20/11
Bldgs 4,5,6 Standing water sidewalks and mulch beds
Repairs still in
Bldgs 21,22,23 Standing water, mold, ice on sidewalks
39 7/25/11
progress as we are
40 8/8/11
Relocate 11 satelite Dishes from balconies to Roof
able to gain access to
years of the original
the homes Pulte
buildings are past the
onsite field
Warranty period and
representative is
does not warrant a
sending requests for
repair according to the
Quality Issue
owner contact
Site Drainage is
information to Aleta
warranted by the
Wilson Property
All Bldgs Roof Soil Pipes length
Code Violation
Manager
warranty period for
Complete per HOA
Code Violation
expired.
turnover inspection
All Bldgs Dryer Vent Lint Screens not Removed
Code Violation
item response sheet
Quality Issue
Complete
Complete per HOA
Not Pulte responsibility
turnover inspection
All Bldgs Leaning Furnance Flue Pipes =15 total
Code Violation
item response sheet
missing Pulte will
Quality Issue
Complete per HOA
TOTAL
turnover inspection
All Bldgs HVAC units missing rock (7/18 10 bldg ends noted)
Code Violation
item response sheet
Complete per HOA
turnover inspection
All Bldgs service wiring not bundled, cable tied, 7/18 Total 15
Quality Issue
item response sheet
Cracks exceeding 1/4"
in width will be
Cracked Concrete Drives Bldg1 =3 Bldg 9 =2 Bldg 2 =1 Bldg 11 =1
repaired per the
Warranty during the
first 2 years from the
Quality issue
original closing date.
Bldg 3 =1 Bldg 5 =1 Bldg 6 =2 Bldg 8 =1 Bldg 15 =1 Total =12
Bldgs 18, 19 Concrete drives have surface flaking
37 7/20/11
Bldgs 4,5,6 Standing water sidewalks and mulch beds
38 7/20/11
Bldgs 21,22,23 Standing water, mold, ice on sidewalks
39 7/25/11
All Bldgs Roof fasia boards have "unpainted" bare ends
40 8/8/11
Relocate 11 satelite Dishes from balconies to Roof
41 8/18/11 Bldg13,14 Missing wood Molding Trim on Bay windows
3450
6900
7500
1750
1125
60,000
2000
9386
11268
900
1650
500
170931
Performance Standard
per the Warranty is
50% of the surface
area affected within 2
years of the original
closing date. These
buildings are past the
Warranty period and
severity of the issue
does not warrant a
repair according to the
Quality Issue
performance standard.
Site Drainage is
warranted by the
builder for a period of 2
years. The 2 year
warranty period for
these buildings is
Code Violation
expired.
Agreed upon work
Code Violation
completed
Quality Issue
Complete
Quality Issue
Not Pulte responsibility
New item Pulte will
review and if trim is
missing Pulte will
Quality Issue
install
TOTAL
3450
6900
7500
1750
1125
60,000
2000
9386
11268
900
1650
500
170931
Traditions on the Monon PUD Based Issues
HOA September 2nd, 2010
HOA Transition Report
Carmel PUD Z- 464 -04
Issues 1.0 -1.7
Parking
Section 11
Issue 3.12
Parking Stripping
Section 14.2J
Issues 2.0 -2.1
Irrigation
Section 8
Issue 3.0
East Retaining Wall
Section 14J
Issue 3.1
Drainage
Section 14 J
Issue 3.7
Mailbox Tipping
"Liability"
Issue 3.10
Asphalt Top Coat
Section 14.2J
Issue 3.11
Street Signage
Section 14.2J
Issue 3.13
Culvert Drainage
Section 14.2J
Issue 4.0
Landscaping
Section 8
Issue 4.1
Landscaping
Section 8
Issue 4.2
Proper Planting
Section 8
Issue 4.3
Dead Tree Removal
Section 8.6
Issue 5.0
HOA Accounts Audit
Section 12.1
Issue 5.1
HOA Records Transition Section 12.1
Traditions on the Monon
Planned Unit Development District
Carmel, Indiana
August 18, 2010
Background The Common Council of Carmel Indiana created the Traditions on the Monon as a Planned
Unit Development District on December 20th 2004 Ordinance No.Z464 -04. A complete copy is located in
the Appendix PUD Z464 -04. The development statement presented to the council defined Traditions on
the Monon as "high -end, classic- styled townhome units to be arranged along Intimate streets,
landscaped courtyards, and along the Afonon Trail."
