Outback Steakhouse
West Carmel Commons Lot 1
10222 N. Michigan Road
Carmel, Indiana 46032
HYDROLOGY HYDRAULIC ANALYSIS AND REPORT
PROFESSIONAL CERTIFICATION
0 0111111111/1/ /6 1
NO.
10200392
-o STATE
The following report and accompanying computations have been developed by me or
under my direct supervision.
WEIHF
ENGINEERS
Land StIrveying I Civil Engineering
Landscape Architecture
Build with confidencef
Drainage Summary and Calculations
For:
Outback Steakhouse
West Carmel Commons Lot 1
10222 N. Michigan Road
Carmel, Indiana 46032
Project #W11.0655
Prepared For:
OSI Restaurant Partners LLC.
2202 N. West Shore Blvd., Suite 500
Tampa, Florida 33607
Telephone: (813) 282-1225
Contact Person: Stacy Miller
Prepared By: James Wm. O'Bara
Checked By: Eric Carter, RLA
Certified By: James K. Shinneman. P.E.
Date:
December 23, 2011
Revised:
UP WEIHE
ENGINEERS
LE■nd Surveying l Civil Engineering
Landscape Architecturc:
Build will' conlidence'!
Hydraulic Report (Project Narrative)
Location Map Aerial
Existing Conditions:
Existing Watershed Exhibit
Existing Release Rates (West East)
Engineering Data
Soils Mapping
o Soils Classification
Storm Sewers
Storm Sewer Watershed
Storm sewer Analysis
Water Quality
Water Quality Analysis
Operation and Manual
Outback Steakhouse
West Carmel Commons Lot 1
10222 N. Michigan Road
Carmel, Indiana 46032
JOB.# W11.0655
Section 1
Section 2
Section 3
Section 4
Section 5
WEIHI-1,
ENGINEERS
Land Surveyinci 1 Civil Eirigineering
Landscape Architecture
Build with confidence'.'
e Hydraulic Report (Project Narrative)
Outback Steakhouse
West Carmel Commons Lot 1
10222 N. Michigan Road
Carmel, Indiana 46032
JOB.# W11.0655
Section 1
WEIH [I,
James K. Shinneman, P.E.
Indiana Registration No. PE10200392
ENGINEERS
Land Surveying I Civil Engineering
Landscape Architecture
Build with confideucef
Outback Steakhouse
West Carmel Commons Lot 1
10222 N. Michigan Road
Carmel, Indiana 46032
HYDROLOGY HYDRAULIC ANALYSIS AND REPORT
PROFESSIONAL CERTIFICATION
The following report and accompanying computations have been developed by me or
under my direct supervision.
W1
ENGINEERS
Land Surveying I Civil Engineering
Landscape Architecture
Build with confidence`
Drainage Summary and Calculations
For:
Outback Steakhouse
West Carmel Commons Lot 1
10222 N. Michigan Road
Carmel, Indiana 46032
Project #W11.0655
Prepared For:
OSI Restaurant Partners LLC.
2202 N. West Shore Blvd., Suite 500
Tampa, Florida 33607
Telephone: (813) 282-1225
Contact Person: Stacy Miller
Prepared By: James Wm. O'Bara
Checked By: Eric Carter, RLA
Certified By: James K. Shinneman. P.E.
Date:
December 23, 2011
Revised:
Project Narrative:
Existing Conditions:
WFIHN
ENGINEERS
Land Surveying I Civil Engine
Landscape Architecture
Build with confidence`.'
Prepared For:
Outback Steakhouse
West Carmel Commons Lot 1
10222 N. Michigan Road
Carmel, Indiana 46032
JOB# W11.0655
OSI Restaurant Partners, LLC., of Tampa, Florida, is proposing the new construction of
an Outback Steakhouse at 10222 North Michigan Road in Carmel Indiana. Said location
is on a site at a Latitude of N 39° 55' 56.424" and Longitude W 86° 14' 10.679 Located
in Clay Township, the proposed Outback Steakhouse is more specifically in the
Northwest Quarter of Section 07, Township 17 North, and Range 3 East, Hamilton
County Indiana. This parcel will be part of the West Carmel Commons Commercial
Subdivision, currently being platted by its owners, Thompson Thrift Development Inc. of
Carmel, Indiana.
