HomeMy WebLinkAbout02 41 10.docMATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
02 41 19 -
CARMEL CITY CENTER Date 03.26.12 SELECTIVE DEMOLITION
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
SECTION 02 41 19 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Demolition and removal of selected portions of building or structure.
2. Demolition and removal of selected site elements.
3. Salvage of existing items to be reused or recycled.
B. Related Requirements:
1. Section 01 10 00 "Summary" for restrictions on the use of the premises, Owner-
occupancy requirements, and phasing requirements.
2. Section 01 73 00 "Execution" for cutting and patching procedures.
3. Section 31 10 00 "Site Clearing" for site clearing and removal of above- and below-grade
improvements.
1.3 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site unless
indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent
damage, and deliver to Owner ready for reuse.
C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall
where indicated.
D. Existing to Remain: Existing items of construction that are not to be permanently removed and
that are not otherwise indicated to be removed, removed and salvaged, or removed and
reinstalled.
1.4 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
1.5 PRE-INSTALLATION MEETINGS
A. Pre-demolition Conference: Conduct conference at Project site.
1. Inspect and discuss condition of construction to be selectively demolished.
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
02 41 19 -
CARMEL CITY CENTER Date 03.26.12 SELECTIVE DEMOLITION
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
2. Review structural load limitations of existing structure.
3. Review and finalize selective demolition schedule and verify availability of materials,
demolition personnel, equipment, and facilities needed to make progress and avoid
delays.
4. Review requirements of work performed by other trades that rely on substrates exposed
by selective demolition operations.
5. Review areas where existing construction is to remain and requires protection.
1.6 INFORMATIONAL SUBMITTALS
A. Proposed Protection Measures: Submit report, including drawings, that indicates the measures
proposed for protecting individuals and property , for environmental protection , for dust control
and , for noise control. Indicate proposed locations and construction of barriers.
1. Interruption of utility services. Indicate how long utility services will be interrupted.
2. Coordination for shutoff, capping, and continuation of utility services.
3. Use of elevator and stairs.
4. Coordination of Owner's continuing occupancy of portions of existing building and of
Owner's partial occupancy of completed Work.
B. Inventory: Submit a list of items to be removed and salvaged and deliver to Owner prior to start
of demolition.
C. Pre-demolition Photographs or Video: Submit before Work begins..
D. Warranties: Documentation indicated that existing warranties are still in effect after completion
of selective demolition.
1.7 CLOSEOUT SUBMITTALS
A. Inventory: Submit a list of items that have been removed and salvaged.
B. Landfill Records: Indicate receipt and acceptance of hazardous wastes by a landfill facility
licensed to accept hazardous wastes.
1.8 FIELD CONDITIONS
A. Owner will occupy portions of building immediately adjacent to selective demolition area.
Conduct selective demolition so Owner's operations will not be disrupted.
B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far
as practical.
C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding
with selective demolition.
D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the
Work.
1. Hazardous materials will be removed by Owner before start of the Work.
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
02 41 19 -
CARMEL CITY CENTER Date 03.26.12 SELECTIVE DEMOLITION
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
2. If suspected hazardous materials are encountered, do not disturb; immediately notify
Architect and Owner. Hazardous materials will be removed by Owner under a separate
contract.
E. Storage or sale of removed items or materials on-site is not permitted.
F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against
damage during selective demolition operations.
1. Maintain fire-protection facilities in service during selective demolition operations.
1.9 WARRANTY
A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or
damaged during selective demolition, by methods and with materials so as not to void existing
warranties. Notify warrantor before proceeding.
B. Notify warrantor on completion of selective demolition, and obtain documentation verifying that
existing system has been inspected and warranty remains in effect. Submit documentation at
Project closeout.
PART 2 - PRODUCTS
2.1 PEFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning
selective demolition. Comply with hauling and disposal regulations of authorities having
jurisdiction.
B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped before starting selective demolition
operations.
B. Review record documents of existing construction provided by Owner. Owner does not
guarantee that existing conditions are same as those indicated in record documents.
C. Survey existing conditions and correlate with requirements indicated to determine extent of
selective demolition required.
D. When unanticipated mechanical, electrical, or structural elements that conflict with intended
function or design are encountered, investigate and measure the nature and extent of conflict.
Promptly submit a written report to Architect.
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
02 41 19 -
CARMEL CITY CENTER Date 03.26.12 SELECTIVE DEMOLITION
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
E. Perform or engage a professional engineer to perform an engineering survey of condition of
building to determine whether removing any element might result in structural deficiency or
unplanned collapse of any portion of structure or adjacent structures during selective building
demolition operations.
1. Perform surveys as the Work progresses to detect hazards resulting from selective
demolition activities.
2. Steel Tendons: Locate tensioned steel tendons and include recommendations for de-
tensioning.
F. Survey of Existing Conditions: Record existing conditions by use of measured drawings and
preconstruction photographs or videotapes.
1. Inventory and record the condition of items to be removed and salvaged. Provide
photographs or video of conditions that might be misconstrued as damage caused by
salvage operations.
2. Before selective demolition or removal of existing building elements that will be
reproduced or duplicated in final Work, make permanent record of measurements,
materials, and construction details required to make exact reproduction.
3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and
protect them against damage.
1. Comply with requirements for existing services/systems interruptions specified.
B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify,
disconnect, and seal or cap off indicated utility services and mechanical/electrical systems
serving areas to be selectively demolished.
1. Owner or Building manager will arrange to shut off indicated services/systems when
requested by Contractor.
