HomeMy WebLinkAbout01 70 00.docMATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
01 70 00 -
CARMEL CITY CENTER Date 03.26.12 EXECUTION REQUIREMENTS
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
SECTION 01 70 00 EXECUTION REQUIREMENTS
PART 1- GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes general procedural requirements governing execution of the Work
including, but not limited to, the following:
1. Field engineering.
2. General installation of products.
3. Protection of installed construction.
4. Correction of the Work.
B. Related Sections include the following:
1. Division 1 Section "Project Management and Coordination" for procedures for
coordinating field engineering with other construction activities.
2. Division 1 Section "Submittal Procedures" for submitting surveys.
3. Division 1 Section "Cutting and Patching" for procedural requirements for cutting
and patching necessary for the installation or performance of other components
of the Work.
4. Division 1 Section "Closeout Procedures" for submitting final property survey with
Project Record Documents, recording of Owner-accepted deviations from
indicated lines and levels, and final cleaning.
5. Division 1 Section "Construction Layout."
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 GENERAL
A. Contractor shall be responsible for performing construction layout work in accordance
with data as indicated on the construction drawings or as directed by the Owner's
Representative.
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
01 70 00 -
CARMEL CITY CENTER Date 03.26.12 EXECUTION REQUIREMENTS
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
3.2 EXAMINATION
A. Existing Utilities: The existence and location of underground and other utilities and
construction indicated as existing are not guaranteed. Before beginning work,
investigate and verify the existence and location of underground utilities and other
construction affecting the Work, where applicable.
1. Before construction, verify the location and invert elevation at points of
connection of sanitary sewer, storm sewer, and water-service piping; and
underground electrical services, where applicable.
B. Acceptance of Conditions: Examine substrates, areas, and conditions, with Installer or
Applicator present where indicated, for compliance with requirements for installation
tolerances and other conditions affecting performance. Record observations.
1. Written Report: Where a written report listing conditions detrimental to
performance of the Work is required by other Sections, include the following:
a. Description of the Work.
b. List of detrimental conditions, including substrates.
c. List of unacceptable installation tolerances.
d. Recommended corrections.
2. Proceed with installation only after unsatisfactory conditions have been
corrected. Proceeding with the Work indicates acceptance of surfaces and
conditions.
3.3 PREPARATION
A. Existing Utility Information: Where necessary, furnish information to the respective
utility companies for the coordination that is necessary to adjust, move, or relocate
existing utility structures, utility poles, lines, services, or other utility appurtenances
located in or affected by construction. Coordinate with authorities having jurisdiction.
Contractor shall be responsible for the cost of any utility relocates, unless specifically
shown or agreed to with the Owner, in writing.
B. Field Measurements: Take field measurements as required to fit the Work properly.
Recheck measurements before installing each product. Where portions of the Work are
indicated to fit to other construction, verify dimensions of other construction by field
measurements before fabrication. Coordinate fabrication schedule with construction
progress to avoid delaying the Work.
C. Review of Contract Documents and Field Conditions: Immediately upon discovery of
the need for clarification of the Contract Documents, submit a request for information
(RFI) to Architect. Include a detailed description of problem encountered, together with
recommendations for changing the Contract Documents.
3.4 FIELD ENGINEERING
A. Identification: Owner will identify existing benchmarks, control points, and property
corners.
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
01 70 00 -
CARMEL CITY CENTER Date 03.26.12 EXECUTION REQUIREMENTS
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
B. Reference Points: Locate existing permanent benchmarks, control points, and similar
reference points before beginning the Work. Preserve and protect permanent
benchmarks and control points during construction operations.
1. Do not change or relocate existing benchmarks or control points without prior
written approval of Architect. Report lost or destroyed permanent benchmarks or
control points promptly. Report the need to relocate permanent benchmarks or
control points to Architect before proceeding.
2. Replace lost or destroyed permanent benchmarks and control points promptly.
Base replacements on the original survey control points.
C. Benchmarks: Work from established site benchmarks.
1. Record benchmark locations, with horizontal and vertical data, on Project Record
Documents.
2. Where the actual location or elevation of layout points cannot be marked, provide
temporary reference points sufficient to locate the Work.
3. Remove temporary reference points when no longer needed. Restore marked
construction to its original condition.
3.5 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct alignment
and elevation, as indicated.
1. Make vertical work plumb and make horizontal work level.
2. Where space is limited, install components to maximize space available for
maintenance and ease of removal for replacement.
B. Conduct construction operations so no part of the Work is subjected to damaging
operations or loading in excess of that expected during normal conditions of occupancy.
C. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels.
D. Templates: Obtain and distribute to the parties involved templates for work specified to
be factory prepared and field installed. Check Shop Drawings of other work to confirm
that adequate provisions are made for locating and installing products to comply with
indicated requirements.
E. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each
component securely in place, accurately located and aligned with other portions of the
Work.
F. Joints: Make joints of uniform width. Where joint locations in exposed work are not
indicated, arrange joints for the best visual effect. Fit exposed connections together to
form hairline joints.
G. Hazardous Materials: Use products, cleaners, and installation materials that are not
considered hazardous.
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
01 70 00 -
CARMEL CITY CENTER Date 03.26.12 EXECUTION REQUIREMENTS
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
3.6 PROTECTION OF INSTALLED CONSTRUCTION
A. Provide final protection and maintain conditions that ensure installed Work is without
damage or deterioration at time of Substantial Completion.
3.7 CORRECTION OF THE WORK
A. Repair or remove and replace defective construction. Restore damaged substrates and
finishes. Comply with requirements in Division 1 Section "Cutting and Patching."
1. Repairing includes replacing defective parts, refinishing damaged surfaces,
touching up with matching materials, and properly adjusting operating equipment.
B. Restore permanent facilities used during construction to their specified condition.
END OF SECTION 01 70 00