This report is an investigation relative to the proposed storm drainage facilities necessary
to convey drainage and water quality that will be implemented on site. The necessary
retention/detention for the site will be located offsite to the west of the proposed Outback
Steakhouse site. The regional retention/detention facilities will be designed by Roger
Ward Engineering of Indianapolis, Indiana.
The proposed runoff from the Outback site and some offsite area from the north
(approximately 1.73 acres) will be routed to the west via storm sewers and controlled to
permissible discharges within the regional retention/detention facility. Approximately
0.78 acres that used to drain to Michigan Road will be reduced to 0.35 acres to the right
of -way of Michigan Road.
An offline mechanical BMP, is proposed for water quality on the Outback site. A
common, second BMP will be designed by Roger Ward Engineering in the regional
retention/detention facility.
The existing soils for the overall Outback parcel, is a combination of a Br Brookston
and CrA Crosby Silt Loam type soils.
10505 N. College Ave 1 Indianapolis, IN 46280 1 www.weihe.net 1 (317) 846 -6611 1 (800) 452 -6408 1 Fax: (317) 843 -0546
Allan H. Weihe, F.E., L.S. Founder
Proposed Conditions:
UP WEIHE
ENGINEERS
The existing site was previously residentially developed; however all the existing
buildings have been razed for the future commercial development.
Based upon IDS software, which includes a topographic survey of the Hamilton County
Surveyors Office depicting the existing conditions and previous locations of the existing
structures on the intended parcels, it was determined that based upon 0.67 acres onsite
and 0.11 acres offsite, a total of 0.78 acres drained to the right -of way of Michigan Road.
Based upon Manning equation, the following existing discharges were calculated:
2 -Year Existing 0.64 cfs
10 -Year Existing 0.84 cfs
50 -Year Existing 1.11 cfs
The pre developed runoff coefficient for the area draining to the Michigan Road right -of-
way depicted above was 0.297, with a watershed area of 0.78 Acres (Onsite and Offsite).
The regional storm water management area will control the runoff from the proposed
Outback building and parking areas. The impervious surfaces of the Outback site (1.73
acres) shall drain west to a manhole being placed by others along the west property line.
The 0.78 acre area that currently drains to Michigan Road will be reduced to 0.35 acres
and contain grass area from the offsite northern property as well as a grass Swale around
the north and east sides of the proposed Outback building. A short portion of the drive
off of Michigan Road will also drain to the existing beehive inlet for Michigan Road.
The following proposed discharges were calculated to discharge into the existing storm
beehive inlet at Michigan Road.
The post developed runoff coefficient depicted above was 0.339, with a watershed area
of 0.35 Acres (Onsite and Offsite).
Based upon the pre and post conditions, the results of the following release rates east to
the Michigan Road beehive inlet are based upon INDOT Standards.
Proposed
2 -Year Proposed 0.38 cfs
10 -Year Proposed 0.51 cfs
50 -Year Proposed 0.67 cfs
Prop. 50 Year 0.67 cfs
Permissible
Ex. 10 Year
0.84 cfs
Storm Sewer Analysis:
Technical Considerations
WEIHE
ENGINEERS
Based upon information from Roger Ward Engineering, the anticipated 100 year
fluctuation of the retention/detention facilities will occur at an elevation of 892.03 feet.
This would indicate a potential backup of storm water into the Outback Steakhouse pipes.
In the analyses of the storm sewers, a 10 -year design was utilized, with a minimum
velocity of 2.5 fps. Those velocities depicted in the drainage summaries that are below
the 2.5 fps for a twelve (12) inch RCP Storm sewer; normally maintain the acceptable
velocities when running full pipe flow.
In the design of the site, certain items could not adhere to the Technical Standards
Manual for the City of Carmel, Indiana. For example, the 0.1 -foot elevation drop within
the manholes could not be maintained. The minimum cover is less than the Technical
Standards recommendation as well. Therefore, we respectfully request a variance from
the strict adherence to the standards due to practical difficulties of elevation of the
approved outlet for the overall development.
Water Quality:
Water quality treatment will be provided for the 1.73 acres of including the onsite and
offsite. Water quality will be managed via a BMP mechanical unit, which will provide for
the first flush. This unit will be constructed at the downstream end of the internal storm
water, upstream of where the storm sewer discharges into the existing storm sewer
proposed by others.