Centex Homes was the original developeribuilder and promptly started construction of the Planned Unit
Development District (PUD). Pulte Homes took ownership of the development/builder role by simple
purchase of Centex's business interests nationwide during fourth quarter 2009. By the spring of 2010
Pulte had functionally assumed their management role at Traditions on the Monon.
On 10/14/05 the Traditions on the Monon Home Owners Association (HOA) had been initiated and
recorded with the State of Indiana. Timothy McMahon of Centex was President of the HOA. Omni
Management Services of Indianapolis Indiana was selected as the HOA company. Omni remains as the
management company currently.
During May of 2010, Omni Management Services notified the Tradition on the Monon homeowners that the
developer's Declarant Control Period had ended based on the percentage of the total town home units now
owned by individuals. At this point the home owners were required to elect per the by -laws a new set of
five officers to manage the HOA. Officers were elected at an official HOA meeting on Thursday May 13th
2010. By July 6th 2010 the new officers were recorded with the State of Indiana Robert Potokar as
President and Victoria Mandras as Secretary.
At this point Pulte Homes had one remaining building of 5-7 units to build. They had completed 17 of the
18 buildings which represented 119 townhome units. The final building, now under construction, will have 7
town home units for a final total of 126 town homes in the PUD.
HOA Transition Process The May 2010 HOA election marked the beginning of a "transition' from a
developer controlled HOA to one controlled by the individual home owners The new HOA Board
immediately found itself deluged with homeowner complaints, questions, and concerns. Obviously and
quite naturally the developer and the homeowners will very often view situations from different perspectives.
This can obviously be accentuated by an environment of slow or inadequate service response to
homeowner's warranty claims or problems as was the case at the Traditions on the Monon development.
The first case in task for the new Board was to request a formal transition process. This would generally be
defined as an organized and formal transfer of the HOA's business such as, but limited to a financial audit,
meetings minutes, key problem areas, legal issues etc. No formal or organized HOA transition was
proactively offered of located. Of greater concern was the lack of any real interest on the part of the
previous HOA officers, Omni Management Services, nor Puke lo develop a formal transition of the HOA's
business.
DevelopedBuilder Build Out Transition Process Concurrent and directly related is the fact that PULTE
homes is in the final build out phase of Traditions on the Monon. With the completion and sales of the units
of Building 13, the development will be finished. Many builder issues had been brought to the attention of
the new Board concerning the condition of the buildings and grounds. Pults Homes was approached to
determine if they again had a formal build out transition process. The answer was no. A walk through
meeting of HOA Officers (Potokar, Sharp) Omni (Andrea Wilson) and the Pulte (Matt Lohmeyer) on May
4N produced a list of 8-10 development wide defects that was all that remained to be done". This was
deemed inadequate and Pulte (Matt Lohmeyer) committed to having an Pulte Area Engineer prepare a
complete punch list the following week. No complete punch list was sent. The Board concluded that even
with the absence of a formal developer transition process upon build out and a builder's prepared punch list
that co- operation in this area was going to be limited on the part of Pults.
It is also important to acknowledge that the City of Carmel has no formal "transition' or "turn over process
for their Planned Unit Development Districts (PUD). We are unable at this time through conversations with
the City of Carmel and City Council to determine how in fact the Tradition on the Monon PUD ordinance is
to be enforced as passed.