2. Arrange to shut off indicated utilities with utility companies.
3. If services/systems are required to be removed, relocated, or abandoned, provide
temporary services/systems that bypass area of selective demolition and that maintain
continuity of services/systems to other parts of building.
4. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC
systems, equipment, and components indicated to be removed.
a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap
or plug remaining piping with same or compatible piping material.
b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same
or compatible piping material.
c. Equipment to Be Removed: Disconnect and cap services and remove equipment.
d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and
remove, clean, and store equipment; when appropriate, reinstall, reconnect, and
make equipment operational.
e. Equipment to Be Removed and Salvaged: Disconnect and cap services and
remove equipment and deliver to Owner.
f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug
remaining ducts with same or compatible ductwork material.
g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible
ductwork material.
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
02 41 19 -
CARMEL CITY CENTER Date 03.26.12 SELECTIVE DEMOLITION
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
3.3 PREPARATION
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal
operations to ensure minimum interference with roads, streets, walks, walkways, and other
adjacent occupied and used facilities.
1. Comply with requirements for access and protection specified in Section 01 50 00
"Temporary Facilities and Controls."
B. Temporary Facilities: Provide temporary barricades and other protection required to prevent
injury to people and damage to adjacent buildings and facilities to remain.
1. Provide protection to ensure safe passage of people around selective demolition area
and to and from occupied portions of building.
2. Provide temporary weather protection, during interval between selective demolition of
existing construction on exterior surfaces and new construction, to prevent water leakage
and damage to structure and interior areas.
3. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are
exposed during selective demolition operations.
4. Cover and protect furniture, furnishings, and equipment that have not been removed.
5. Comply with requirements for temporary enclosures, dust control, heating, and cooling
specified in Section 01 50 00 "Temporary Facilities and Controls."
C. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required
to preserve stability and prevent movement, settlement, or collapse of construction and finishes
to remain, and to prevent unexpected or uncontrolled movement or collapse of construction
being demolished.
1. Strengthen or add new supports when required during progress of selective demolition.
3.4 SELECTIVE DEMOLITION, GENERAL
A. General: Demolish and remove existing construction only to the extent required by new
construction and as indicated. Use methods required to complete the Work within limitations of
governing regulations and as follows:
1. Proceed with selective demolition systematically, from higher to lower level. Complete
selective demolition operations above each floor or tier before disturbing supporting
members on the next lower level.
2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use
cutting methods least likely to damage construction to remain or adjoining construction.
Use hand tools or small power tools designed for sawing or grinding, not hammering and
chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to
remain.
3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring
existing finished surfaces.
4. Do not use cutting torches until work area is cleared of flammable materials. At
concealed spaces, such as duct and pipe interiors, verify condition and contents of
hidden space before starting flame-cutting operations. Maintain fire watch and portable
fire-suppression devices during flame-cutting operations.
5. Maintain adequate ventilation when using cutting torches.
6. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and
promptly dispose of off-site.
7. Remove structural framing members and lower to ground by method suitable to avoid
free fall and to prevent ground impact or dust generation.
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
02 41 19 -
CARMEL CITY CENTER Date 03.26.12 SELECTIVE DEMOLITION
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
8. Locate selective demolition equipment and remove debris and materials so as not to
impose excessive loads on supporting walls, floors, or framing.
9. Dispose of demolished items and materials promptly.
B. Reuse of Building Elements: Project has been designed to result in reuse of building elements.
Do not demolish building elements beyond what is indicated on Drawings without Architect's
approval.
C. Removed and Salvaged Items:
1. Clean salvaged items.
2. Pack or crate items after cleaning. Identify contents of containers.
3. Store items in a secure area until delivery to Owner.
4. Transport items to Owner's storage area designated by Owner or indicated on Drawings.
5. Protect items from damage during transport and storage.
D. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse.
2. Pack or crate items after cleaning and repairing. Identify contents of containers.
3. Protect items from damage during transport and storage.
4. Reinstall items in locations indicated. Comply with installation requirements for new
materials and equipment. Provide connections, supports, and miscellaneous materials
necessary to make item functional for use indicated.
E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling
during selective demolition. When permitted by Architect, items may be removed to a suitable,
protected storage location during selective demolition and cleaned and reinstalled in their
original locations after selective demolition operations are complete.
3.5 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS
A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at
least 3/4 inch at junctures with construction to remain. Dislodge concrete from reinforcement at
perimeter of areas being demolished, cut reinforcement, and then remove remainder of
concrete. Neatly trim openings to dimensions indicated.
B. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain,
using power-driven saw, then remove masonry between saw cuts.
C. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, then break up and
remove.
3.6 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Except for items or materials indicated to be recycled, reused, salvaged, reinstalled,
or otherwise indicated to remain Owner's property, remove demolished materials from Project
site and legally dispose of them.
1. Do not allow demolished materials to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces
and areas.
3. Remove debris from elevated portions of building by chute, hoist, or other device that will
convey debris to grade level in a controlled descent.
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
02 41 19 -
CARMEL CITY CENTER Date 03.26.12 SELECTIVE DEMOLITION
MATT THE MILLER’S; CARMEL CITY CENTER; SUITE 101
B. Burning: Do not burn demolished materials.
C. Disposal: Transport demolished materials off Owner's property and legally dispose of them.
3.7 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective
demolition operations. Return adjacent areas to condition existing before selective demolition
operations began.
3.8 SELECTIVE DEMOLITION SCHEDULE
A. Refer to Demolition Plan in Drawings items and areas requiring demolition.
END OF SECTION 02 41 19