Based upon water quality requirements of a one -inch precipitation, the following for
BMP Water quality unit is proposed Aqua -Swirl AS -3.
The second water quality BMP which will serve the Outback Steakhouse site will be
provided within the regional detention/retention facility designed by others.
H: \11 \W 110665rp0111 °1311
jo'b /jks 12/19/11
IFF WF,IH1
ENGINEERS
Land Su rveyina Civil Engineering
Landscape Architecture
Build with confidence':
Outback Steakhouse
West Carmel Commons Lot 1
10222 N. Michigan Road
Carmel, Indiana 46032
JOB.# W11.0655
o Location Map Aerial Section 2
Aqua-Swirl BMP's
Operations and Maintenance Manual
For:
Outback Steakhouse
West Carmel Commons Lot 1
10222 N. Michigan Road
Carmel, Indiana 46032
Project #W11.0655
Prepared For:
OSI Restaurant Partners LLC.
2202 N. West Shore Blvd., Suite 500
Tampa, Florida 33607
Contact Person: Stacy Miller
Telephone: (813) 282-1225
Prepared By: James Wm. O'Bara
Checked By: Eric Carter RLA
Certified By: James K. Shinneman. P.E.
Date:
23 December 2011
Revised:
Definitions
BMP- Best management practices refer to structural or non structural measures designed
for the benefit of water quality and quantity.
BMP owner- The owner of the BMP, typically the property owner. The BMP owner may
also be the lessee of property in the case of long -term leases of commercial and industrial
zoned properties. The lessee is considered the BMP owner only if the lease specifically
states that construction by the lessee must meet applicable local codes and regulations.
Purpose and Specific Narrative
For: Outback Steakhouse
West Carmel Commons Lot 1
10222 N. Michigan Road
Carmel, Indiana 46032
Owner Contact Information:
OSI Restaurant Partners LLC.
2202 N. West Shore Blvd., Suite 500
Tampa, Florida 33607
Telephone: (813) 282 -1225
Contact Person: Stacy Miller
It is recognized that developed areas, as compared to undeveloped areas, generally have
increased imperviousness, decreased infiltration rates, increased runoff rates, and
increased concentrations of pollutants such as fertilizers, herbicides, greases, oil, salts and
other pollutants. As new development and re- development continues in the City of
Carmel, measures must be taken to intercept and filter pollutants from stormwater runoff
prior to reaching regional creeks, streams, and rivers. Through the use of Best
Management Practices (BMP), stormwater runoff will be filtered and harmful amounts of
sediment, nutrients, and contaminants will be removed. The City of Carmel has
established a minimum standard that the measurement of the effectiveness of the control
of stormwater quality will be based on the management of Total Suspended Solids (TSS).
After the approval of the stormwater management permit by the City of Carmel and the
commencement of construction activities, the City of Carmel has the authority to conduct
inspections of the work being done to ensure full compliance with the provisions of this
chapter, this document, and the terms and conditions of the approved permit.
Stormwater quality facilities shall be maintained in good condition, in accordance with
the Operation and Maintenance procedures and schedules listed in the Indiana
Stormwater Quality Manual or this document, and /or the terms and conditions of the
approved stormwater permit, and shall not be subsequently altered, revised, or replaced
except in accordance with the approved stormwater permit, or in accordance with
approved amendments or revisions in the permit. Checklists provided in this O &M
Manual must be completed and maintained by the owner.
The City of Carmel also has the authority to perform long -term, post construction
inspection of all public or privately owned stormwater quality facilities. The inspections
will follow the operation and maintenance procedures included in this document and /or
permit application for each specific BMP. The inspection will cover physical conditions,
available water quality storage capacity and the operational condition of key facility
elements. Noted deficiencies and recommended corrective action will be included in an
inspection report.
Best management practices (BMPs), both structural and non structural, can reduce the
amount of pollutants in stormwater. This site will utilize an offline AquaSwirl Model
AS -3 unit.
Owner Acknowledgment
This Operation and Maintenance Manual is submitted to the City of Carmel with the
intent to insure the longevity and adequate functioning of the BMP's owned by OSI
Restaurant Partners LLC. By submitting this Operation and Maintenance Manual to the
City of Carmel's Office the BMP owner noted above agrees to follow and abide by the
inspection schedule and maintenance activities listed in this manual. The BMP owner
noted above is responsible for any additional maintenance and/or repair activities to
maintain the function and longevity of the BMP(s).