Need for Traditions on the Monon DefeetsiDeficiencies Audit Given the situation that no one party was
stepping forward to prepare an audit and a transition process the Board took action. It appears that the
town home owners may find themselves liable, financially and otherwise, to unregulated actions of the
developer and a developer controlled HOA. Therefore, the new HOA Board concluded based on:
the absence any orderly and formal transition process
the discovery from recent Board due diligence
the potential current and future financial exposure of the HOA (home owner's dues)
that the home owners of Traditions on the Monon will required a more formalized audit of all the defects
and deficiencies currently present at the development. This document is the basis and beginning of an
orderly and formal turnover of the development from the builder to the home owners. It is designed to be
useful and promote a positive and healthy dialogue between Pulte Homes, the HOA, and the City of Carmel.
The Audit is organized into five sections for easy discussion and resolution of the issue or deficiency.
Section 1
Parking deficiencies and Congestion
Section 2
Irrigation System Defects
Section 3
Building and Infrastructure Defects
Section 4
Landscaping Plan Defects
Section 5
HOA Funds Management Discrepancies
Appendix
Summary It is genuinely expressed that all of these parties have the same intent In mind to deliver the
community defined in the PUD as "high -end, classic- styled townhome units to be arranged along
Intimate streets, landscaped courtyards, and along the Monon Trail." The intent is that this initial audit
provides a professional approach and base document to achieve our common goal of providing a Carmel
community of which we can be very proud.
Traditions on the Monon HOA Turnover Inspection Items Response Status
Pulte Agreed to Correct
Completion
Description of Issue
Pulte Response
Status
Date
Air Conditioning Units not level do not
Proper clearance specified by manufacturer not met in
Complete
have the proper clearance from buildings
many units throughout the community. Pulte will correct
and other A/C units
this Issue and level the units as the work Is done to
achieve proper clearance. In some areas this will require a
April 11th
Some dryer vents thru roofs have screens
This is a building code violation Pulte will correct this
Complete
March 25th
Furnace flue pipes exiting thru roofs are
Pulte will correct leaning flue pipes and secure
Complete
April 15th
Unbalanced temperatures on lower level of
Pulte has agreed to correct this concern according to the
Work complete In units where
townhome units
Warranty. Any homeowner experiencing this Issue and
service was requested.
feels they are missing a cold air return vent for the lower
Work completed
level of their unit can contact us at 866 -501 -2854 and we
as requests are
will schedule an appointment to evaluat their c oncern.
received
Some plumbing vent pipes thru roof do not
Pulte will correct
Most units are complete. Still
meet the 12" clearance code requirement
have some to correct and on
these we have contacted the
homeowners, but received no
response so we will continue to
try to arrange a time with the
homeowners to make the repalrs.
May 1st
Mailboxes not Installed per manufacturer's
Pulte will change the installation of the mailboxes so that
HOA requested that mailboxes at
specifications
each unit is supported by 2 black metal decorative posts.
round -a -bout be relocated. Pulte
Posts will be attached to a concrete footing extending
agreed to do this. Work is
below the frost depth.
complete
May 1st
Surface drainage between Buildings 17 18
Pulte agreed to add drain tiles from each downspout that
Drain tiles have been installed.
tie Into drain tiles along the sidewalk to collect and carry
water to the storm structures at each end of these
buildings. Surface drains In sodded areas were agreed to
April 11th
Remove bubbler drains buried at
Pulte agreed to do this work to help alleviate the
Bubblers have been removed,
downspout locations and Install landscape
maintenance issue of clogged bubbler drains. Intent is to
landscape stone and splash
rock in the splash area. During on site
allow downspouts to drain without Interference of
blocks are installed. Elbows have
meeting on March 23rd between Tom
bubblers so that the water can drain away from the
been added to the end of
Sharp and Mike Barden Tom requested
buildings. This should also help with the HO A's concern of
downspouts where bubblers were
May 1st
Change downspout locations where
Pulte agreed to correct
Complete
downspouts discharge directly onto front
April 18th
Some sections of brick veneer on Building
Pulte agreed to correct
Complete
#20 need cleaned of excess mortar
March 1st
Loose trim pieces at south dormer of first
Pulte agreed to correct
Complete
April 25th
Replace glass with failed seal at dormer
Pulte agreed to correct
Complete
May 1st
Excess low voltage wiring
Centex installed low voltage wires from the interior of
Complete
each unit to the exterior of the builidng to allow for future
connection by phone cable utility companies. In many
cases the utility company did a sloppy job of connecting
utility wires to wires provided by the Builder. This result is
not the Builder's responsibility and no action will be taken.
