HomeMy WebLinkAboutReith RIley/CO 6/inc 30,947.66/106th St Path-Mich to Ditch CITY OF CARMEL TO: Engineering Department CONTRACT CHANGE ORDER NO.: 6 FINAL CHANGE ORDER One Civic Square DATE:January 18, 2011 Carmel, IN 46032 PROJECT NAME: #09-05 106th St. Path Michigan Rd. to Ditch Rd. CITY REQ. NO.: CITY PO NO.: #27441 CITY PO DATE: 7/21/2010 I. You are directed to make the following changes in this Contract: See Attached Exhibit A 1.11143-4A SCHEDULED ADJUSTMENT bZ•tt ITEM AMOUNT OR DAYS See Attached Change Order Table $30,947.66 0 Days 11. The following referenced Documents further describe the changes outlined in Paragraph 1, and are to be considered a part of this Change Order: Other: The changes result in the following adjustment of Contract Price and Contract Cann Price prior to this Change Order $886,545.50 Contract Price will belnereased/decreased by this Change Order $30,947.66 New Contract Price including this Change Order $917,493.16 Contract Time prior to this Change Order 168 Days 7/23/2011 Completion Date Net increasedldecreased resulting from.this Change Order 0 Days Current Contract Time ineluding this Change Order 168 Days 7/23/2011 Completion Date This Change Order is for full and final settlement of all direct; indirect, impact costs and time extensions incurred at any time resulting from the performance of the changecrwork. The Above Changes Are The Above Changes Are Approved Recominended Accepted CROSSROAD ENGINEERS Rieth-Riley Construction Co. ENGINEER CONTRACTOR an_es .r tar r 3417 Sherman Drive 1751 W. Minnesota Address Address 210v 't.. el Mc iide, Ci1 ngi ,er Beech Grove. IN 46107 Indianapolis, IN 46221 City/State/Zip City/State/Zip Ma Bur.—: Member fir Lo j W. on, Member By:Derrick Bye :John Wischme er Al I "'ST: Area Manager Phone: 317-780-1555 Phone: 317-634-556 iana Cordra Arr erk-ireasurer Date: .2/7/ Date: .2 /714,) Date: 3- 7-12/ CITY OF CARMEL 106th Street Path Michigan Road to Ditch Road Project 09 -05 CHANGE ORDER TABLE #6 (FINAL CHANGE ORDER) ORIGINAL ORIGINAL FINAL FINAL ITEM NO. DESCRIPTION UNIT PRICE QUANTITY AMOUNT QUANTITY AMOUNT OVER /UNDER 1 Mobilization /Demobilization $33,000.00 1 $33,000.00 1 $33,000.00 $0.00 2 Maintenance of Traffic $26,000.00 1 $26,000.00 1 $26,000.00 $0.00 3 Clearing Right of Way $38,188.16 1 $38,188.16 1 $38,188.16 $0.00 4 Tree Removal $22,850.00 1 $22,850.00 1 $22,850.00 $0.00 5 Linear Ditch Grading $14.00 4142 $57,988.00 4142 $57,988.00 $0.00 6 Linear Grading for Path $10.30 12180.51 $125,459.25 12180.51 $125,459.25 $0.00 7 Manhole, Type C $2,500.00 1 $2,500.00 1 $2,500.00 $0.00 8 Concrete Pipe Catch Basin, 18" $1,200.00 2 $2,400.00 2 $2,400.00 $0.00 9 4" HDPE $56.00 61 $3,416.00 61 $3,416.00 $0.00 10 12" CMP $51.00 37 $1,887.00 37 $1,887.00 $0.00 11 12" RCP $44.00 116 $5,104.00 116 $5,104.00 $0.00 12 12" Concrete Pipe End Section $827.00 4 $3,308.00 4 $3,308.00 $0.00 13 71" x 47" Elliptical CMP $130.00 34 $4,420.00 34 $4,420.00 $0.00 14 Mechanically Core Existing Structure $960.00 3 $2,880.00 3 $2,880.00 $0.00 15 Str. #15 Relocation $2,000.00 1 $2,000.00 1 $2,000.00 $0.00 16 Reinforced Concrete Headwall $11,000.00 3 $33,000.00 3 $33,000.00 $0.00 17 Handrail $315.00 105 $33,075.00 121.54 $38,285.10 $5,210.10 18 B- Borrow for Structure Backfill $21.00 116.1 $2,438.10 116.1 $2,438.10 $0.00 19 Rip Rap, Revetment, Maximum 6 IN. $45.50 291.74 $13,274.17 291.74 $13,274.17 $0.00 20 Replace Casting and Adjust to Grade $625.00 13 $8,125.00 13 $8,125.00 $0.00 21 Str. #11, Adjust to Grade $210.00 0 $0.00 0 $0.00 $0.00 22 Utility Manhole, Adjust to Grade $210.00 2 $420.00 2 $420.00 $0.00 23 Sanitary Manhole, Adjust to Grade $210.00 2 $420.00 2 $420.00 $0.00 24 Water Valve, Adjust to Grade $210.00 23 $4,830.00 23 $4,830.00 $0.00 25 Sprinkler Heads, Remove and Relocate $2,700.00 0 $0.00 0 $0.00 $0.00 26 Sanitary Cleanout Relocation $3,500.00 0 $0.00 0 $0.00 $0.00 27 HMA Surface, Type A $73.50 838.22 $61,609.17 838.22 $61,609.17 $0.00 28 HMA Intermediate, Type A $55.00 2149.4 $118,217.00 2149.4 $118,217.00 $0.00 29 Surface Milling, 1 -1/2" $10.00 0 $0.00 0 $0.00 $0.00 30 Compacted Agg. No. 53, Base $23.50 4306 $101,191.00 4306 $101,191.00 $0.00 31 Sidewalk, Concrete, 4" $56.00 142.8 $7,996.80 142.8 $7,996.80 $0.00 32 Concrete Paved Side Ditch, Type A $31.50 405 $12,757.50 405 $12,757.50 $0.00 33 Curb and Gutter, Concrete $29.50 943.3 $27,827.35 943.3 $27,827.35 $0.00 34 Concrete Curb Ramp, Type G $87.50 188.8 $16,520.00 188.8 $16,520.00 $0.00 35 Nursery Sodding $2.72 0 $0.00 0 $0.00 $0.00 36 Erosion Control Blanket $2.30 1816.67 $4,178.34 1912 $4,397.60 $219.26 37 Erosion Control Measures $11,904.94 1 $11,904.94 1 $11,904.94 $0.00 38 Topsoil (Undistributed) $1.00 330 $330.00 330 $330.00 $0.00 Street Sign and Post, Remove and 39 Relocate $150.00 2 $300.00 2 $300.00 $0.00 40 Yard Light, Remove and Relocate $500.00 0 $0.00 0 $0.00 $0.00 A -1 Additional, Clearing of Right -of -Way $1,000.00 1 $1,000.00 1 $1,000.00 $0.00 A -2 Additional, Tree Removal $2,000.00 1 $2,000.00 1 $2,000.00 $0.00 41 3' x 5' Precast Concrete Box Culvert $868.97 16 $13,903.52 16 $13,903.52 $0.00 42 3' x 8' Precast Concrete Box Culvert $387.59 32 $12,402.88 32 $12,402.88 $0.00 *45 Mobilization /Demobilization 2,680.28 1 $2,680.28 1 $2,680.28 $0.00 *46 Clearing Right of Way 2,799.26 1 $2,799.26 1 $2,799.26 $0.00 *47 15" RCP End Section 1,143.59 1 $1,143.59 1 $1,143.59 $0.00 *48 18" RCP 130.25 54 $7,033.50 54 $7,033.50 $0.00 *49 18" Concrete Pipe End Section 1,193.99 1 $1,193.99 1 $1,193.99 $0.00 *50 Reinforced Concrete Headwall 1,144.44 5.5 $6,294.42 5.5 $6,294.42 $0.00 *51 12" Class A Concrete for Roadway Path 250.06 24.4 $6,101.46 24.4 $6,101.46 $0.00 *52 Detour Route Marker Assembly 192.50 10 $1,925.00 10 $1,925.00 $0.00 *53 Construction Sign A 328.50 12 $3,942.00 12 $3,942.00 $0.00 *54 Construction Sign B 110.00 2 $220.00 2 $220.00 $0.00 *55 Barricade, Type III 22.00 72 $1,584.00 72 $1,584.00 $0.00 *56 Line, Thermo, Solid White 4" 5.50 80 $440.00 80 $440.00 $0.00 *57 Line, Thermo, Solid Yellow 4" 5.50 80 $440.00 80 $440.00 $0.00 *58 Clean Existing 3' x 8' Box Culvert 2,824.93 1 $2,824.93 1 $2,824.93 $0.00 *59 Stand Up Curb, 18" $45.05 104 $4,685.20 104 $4,685.20 $0.00 *60 4" PVC Smooth Wall $40.37 27 $1,089.99 27 $1,089.99 $0.00 *61 Mulching Seeding Special Blend $0.85 17091.49 $14,527.77 33032 $28,077.15 $13,549.38 *62 Mobilization Demobilization for Seeding $779.32 1 $779.32 3 $2,337.96 $1,558.64 *63 A-4 Manhole replacement Structure #5 $4,071.47 1 $4,071.47 1 $4,071.47 $0.00 *64 Meter Pit Relocation 2100 W. 106th $3,648.13 1 $3,648.13 1 $3,648.13 $0.00 *65 Grate Replacement 483.68 0 $0.00 6 $2,902.08 $2,902.08 *66 Herbicide Treatment 1,647.70 0 $0.00 1 $1,647.70 $1,647.70 *67 Fence Relocation STA 95 +50 to 96 +75 5,860.50 0 $0.00 1 $5,860.50 $5,860.50 i. rk :P; g 'x' ia l.,. :z ;�-�ixF= iG bfF':: i s �'a; A ::j. P,' .r,9c 4 r'l 6'. f ;::',4.:4j1,711:,,,,,,,-,,!4.-:1,1 7 0 En b i i s +s $�/Yi,.`,�€� 'n�.°'� a5� ti ..f .4 -r3 TOTAL; OF G HAfVGE O RDER' I TEMS i ,41886;545:4§;*,),"."'': $9 TOTAL ORIGINAL CONTRACT PLUS CHANGE ORDER ITEMS ORIGINAL CONTRACT PRICE $664,400.00 CHANGE ORDER #1 $26,306.40 CHANGE ORDER #2 $34,535.12 CHANGE ORDER #3 $2,824.93 CHANGE ORDER #4 $20,109.81 CHANGE ORDER #5 $178,588.86 CHANGE ORDER #6 (FINAL CHANGE ORDER) $30,947.66 NEW CONTRACT AMOUNT INCLUDING APPROVED CHANGE ORDERS $917,493.16 Indicates additional item added to the contract.