Owner Signature: Date
Printed
SS:
COUNTY OF HAMILTON
STATE OF INDIANA
BEFORE ME, the undersigned, a Notary Public in and for said County and State,
personally appeared Owners, /Agent,
subscribed and sworn before me this day of
County of Residence Signature
Commission Expiration Date Printed Name
Aqua -Swirl TM
Operation, Maintenance, and Inspection Manual for BMP Owners
City of Carmel, Indiana
(Note: Attach certifications for local regulatory authority including any applicable fees.)
Site Name: Outback Steakhouse
Owner Name:
Owner Address:
Owner Phone Number:
Emergency Phone Number:
Location:
Date:
Time:
Inspector Name:
Figure 1
OSI Restaurant Partners LLC.
2202 N. West Shore Blvd., Suite 500 Tampa, Florida 33607
(813) 282 -1225
10222 N. Michigan Road Carmel, Indiana 46032
Floatable Debris and Oil
1. Remove manhole lid to expose liquid surface of Aqua- Swirl
2. Remove floatable debris with basket or net if any is present.
3. If a hydrocarbon spill has occurred, (e.g. more than a sheen of oil or gas is present) the system should be cleaned immediately
(see "Cleaning" Figure 3).
Note: Water in an Aqua- SwirI can appear black like oil due to the dark body of the surrounding structure. Oil appears
darker than water in the system and is usually accompanied by debris (e.g. Styrofoam, etc.) with obvious signs of oil stains.
The depth of oil can be measured with an oil /water interface probe, a stadia rod with water phylic paste,
a coliwasa, or by simply collecting a representative sample with a jar attached to a rod.
4. If hydrocarbon absorbant floc or pads are used, these should be inspected to determine whether they are loaded with
hydrocarbons. This will be indicated by a dark colaration of the pad or floc. Pads and /or floc should be removed and
disposed of in accordance with City of Indianapolis and any applicable state and /or federal laws if they contain hydrocarbons.
Sediment Accumulation
Lower a dipstick tube equipped with a ball valve (e.g. Sludge Judge or similar device) into Aqua- Swirl through the service access provided.
Measure the depth of the sludge. At a maximum, the sludge should not exceed 36" depth before maintenance. See Figures 1 and 2.
Site and Owner Information
Maintenance Items
Inspection
36"
Aqua- SwirI 0 and M Manual
Page 1
Change in ownership since last inspection? Y N
Figure 2
Remove sediments, oils and other
floatable pollutants with a vactor. Dispose of all waste in
accordance with City of Indianapolis and any applicable state,
and /or federal requirements.
Oil should be pumped and removed with any liquids and
sediments that have been trapped in the system.
These liquids should be taken to an industrial waste water
treatment facility for treatment. Liquids and solids pumped from
the AquaSwirl should not be dumped back into the
stormwater system or into a sanitary sewer.
nspection (continued)
eanin
Maintenance Schedules
Bypass Structures
Bypass structures should be inspected whenever the AquaSwirl is inspected and maintained as needed.
Aqua- SwirI 0 and M Manual
Page 2
Diversion Structures
If an external diversion structure is present on the site, this should be inspected for the following items.
1. Inspect weir or other structure for structural decay or damage. Weirs are more susceptible to damage than off -set piping and should
be checked to confirm that they are not crumbling or decaying.
2. Inspect diversion structure and by -pass piping for signs of structural damage or blockage from debris or sediment accumulation.
3. Measure elevations on diversion weir or piping to ensure it is consistent with site plan design.
4. Inspect downstream structure in diversion system for signs of blockage or structural failure.
Figure 3
Note: The AquaSwirl is designed so that entry to the system is not necessary for inspection or maintenance. If, however,
you wish to enter the system, this is an OSHA confined space entry and OSHA confined space entry procedures should be followed
to enter the system.
During Construction
Inspect the AquaSwirl every three months (minimum) and clean the system as needed. The AquaSwirl should be inspected and
cleaned at the end of construction regardless of whether it has reached its sediment or oil storage capacity.