For wires provided by Centex that were left unused, Pulte
agrees to have a contractor coil up and zip -tie these wires
to keep them organized, but still available f future
March 25th
Front yard lights are wired without conduit
Puite agreed to correct
Complete
near front entrance east wall
April 15th
Exterior penetrations not properly sealed
Pulte agreed to correct hole In brick veneer noted in photo
Complete
k3 on Inspetion report
March 1st
Gaps in trim near door openings
Pulte agreed to fill excessive gaps with d monic caulking
Complete
April 25th
Concerns Declined b
o"oription of ftsm
Rusting exterior gas piping
to buildings
Add guttering to eyebrows
Buildings for consistency
Pulte
PuRe Response
ran gas meters Rusting exterior gas pipes Is a maintenance item. No
a ction to be taken.
Of
to guttering at roof valley
)ulte acknowledges that guttering throughout the
;ommunity Is Inconsistent, however we feel that adequate
;uttering has been installed to meet the intent of
:ollecting raln water from the roofs of the building and
directing It toward the ground for surface drainage. It is
not uncommon for a builder to make product and design
HOA requested that Pulte add the diverters as a way of
improving the ice build up concern. Ice build up in gutters
Is not something that Pulte is responsible to control, nor
do we aeree that the diverters will Im prove the issue.
Traditions on the Monon Foundation Piantinits
Blda.1- Front and Sides
1- Holly
1- Yew
1- Viburnum
Bldg. 2 Front and Sides
2 Viburnum
Bldg. 4 Front and Sides
1- Burning Bush
Bldg. 6 Front and Sides
1- Holly
5 Morning Light Grass
Bide. 7 Front and Sides
1- Barberry
Bids. 8 Front and Sides
1- Yew
Bide. 10 Front and Sides
1- Yew
2 Boxwood
2 Spirea
Blde.11- Front and Sides
2 Barberry
Bide. 13 Front and Sides
2 -Yew
1 Spirea
1- Weigela
Blde.14 Front and Sides
2 Holly
4 Boxwood
1- Burning Bush
City of Carmel Inspection Report 10/06/11
TRADITIONS ON THE MONON
speaes to match rest
of building
Damazed by Homeowner
Building 6 5 yews
Building 9 2 yews
Missing- Dead /Installed Improperly (II)
Building 1
3 grass
1 yew
Building 2
2 arborvitae
4 yew (3 II)
Building 3
2 arborvitae
6 grass
2 yew
Building 4
1 grass
1 yew
Building 5
4 grass
1 yew
Building 6
3 grass
Building 7
Building 8
4 grass
3 yew (3 II)
Building 9
3 grass
Building 10
2 yew (1 II)
Building 11
4 grass
Building 12
Building 13
3 arborvitae
1 bayberry
Building 14
2 arborvitae
2 grass
Building 15
2 arborvitae
Building 16
Building 17
2 arborvitae
1 grass
Building 18
1 yew (1 II)
Building 19
1 grass
1 yew
Building 20
2 grass
Building 21
Building 22
1 yew
Building 23
TOTALS
10 arborvitae (M -D)
34 grass (M -D)
17 yew(9 M -D)(8 II) /1 bayberry(1 M -D)
speaes to match rest
of building
Damazed by Homeowner
Building 6 5 yews
Building 9 2 yews
Traditions on the Monon Common Area Plantinas
N.E. Corner behind Funeral Home
1 -Crab
4 Emerald Green Arborvitae
Funeral Home Parking Lot
5 Emerald Green Arborvitae
C.A. Between Bldg. 14 15
1- Crab
Building 8, Both Corners
2 Oaks, 3 -4" Older Trees
'West of Power Station
6 arborvitae above wall
2 Arborvitae below wall
1 arborvitae on south end (not newer planting)
All Trees need to be adjusted for "Volcano" Mulch
`Additional location per Daren Mindham, City of Carmel
Traditons on the Monon Irrigation Repair List
Zone Description
Parts
Action
Pulte Notes
1
Add 1 Head to west end by unit 101
1- 4" Head
Pulte to look at
Complete
1 -30' Van Nozzle
2
ok
3
Change spacing on 6 heads
20 Feet Swing pipe
wish list
Not Pulte responsibility
4
Add 2 Heads to East end of zone
2 -4" heads
Pulte to look at
Not Pulte responsibility
Straighten heads throughout zone
2 -12' Van Nozzles
5
Add 1 Head to west end by roadway
14" head
done
Complete
Change 10 nozzles to Van Sprays
11 -12' Van Nozzles
6
Adjust 8 heads to face landscape beds
pulte to verify problem
Not Pulte responsibility
7
Adjust nozzles to redirect pressure to low
Pulte to look at
Not Pulte responsibility
pressure areas
8
Add 1 Head on southeast corner
1 -4" head
Pulte to look at
Pulte will add
1 -12' Van nozzle
Change 4 nozzles by sidewalk to SST sprays
4 -15' SST Nozzles
up to hoa
Not Pulte responsibility
9
ok
10
ok
11
Add 3 Heads to make up coverage in front of sign
3- 4" Heads
done
Complete
by road
3- 12' Van Nozzles
12
Turn 6 Nozzles down facing landscape beds
pulte to verify with hoa
Not Pulte responsibility
13
Adjust 6 Heads to throw staright out not upward
Not Pulte responsibility
14
Add New Zone to incorporate half of zone 43 as
200 LF 1" pipe
pulte to verify with hoa
Not Pulte responsibility
well.
1- 1" Valve
Reconnect Zone 14 to go infront of building and
1- Large Valve box cover
east end turf
1- Decoder
Misc Fittings
Pulte to look at "nozzle
Pulte has verified that the
nozzle type installed is
spec" rather than
d m
appropriate and may require
15
Separate zone so that North and South end are tog
240 LF Pipe
seperate
adjustment by HOA
removing landscape beds from zone line.
Misc Fittings
Pulte has verified that the
Pulte to look at "nozzle
nozzle type installed is
spec" rather than
appropriate and may require
16
Add Landscape zone from 15 to zone 16.