First Year Post Construction
Inspect the AquaSwirl every six months and clean the system as needed.
Inspect and clean the system at least once bi- annually regardless of whether it has reached its sediment or floatable pollutant storage capacity.
Second and Subsequent Years Post Construction
If the AquaSwirl did not reach full sediment or floatable pollutant capacity in the First Year Post Construction,
the system can be inspected once annually and cleaned as need or bi- annually at a minimum.
If the AquaSwirl reached full sediment or floatable pollutant capacity in less than 12 months in the First Year Post Construction,
the system should be inspected once every six months and cleaned as needed. The AquaSwirl should be cleaned
at least bi- annually regardless of whether it reaches its sediment or floatable pollutant capacity.
AQUA- SWIRL SPECIFICATION NOTES
1. Manufacturer shall be responsible for
complete assembly of Swirl Concentrator.
2. Swirl Concentrator shall be fabricated from
high density polyethylene (HDPE) ASTM F
714 cell class 345464C per ASTM D 3350.
The Swirl Concentrator wall (greater than 54"
OD) shall be fabricated from profile wall
HDPE ASTM F 894 RSC 250.
3. HDPE stub outs and internal components
shall be extrusion welded using accepted
welding practices. Stub outs shall be
supplied by Manufacturer and welded on
inside and outside.
4. If lifting eyes disturb grade elevation (rim)
or concrete pad rebar alignment, they may
be cut in field after installation of Swirl
Concentrator by Contractor.
5. Manufacturer shall supply direct access to
Swirl Concentrator via 32 -inch OD riser(s),
which can be field cut to match finished
grade by Contractor.
6. Contractor shall supply pipe couplings to
and from Swirl Concentrator, which shall be
Fernco or Mission style neoprene boot with
stainless steel tension bands and shear
guard.
For corrugated plastic pipe, or pipe with a
diameter of 24" or larger, it is recommended
that Contractor use a Mar Mac coupling
(www.marmac.com), or equal, with adhesive
mastic and tightening bands to create a
watertight seal around the joint. The joint
shall then be immobilized with a concrete
collar with compacted base as described in
either Note 11 or 12 herein. Mar Mac, or
equal, couplings shall overlap the pipe joint a
minimum of 1 foot on either side.
7. Contractor shall prepare excavation and
off -load Swirl Concentrator. Contractor is
responsible for bedding and backfill around
Swirl Concentrator as detailed on site plan.
(see notes 11 and 12)
8. Manufacturer shall supply standard
manhole frame(s) and cover(s). (Traffic
rated H20)
9. Where traffic loading (H -20) is required or
anticipated, a reinforced concrete pad must
be placed over the Swirl Concentrator per
concrete design as calculated by Engineer.
For systems where the depth from grade to
the roof of the chamber is greater than the
radius of the chamber, only a 5' X 5' re-
enforced concrete pad is necessary. For
shallower burials, a pad extending over the
entire chamber is required. Sample of typical
concrete design detail is available upon
request.
10. Unless other traffic barriers are present,
bollards shall be placed around access risers
in non traffic areas to prevent inadvertent
loading by maintenance vehicles. Sample of
typical bollard installation detail and
recommended locations of bollards around
the Swirl Concentrator can be provided upon
request.
11. Excavation and Bedding The trench and
trench bottom shall be constructed in
accordance with ASTM D -2321, Section 6,
Trench Excavation, and Section 7,
Installation. The HDPE Swirl Concentrator
shall be installed on a stable base consisting
of 12- inches of Class I stone materials as
defined by ASTM D2321, Section 5,
Materials, and compacted to 95% proctor
density. All required safety precautions for
Swirl Concentrator installation are the
responsibility of the Contractor.
12. Backfill Requirements Backfill materials
shall be Class I Stone or Class II materials
(well graded gravels, gravelly sands; contains
little or no fines), as defined by ASTM D2321,
Section 5, Materials, and compacted to 90%
proctor density. Class I stone is preferred.
Backfill and bedding materials shall be free of
debris. Backfilling shall conform to ASTM
F1759, Section 4.2, "Design Assumptions
Backfill shall extend at least 42 inches
outward from Swirl Concentrator and for the
full height of the Swirl Concentrator
(including riser(s)) extending laterally to
undisturbed soils.