40 LF 1" Pipe
seperate
adjustment by HOA
1.1" Valve
1 -Large Valve box cover
1- Decoder
Misc Fittings
Pulte has verified that the
Pulte to look at "nozzle nozzle type installed is
spec" rather than appropriate and may require
17 Add a zone to make North and South turf beds tog- 160 LF 1" Pipe seperate adjustment by HOA
Separate zone for landscape bed 1.1" Valve
1 -Large Valve box cover
1- Decoder
Misc Fittings
18 Add a zone to make West end of building be one z(120 LF 1" Pipe
South and East of building a second zone 1 -1" Valve
1 -Large Valve box cover
1- Decoder
Misc Fittings
19 ok
20 Adjust 8 heads to spray water appropriately
21 Add Head on Southeast corner, move head on Sou 1- 4" Head
corner of island 1 -12' Van Nozzle
15' Swing Pipe
22 ok
23 Check decoder to find out why zone is not working.
Adjust nozzles to get even spray throughout zone
24 ok
Pulte to look at "nozzle Pulte has verified that the
spec" rather than nozzle type installed is
seperate appropriate and may require
adjustment by HOA
done
Pulte to look at
Now working, replaced
decoder
Complete
Not Pulte responsibility
Complete
25 Add zone to split North and South of center park a+ 160 LF 1" Pipe
Adjust 6 heads to get proper coverage 1 -1" Valve Pulte to look at "nozzle
Pulte has verified that the
Move 2 heads on south end to other side of landsc 1- Large Valve Box Cover spec" rather than seperate
nozzle type installed is
1- Decoder
appropriate and may require
30' Swing Pipe
adjustment by HOA
Misc Fittings
26 ok
27 Connect North end of zone 28 to 27 (to help water 60 LF 1" Pipe
Adjust 5 heads to get proper water coverage Misc Fittings
28 Connect North end of zone to zone 27 20 LF 1" Pipe
Adjust 7 heads to get proper water coverage Misc Fittings
29 ok
30 Adjust 4 Heads for proper coverage
31 Adjust 3 Heads for proper coverage
32 ok
33 Reconnect island bed to southeast corner and chec 20 LF 1" Pipe
Misc Fittings
34 Add 1 Head on northside find out why zone not we 1- 4" Head
1 -10' Van Nozzle
up to HOA
up to HOA
reconfigured for new
parking area
reconfigured for new
parking area
done
Pulte to look at
Not Pulte responsibility
Not Pulte Responsibility
Complete
Complete
Complete
Complete
Mulch bed irrigation is not a
PUD requirement
35 Lawn areas ok, add one zone for landscape beds of 180 LF 1" Pipe Pulte to look at
of building 1 -1" Valve
1- Large Valve Cover Box
1- Decoder
12- 6" Heads
12 -12' Van Nozzles
24' Swing Pipe
24- Barbed 90's
Misc Fittings
36 ok
37 Find out why zone is not working. Other damages 13 Rotors
now working
Complete
Add 3 Rotors to cover area on top of hillside by new parking
40 LF 1" Pipe
6 barbed 90's
Misc Fittings
Mulch bed irrigation is not a
38 Add zone for landscape beds on south side of builc 160 LF 1" Pipe
Pulte will look at
PUD requirement
Add Heads to East side of building for lawn coveral 6- 4" Heads
done
Find out why zone is not working 6 -12' Van Nozzles
done
1- Decoder
1- Large Valve Cover Box
12- Barbed 90's
12' Swing Pipe
1- 1" Valve
Misc Fittings
39 Find out why zone is not working, other damages possible
no 'zone 39' in system
No Zone 39 exists
40 Add zone for landscape bed west of unit 130 and s 100 LF 1" Pipe Pulte will look at
into two zones 1 -1" Valve
Find out why zone is not working. Other 1- Decoder
damages possible 1- Large Valve Cover Box
6- 4" Heads
6 -12' Van Nozzles
12- Barbed 90's
12' Swing Pipe
Misc Fittings
41 Find out why zone is not working. Other damages possible
42 Add zone to west side of builing for landscape bed: 120 LF 1" Pipe
zone into two zones. Find out why zone not workir 1 -1" Valve
1- Decoder
1- Large Valve Cover Box
6- 4" Heads
6 -12' Van Nozzles
12- Barbed 90's
12' Swing Pipe
Misc Fittings
43 Added valve on zone 14 to remove heads from zon 120 LF 1" Pipe
to valve Misc Fittings
44 Add 1 valves and split East from Westside zones. A 260 LF 1" Pipe
landscape beds on north and westside of building 18- 6" Heads
18- 30' Van Nozzles
2- 1" Valves
1- Large Valve Cover Box
28 Barbed 90's
28' Swing Pipe
Misc Fittings
Pulte will look at
Pulte will look at
Mulch bed irrigation is not a
PUD requirement
Complete
Zone works
Mulch bed irrigation is not a
PUD requirement
will call Keith to interpret Zone works
will call Keith to interpret Zone Works
Mulch bed irrigation is not a
PUD requirement
Clock Install Rain Sensor Check System for Fault, there Rain Sensor up to HOA
gurantee this will solve the problem (testing only)
There is no system fault. The
alternating green -to -red light
indicates proper function.
IK'